U.S. DEPARTMENT OF THE INTERIOR – BUREAU OF LAND MANAGEMENT

RADIO FACILITY TECHNICAL PACKAGE 1 – NEVADA

Tenabo 01 11 00 - 39 Bid Schedule

10/16/2020

PART 5: TENABO – BID SCHEDULE

BID ITEM SOW REF

Unit of

Measure

UNITS MATERIALS LABOR TOTAL

2.3 RADIO FACILITY DESIGNS

Civil Improvement Plans 2.3 each 1 $ $ $

Site Survey - Topographic 2.3 each 1 $ $ $

Electrical One-Line for Modification to Existing Electrical Service 2.3 each 1 $ $ $

Third Party Inspection Services 3.6 each 1 $ $ $

2.3 - SUBTOTAL $ $ $

2.6.1 ALUMINUM CABINET WITH ARTICULATING MAST SHELTER INSTALLATION

Transport and install New Pepro Cabinet (GFM) with 20-foot articulating mast 2.6.1 each 1 $ $ $

2.6.1 - SUBTOTAL $ $ $

3.5.1 PHOTOVOLTAIC POWER AND BATTERY BACKUP SYSTEM

Install Solar Panels and frame (GFM) 3.5.1 each 2 $ $ $

Procure and Install External Wiring between Solar Panels and Entrance to the Shelter 3.5.1 Lineal Foot 20 $ $ $

Install Photovoltaic Charger/Controller (60 - Ampere) including internal wiring 3.5.1 each 1 $ $ $

Install Batteries GFM 3.5.1 each 4 $ $ $

Procure and Install DC Wiring 3.5.1 each 3 $ $ $

3.5.1 - SUBTOTAL $ $ $

3.11 EXTERNAL RF CABLE & WAVEGUIDE INSTALLATION

RF Cable Routing and Support (Pipe-Masts) 3.11 each 2 $ $ $

RF Cable Entrance Installation and Sealing 3.11 each 2 $ $ $

RF Cable Testing and Report 3.17 each 2 $ $ $

Tenabo 01 11 00 - 40 Bid Schedule

10/16/2020

BID ITEM SOW REF

Unit of

Measure

UNITS MATERIALS LABOR TOTAL

Ground RF Cable to Entry Port using Stainless Steel Strap Provided by Pepro 3.11 each 2 $ $ $

3.11 - SUBTOTAL $ $ $

3.12 ANTENNA SYSTEMS INSTALLATION

Antenna Installation (Secured, Plumb, RF Cable Weather Seal) 3.12 each 2 $ $ $

3.12 - SUBTOTAL $ $ $

3.14 COMMON EXTERNAL GROUNDING SYSTEM

Trenching for Grounding System 3.14 per lineal foot 220 $ $ $

Provide and Install Ground Rods: (3/4" diameter, 10-foot long) Includes Exothermic Connections 3.14 each 9 $ $ $

Provide and Install Electrolytic Ground Rods: (2.12" diameter, 20-foot long) Includes Exothermic Connections

3.14 each 1 $ $ $

Provide and Install External Grounding Conductor: # 2 AWG, bare, solid, tinned, copper for Grounding System

3.14 per lineal foot 300 $ $ $

Backfilling for Grounding System (Includes Grounding Enhancement Material for High Soil Resistivity Sites)

3.14 per lineal foot 220 $ $ $

Bond Existing Tower Ground Bus Bar (TGB) to Ground Ring - Remote Facilities 3.14 each 1 $ $ $

Concrete Encased Electrodes in Shelter Foundations Connected to the Shelter Ground Ring 3.14 each 4 $ $ $

Ground Each Grounding Tab on the Cabinet (x3) to the Grounding System 3.14 each 3 $ $ $

Solar Panel and Framework Grounding 3.14 Lump Sum 1 $ $ $

RF Cables Grounded at Base of Pipe Mast 3.14 each 1 $ $ $

Ground RF Cable to Entry Port using Stainless Steel Strap Provided by Pepro 3.14 each 1 $ $ $

RF Cable Surge Protection 3.14 each 2 $ $ $

3.14 - SUBTOTAL $ $ $

3.16 EQUIPMENT RACKS AND CABINETS

Tenabo 01 11 00 - 41 Bid Schedule

10/16/2020

BID ITEM SOW REF

Unit of

Measure

UNITS MATERIALS LABOR TOTAL

Radio Equipment Installation in Racks and Cabinets 3.16 each 1 $ $ $

Ancillary Equipment Installation in Racks and Cabinets 3.16 each 2 $ $ $

Ground Rack-Mounted Equipment (per device to be grounded) 3.16 each 3 $ $ $

3.16 - SUBTOTAL $ $ $

COST SUMMARY MATERIALS LABOR TOTAL

LABOR AND MATERIALS - SUBTOTAL $ $ $

MATERIAL HANDLING AND DELIVERY $ $ $

MOBILIZATION FEES $ $ $

OTHER DIRECT COSTS $ $ $

BOND $ $ $

PROJECT MANAGEMENT FEES $ $ $

OVERHEAD $ $ $

PROFIT $ $ $

TOTAL ESTIMATED COST $ $ $