A06_OLYM_215532_Final_Specifications_stamped-2024-03-25_Attachmnet__1.pdf

PDF 5 MB Posted

Attached to
Olympic National Park REHAB Wastewater Lagoons
Solicitation number
140P8325R0003
Issued by

About this file

This document is a comprehensive construction project manual for rehabilitating the wastewater lagoons at Olympic National Park's Kalaloch area in Washington. The project involves multiple key components including installing a manual headworks screen, floating dock systems for each lagoon cell, water depth markers, new lagoon aerators, fence repairs, a new effluent decanter, replacing the existing pump building with a precast concrete structure, installing effluent flow monitoring and sampling ports, and replacing the effluent spray field. Optional work includes road improvements and vegetation clearing.

The project will be constructed under a single prime contract with a focus on minimal disruption to the existing lagoon treatment system, potentially requiring temporary shutdowns or bypass pumping. The work must be coordinated with park personnel and the Contracting Officer, with specific constraints such as working only between two hours after sunrise and two hours before sunset during marbled murrelet nesting season (April 1 through September 23). The contractor will be responsible for environmental protection, wildlife considerations, and maintaining park operations throughout the rehabilitation process. Deliverables include detailed shop drawings, operation and maintenance manuals, and compliance with various environmental and construction specifications.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OLYMPIC

NATIONAL PARK

REHABILITATE KALALOCH WASTEWATER LAGOONS

OLYM

PMIS NO. 215532

CONSTRUCTION DOCUMENTS

PROJECT MANUAL

DIVISION 1

NATIONAL PARK SERVICE

PACIFIC WEST REGION

MARCH 2024

03.18.202403.25.2024

THIS PAGE IS INTENTIONALLY LEFT BLANK

OLYM-215532 TOC-1

012721

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work

01 26 01 Contract Modification Procedures

01 27 00 Definition of Contract Line Items

01 31 00 Project Management & Coordination

01 32 16 Construction Schedule

01 32 33 Photo Documentation

01 33 23 Submittal Procedures

01 35 05 Environmental Protection and Special Controls

01 35 13 Archeological Protection

01 35 23 Safety Requirements

01 40 00 Quality Requirements

01 50 00 Temporary Facilities and Controls

01 57 23 Temporary Storm Water Pollution Prevention

01 73 40 Execution

01 74 19 Construction Waste Management and Disposal

01 77 00 Closeout Procedures

01 78 23 Operation and Maintenance Data

01 79 00 Demonstration and Training

OLYM - 215532

01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work Phases.

3. Work Under Other Contracts.

4. Government Furnished Materials.

5. Contractor Use of Site.

6. Public Use of Site.

7. Occupancy Requirements for Buildings.

8. Conduct of Operations.

9. Work Restrictions.

10. Special Construction Requirements.

11. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: The project is located at the Kalaloch Area in Olympic National Park (OLYM) near Kalaloch, Washington.

B. The Work of this Contract consists of the following:

1. Installing manual headworks screen and changes to splitter box (Option A).

2. Adding floating dock system for each cell pond.

3. Installing water depth marker & level sensor with data logger.

4. Replacing aerators with new lagoon aerators.

5. Making fence repairs, adding signage, and removing vegetation at lagoon and spray field areas (Option C).

6. Installing new effluent decanter.

7. Replacing existing pump building with new precast concrete and effluent pump system, including all electrical and controls.

8. Adding effluent flow monitoring & sampling ports/stations.

9. Replacing existing effluent piping with chlorine contact pipe and de-chlorination system.

10. Replacing effluent spray field.

11. Improvements to access road (Option B).

01 11 00 - 2

C. Project will be constructed under a single prime contract.

1.3 WORK PHASES

A. The Work will be completed under a single phase.

B. The Work shall be coordinated with operation of the lagoon treatment system to allow for continuous operation of the plant.

This may involve temporary shutdowns, bypass pumping, or planning some portions of work during less busy time of the year. Work schedule must be coordinated with park personnel and

Contracting Officer.

1.4 WORK UNDER OTHER CONTRACTS

A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.

