A06_Specifications_LAVO_Grade_and_Pave.pdf

PDF 109 KB Posted

Attached to
Grade and Pave, Lassen Volcanic NP Federal contract opportunity
Solicitation number
140P8426Q0035
Issued by
Department of the Interior National Park Service

About this file

This is a Contract Specifications document for grade and pave work at Lassen Volcanic National Park issued by the National Park Service under Solicitation #140P8426P0035 (PMIS Nos. 351252 and 206780), prepared in March 2026.

The work consists of grade reestablishment, drainage correction, subgrade preparation, compaction, and asphalt paving at two locations totaling approximately 31,400 square feet. Location 1—Summertown Service Road & Maintenance Area (39489 Highway 44, Shingletown, California)—comprises a 700-foot service road (7,000 SF) and 14,000 SF parking area requiring fine grading, compaction, drainage correction, and paving. Location 2—Mineral Headquarters Historic District (38050 Highway 36E, Mineral, California)—covers 10,400 SF between Buildings 16, 17, and 14, requiring minor grade improvements and drainage reestablishment prior to paving. The contractor must furnish all labor, materials, equipment, supervision, testing, and traffic control necessary for completion.

Specifications require subgrade compaction to minimum 95% Modified Proctor density with ±2% moisture conditioning, establishment of minimum 2% cross slope, proof-rolling with undercut and replacement of failing areas, and positive drainage restoration at Location 2. Asphalt placement must meet Caltrans Section 39 standards with 3/8" to 1/2" maximum aggregate size, 2-inch final compacted thickness (±1/4 inch tolerance), and 92–96% theoretical maximum density achievement. Surface tolerances include maximum 1/4-inch deviation in 10 feet with proper crown maintenance and no standing water permitted. Environmental compliance includes dust control, prohibition of petroleum discharge, protection of historic resources and utilities, and disposal of spoils at approved locations. The contractor provides a one-year warranty against rutting, surface failure, premature cracking, and drainage failure, with final acceptance contingent upon visual inspection and drainage verification.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT SPECIFICATIONS

FOR

GRADE AND PAVE SUMMERTOWN ROAD AND

MINERAL HEADQUARTERS PARKING AREA AT

LASSEN VOLCANIC NATIONAL PARK

Solicitation #140P8426P0035

NATIONAL PARK SERVICE

PMIS No. 351252 AND 206780

MARCH, 2026

Prepared by: Joe Pettegrew

Lassen Volcanic National Park

38050 Highway 36 East

Mineral, CA 96063

SECTION 01 10 00 – SUMMARY OF WORK

1.1 PROJECT DESCRIPTION

The work consists of grade reestablishment, drainage correction, subgrade preparation, compaction, and asphalt paving at two locations within Lassen Volcanic National Park.

Work includes furnishing all labor, materials, equipment, supervision, testing, traffic control, and incidentals necessary to complete the work as specified.

1.2 PROJECT LOCATIONS

Location 1 – Summertown Service Road & Maintenance Area

Located at the Northwest Entrance near Manzanita Lake at 39489 Hwy 44 Shingletown California 96088.

• Service Road: Approx. 700 feet long x 10 feet wide (≈ 7,000 SF)

• Parking Area: Approx. 14,000 SF

• Total Approximate Surface Area: 21,000 SF

Scope includes fine grading, compaction, drainage correction, and asphalt paving.

Location 2 – Mineral Headquarters Historic District

Located at the Mineral Headquarters at 38050 Hwy 36E Mineral California 96063.

Located between Buildings 16, 17, and 14.

• Approximate Area: 10,400 SF

• Requires minor grade improvements and drainage reestablishment prior to paving.

Total Estimated Combined Paving Area (Both Sites): ~31,400 SF

SECTION 01 35 43 – ENVIRONMENTAL PROCEDURES

1. Contractor shall comply with all National Park Service environmental protection requirements.

2. Dust control measures shall be implemented during grading and base preparation.

3. No petroleum products, oils, or hazardous materials shall be discharged onto park lands.

4. Work within the Historic District shall avoid disturbance outside defined limits.

5. Contractor shall protect adjacent vegetation, historic resources, and utilities.

6. All spoils shall be disposed of in approved locations.

SECTION 31 20 00 – EARTHWORK

1. GENERAL

Work includes grade reestablishment, drainage correction, subgrade shaping, moisture conditioning, and compaction.

2. SUBGRADE PREPARATION

• Strip loose or unsuitable material.

• Reestablish proper cross slope (minimum 2% unless otherwise directed).

• Shape and proof-roll subgrade.

• Moisture condition to within ±2% of optimum moisture content.

• Compact to minimum 95% of Modified Proctor (ASTM D1557).

Areas failing proof-roll shall be undercut and replaced with approved structural fill.

3. DRAINAGE RESTORATION (LOCATION 2)

• Reestablish positive drainage away from buildings.

• Restore or reshape swales as necessary.

• Ensure no ponding adjacent to structures.

• Maintain historic district drainage patterns where applicable.

SECTION 32 12 16 – ASPHALT PAVING

1. MATERIALS

Asphalt Concrete

• 3/8" to 1/2" maximum aggregate size

• Hot Mix Asphalt (HMA) meeting Caltrans Section 39 or equivalent

• Suitable for heavy-duty service and snow load conditions

• PG grade appropriate for Lassen climate conditions

2. LIFT THICKNESS

• Final compacted thickness: 2 inches

• Placement may be single lift if approved

• Thickness tolerance: ± 1/4 inch

3. PLACEMENT

• Surface shall be dry and free of debris.

• Apply tack coat where paving over existing asphalt.

• Place asphalt at manufacturer-recommended temperature.

• Use mechanical paver for uniform placement.

• Hand work permitted only in tight areas.

4. COMPACTION

• Roll using steel-wheel and/or pneumatic rollers.

• Achieve minimum 92–96% of theoretical maximum density.

• Finished surface shall be smooth, uniform, and free of roller marks.

5. SURFACE TOLERANCES

• Maximum deviation: 1/4 inch in 10 feet.

• Proper crown or cross slope maintained.

• No standing water permitted after completion.

SECTION 01 45 00 – QUALITY CONTROL

1. Contractor shall provide compaction testing.

2. Density testing may be required at random intervals.

3. Unsatisfactory areas shall be removed and replaced at no cost to the Government.

4. Final acceptance contingent upon visual inspection and drainage verification.

SECTION 01 55 00 – TRAFFIC CONTROL

1. Maintain access for park operations where required.

2. Provide temporary signage and barriers.

3. Coordinate closures with Park management.

4. Contractor responsible for public and employee safety within work zones.

SECTION 01 77 00 – CLOSEOUT PROCEDURES

1. Remove all debris, excess material, and equipment.

2. Restore disturbed areas.

3. Provide documentation of material sources and compaction results.

4. Warranty asphalt paving for minimum one (1) year against:

➢ Rutting

➢ Surface failure

➢ Premature cracking

➢ Drainage failure due to improper grading

PERFORMANCE REQUIREMENTS

The finished surfaces shall:

• Provide safe vehicle access.

• Restore and maintain positive drainage.

• Prevent standing water accumulation.

• Support snow load and maintenance vehicle traffic.

• Provide a durable surface suitable for park operations.