This is a comprehensive specifications document for the Crawford Dam Removal and Diversion Headgate Replacement Project at Zion National Park in Utah. The work includes partial removal and disposal of an existing concrete dam and headgate structure, regrading of approximately 300 feet of the North Fork Virgin River, construction of a new intake structure with fish screen, removal of approximately 275 feet of existing CMP pipe and concrete manhole, installation of approximately 285 feet of 18-inch ADS N-12 pipe, removal of a concrete turnout box, reseating of an existing 12-inch flume, approximately 150 feet of boulder embankment riprap, and installation of approximately 350 feet of Smart Ditch or equivalent irrigation liner. The project must be completed within 180 calendar days of the Notice to Proceed, with no in-water work permitted between April 1 and July 31 to protect fish during reproductive cycles, and all work must be completed prior to April 1, 2027.
The specifications document contains detailed Division 01 General Requirements addressing project management, construction scheduling, surveying, safety, quality control, environmental protection, temporary facilities, erosion control, waste management, and closeout procedures, along with Division 02-32 technical specifications for site demolition, concrete formwork and reinforcement, concrete placement and curing, miscellaneous metalwork, grating, headgates, earthwork, trenching, grading, rock ramp placement, and canal liner installation. The contractor must obtain performance and payment bonds, provide comprehensive submittals including construction schedules and quality control plans, implement extensive environmental protection measures including fish clearance coordination and wildlife monitoring, maintain a 100 percent biodegradable erosion control plan, achieve a 50 percent waste diversion rate from landfills, conduct Davis-Bacon wage compliance, and comply with all National Park Service regulations and Zion National Park-specific requirements. The solicitation is a firm-fixed-price contract set aside 100 percent for Total Small Businesses, with the NAICS code 237990 and size standard of $45 million, and construction wage rate requirements for Washington County, Utah apply.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P6426B0008_Amd_0002.pdf | ||
| Crawford_PrebidSiteVisit_20260520_0002.pdf | ||
| Questions_and_Answers_-_Crawford_Dam_Removal_0001.pdf | ||
| Sol_140P6426B0008_Amd_0001.pdf | ||
| B08_Solicitation_-_Bid_Schedule.xlsx | XLSX spreadsheet | |
| B08_Solicitation_-_Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| A06_Drawings.pdf | ||
| B08_Solicitation_-_DOL_Wage_Determination.pdf | ||
| Sol_140P6426B0008.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ZION NATIONAL PARK
CRAWFORD DAM REMOVAL
AND DIVERSION HEADGATE
REPLACEMENT PROJECT
SPECIFICATIONS
MARCH 2026
BLANK PAGE
CRAWFORD DAM
TOC - 3
TABLE OF CONTENTS
Crawford Dam Specifications
Table of Contents (TOC)
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 28 00 Construction Surveying 01 31 00 Project Management and Coordination 01 32 16 Construction Schedule 01 32 33 Photographic Documentation 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 50 00 Temporary Facilities, Controls and Construction Signage 01 55 26 Traffic Control 01 56 39 Tree Retention and Protection 01 57 19.12 Noise and Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention (SWPP), Under-an-Acre Pollution Prevention (UPP) 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance (O&M) Data 01 79 00 Demonstration & Training 01 81 13 Sustainable Design Requirements
Supporting Documents Project Waste Management Plan Worksheet Sample
DIVISION 02 – SITE WORK
02 40 01 Care of Water 02 41 13 Selective Site Demolition 02 93 01 Site Signage
DIVISION 03 – CONCRETE
03 01 00 Concrete Formwork 03 02 00 Concrete Reinforcement 03 03 00 Concrete
DIVISION 05 – METALS
05 05 00 Miscellaneous Metal Work 05 05 30 Fabricated Grating
TOC - 4
DIVISION 15 - MECHANICAL
15 04 00 Headgates
DIVISION 31 - EARTHWORK
31 03 00 Tree Protection 31 20 15 Clearing, Grubbing and Tree Removal 31 21 05 Earthwork and Trenching Materials 31 21 50 Subgrade Preparation 31 22 00 Site Excavation and Backfill 31 22 01 Trench Excavation and Backfill for Utilities 31 23 00 Watering 31 24 00 Finish Grading
31 88 00 Boulder and Riprap Placement
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 80 00 Canal Liner Placement
APPENDICES
A – Visitor Information System Templates
TOC - 5
01 11 00 - 1
SUMMARY OF WORK CRAWFORD DAM
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Work Phases
3. Work Under Other Contracts
4. Government-Furnished Materials
5. Contractor Use of Site
6. Public Use of Site
7. Occupancy Requirements for Buildings
8. Conduct of Operations
9. Work Restrictions
10. Special Construction Requirements
11. Additional Reports
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Zion National Park, 37.2191 N, 112.9741 W, near junction of Zion Canyon Scenic Drive and Zion-Mt. Carmel Highway, Springdale, Utah.
