This is a Statement of Work (SOW) for technical repair services to upgrade the security system at the Bureau of Land Management's Cody Field Office in Cody, Wyoming (1002 Blackburn Street, Cody, WY 82414).
The Contractor must complete security system repairs and upgrades within 90 days of contract award. The primary scope includes: replacing RS-485 Reader Expansion Board (RREB) and Secure Network Interface Board 3 (SNIB3) in the existing controller; installing five FICAM-compliant uTrust TS SC Keypad Contact Readers (or approved equal) at three building access points and two warehouse yard gates; integrating new readers with Identiv's Velocity software; and conducting comprehensive testing to ensure optimal functionality. All labor, materials, tools, transportation, supervision, and technical expertise must be provided by the Contractor at a fixed price with no separately reimbursable travel or Other Direct Costs (ODCs) authorized. Standard work hours are 8:00 a.m.–4:30 p.m., Monday–Friday, with flexible hours between 7:00 a.m. and 7:00 p.m. available with verbal government approval. After-hours work or utility disruptions require written authorization with 48 hours' advance notice.
Deliverables due within 10 business days of project completion include: Installation Work Summary Report, Software Update Confirmation, Functional Testing Report, Updated Inventory List, System Configuration Change Log, As-Built Updates, and a Final Project Completion Package consolidating all documentation. The Government will review deliverables within five days, with the Contractor required to submit revisions within five days of receiving comments. The Government furnishes the existing Identiv Velocity system, pre-installed wiring to five reader locations, building infrastructure, and facility access via escorts (no permanent credentials); all card readers, mounting equipment, and installation materials are the Contractor's responsibility. The Contractor must comply with BLM facility security procedures, visitor badge requirements, escort requirements in restricted areas, and safety guidelines; alarms and security devices cannot be disabled without COR approval. All project information, data, and observations are Government property and cannot be released publicly without written authorization from the Contracting Officer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions_Addressed_0001.docx | DOCX document | |
| Sol_140L6226Q0025_Amd_0001.pdf | ||
| Sol_140L6226Q0025.pdf | ||
| B03-_Wage_Determination_Park_Co.pdf | ||
| Evaluation_Factors_for_Award_Cody_Security_System_Repairs_20260622.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bureau of Land Management
Cody Field Office
CYFO Security System Repairs
Statement of Work for
Technical Repair Services
June 2026
0.0 Contents
1.0 General
1.1 Introduction
1.2 Objectives
1.3 Scope of Work
1.4 Period of Performance
1.5 Place of Performance
1.6 Hours of Operation
1.7 Federal Holidays
1.8 Applicable Documents
2.0 Specific Requirements
2.1 System Support
2.2 Card Reader Installation
2.3 Controller and Infrastructure
2.4 Software, Programming, and System Configuration
2.5 Testing and Verification
2.6 Documentation and Reporting
2.7 Coordination Requirements
3.0 Deliverables
3.1 Deliverables Summary Table
3.2 Draft and Final Deliverable Review Timelines
4.0 Meetings
4.1 Post-award Kickoff Meeting
4.2 Intermittent Project Status Reviews
5.0 Required Travel and Other Direct Costs
5.1 Travel Not Authorized
5.2 Other Direct Costs (ODCs)
6.0 Government Furnished Property/Equipment/Information
6.1 Government Furnished Property (GFP)
6.2 Government-Furnished Facility Access
6.3 Government-Furnished Information (GFI)
6.4 Government-Furnished Utilities and Workspace
6.5 Inspection and Responsibilities
7.0 Special Instructions
7.1 Contractor Personnel Security Requirements
7.2 Safety and Security Requirements
7.3 Access to Government Systems and Information
7.4 Installation Constraints and Coordination Requirements
7.5 Protection of Government Property and Facilities
7.6 Prohibition of Unauthorized Public Release
8.0 Glossary and Acronyms
8.1 Definitions
8.2 Acronyms
CYFO Security System Repairs Page 4 of 14 Technical Repair Services SOW
Statement of Work for Technical Repair Services
1.0 General
1.1 Introduction
The Bureau of Land Management (BLM) Cody Field Office requires technical maintenance services to repair and upgrade its security systems. This includes replacement of controller boards, installation of FICAM-compliant card readers, integration with Identiv’s Velocity software, and comprehensive testing to ensure optimal functionality and enhanced security.
