A02_Appendix B - Contract Drawings - JFC LED Lighting Upgrades.pdf
PDF 7 MB Posted
- Solicitation number
- W912P923Q0027
About this file
This document package includes engineering drawings and specifications for an electrical upgrade project at Jerry F. Costello Lock and Dam. The project involves replacing existing lighting fixtures and low-voltage electrical equipment with new LED alternatives. Specific work items include replacing parking area and lock chamber lighting, sump pump controllers, power receptacles, the lock gallery lighting system, and the dam's low-voltage distribution equipment. The drawings provide plans and details for the lighting upgrades around the parking area, lock and guide walls, and dam structures. Product specifications and reference drawings are included in an appendix. The solicitation number is W912P923Q0027 and is seeking supply and installation services for the various new LED light fixtures and low-voltage equipment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
S O
L
IC
IT
A
T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S I Z
E
S U
B M
IT
T
E D
B Y
D A
T E
C O
N T
R A
C T
N O
C
H E
C K
E D
B Y
D R
A W
N B
Y
IS
S
U E
D A
T E
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
SHEET ID
of Engineers
US Army Corps
K A
S K
A S
K
IA
R
IV
E R
M O
D O
C
IL
L
IN
O
IS
L E
D L
IG
H
T
IN
G U
P G
R A
D E
S
JE
R
R Y
F C
O S
T E
L L
O L
O C
K
D A
M
S T
L
O U
IS
M
IS
S O
U R
I
S T
L
O U
IS
D
IS
T
R
IC
T
U .S
A
R M
Y C
O R
P S
O F
E N
G
IN
E E
R S
M A
Y
A N
S I
D
B L
E W
IS
P
.E
%PRODUCTION DATA 4%%PRODUCTION DATA 3%
SOLICITATION NO.:
CONTRACT NO.:
ISSUE DATE:
2022/07/18 of Engineers
C
V E
R S
H E
E T
G-001
D R
G
D R
G
N M
C
G E
N E
R
L
JERRY F. COSTELLO LOCK & DAM
LED LIGHTING & ELECTRICAL UPGRADES
MODOC, ILLINOIS
KASKASKIA RIVER
L
IC
IT
A
T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S I Z
E
S U
B M
IT
T
E D
B Y
D A
T E
C O
N T
R A
C T
N O
C
H E
C K
E D
B Y
D R
A W
N B
Y
IS
S
U E
D A
T E
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
SHEET ID
of Engineers
S K
A S
K
IA
R
IV
E R
M O
D O
C
IL
L
IN
O
IS
L E
D L
IG
H
T
IN
G U
P G
R A
D E
S
JE
R
R Y
F C
O S
T E
L L
O L
O C
K
D A
M
S T
L
O U
IS
M
IS
S O
U R
I
S T
L
O U
IS
D
IS
T
R
IC
T
U .S
A
R M
Y C
O R
P S
O F
E N
G
IN
E E
R S
M A
Y
A N
S I
D
B L
E W
IS
P
.E
G-002
D R
G
D R
G
N M
C
G E
N E
R
L
IN
E X
O F
D R
A W
IN
G
S
GENERAL
TITLESHT
ELECTRICAL
G-001 COVER SHEET
G-002
G-003 PROJECT LOCATION AND VICINITY MAP
E-001
E-101
E-102
E-103
E-104
DWG TITLE
REFERENCE
DRAWING/DETAIL LOCATION DESIGNATION
DRAWING/DETAIL TITLE
DRAWING NAME
1/8" = 1' 0"
(DRAWN) SHOWN
DRAWING/DETAIL LIMITS
