This document is a request for proposal for replacement of the HVAC system at the Waubay National Wildlife Refuge office in Waubay, South Dakota. The U.S. Fish and Wildlife Service is seeking proposals to remove the existing HVAC equipment installed in 1983 and 2004, which utilizes geothermal systems, and install a new high-efficiency HVAC system per the attached statement of work and drawings. Proposals are due by March 15, 2024 and the contract will be awarded based on lowest price technically acceptable. The work must be completed within 120 days of the notice to proceed. The contractor must be licensed in South Dakota and all work must comply with state and national codes for mechanical, electrical, plumbing and energy efficiency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140FC124R0035_Amd_0003.pdf | ||
| Waubay_-_Main_Level_Areas_Square_Footage_0003.pdf | ||
| Sol_140FC124R0035_Amd_0002.pdf | ||
| Sol_140FC124R0035_Amd_0001.pdf | ||
| WD___SD20240021__Day_County_Building_01-05-2024.pdf | ||
| Sol_140FC124R0035.pdf | ||
| A06_Drawings_-_22-009_Waubay_HVAC.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Statement of Work
Installation of HVAC System Office Building
Waubay National Wildlife Refuge, Waubay, South Dakota
1.0 Introduction and Overview
Waubay National Wildlife Refuge is a National Wildlife Refuge in South Dakota. "Waubay" means "a place where numbers of birds make their nests" in the Dakota language. The Refuge encompasses 4,650 acres of wetlands, native tallgrass prairie, and bur oak forest that provide a wide variety of nesting habitat for more than 100 species of waterfowl, song birds, and upland game birds as well as 140 additional bird species during migrations. Mammals include species from the ever-present white-tailed deer to the more elusive coyote and the diminutive pygmy shrew. The central location of Waubay National Wildlife Refuge in North America gives visitors the chance to see a mix of eastern, western, northern, and southern species.
Replace the existing HVAC systems at Waubay NWR office and equipment with a properly designed, high efficiency system that can meet proper comfort and environmental control levels within the building.
The office was constructed in 1983 and an addition was built on to the structure in 2004. The office utilizes two separate HVAC systems, one installed in 1983, which has one HVAC unit utilizing a geothermal system with propane backup and one installed in 2004 with two HVAC units utilizing a separate geothermal system. However, the systems are not functioning properly resulting in an extremely inefficient heating and cooling throughout the facility. Portions of the office never receive adequate heating regardless of thermostat settings due to the overall HVAC design. Service technicians have indicated the only way to solve the issue is to install new HVAC system/units. In addition, HVAC units have been repeatedly serviced and have reached life expectancy.
1.1 Scope of Work
Remove existing HVAC Systems installed in 1983 and 2004 (geothermal units) and design / furnish / install a new and appropriately sized system. The new systems should be a 90% energy efficient and include a system to clean the air and kill airborne virus and bacteria (to include Covid 19) such as the GPS Needle Point Bi-Polar Ionization System or an approved equivalent. The Office Building is a single-story building built over a basement with approximately 5,450 square feet with several offices and large conference rooms.
1. The completed system shall be tested for proper operation upon completion of installation. The new HVAC control system shall communicate with all the air handlers, pump, and valves, etc.
seamlessly and efficiently, providing staff a comfortable work environment year-round.
2. The contractor shall be licensed in the state of South Dakota. All work and testing shall be in accordance with the International Mechanical Code (IMC 2021) and International Energy Conservation Code (IECC 2018). Duct work shall be performed in accordance with NFPA90B.
Electrical work shall be in accordance with NFPA National Electrical Code 2017.
3. The contractor shall inspect buildings, perform, and submit load calculations (ACCA Manual N) and confirm that the specified system will be efficient and provide adequate capacity.
4. The contractor shall submit any necessary Architectural, Structural, Mechanical, Electrical or Plumbing drawings in CAD or PDF format to the Project Manager prior to construction or upon request of the Project Manager.
https://en.wikipedia.org/wiki/National_Wildlife_Refuge https://en.wikipedia.org/wiki/South_Dakota https://en.wikipedia.org/wiki/Dakota_language https://en.wikipedia.org/wiki/Wetland https://en.wikipedia.org/wiki/Tallgrass_prairie https://en.wikipedia.org/wiki/Bur_oak https://en.wikipedia.org/wiki/Waterfowl https://en.wikipedia.org/wiki/White-tailed_deer https://en.wikipedia.org/wiki/Coyote https://en.wikipedia.org/wiki/American_Pygmy_Shrew
5. The contractor shall maintain and protect existing facilities from damage during all work.
· Protect building structure and interior from weather and water leakage and damage.
· Locate, identify, shutoff or disconnect utility services prior as needed.
· Notify the facility manager in advance of power and/or water disconnections
5. All system components shall be from the same manufacturer, including controls.
1.2 Period of Performance
The work shall be completed in 120 days from notice to proceed.
1.3 Project Safety
The Contractor shall be responsible for strict compliance with all provisions of Occupational Safety and Health Administration (OSHA) requirements 29 CFR 1910 and 29CFR 1926 during performance of the work.