1.2 Objectives
1.2.1 Replace SNIB and RREB boards in the security system controller and install/integrate five (5) FICAM-compliant Keypad Contact Readers to enhance security at three building access points and two ware yard gates.
1.2.2 Ensure successful integration with the existing Identiv Velocity access control system.
1.3 Scope of Work
The Contractor must provide all labor, materials, tools, transportation, supervision, and technical expertise required to:
1.3.1 Confirm diagnosis and solution for door access issues.
1.3.2 Replace RS-485 Reader Expansion Board (RREB).
1.3.3 Replace Secure Network Interface Board 3 (SNIB3).
1.3.4 Test and program all replaced components.
1.3.5 Install five (5) FICAM-compliant uTrust TS SC Keypad Contact Readers (or approved equal).
1.3.6 Integrate new card readers with Identiv’s Velocity software.
1.3.7 Enhance security at specified access points (3 building locations, 2 ware yard gates).
1.3.8 Conduct comprehensive testing to ensure all card readers function optimally with the existing security system.
1.4 Period of Performance
The contractor must complete the installation and software integration within 90 days from the date of award.
1.5 Place of Performance
Cody Field Office, 1002 Blackburn Street, Cody, WY 82414
CYFO Security System Repairs Page 5 of 14
1.6 Hours of Operation
Normal work hours are 8:00 a.m.–4:30 p.m., Monday–Friday. Flexible hours to allow disruptive work activities to be performed outside of normal duty hours may be allowed between 7:00 a.m.
and 7:00 p.m. without a formal written request, provided the on-site Government representative grants verbal approval prior to the start of the activity.
After-hours work or activities requiring utility disruptions must be coordinated with the
Government and require written approval in advance. The Contractor must provide notice forty-eight (48) hours before any interruption in any utility. No utility shutdown may occur without
Government authorization.
1.7 Federal Holidays
The Contractor is not required to perform work on federal holidays. Refer to the U.S. Office of
Personnel Management’s website at https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/ for the current schedule.
1.8 Applicable Documents
1.8.1 BLM Facility Security Plans (post-award)
1.8.2 OEM documentation for Identiv system (post-award)
2.0 Specific Requirements
2.1 System Support
The Contractor must perform all installation, wiring verification, programming, integration, and testing activities required to complete the repairs described in Section 1.
2.2 Card Reader Installation
The Contractor must:
2.2.1 Install Government‑designated FICAM‑compliant card readers and associated hardware.
2.2.2 Install all readers at locations identified by the COR.
2.2.3 Utilize existing wiring previously pulled from the control panels to each reader location, verifying proper termination and continuity prior to installation.
2.2.4 Mount, connect, and physically secure all readers in compliance with OEM and BLM requirements.
2.3 Controller and Infrastructure
The contractor must
2.3.1 Ensure all newly installed devices are properly connected to the existing access‑control infrastructure.
2.3.2 Verify proper RS‑485 communication pathways and ensure compatibility with system controller hardware.
https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/ https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/
CYFO Security System Repairs Page 6 of 14
2.3.3 Confirm that all wiring integrity meets OEM specifications and correct any deficiencies discovered during verification.
2.4 Software, Programming, and System Configuration
The Contractor must:
2.4.1 Update Identiv’s Velocity software to recognize, manage, and fully integrate the newly installed card readers.
2.4.2 Program access levels, schedules, permissions, and required configurations for each new access point.
2.4.3 Ensure programming supports proper device operation; functional verification will occur under Section 2.5.
2.4.4 Coordinate with the COR before making any configuration changes that may impact system availability.
2.5 Testing and Verification
The Contractor must:
2.5.1 Conduct comprehensive testing of all newly installed components, including badge‑read tests, system communication, alarm inputs, and controller responses.
