A04_SOW_BLRI_Repair_chinking___stain_3_Cabins_20250924.docx

DOCX document 23 KB Posted

Attached to
BLRI-STAIN REPAIR CHINKING B828, 832, 545
Solicitation number
140P5126Q0018
Issued by

About this file

This is a Statement of Work (SOW) for the repair of chinking and staining of three log cabins located at Blue Ridge Parkway campgrounds. The National Park Service seeks restoration services for cabins at Price Park Campground B545 (Mile Post 296.9), Crabtree Falls Campground B832 (Mile Post 339.4), and Mt. Pisgah Campground B828 (Mile Post 408.6). The contractor must remove and replace deteriorated chinking totaling 1,794 linear feet across all three cabins and power wash, prep, and stain 3,032 square feet of log and siding surfaces. Additionally, the contractor shall stain window and door trim at each cabin (12 windows and 6 doors total) using exterior-grade primer and two coats of park-approved low-VOC trim paint. Chinking materials must be a compatible synthetic system such as Sashco Log Jam or approved equivalent, and stain must be breathable, low-VOC, semi-transparent log stain such as Perma-Chink Ultra-2 or equivalent in a park-approved color. All work must comply with National Park Service conservation standards and the Secretary of the Interior's Standards for Rehabilitation, as well as standards including OSHA 29 CFR 1926, ASTM C920, and EPA VOC requirements.

The period of performance is 120 calendar days from contract award. Work hours are restricted to Monday through Friday, 8:00 a.m. to 4:30 p.m., with no weekend or holiday work permitted. The contractor must submit a critical path schedule with milestones, site-specific Accident Prevention Plan, material specifications, and access/staging diagrams 15 days prior to mobilization. The related solicitation (140P5126Q0018) is a total small business set-aside issued as a Request for Quote under FAR 13 negotiated procedures for a Firm-Fixed Price Contract. The principal NAICS code is 238320 (Painting and Wall Covering Contractors) with a $19 million size standard. All offerors must have a valid UEI number and be registered with SAM.gov.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

Project Title: Repair Chinking and Staining of Cabins – Blue Ridge Parkway Location:

Price Park Campground B545 can be accessed at Mile Post 296.9 Crabtree Falls Campground B832 can be accessed at Mile Post 339.4 *Please note Crabtree Falls cabin will only be accessible from Highway 80, they are still working on the damaged roadway from Hurricane Helen.

Mt. Pisgah Campground B828 can be accessed at Mile Post 408.6

PART 1 – GENERAL

ITEM 1 – DESCRIPTION OF WORK

1.1 Background:

The log cabins located at Price Park B545, Crabtree Falls B832, and Mt. Pisgah Campgrounds B828 on the Blue Ridge Parkway have experienced progressive weathering, deteriorated chinking, and fading of protective wood stain due to prolonged environmental exposure. These cabins are vital assets to the housing program at BLRI and are a huge asset to being able to hire seasonal employees that care for our campgrounds and thousands of visitors. This project aims to restore the cabins' weather resistance and aesthetics through the complete removal and replacement of failed chinking and the application of an approved semi-transparent stain to all log and siding surfaces.

1.2 Work Covered by the Contract Documents:

The contractor shall provide all labor, materials, equipment, and supervision to perform the following work under a single lump-sum contract:

· Stain window and door trim at each cabin (each cabin has 4 windows and 2 doors, total: 12 windows and 6 doors). This work shall include surface cleaning, masking, application of exterior-grade primer as needed, and two coats of park-approved low-VOC trim paint. Execution details are provided under Phase 3 – Staining.

· Cabin 1 – Price Park Campground B545:

· Remove deteriorated chinking and install new synthetic chinking: 622 linear feet

· Power wash, prep, and stain logs/siding: 1,010 square feet

· Cabin 2 – Crabtree Falls Campground B832:

· Remove deteriorated chinking and install new synthetic chinking: 545 linear feet

· Power wash, prep, and stain logs/siding: 1,005 square feet

· Cabin 3 – Mt. Pisgah Campground B828:

· Remove deteriorated chinking and install new synthetic chinking: 627 linear feet

· Power wash, prep, and stain logs/siding: 1,017 square feet Work shall comply with National Park Service conservation standards and Secretary of the Interior’s Standards for Rehabilitation. Chinking shall be a compatible synthetic system (e.g., Sashco Log Jam or approved equal) matching original appearance and texture. Stain shall be breathable, low-VOC, semi-transparent log stain (e.g., Perma-Chink Ultra-2 or equivalent) in a park-approved color.

Period of Performance:

All work shall be completed within 120 calendar days from time of award.

ITEM 2 – EXISTING UTILITIES

2.1 Contractor shall contact the Contracting Officer and local utility authorities for utility locating services before any anchoring or drilling activities.

2.2 The contractor is responsible for the protection of all known and discovered utilities. All damages shall be reported and repaired at no cost to the Government.