B. The Work consists of:
1. The Work includes but is not limited to partial removal and disposal of an existing concrete dam and headgate structure comprised of concrete, rock, rebar, regrading of the North Fork Virgin River for a distance of approximately 300 feet, construction of a new intake structure including a fish screen, removal and disposal of approximately 275’ of existing CMP pipe and concrete manhole, installation of approximately 285’ of 18”Ø ADS N-12 pipe (approximately 40’ to be placed within 24”Ø CMP pipe), removal of a concrete turnout box, reseating of an existing 12” flume, approximately 150 feet of boulder embankment rip rap and installation of approximately 350’ of Smart Ditch or Contracting Officer approved equivalent.
C. Project will be constructed under a single prime contract.
D. Period of Performance – Work shall be completed within 180 calendar days of the start date provided on the Notice to Proceed.
1. Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If weather impacts project beyond typical average weather patterns, contractor shall provide documentation in request for additional
01 11 00 - 2 days.
2. No in-water work shall be completed between April 1 though July 31 to protect fish during their reproductive cycle.
3. Work must be completed prior to April 1, 2027.
1.3 WORK UNDER OTHER CONTRACTS
A. General: Cooperate with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate Work of this Contract with work performed under separate contracts.
01 11 00 - 3
1.4 GOVERNMENT-FURNISHED MATERIALS
A. In case of Government -furnished materials:
1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.
2. Contractor is responsible for initial inspection, receiving, unloading, and handling Government-furnished items at Project site.
3. Government will inspect delivered items for damage after delivery. Contractor shall be present for and assist in Government's inspection.
4. Government will arrange for replacement if Government-furnished items are damaged, defective, or missing.
5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.
6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.
7. Contractor shall install and otherwise incorporate Government-furnished items into Work.
B. Government-Furnished Materials:
1. All seed for revegetation will be provided and planted by Zion National Park Revegetation Staff.
Contractor will be responsible for preparing the soil for revegetation.
2. Archeological Monitor and Biological Monitor will be provided by the NPS and will monitor certain excavation activities per construction schedule.
1.5 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to areas of disturbance within the limits of work indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Storage of Materials: Confine storage of materials to within staging area as shown on the drawings.
C. Parking and equipment staging: Confine parking and equipment staging to staging areas as described on the design drawings or areas as approved by the CO.
D. Stockpiling: Confine stockpiling to staging area as defined on the design drawings or areas as approved by CO.
E. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.
3. Do not fasten ropes, cables, or guys to existing trees.
4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
01 11 00 - 4
F. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
G. Construction Camp: Establishment of a camp within park will not be permitted.
H. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
I. Restrictions: Contractor to confirm adequate space at fee station lanes for equipment prior to bringing equipment through Springdale. Contractor shall abide by restrictions when traveling through the Zion-Mt. Carmel Tunnel including restrictions on vehicles over thirteen feet and one inch tall, semi-trucks, vehicles carrying hazardous materials, vehicles weighing more than 50,000 pounds, single vehicles over 40 feet long, and vehicles and trailers with combined length over 50 feet. Vehicles over 50,000 pounds are not allowed to drive across the Canyon Junction Bridge or Pine Creek Bridge on the Zion-Mt. Carmel Highway.