2.5.2 Confirm that all installed card readers operate seamlessly within the existing security system architecture.
2.5.3 Document all test results and any corrective actions taken.
2.5.4 Provide confirmation that system performance meets contract requirements.
2.6 Documentation and Reporting
The Contractor must submit documentation to the COR in accordance with Section 3
(Deliverables).
2.7 Coordination Requirements
The Contractor must:
2.7.1 Coordinate site access and schedules with the COR.
2.7.2 Minimize operational disruptions during installation.
2.7.3 Notify the COR prior to any activity that may affect system availability.
CYFO Security System Repairs Page 7 of 14
3.0 Deliverables
Timely submission of deliverables and reports is essential for successful completion of this requirement. All deliverables must be prepared and submitted as specified in this section. The
Contractor must deliver all reports electronically to the COR unless otherwise directed by the
Contracting Officer.
All information and data gathered, created, or derived under this contract are considered
Government property. Public release restrictions are described in Section 7.
The table below provides a complete listing of all deliverables required under this contract.
3.1 Deliverables Summary Table
Deliverable Description / Content
Requirements Format
Due Date /
Frequency Recipient
Installation
Work Summary
Report
Summary of installation activities performed. Include photos where applicable.
Electronic
(PDF)
Within 10 business days after project completion
COR
Software
Update
Confirmation
Documentation that the Velocity software database was updated to add and manage all installed readers. Identify version, impacted devices, and validation steps.
Electronic
(PDF)
Submitted with
Programming &
Configuration
Report
COR
Functional
Testing Report
Results of all functional tests, including badge reads, access-denial tests, tamper response, gate/door operation, and alarm reporting. Identify any issues discovered and corrective actions taken.
Electronic
(PDF)
Within 10 business days after project completion
COR
Updated
Inventory List
Updated inventory of all newly installed components (model, serial number, location, operational status).
Electronic
(PDF /
Excel)
Within 10 business days after project completion
COR
System
Configuration
Change Log
Log of all configuration changes to existing controllers, panels, or software databases. Must include reasons for changes and observed impacts.
Electronic
(PDF)
Within 10 business days after project completion
COR
CYFO Security System Repairs Page 8 of 14
Deliverable Description / Content
Requirements Format
Due Date /
Frequency Recipient
As-Built
Updates (if applicable)
Updated drawings or diagrams showing wiring confirmation, device locations, and connectivity.
Electronic
(PDF)
Within 10 business days after project completion
COR
Final Project
Completion
Package
Consolidated binder of all deliverables: installation report, wiring verification, programming report, testing documentation, final inventory, as-built updates, and configuration logs.
Electronic
(single
PDF)
Within 10 business days after project completion
COR &
CO
3.2 Draft and Final Deliverable Review Timelines
The following review cycle applies:
3.2.1 The Government will review deliverables within five (5) days of receipt.
3.2.2 If changes are required, the Contractor must deliver revised deliverables within five (5) days after receiving Government comments.
4.0 Meetings
4.1 Post-award Kickoff Meeting
Within 10 business days of contract award, the Government will conduct a post-award kickoff meeting at a time and location coordinated with the COR.
4.2 Intermittent Project Status Reviews
At the discretion of the Government, periodic project status reviews may be conducted as needed and scheduled by the COR.
5.0 Required Travel and Other Direct Costs
5.1 Travel Not Authorized
The principal place of performance for this project is the BLM Cody Field Office and associated site access points. Accordingly, reimbursable travel and per diem expenses are not authorized under this contract. Any travel necessary to complete the installation, configuration, and testing work must be included in the Contractor’s fixed price and will not be separately reimbursed.
Any exception must be approved by the Contracting Officer.
CYFO Security System Repairs Page 9 of 14
5.2 Other Direct Costs (ODCs)
Reimbursable Other Direct Costs (ODCs) such as travel, shipping, reproduction, equipment rental, or subcontractor expenses, are not authorized. All such costs must be fully incorporated into the Contractor’s fixed price.