2.3 Water and power will be provided by the park at each cabin site. Contractor shall coordinate with the COR during the preconstruction conference for utility access logistics and connection points.

ITEM 3 – CONTRACTOR’S USE OF PREMISES

3.1 Project access shall be confined to designated parking and driveway areas. Do not disturb adjacent vegetation or trails.

3.2 Working hours are Monday–Friday, 8:00 a.m.–4:30 p.m. Work on weekends or holidays will not be permitted.

3.3 Storage and staging are limited to pre-approved laydown areas adjacent to each cabin. Protect all resources, trees, and surfaces during performance.

ITEM 4 – COMMENCEMENT, PROSECUTION, AND COMPLETION

4.1 Contractor must submit a critical path schedule with milestones for mobilization, chinking removal, surface prep, chinking install, staining, and final inspection.

4.2 Work shall commence once contract is award.

ITEM 5 – EXAMINATION OF THE SITE

5.1 Site visits are highly encouraged. Contractor shall be held responsible for understanding terrain, access constraints, and logistics at each location.

ITEM 6 – ABBREVIATIONS

Standards referenced include, but are not limited to:

· OSHA 29 CFR 1926

· ASTM C920 (Sealants/Chinking)

· EPA VOC Requirements

· Secretary of the Interior’s Standards for Treatment of Historic Properties

· NFPA 241

· ANSI Z117

· NECA 1

ITEM 7 – ACCIDENT PREVENTION

7.1 Submit a site-specific Accident Prevention Plan (APP). Include first-aid, emergency contacts, equipment hazard mitigation, and PPE use.

7.2 All employees must wear ANSI-compliant PPE. Safety meetings must be held weekly and documented.

ITEM 8 – PRECONSTRUCTION CONFERENCE

8.1 Contractor shall attend the pre-conference meeting and submit:

· Project schedule

· APP

· Material cut sheets (chinking, stain)

· Subcontractor list

· Equipment sanitation protocol

ITEM 9 – SUBMITTALS

9.1 Submit the following 15 days prior to mobilization:

· Color samples and manufacturer datasheets for proposed stain

· Chinking product specs

· Work schedule

· Site Specific Safety Plan (see attached instructions and checklist from the NPS safety manual)

· Access/staging diagram

ITEM 10 – TEMPORARY SERVICES

10.1 Water and power will be provided by the park. The contractor shall provide their own portable toilets and refuse dumpsters for the duration of the project and shall coordinate their placement with the COR during the preconstruction conference.

ITEM 11 – PROJECT CLOSEOUT

11.1 Submit:

· Completion photos

· Product warranties

· Material usage logs

· Chinking installation verification (depth, bond-breaker use, tooling)

11.2 Final inspection by COR required. All punch list items must be resolved within 10 calendar days.

PART 3 – EXECUTION

Phase 1 – Mobilization and Surface Prep

· Sanitize equipment to prevent introduction of invasive species in accordance with Blue Ridge Parkway’s Invasive Species Management Policy (refer to NPS BRP-ISMP 2022 or consult with COR for current version). per Executive Order 13112.

· Use low-impact access and avoid rutting soft soils.

· Protect cabin grounds, vegetation, and adjacent cultural features with plywood or geotextile mats.

Phase 2 – Chinking Removal

· Use non-damaging hand tools or pneumatic chisels with chisels designed for logwork.

· Remove all loose, cracked, or deteriorated chinking back to solid bond lines.

· Clean log surfaces with compressed air and vacuum debris.

Phase 3 – Staining

· Mask logs, windows, trim, and hardware.

· Power wash logs using 1,200–1,500 PSI. Allow drying to <18% MC.

· Apply log stain with airless sprayer followed by back-brushing per manufacturer’s instructions. Two coats minimum, allowing proper curing time between coats.

Phase 3A – Trim Painting

· Clean and prepare all window and door trim surfaces.

· Apply primer where necessary for adhesion and durability.

· Apply two coats of low-VOC, exterior-grade trim paint in a park-approved color.

· Use brushes or rollers suited to the trim material for precision application.

· Allow adequate drying time per manufacturer’s instructions between coats. Mask windows, trim, and hardware.

· Power wash logs using 1,200–1,500 PSI. Allow drying to <18% MC.

· Apply stain with airless sprayer followed by back-brushing per manufacturer’s instructions. Two coats minimum, allowing proper curing time between coats.

Phase 4 – Chinking Installation

· Install backer rod as per ASTM C1193 to control depth and adhesion profile.

· Apply chinking with sausage guns or bulk loaders.

· Tool chinking smooth with water-dampened spatulas to ensure full adhesion and uniform profile.

· Thickness minimum 3/8", width varies by joint condition.

· Cure for minimum 72 hours. Avoid rain and dust exposure during curing.

Phase 5 – Site Cleanup and Final Inspection

· Remove all masking, staging, and surplus materials.

· Restore staging areas to original condition.

· COR to conduct final walkthrough using NPS Final Inspection Checklist.

· Submit warranty, photos, and closeout documents.