1.6 PUBLIC USE OF SITE
A. Contractor shall at all times conduct operations to ensure the least inconvenience to the public.
Lane closures will be permitted, when required, upon specific approval of the Contracting Officer.
1.8 CONDUCT OF OPERATIONS
A. Contractor shall conduct their operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 72 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.9 WORK RESTRICTIONS
A. On-Site Work Hours: See schedule in section 013218 - 2.2 A 1 b.
B. Existing Utilities
1. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
2. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be
01 11 00 - 5 made in accordance with the Changes clause of the contract.
3. The Contractor shall plan to supply their own water for construction.
4. The Contractor shall plan to supply their own power for construction.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within buildings or within 25 feet of entrances, operable windows, or outdoor air intakes. Smoking is not permitted within 25 feet of public use areas such as trails.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
01 11 00 - 6
01 26 01
CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager (PM), Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.
Include as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.
3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead… ................... 10% Profit… ................... 8.00%
2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 – PRODUCTS (Not Used)
PART 3 – EXECUTION
(Not Used)
END OF SECTION 01 26 01
01 27 00
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
C. General items related to the construction, including but not limited to construction fencing, erosion control measures, temporary diversion, staging, construction signage, construction trailers, temporary utilities, temporary facilities and controls, reporting, construction survey staking, overhead and profit etc. will not be measured separately but shall be included in the work.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item Number 1 Mobilization and Temporary Access Road Construction
1. This item consists of furnishing all materials, equipment, operations and labor necessary for moving equipment and materials to the site and building temporary access roads, staging areas, signage, required pre- and post-mobilization documentation and permits as depicted in the drawings and specifications.
2. No measurement will be made for separate items related to this work.
3. Payment will be made at a lump sum price.
B. Contract Line Item Number 2 Construction Staking and Surveying
1. This item consists of furnishing all materials, equipment, operations and labor necessary for performing surveying and staking for the delineation of the project components.
2. No measurement will be made for separate items related to this work.
3. Payment will be made at a lump sum price.
C. Contract Line Item Number 3 Erosion Control
1. This item consists of furnishing all materials, equipment, operations and labor necessary for installing and maintaining erosion control measures throughout the project. All work to install and maintain erosion control measures per the drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work.
3. Payment will be made at a lump sum price.
D. Contract Line Item Number 4 Clearing and Grubbing
1. This item consists of furnishing all materials, equipment, operations and labor necessary for clearing and grubbing throughout the project. All work to complete clearing and grubbing per the drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work.
3. Payment will be made at a per acre price.
E. Contract Line Item 5 Temporary Fencing
1. This item consists of furnishing all materials, equipment, operations and labor necessary for installing, maintaining and removal at the conclusion of work of temporary fencing throughout the project. All work to complete and maintain temporary fencing per the drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work.
3. Payment will be made at a linear foot price.
F. Contract Line Item 6 Traffic Control
1. This item consists of furnishing all materials, equipment, operations and labor necessary for traffic control throughout the project. All work to complete the installation of traffic control per the drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work.
3. Payment will be made at a lump sum price.
G. Contract Line Item Number 7 Site Dewatering and Diversion
1. This item consists of furnishing all materials, equipment, operations, and labor necessary for installing, maintaining and removing at the conclusion of in-stream work river diversion. All work to complete the installation of dewatering and diversion per the drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work.
3. Payment will be made at the contract at a lump sum price.
H. Contract Line Item Number 8 Existing Structure Removal (Dam, Headgate, Manhole, Turnout Box)
1. This item consists of furnishing all materials, equipment, operations, and labor necessary to remove and dispose of the existing concrete dam structure including indicated portions of the headgate structure, turnout box and associated dam materials including but not limited to concrete, pipe, metal rebar, and rock. This item includes but is not limited to demolition of existing dam for removal purposes, removal of all indicated portions of concrete dam, and off-site disposal of material. All work to complete the dam removal per the drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work. All work to complete the existing dam removal per the drawings and specifications shall be included.