2.0 Project Requirements
A. All work will adhere to local building codes. All work and materials shall be in compliance with all applicable building codes, and the applicable performance standards:
1. American Society of Mechanical Engineers (ASME)
2. American Society for Testing Materials (ASTM)
3. National Electric Code (NEC), National Energy Conservation Code (NECC), & International Mechanical Code (IMC).
4. Air-Conditioning, Heating, and Refrigeration Institute (AHRI)
5. American Society of Heating, Refrigerating and Air Conditioning Engineers (ASHRAE)
B. Field Measurements:
On site field investigation and measurements shall be made prior to procurement of the new HVAC system, to ensure that the proposed mechanical equipment will fit the site of the installation.
C. HVAC Equipment and appurtenant work:
The Contractor shall furnish and install all required equipment to include piping, valves, electrical wiring, switches, and appurtenant items as required for a fully functional energy efficient (95% minimum) HVAC system.
D. HVAC equipment shall meet the following performance requirements:
1. Provide and install a new HVAC system for heating, ventilation, and cooling. The HVAC system shall be in compliance with the following applicable performance standards: Air- Conditioning, Heating, and Refrigeration Institute (AHRI), and the American Society of Heating, Refrigerating and Air Conditioning Engineers (ASHRAE).
2. The Contractor shall provide all required adjustments or components so the HVAC unit will properly function when installed. Contractor shall replace the insulation that has been removed.
Provide and install all incidental materials required to install the HVAC unit, including piping, valves, regulators, electrical wiring, switches, connections, drain pan, air filters, and compatible thermostats.
3. The system shall be a minimum 90% energy efficient Energy Star rated.
4. Upon completion of the installation, the HVAC system shall be complete and fully operational.
Perform startup operations with the presence of Refuge personnel.
5. The installer shall provide training to refuge personnel on operation and maintenance needs of the system. O&M manuals shall be provided to the refuge personnel.
6. All workmanship and function of the system shall be warranted for one year. All equipment warranties shall be provided to the Refuge personnel upon completion of the work.
7. Provide to the Service a one-year maintenance contract covering system components and operability.
E. HVAC system installation requirements:
1. All ductwork, equipment, and system installation shall be performed per industry standards and NECC code requirements.
2. Any installation through walls or ceilings shall be patched and painted by the contractor to match existing.
3.0 Material Submittals
A. Material submittals consisting of manufacturer's product information shall be provided for Government approval before any materials are installed on this project.
4.0 End Results/Deliverables
A. Provide and install all materials required to install the HVAC system. Upon completion of the installation, the HVAC system shall be fully operational. Provide all Operations and Maintenance Manuals to the Refuge, including warranty information on the parts.
B. Upon completion of the project, all work areas shall be free of rubbish and debris. All old radiant heating equipment will be removed, disposed, and recycled per federal and state laws.
5.0 Special considerations
1. Technical / government liaison for this contract:
Michael LeMieux 134 Union Blvd, Lakewood, CO 80228 303-681-5731 michael_lemieux@fws.gov
Normal working hours for Facility Staff are from 7:00 AM to 3:30 PM Monday through Friday except for Government holidays and special events.
2. Contractor allowable work hours are 7AM to 6:00 PM Monday through Friday.
3. Weekend work is acceptable from 8:00 am to 6:00 pm. Any work on weekends must be scheduled in advance and must be approved by the Contracting Officer and at the Station Managers discretion and availability.
4. No work will take place over Federally observed holidays.
mailto:michael_lemieux@fws.gov
5. Building shall be occupied by refuge personnel through-out the contract period. Coordination of work with refuge staff will be necessary.
| Waubay National Wildlife Refuge is a National Wildlife Refuge in South Dakota. "Waubay" means "a place where numbers of birds make their nests" in the Dakota language. The Refuge encompasses 4,650 acres of wetlands, native tallgrass prairie, and bur o... |
| Remove existing HVAC Systems installed in 1983 and 2004 (geothermal units) and design / furnish / install a new and appropriately sized system. The new systems should be a 90% energy efficient and include a system to clean the air and kill airborne v... |
| 1. The completed system shall be tested for proper operation upon completion of installation. The new HVAC control system shall communicate with all the air handlers, pump, and valves, etc. seamlessly and efficiently, providing staff a comfortable wo... |
| 2. The contractor shall be licensed in the state of South Dakota. All work and testing shall be in accordance with the International Mechanical Code (IMC 2021) and International Energy Conservation Code (IECC 2018). Duct work shall be performed in a... |
| 3. The contractor shall inspect buildings, perform, and submit load calculations (ACCA Manual N) and confirm that the specified system will be efficient and provide adequate capacity. |
| 4. The contractor shall submit any necessary Architectural, Structural, Mechanical, Electrical or Plumbing drawings in CAD or PDF format to the Project Manager prior to construction or upon request of the Project Manager. |
| 5. The contractor shall maintain and protect existing facilities from damage during all work. |