B. Existing NPS Operations: Conduct operations to ensure minimal impacts to NPS operators at the lagoon treatment system.

C. Park Operations: When the contractor activities are located adjacent to other Park Operations, Contractor shall conduct work to have minimal impact to these facilities or operations.

D. Preceding Work: None.

E. Concurrent Work: No other contract work is anticipated during this contract at this time.

1.5 GOVERNMENT-FURNISHED MATERIALS

A. None.

1.6 CONTRACTOR USE OF SITE

A. Contractor shall have limited use of site for construction operations. Limit use of premises to limits of construction indicated on drawings. Do not disturb areas beyond the limits of construction.

1. Limit site disturbance, including earthwork and clearing of vegetation, as shown on the drawings.

2. The Contractor shall keep operations confined to areas designated to be disturbed.

01 11 00 - 3

3. Contractor shall keep materials, equipment, and vehicles confined to designated staging areas as shown and minimize blocking road to treatment plant for park staff.

B. Storage of Materials: Confine storage of materials to designated staging areas identified on the Drawings.

C. Parking: Confine parking to within the contractor area approved by the CO and within the Limits of Construction noted in the drawings.

D. Stockpiling: Confine stockpiling to staging areas, within the

Limits of Construction, or within the limits of trenching as shown on the Contract Drawings. Refer to CD package for stockpiling size and coordinate with the CO to define height restrictions in specific areas.

E. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants.

Consult with Contracting Officer (CO) and the Park’s vegetation management specialist to identify tree roots, branches or other portions that may interfere with construction.

4. Tree trimming, root mitigation, and removal will be completed by Contractor. Provide ample time in the schedule to allow for coordination and completion prior to the commencement of work.

5. Do not fasten ropes, cables, or guys to existing trees.

6. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

F. Trails and Entrances: Keep trails and entrances serving premises clear and available to Government, Government’s employees and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize impacts to visitors.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

3. No mechanized ground transportation equipment is permitted on any non-paved trails.

01 11 00 - 4

G. Construction Camps: Establishment of construction camps is prohibited within the Park.

H. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. The Contractor shall be liable for damage which directly results from moving of equipment.

1. Load restriction on park roads matches nearby Washington road restrictions.

2. Deliveries to the site for the project shall be limited to weekday hours between 7:00 AM and 6:00 PM, and no

Holiday deliveries are permitted. Any deliveries outside of these restrictions shall be approved by the CO.

3. Heavy equipment access should be carefully considered and all loads entering and exiting the park shall be covered to ensure wildlife and visitor safety.

1.7 PUBLIC USE OF SITE

A. The work site is closed to the public but access and equipment delivery may impact public. Contractor shall at all times conduct operations to ensure the least inconvenience to the public, and shall incorporate CO approval and park input on any impacts to the public and park staff during construction.

1.8 CONDUCT OF OPERATIONS

A. At all times, the Contractor shall conduct their operations in conformance with the rules and regulations promulgated by the

Secretary of the Interior for the NPS, and applicable park rules and regulations prescribed by the Park Superintendent.

B. Work on Federal holidays, weekends, or at night may not be performed without prior consent from the CO. Submit requests 5 business days in advance of the work to the CO for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the CO.

D. Contractor shall abide by posted speed limits.

01 11 00 - 5

1.9 WORK RESTRICTIONS

A. On-Site Work Hours,

1. Limit work and deliveries to weekday hours of 7:00 AM to

6:00 PM, Monday through Friday, unless otherwise approved by CO.

a. If weekend hours are required: Specific work hours to be determined on a case-by-case basis when obtaining consent for weekend work from the CO.

2. Low traffic and low visitor times are weather dependent but are generally from October through April.

3. Hours and workdays for noise intensive activities shall be coordinated with the CO a minimum of 72 hours in advance. From April 1 through September 23, activities that produce noise above ambient levels shall be conducted between two hours after sunrise and two hours before sunset to minimize or prevent impacts to marbled murrelets.

4. Night work will not be permitted as part of this project.

Park quiet hours are between 9:00 PM and 6:00 AM.