All such costs must be included in the Contractor’s fixed price.
6.0 Government Furnished Property/Equipment/Information
The Government will furnish certain property, facility access, and information required for performance. Items are furnished as‑is; the Contractor must inspect them prior to use and notify the COR of concerns.
6.1 Government Furnished Property (GFP)
The following items will be made available to the Contractor for the purpose of installation, testing, and configuration associated with the access-control upgrades:
Item Description Manufacturer /
Model Quantity Condition Notes
Existing Identiv controllers and associated control panels
Identiv Velocity
(system) As-is
For system integration, software updates, and reader database configuration
Pre-installed wiring from control panel to each reader location
N/A 5 wire runs As-is
Contractor must verify wiring integrity prior to installation
Existing building infrastructure, junction boxes, and conduit
Various As installed As-is
Provided for mounting and routing of device connections
The Government is not furnishing hardware, equipment, or replacement devices for this project.
All card readers, mounting equipment, tools, and installation materials must be provided by the
Contractor.
6.2 Government-Furnished Facility Access
The Contractor must coordinate all access with the COR. Permanent access credentials will not be issued; escorts are required in restricted areas.
The Government will provide the Contractor with escorted access to:
6.2.1 Cody Field Office building interior (3 reader installation locations).
6.2.2 Ware yard access gates (2 installation locations).
6.2.3 Communications rooms, as required for access‑control panel work.
CYFO Security System Repairs Page 10 of 14
6.3 Government-Furnished Information (GFI)
The Government will furnish the following information necessary for successful system installation and configuration:
6.3.1 Existing access‑control system configuration data.
6.3.2 Controller and panel layout information.
6.3.3 System architecture diagrams or device maps (when available).
6.3.4 Applicable BLM security policies and facility access procedures.
GFI is for contract use only.
6.4 Government-Furnished Utilities and Workspace
The Government may provide:
6.4.1 Access to electrical outlets.
6.4.2 Limited workspace for staging tools and equipment.
6.4.3 Temporary access to IT network ports only when approved by BLM IT staff.
No long‑term storage or permanent workspace is provided.
6.5 Inspection and Responsibilities
6.5.1 The Contractor must maintain accountability for all Government‑furnished access, information, and facilities while in use.
6.5.2 Any loss, damage, or misuse of Government property attributable to Contractor personnel may result in reimbursement to the Government.
7.0 Special Instructions
7.1 Contractor Personnel Security Requirements
The Contractor must comply with all BLM facility access, escort, and identification procedures.
7.1.1 All personnel must check in at the Cody Field Office reception area upon arrival and obtain a visitor access badge.
7.1.2 Visitor badges must be visibly displayed while onsite and returned upon departure.
7.1.3 Escorts are required in all restricted or secure areas.
7.1.4 No permanent credentials will be issued.
The Contractor must notify the COR in advance if escorted access is unavailable or if entry restrictions prevent scheduled work.
CYFO Security System Repairs Page 11 of 14
7.2 Safety and Security Requirements
The Contractor must conduct all work in a safe manner consistent with BLM facility requirements, federal safety guidelines, and OEM installation practices.
7.2.1 Tools, equipment, and wiring must be secured to prevent hazards.
7.2.2 Work must not affect building security systems without prior coordination with the COR.
7.2.3 Alarms or security devices must not be disabled, bypassed, or reset without COR approval.
Any incident involving safety hazards, unexpected outages, or inadvertent alarms must be reported to the COR immediately.
7.3 Access to Government Systems and Information
The Contractor will be provided temporary access to Government‑furnished system information required to configure the Identiv Velocity platform.
7.3.1 System access will be supervised by COR‑designated personnel.
7.3.2 No system passwords, credentials, or configuration files may be removed from
Government facilities or copied without COR approval.
Government‑furnished information shall be used solely for performance of this SOW.