3. Payment will be made at the contract at a per cubic yard price.
I. Contract Line Item Number 9 CMP Pipe Removal and Restoration
1. This item consists of furnishing all materials, equipment, operations, and labor necessary to install the new diversion pipe. This item includes but is not limited to excavation, removal of existing pipe and manhole and regrading, soil placement and compaction as per the construction drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work. All work to complete the diversion pipe per the drawings and specifications shall be included.
3. Payment will be made at the contract at a linear foot price.
J. Contract Line Item Number 10 Diversion Pipe Installation
1. This item consists of furnishing all materials, equipment, operations, and labor necessary to install the new diversion pipe. This item includes but is not limited to pipe bedding material, soil material, approximately 285’ of 18”Ø ADS N-12 pipe with approximately 40’ of 24”Ø CMP pipe casing placement, soil placement and compaction as per the construction drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work. All work to complete the diversion pipe per the drawings and specifications shall be included.
3. Payment will be made at the contract at a linear foot price.
K. Contract Line Item Number 11 New Concrete Headgate and Fish Screen Structure Construction
1. This item consists of furnishing all materials, equipment, operations, and labor necessary to construct the headgate and fish screen on the construction drawings. This item includes but is not limited to excavation and subgrade preparation; concrete forming and pouring, metal fabrication, screen placement, multiple head gate installations and trash rack installation as per the construction drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work. All work to complete the headgate and fish screen structure per the drawings and specifications shall be included.
3. Payment will be made at the contract at a lump sum price.
L. Contract Line Item Number 12 Channel Grading (Excavation and Fill)
1. This item consists of furnishing all materials, equipment, operations, and labor necessary to regrade the river channel through excavation and placement of fill as necessary in preparation for other project components. This item includes but is not limited to salvaging material, stockpiling material as appropriate for use in other channel grading sections, bringing in fill to supplement existing material to achieve design grade and all other features as per the construction drawings and specifications or as directed by the
CO.
2. No measurement will be made for separate items related to this work. All work to complete the channel regrading (excavation and fill) per the drawings and specifications shall be included.
3. No measurement will be made for subgrade prep, compaction, or other items required to complete the work.
4. Payment will be made at the contract at a cubic yard price for channel grading.
M. Contract Line Item Number 13 Rock Ramp Construction (Size D15 through D85 – Material Furnishing and Installing)
1. This item consists of furnishing all materials, equipment, operations, and labor necessary to construct a rock ramp through the placement of a filter layer and then a rock layer of the size D15 through D85 as indicated per the construction drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work. All work to complete the rock ramp per the drawings and specifications shall be included.
3. No measurement will be made for subgrade prep, compaction, or other items required to complete the work.
4. Payment will be made at the contract at a cubic yard price for rock ramp construction.
N. Contract Line Item Number 14 Rock Ramp Construction (Size D15 through D85 – Harvested on Site and Installing)
1. This item consists of materials harvested from on site, equipment, operations, and labor necessary to construct a rock ramp through the placement of a filter layer and then a rock layer of the size D15 through D85 as indicated per the construction drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work. All work to complete the rock ramp per the drawings and specifications shall be included.
3. No measurement will be made for subgrade prep, compaction, or other items required to complete the work.
4. Payment will be made at the contract at a cubic yard price for rock ramp construction.
O. Contract Line Item Number 15 Rock Ramp Construction (Size D100 – Special Placement Habitat Boulders)
1. This item consists of furnishing all materials, equipment, operations, and labor necessary to construct a rock ramp through the placement of D100 Habitat Boulders as indicated per the construction drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work. All work to complete the rock ramp per the drawings and specifications shall be included.
3. No measurement will be made for subgrade prep, compaction, or other items required to complete the work.
4. Payment will be made at the contract at a cubic yard price for rock ramp construction.
P. Contract Line Item Number 16 Riprap Embankment Stabilization to construct the riprap. This item includes but is not limited to riprap material, soil material, placement and compaction as per the construction drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work. All work to complete the buried riprap per the drawings and specifications shall be included.
