This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for the Olympic National Park's Kalaloch Lagoons Rehabilitation project. Amendment 0003, effective 04/22/2025, extends the Request for Proposal (RFP) deadline from May 28th to June 4th, 2025 at noon Pacific time. The contracting office will continue to accept vendor questions until May 22, 2025 at noon, and has incorporated Clause 52.225-21 regarding the Required Use of American Iron, Steel, and Manufactured Goods under the Buy American Statute for construction materials. The amendment also references attachment #17, which provides responses to previous contractor questions, and makes no other substantive changes to the original solicitation.
The contract opportunity is for rehabilitation work at the Kalaloch Lagoons within Olympic National Park, with a performance period from 06/16/2025 to 12/31/2025. Previous amendments (0001 and 0002) clarified evaluation criteria, revised various attachments including past performance questionnaires and project experience documents, and addressed vendor questions from a site visit. The solicitation is being issued by the National Park Service, Pacific West Region, located in Port Angeles, Washington.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P8325R0003 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PPY
Port Angeles WA 98362-6757 600 E. Park Avenue
NPS, PWR - OLYM MABO
04/22/20250003
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
04/22/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
OLYMPIC National Park
REHAB KALALOCH LAGOONS
Purpose of Amendment 0003 is to provide responses to contractor question (attachment #17) and extend the RFP FROM May 28th TO; 6/04/2025 Noon PD. CO will accept more questions up to
May 22, 2025, NOON.
Also to incorporate Clause: 52.225-21 Required Use of American Iron, Steel, and
Manufactured Goods-Buy American Statute-Construction Materials. JAN 2021. Under Section
I-Contract Clauses.
NO other Change
END of AMEND 0003
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Geraldine Larsen
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P8325R0003/0003
Purpose of Amendment 0002 is to provide clarification to vendor questions. New attachments #12-#16.
Please make sure that you use these revised documents when submitting your proposal.
Revised documents:
Attachment # 12: Revised Clauses and Provisions attached separately, error: changes days from 365 to 200 days to allow for Holidays. POP 6/16/2025-
12/31/2025 remains the same.
Attachment #13: Section L: Clarified how proposals will be evaluated.
Attachment #14: Revised Section M: Clarified how proposals will be evaluated.
Attachment #15: REVISED PAST PERFORMANCE
QUESTIONNAIRE: Attachment 4 Revised, to reflect the correct close date.
Attachment #16: REVISED Project Experience
Questionnaire: Revised header.
No other Change
END of AMENDMENT 00002.
Purpose of Amendment 0001 is to provide response to vendor questions from site visit, also attached is the sign-in sheet.
NO OTHER CHANGE
END of AMEND 0001
Period of Performance: 06/16/2025 to 12/31/2025
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)