7.4 Installation Constraints and Coordination Requirements
To minimize disruption to BLM operations:
7.4.1 All work must be coordinated with the COR prior to commencement.
7.4.2 Installation activities that may affect building access, ware yard gate operation, or alarm reporting must be scheduled in advance.
7.4.3 Temporary system outages required for wiring verification, component testing, or reader activation must be approved by the COR prior to initiation.
7.5 Protection of Government Property and Facilities
The Contractor must protect Government property from damage during installation.
7.5.1 Any damage caused by Contractor personnel must be repaired at no additional cost to the Government.
7.5.2 Tools and materials must remain under the Contractor’s control and must not be left unattended in secure areas.
CYFO Security System Repairs Page 12 of 14
7.6 Prohibition of Unauthorized Public Release
All information, data, and observations related to this project—including installation details, system diagrams, testing results, or photographs—are Government property.
7.6.1 The Contractor must not release, publish, display, or distribute any project‑related information without written authorization from the Contracting Officer.
7.6.2 No marketing, social‑media, or promotional materials may reference this project without approval.
8.0 Glossary and Acronyms
8.1 Definitions
8.1.1 CONTRACTOR
A supplier or vendor awarded a contract to provide specific supplies or service to the
Government. The term used in this contract refers to the prime.
8.1.2 CONTRACTING OFFICER
A person with authority to enter, administer, and or terminate contracts, and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.
8.1.3 CONTRACTING OFFICER’S REPRESENTATIVE (COR)
An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor if that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
8.1.4 DEFECTIVE SERVICE
A service output that does not meet the standard of performance associated with the Statement of Work.
8.1.5 DELIVERABLE
Anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.
8.1.6 FICAM-COMPLIANT READER
A card reader meeting the Federal Identity, Credential, and Access Management (FICAM) guidelines for secure authentication at federal facilities.
8.1.7 KEY PERSONNEL
Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the people that are listed in the proposal.
CYFO Security System Repairs Page 13 of 14
8.1.8 PHYSICAL SECURITY
Actions that prevent the loss or damage of Government property.
8.1.9 QUALITY ASSURANCE
The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
8.1.10 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
An organized written document specifying the surveillance methodology to be used for surveillance of Contractor performance.
8.1.11 QUALITY CONTROL
All necessary measures taken by the Contractor to assure that the quality of a product or service shall meet contract requirements.
8.1.12 SUBCONTRACTOR
One that enters a contract with a prime Contractor. The Government does not have privity of contract with the Subcontractor.
8.1.13 WORKDAY
The number of hours per day the Contractor provides services in accordance with the contract.
8.1.14 WORK WEEK
Monday through Friday, unless specified otherwise.
CYFO Security System Repairs Page 14 of 14
8.2 Acronyms
BLM Bureau of Land Management
CFR Code of Federal Regulations
CIDC Cody Interagency Dispatch Center
CO Contracting Officer
CONUS Continental United States (excludes Alaska and Hawaii)
COR Contracting Officer Representative
COTR Contracting Officer's Technical Representative
COTS Commercial-Off-the-Shelf
DIAR Department of the Interior Acquisition Regulation
DOI Department of the Interior
FAR Federal Acquisition Regulation
FICAM Federal Identity, Credential, and Access Management
HIPAA Health Insurance Portability and Accountability Act of 1996
OCI Organizational Conflict of Interest
OCONUS Outside Continental United States (includes Alaska and Hawaii)
ODC Other Direct Costs
PI Project Inspector
PIPO Phase In/Phase Out
POC Point of Contact
PRS Performance Requirements Summary
QA Quality Assurance
QAP Quality Assurance Program
QASP Quality Assurance Surveillance Plan
QC Quality Control
QCP Quality Control Program
RS-485 Recommended Standard 485 (serial communication interface used for access-control components)
RREB RS-485 Reader Expansion Board
SNIB Secure Network Interface Board
SOW Statement of Work
TE Technical Exhibit
TS SC Time-Series Smart Card (Identiv uTrust product line designation)