3. Payment will be made at the contract at a cubic yard of riprap price.
Q. Contract Line Item Number 17 Site Restoration to restore the site after construction. This item includes but is not limited to removal of the access road and scarification of the surface as per the construction drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work. All work to complete the buried riprap per the drawings and specifications shall be included.
3. Payment will be made at the contract at a per acre price.
R. Contract Line Item Number 18 Smart Ditch Irrigation Ditch Liner or Contracting Officer Approved Equivalent Installation
1. This item consists of furnishing all materials, equipment, operations, and labor necessary to install the Smart Ditch irrigation ditch liner or Contracting Officer Approved Equivalent.
This item includes but is not limited to cleaning out the existing ditch including excavation, if necessary, reseating the existing flume to the appropriate elevation, installation of transition areas and inlet/outlet, grading, backfill and compaction as per the construction drawings and specifications or as directed by the CO.
2. No measurement will be made for separate items related to this work. All work to complete the installation per the drawings and specifications shall be included.
3. Payment will be made at the contract at a linear foot of Smart Ditch or Contracting Officer Approved Equivalent installation price.
END OF SECTION 01 27 00
01 28 00
CONSTRUCTION SURVEYING
SECTION 01 28 00 -CONSTRUCTION SURVEYING
1.1 RELATED DOCUMENTS: The General Contract Conditions, Drawings and other Division-1 Specification sections apply to work of this section.
1.2 DESCRIPTION: Section includes general requirements and procedures for construction surveying.
1.3 RELATED SECTIONS:
A. Construction facilities and temporary controls B. Earthwork C. 01 73 40 Execution
1.4 EXISTING UTILITIES:
A. The existence and location of all underground utilities and construction indicated as existing are not guaranteed.
B. Before starting any work disturbing, moving or penetrating the ground, the Contractor must have all existing utilities located, staked, and depth identified by the Contractor.
1.5 QUALITY ASSURANCE:
A. If there are discrepancies in the existing survey info and actual existing surface features, the Contractor will notify the CO immediately. It is the requirement of the government that the Contractor will work with the CO to make adjustments in the field as needed to get to acceptable final grades with no additional cost to the government.
PART 2 - PRODUCTS
1.1 CONSTRUCTION LAYOUT AND SURVEYING:
A. General: The work shall consist of the construction surveying, calculating, and staking necessary for the construction of all elements of the project. Layout of site elements will be accomplished by means of coordinates.
B. The work shall be done under the supervision of a Professional Engineer (P.E.) or Professional Land Surveyor (P.L.S.) who is experienced and competent in site construction surveying and registered in the State of Utah. The P.E. or P.L.S. shall be available to review work, resolve problems and make decisions in a timely manner.
C. The Contractor shall furnish all personnel, materials and traffic control necessary to perform the required construction surveying. All surveying equipment, including Electronic Distance Meters, tapes, tribrachs, theodolites, total stations, GPS receivers and levels shall be calibrated prior to the start of work. EDM’s, total stations, and GPS receivers shall be checked on a National Oceanic and Atmospheric Administration (NOAA) calibrated baseline. Equipment calibration accuracy and adjustments made to meet requirements specified in the Utah Department of Transportation (UDOT) Survey Manual shall be documented in the Survey Records.
D. Contractor shall establish horizontal and vertical control for the project. A Pre-survey
Conference shall be held prior to performing any surveying work. The CO, Contractor’s Superintendent, and Contractor’s Surveyor (P.E. or P.L.S.) shall attend. A surveying work schedule shall be submitted to the CO for review prior to the conference.
E. Contractor shall check all Government-established control points, and verify and document their accuracy, prior to using them for construction surveying control.
F. Contractor shall perform all construction surveying and staking that is necessary for construction of the project.
1. The Contractor shall pay the cost of all construction surveying for line and grade.
2. Working from lines and levels established by the benchmarks, establish and maintain project benchmarks and other dependable markers to set the lines and levels for the work and elsewhere on the site as needed to properly locate every element of the Work.