B. Existing Utilities

1. Existing Utilities:

a. Existing utilities shown on the Drawings are based on data available from the NPS including previous projects and/or geographic information system data.

b. Notify the CO and utility companies of proposed locations and times for excavation.

c. Contractor shall notify CO about any unforeseen conditions and damage to unknown utilities.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, Contractor shall notify CO and get authorization prior to repairing utility at no additional expense to the

Government.

3. If damage occurs to an unknown utility, Contractor shall notify CO and get authorization prior to repairing utility. An equitable adjustment will be made in accordance with the Changes clause of the Contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions:

1. Notify the CO not less than fourteen (14) days in advance of proposed utility interruptions.

01 11 00 - 6

2. Do not proceed with utility interruptions without the CO’s written permission.

3. Hours for Utility Shutdowns: To be determined on a case-by-case basis with the CO.

4. Refer to Specification 01 73 40 – Execution for specific coordination requirements associated with outages, scheduling, and timing.

5. Shutdown duration: Utilities shall not be disconnected and out of operation without Contracting Officer’s written permission. A contingency plan shall be in place to re-instate service if work cannot be completed as planned.

Look ahead schedules are of critical importance for communicating shutdowns in advance.

a. Sanitary disruptions shall be coordinated and approved by the Park and CO.

b. Brief electrical disruptions, as defined in 01 73 40 shall also be coordinated with the utility Owner and the CO.

D. Tree removal shall occur between September 24 and March 31 to avoid habitat removal during the murrelet nesting season.

E. Fueling of any type, whether equipment or vehicles, must be done either on non-pervious surfaces such as concrete or asphalt, or deploy a spill containment pad.

F. Nonsmoking Building and Site Restrictions:

1. Smoking including vaping is prohibited inside any structure including buildings.

2. Smoking is permissible outdoors at designated smoking areas.

1.10 SPECIAL CONSTRUCTION REQUIREMENTS

A. None.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

OLYM - 215532 01 26 01 - 1

012721 CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition

Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with modifications.

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications

OLYM - 215532 01 26 01 - 2

will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate.

Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager (PM), Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal

Travel Regulations)

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent pickup trucks

C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General

Requirements:

1. Hoisting,

2. Material handling,

3. Temporary fencing,

4. Port-a-lets,

5. Trash removal, dumpsters,

6. Barricades,

7. Small tools,

8. Safety supplies,

9. Scaffolding,

10. Daily cleaning,

11. Traffic control,

12. Temporary signage,

13. Temporary heating and power.

OLYM - 215532 01 26 01 - 3

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a maximum 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker.

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security,

2) Medicare.

3) Workers Compensation– Policy and company calculation to be made available,

4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year,

5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year,

6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums,

2) Cell Phone,

3) Clothing,

4) 401K and Pensions,

5) Vehicle allowances,

6) Gas allowance,

7) Life insurance premiums,

8) Disability insurance,

9) Other Fringe Benefits required under an enforceable collective bargaining agreement.

D. Bonuses or Deferred Compensation: No Bonus or Deferred

Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

OLYM - 215532 01 26 01 - 4

E. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.

F. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

G. Builder’s Risk Insurance: Covers the Contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

H. Mobilization/Demobilization: Covers the work required to set up the construction site including but not limited to installation of a construction trailer, temporary utility connections, erection of temporary storage fencing or structures, as well as the removal of these elements at the end of the construction project.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Contractor’s proposal must be received in the format and within the time frame specified in the Request for

Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government

OLYM - 215532 01 26 01 - 5

provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact

Analysis (TIA). Contractor’s failure to submit within the specified time frame will be construed as the

Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the

Contracting Officer (CO) upon request.

5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate

(base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social

Security, unemployment insurances, workers compensation insurance, Federal Insurance

Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices shall include all applicable fees and credits, including but not

OLYM - 215532 01 26 01 - 6

limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region),

b. Construction Blue Book,

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance

(cost of major repair and overhaul is not allowed per

Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.

Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used in accordance with paragraph

1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If

Bluebook or local equipment pricing is accepted, then

1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the job site for up to five consecutive days may be classified at standby

OLYM - 215532 01 26 01 - 7

rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.

Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit

Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit. Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31 which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10%

Profit…………………7.5%

2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If Contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

OLYM - 215532 01 26 01 - 8

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 01 26 01

OLYM - 215532 01 27 00 - 1

012721 DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

C. Contract Line Item costs shall be developed such that individual Work Item prices, as defined in Section 3.1, can be determined by the Contracting Officer.

1.2 REFERENCES

A. 01 11 00 – Summary of Work.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item Number 1 Mobilization/ Demobilization

1. This item consists of mobilization and demobilization including installation of tree protection, silt fencing, site restoration, removal of trash, equipment, unused materials.

2. Final payment will be made at the contract lump sum price.

B. Contract Line Item Number 2 Demolition

1. This item consists of demolition and disposal of existing piping, pump building and all associated equipment, aerators, spray field piping valves and equipment, and concrete as shown.

2. Payment will be made at the contract lump sum price.

C. Contract Line Item Number 3 Lagoon Aerator System

OLYM - 215532 01 27 00 - 2

1. This item consists of replacing the existing lagoon aerators with new aerators including replacing enclosure, controls, wiring, anchors and cables, and conduit for a complete and operable system in conjunction with salvage and re-use of existing H-frame and disconnect switches.

2. Payment will be made at the contract lump sum price.

D. Contract Line Item Number 4 Floating Dock System and Depth

Marker

1. This item consists of constructing the floating docks at each of the lagoons including docks, ramps, anchoring system, and constructing the depth marker in lagoon 3.

2. Payment will be made at the contract lump sum price for all three docks and the depth marker.

E. Contract Line Item Number 5 Precast Concrete Building

1. This item consists of replacing the pump building with a new precast building including the site prep, building pad, building and building components including doors, vents, lights, building electric service, building electrical, eye wash system, rain water collection system, and all building appurtenances.

2. Payment will be made at the contract lump sum price.

F. Contract Line Item Number 6 Effluent System

1. This item consists of constructing the effluent pump system including floating decanter and decanter anchoring system; intake piping, effluent pumps and control system; piping, valves, sampling ports, and pressure gauges; disinfection system including chemical tanks, spill containment, and feed pumps; flow monitoring and level sensor and data logger; and all effluent, disinfection, and dechlorination piping to the sprayfield.

2. Payment will be made at the contract lump sum price.

G. Contract Line Item Number 7 Spray Field

1. This item consists of installing the effluent spray field including the header and distribution piping, risers, valves, hydrants, and impact heads, and clearing vegetation in the spray field area.

2. Payment will be made at the contract lump sum price.

H. Contract Line Item Number 8 – Option A - Manual Headworks

Screen

1. This item consists of constructing the manual headworks screen including the screen equipment, concrete, valves, OLYM - 215532 01 27 00 - 3 piping, modifications to the splitter box and piping as shown.

2. Payment will be made at the contract lump sum price.

I. Contract Line Item Number 9 – Option B – Turnaround and Road

Repairs

1. This item consists of constructing repairs to the access road to the spray field and lagoon areas including widening, grading, gravel, and reconstruction of turnarounds as shown on the drawings.

2. Payment will be made at the contract lump sum price.

J. Contract Line Item Number 10 – Option C - Fence Repairs, Signage, and Lagoon Vegetation Clearing

1. This item consists of repairing fencing around the lagoon system where indicated, adding warning signs and posts to the lagoons and spray field, installing concrete splash blocks under the overflow pipes, and clearing vegetation away from lagoon cell and fence areas.

2. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

OLYM - 215532 01 31 00 - 1

012721 PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions,

2. Construction Coordination,

3. Submittals,

4. Coordination Drawings

5. Requests for Information (RFIs),

6. Project Meetings,

7. Environmental Coordination, and

8. Permits.

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 35 05 “Environmental Protection and Special

Controls” for coordinating environmental requirements of the Contract.

3. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

4. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

5. Section 01 79 00 “Demonstration and Training” for coordinating training requirements for Wastewater

Facilities.

1.2 DEFINITIONS

A. AHJ: Authority Having Jurisdiction

B. Construction Permits – Contractor Provided

C. Government Furnished Permits

OLYM - 215532 01 31 00 - 2

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination.

Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the

Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule,

2. Preparation of the Schedule of Values,

3. Installation and removal of temporary facilities and controls,

4. Delivery and processing of submittals,

5. Progress meetings,

6. Permit requirements,

7. Project closeout activities, and

8. Commissioning activities.

OLYM - 215532 01 31 00 - 3

1.4 SUBMITTALS

A. Division 1 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction

Conference. The CO will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent

2. Construction Schedule

3. A Comprehensive Schedule of Values

4. Accident Prevention Plan

5. A List of Subcontractors for this project

6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.

7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors

8. Waste Management Plan

9. Quality Control Plan

10. Under-an-Acre Pollution Prevention Plan (UPPP)

11. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit

b. Agency(ies) with Jurisdiction issuing the permit

B. Information required from Government to complete permit application

C. All items listed must be provided to the CO before the Pre-

Construction Conference is held. If all of the documents have not been received one week prior to the scheduled Pre-

Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the CO will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the

Request for Information (RFI) form.

1. The CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

OLYM - 215532 01 31 00 - 4

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution: If Contractor's suggested resolution impacts the Contract Time or the

Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the

Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information:, in which case time for response will date from time of receipt of additional information.

OLYM - 215532 01 31 00 - 5

3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.6 PROJECT MANAGEMENT SOFTWARE (NOT USED)

1.7 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, CO will arrange a teleconference (e.g., Microsoft Teams or similar) meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Jobsite Safety.

4. Resolution of comments on required Division 01 documents.

5. Coordination of Subcontractors.

6. Labor law application.

7. Modifications.

8. Payments to Contractor.

9. Payroll reports.

10. Contract time.

11. Liquidated damages.

12. Contractor Performance Evaluation.

13. Display of Hotline posters.

14. Notice to proceed.

15. Correspondence procedures.

16. Acceptance/rejection of work.

17. Progress meetings.

18. Submittal procedures.

19. NPS Final Accessibility Inspection.

20. Environmental requirements.

21. Permit requirements.

22. As-constructed drawings/operation and maintenance (O&M) manuals.

23. Saturday, Sunday, holiday and night work.

24. Reference materials.

25. Value engineering.

26. Schedule of Values.

B. Progress Meetings: The Contracting Officer will schedule weekly or biweekly meetings with the Contractor. The

Contractor shall be responsible for preparing meeting

OLYM - 215532 01 31 00 - 6

agendas, facilitating progress meetings, taking notes, and distributing meeting minutes.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

1) Status of required inspections (Special

Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected

(Special inspections, Accessibility, etc.)

h. Construction Schedule update (provide updated

Critical Path Method (CPM)

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

1.8 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of the Waste Management Plan (WMP).

OLYM - 215532 01 31 00 - 7

c. Implementation of the Under-an-Acre Pollution

Prevention Plan (UPPP).

d. Training for Contractor personnel in accordance with their position requirements.

e. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements.

2. Regulatory Requirements.

3. Noise and Acoustics Management.

4. Temporary Storm Water Pollution Prevention

Environnemental Management.

5. Construction Waste Management.

C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:

1. Overview of environmental issues related to the Project.

2. Review of site specific procedures and management plans:

a. Construction Waste Management.

b. Noise and Acoustics Management.

c. Temporary Storm Water Pollution Prevention.

3. Compliance with environmental regulations: As specified in Regulatory Requirements. Submit Contractor 40 CFR

(Code of Federal Regulations) employee training records upon request of CO.

D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste

Management Plan (WMP), and Under-an-Acre Pollution

Prevention Plan (UPPP).

1.9 PERMITS

A. General:

1. Permits and Responsibilities: The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that

OLYM - 215532 01 31 00 - 8

occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the work.

2. For the purpose of this contract, the Contractor will not be considered an agent of the Government. Therefore, the Contractor will comply with the appropriate Federal, State and local laws.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 31 00

OLYM - 215532 01 32 16 - 1

012721 CONSTRUCTION SCHEDULE

SECTION 01 32 16 – CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The

Construction Schedule will assist the Contractor and

Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, mobilization and demobilization, a critical path and the requirements of this section.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path.

