A04_0040629068_GR_SOW_HVAC_replacement_2023.pdf

PDF 137 KB Posted

Attached to
Various rehab projects Federal contract opportunity
Solicitation number
140FC124Q0001
Issued by
Department of the Interior Fish and Wildlife Service

About this file

This statement of work outlines requirements for replacing the HVAC system at the Green River National Wildlife Refuge headquarters facility in Spottsville, Kentucky. The project involves removing the existing unit from the attic and disposing of it properly. A new minimum 15 SEER unit is to be installed outside on an approved platform approximately four feet above ground level. This will provide heating and cooling to the upper level of approximately 2,500 square feet. A second HVAC system and ductwork must also be installed to heat and cool the lower level of approximately 2,500 square feet. Normal work hours are weekdays from 8:00 a.m. to 4:30 p.m., with an emergency contact required. The selected contractor will meet with the site representative as needed to provide updates and ensure the work meets government expectations, providing weekly progress updates at a minimum to the contracting officer and site representative.

This statement of work is related to solicitation number 140FC124Q0001 for various rehabilitation projects issued by the U.S. Department of the Interior Fish and Wildlife Service.

View the file

Other files for this federal contract opportunity

Other files attached to Various rehab projects, newest first.
File Type Posted
Sol_140FC124Q0001_Amd_0002.pdf PDF
B03_General_Decision_Number_0001.txt TXT text file
Sol_140FC124Q0001_Amd_0001.pdf PDF
Sol_140FC124Q0001.pdf PDF
A04_0040629687_Statement_of_Work_(SOW).pdf PDF
B03_General_Decision.txt TXT text file
0040634990_Statement_of_Work_Rehab_Parking_Lot_Clarks_River_NWR.pdf PDF
A04_0040629154_SOW-GRNWR_roof_replacement_2023.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

HVAC Replacement

1. General: The headquarters facility at the Green River NWR will require replacement of the existing HVAC system that currently heats and cools the upper level (approximately 2,500 sq. ft.)

of the facility. Summer months and winter months will become a safety hazard for employees and volunteers as well as public. The existing unit will need to be removed from the attic and properly disposed of by the contractor. The new unit will be installed outside the facility on an approved platform approximately 4 feet above ground level. The work will also include a thorough inspection of the existing duct work to ensure full heating and cooling efficiencies are achieved. A second HVAC system, including duct work, will be installed to heat and cool the lower level (approximately 2,500 sq. ft.) of the facility. Minimum of 15 SEER units should be installed. Green River NWR; 10847 Green River Road #2, Spottsville, KY 42458-0091

1.2 The structure serves as a quarters for volunteers/staff, etc. The HVAC unit has failed and in critical need of replacement. The existing unit and duct work was insufficient to heat and cool the bottom floor of the structure when operable. The rehabilitation of the system is a critical need for the station.

1.3 Masters HVAC required by KY Law.

1.4 Department of HVAC in Frankfort KY issues permits for HVAC installations.

2. Normal duty hours: Monday thru Friday 8:00 a.m. - 4:30 p.m. In the event of emergencies, Contractor shall provide contact information.

3. Scope: The contractor or their representative shall meet with the site rep upon request while work is ongoing to provide updates and ensure the product and performance are in accordance to expectations of the government. The contractor will provide the CO and the Site Rep. with progress updates weekly at minimum

STATEMENT OF WORK
1. General: The headquarters facility at the Green River NWR will require replacement of the existing HVAC system that currently heats and cools the upper level (approximately 2,500 sq. ft.) of the facility. Summer months and winter months will beco...
2. Normal duty hours: Monday thru Friday 8:00 a.m. - 4:30 p.m. In the event of emergencies, Contractor shall provide contact information.
3. Scope: The contractor or their representative shall meet with the site rep upon request while work is ongoing to provide updates and ensure the product and performance are in accordance to expectations of the government. The contractor will provi...