3. As construction proceeds, check every major element for line, level and plumb.
4. Calculate and measure required dimensions as shown within recognized tolerances. Do not scale the Drawings to determine dimensions. Advise entities engaged in construction activities of the marked lines and levels provided for use.
5. The Contractor is to establish all necessary benchmarks on site for layout and grading based on the control points provided by the Government from the original survey.
6. Grades noted on the plans as “MG” (match grade) shall require the contractor to survey those points and provide the existing elevations at those points back to the CO for verification of grades and proposed elevations. Allow 14 calendar days for the government to refine the grading sheet and elevations to match with the existing elevations at those points. All elevations given referencing MG are used to show relative height differences (i.e. height of curb, height of wall) not exact elevations.
7. All survey points on the ground shall match the numbering system of the coordinate points shown on the drawings.
G. Site Improvements: Locate and lay out site improvements, including pavements, stakes for grading, fill and topsoil placement, utility line gradients and invert elevations by instrumentation and similar appropriate means.
H. Layout Procedures:
1. Verify layout information shown on the Drawings in relation to the control points and existing benchmarks, before proceeding with the layout of the actual work.
Locate and protect existing benchmarks and control points. Preserve permanent reference points during construction.
2. Do not change or relocate benchmarks or control points without prior written approval. Promptly report lost or destroyed reference points, or requirements to relocate reference points because of necessary changes in grades or locations.
3. Promptly replace lost or destroyed project control points. Base replacements on the original survey control points.
4. Establish and maintain a minimum of two temporary benchmarks on the site, reference to data established by survey control points.
I. Staking: Acceptable staking placement intervals for the various construction survey control operations shall be approved by the CO prior to the beginning of work. Stationing shall be established in the field on centerline or an approved offset. The Contractor shall maintain staking throughout the duration of the project or until construction is complete for individual bid items. Restaking will be as needed or as directed by the CO. The Contractor shall alert the CO immediately if any irregularities are detected in the survey work.
J. Accuracy and Tolerances: Accuracy of surveys and survey tolerances shall be as specified in the Contract or the UDOT Survey Manual. If a discrepancy should occur, the higher degree of accuracy or the more restrictive tolerance shall apply.
K. Responsibility and Inspection: Supervision and coordination of construction surveying is the Contractor’s responsibility. The CO may inspect the Contractor’s surveying; however, such inspection will not relieve the Contractor of any responsibility for accuracy or completeness of work. The Contractor shall check the work to verify the accuracy and include documentation of this check in the Survey Records. All Contractor surveying inaccuracies, errors or omissions shall be corrected at the Contractor’s expense. The CO’s inspection or the Contractor’s corrections shall not entitle the Contractor to additional payment or contract time extension.
L. Changes: All changes in lines and grades required by field conditions and all discrepancies in grades, alignment, location or dimensions detected by the Contractor shall be immediately submitted to the CO in writing. No changes in given data or plans will be allowed unless approved by the CO in writing. All changes shall be documented in the survey records.
END OF SECTION 01 28 00
01 31 00
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Requests for Information (RFIs)
5. NPS/DSC Project Website
6. Project Meetings
7. Environmental Coordination
8. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
9. Commissioning activities
1.4 SUBMITTALS
A. Division 1 documents: The following items shall be submitted a minimum of one week prior to Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre- Construction Conference.
1. Letter designating Project Superintendent
2. Construction Schedule
3. A Comprehensive Schedule of Values
4. Accident Prevention Plan
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors
8. Waste Management Plan
9. Quality Control Plan
10. Utility Bypass Plans
11. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP)
12. Contractors Commissioning Plan
13. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from Government to complete permit application
B. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on NPS/DSC management software website.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete RFI Form on NPS/DSC Project Website as follows:
1. Enter general information at the top of the form.
2. Under the "Action" section at the bottom of the form, select "Question" then select "CMR" in drop-down of "Send to" box.
3. Enter details of question and attach related documents.
4. Select "Submit Form" at bottom of page.
D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.
1.6 PROJECT MEETINGS
A.…