They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. Critical Path Method (CPM): CPM of planning and scheduling a construction project where activities are arranged based on

OLYM - 215532 01 32 16 - 2

activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Float: The measure of leeway in starting and completing an activity.

1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor, but is jointly owned.

2. Free Float: Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total Float: Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3 SUBMITTALS

A. Electronic Copies: All schedules and reports submitted shall be in PDF file format sent via email to the Contracting

Officer.

B. Schedule of Values: After contract award and before the Pre-

Construction conference, submit a schedule of dollar values based on the Contract Price Schedule.

C. Construction Baseline Schedule: Schedule shall be submitted within 30 calendar days following contract award and before the Pre-Construction conference. Submit the baseline schedule, large enough to show entire schedule for entire construction period. Utilize Schedule of Values in preparation of Construction Baseline Schedule.

D. Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data.

OLYM - 215532 01 32 16 - 3

1.4 QUALITY ASSURANCE

A. The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:

1. Discuss constraints, including traffic control, phasing, work stages, area separations, interim milestones, and partial Government occupancy/substantial completions

2. Review delivery dates for Government-furnished products.

3. Review schedule for work of separate Government contracts.

4. Review time required for review of submittals and re-submittals.

5. Review requirements for tests and inspections by independent testing and inspecting agencies.

6. Review time required for completion and startup procedures.

7. Review and finalize list of construction activities to be included in schedule.

8. Review baseline schedule comments, resolve issues and progress on incorporating them

9. Review procedures for updating schedule.

10. Discuss reporting requirements and establish a protocol for naming and transmitting electronic schedules.

B. Contractor's Schedule Representative: Before or at the preconstruction conference, designate an authorized representative to be responsible for the preparation and maintenance of the Construction Schedule. The authorized representative will be responsible for preparing the Baseline

Schedule, all required updates, revisions, and preparation of reports.

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.

B. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. In developing the Construction Baseline Schedule, ensure that the Subcontractor’s work at all tiers, as well as the prime Contractor’s work, is included and coordinated.

OLYM - 215532 01 32 16 - 4

2. Secure time commitments for performing critical elements of the Work from parties involved.

3. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 - PRODUCTS

2.1 SCHEDULE OF VALUES

A. Breakdown each lump-sum item into component work activities used in the schedule for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include general condition costs, overhead or profit as a separate item.

B. Do not break down unit price items. Use only the contract price for unit price items.

C. The total cost of all items shall equal the contract price.

The Schedule of Values will form the basis for progress payments and the Construction Schedule.

D. An acceptable Schedule of Values shall be agreed upon by the

Contractor and CO before the first progress payment is processed.

2.2 CONSTRUCTION SCHEDULE REQUIREMENTS

A. Construction Baseline Schedule: Prepare Construction Baseline

Schedule using a computerized, cost and resource-loaded, time-scaled CPM network analysis diagram for the Work.

1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than 30 days after date established for the Notice of Award.

a. Failure to include any work item required for performance of this Contract shall not excuse

Contractor from completing all work within applicable

OLYM - 215532 01 32 16 - 5

completion dates, regardless of Governments acceptance of the schedule.

2. Establish procedures for monitoring and updating

Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.

B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the preliminary CPM network diagram, prepare a skeleton network to identify probable critical paths.

1. Activities: Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.

2. Critical Path Activities: Identify critical path activities, including those for interim completion dates.

Scheduled start and completion dates shall be consistent with Contract milestone dates.

3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.

4. The Construction Baseline Schedule as developed shall show the sequence and interdependence of activities required for complete performance of the work. Ensure all work sequences are logical and the Construction Baseline

Schedule shows a coordinated plan of the work.

5. Resource loading of each activity shall include all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown.

6. Consider seasonal weather conditions in planning and scheduling all work influenced by high and low ambient temperatures, wind, or precipitation to ensure completion of all work within the contract time.

7. Time Frame: Proposed duration assigned to each activity shall be the…

This is the start of the file's text. The full file is on GovTribe.