DETAIL DESIGNATION
DESIGNATION
SECTION/DETAIL LOCATION DESIGNATION
SECTION/DETAIL
DESIGNATION
EXTERIOR ELEVATION
DESIGNATION
INTERIOR ELEVATION### ##
BREAK LINE, MATERIAL
TO CONTINUE
REVISION CLOUD
NORTH ARROW
REVISION DESIGNATION
ELEVATION/DETAIL LOCATION DESIGNATION
ELEVATION/DETAIL LOCATION DESIGNATION
DETAIL LOCATION DESIGNATION
SIMILAR, OR OPPOSITE HAND
SCALE
SHEET NUMBER DESIGNATION WHERE
X-XXX
(DRAWN) SHOWN
SHEET NUMBER DESIGNATION WHERE
NOT USED ON SHEET
SHOWN
SHEET NUMBER DESIGNATION WHERE (DRAWN)
SHOWN
SHEET NUMBER DESIGNATION WHERE (DRAWN)
FIRST REFERENCED
SHEET NUMBER DESIGNATION WHERE
INDICATES TRUE NORTH
INDICATES PLAN NORTH
ABBREVIATIONS
NORTH
PLAN
KEYNOTE
KEYNOTE
KILOVOLTKV
KILOWATTKVA
MILS
THOUSAND CIRCULAR KCMIL
JUNCTION BOXJB
COMPUTER
INDUSTRIAL PERSONAL IPC
INPUT/OUTPUTI/O
IMMERSIONIMMER
ILLINOISIL
INTERIM CONTROL ROOMICR
INTERIM CONTROL HOUSEICH
HERTZHZ
HIGH MAST LIGHTHML
HYDRAULIC POWER UNITHPU
GUIDE WALLG/W
GROUNDGRD, GND
GALLERYGLRY
INTERRUPTER
GROUND FAULT CIRCUIT GFCI
GREEN G
FUSEFU
FOOT CANDLEFC
FIBER OPTIC F/O
ENABLEEN
EMERGENCYEM
EMERGENCYEMER
ELEVATORELV
ROOM
ELECTRICAL EQUIPMENT EER
DISPLAYDSPLY
DISTRIBUTION PANEL NO.#DP#
DOWNSTREAMD/S
DYNAMIC BRAKEDB
CONTROL TRANSFORMERCT
CONTROL RELAYCR
TRANSFORMER
CONTROL POWER CPT
CONTROL PANELCP
COMPRESSORCOMP
CONVERTERCVTR
CIRCUITCKT
CHARGERCHGR
TELEVISION
CLOSED CIRCUIT CCTV
CIRCUIT BREAKERCB
CABINETCAB
COMMONC
BROWNBR
BUILDINGBLDG
BLUEBL
BLACKBK
BASIC IMPULSE LEVELBIL
BATTERYBTRY
AMERICAN WIRE GAUGEAWG
SWITCH
AUTOMATIC TRANSFER ATS
CONTROL
AUTOMATIC TRANSFER ATC
AMPS TRIPAT
ADJUSTABLE SPEED DRIVEASD
CAPACITY
AMPERES INTERRUPTING AIC
ABOVE FINISH FLOORAFF
FRAME SIZE IN AMPSAF
AMPERESA
INDEX OF DRAWINGS GENERAL SYMBOLS
INDEX OF DRAWINGS, SYMBOLS LEGEND, ABBREVIATIONS, AND GENERAL NOTES
SITE PLAN - GENERAL OVERVIEW
LIGHTING PLAN - PARKING AREA
LIGHTING PLAN - DAM
LIGHTING PLAN - NAVIGATION LOCK & GUIDE WALLS
PLAN - CENTRAL CONTROL HOUSE (CCH)
ELECTRICAL SYMBOLS
SINGLE POLE-MOUNT AREA LIGHT STANDARD
DOUBLE POLE-MOUNT AREA LIGHT STANDARD
MG RECESS FLOOD LIGHT
DAM WALKWAY LIGHT FIXTURE
DAM TUNNEL LIGHT FIXTURE
DAM CANOPY LIGHT FIXTURE
LOCK FMB LIGHT FIXTURE
FLOOD LIGHT
480V POWER RECEPTACLE
120V DUPLEX RECEPTACLE
120V DUPLEX GFCI RECEPTACLE
3-PHASE PUMP MOTOR
CIRCUIT HOME-RUN
(SEE APPENDIX B)
CABLE TRAY
K-1 29/15.2 PARKING AREA LIGHTING
K-1 30/6.1 LOCK LIGHTING PLAN
K-1 30/7.2 LOCK ELECTRICAL CABLE SCHEDULE
K-1 30/15.1 CABLE TRAY PLAN AND SECTIONS
K-1 30/16.1 LOCK GALLERY PLANS AND SECTIONS 1
K-1 30/18.4 LOCK ELECTRICAL CONDUIT LAYOUT
K-1 30/19.1 GUIDE WALLS ELECTRICAL
K-1 30/20 GALLERY LIGHTING SYSTEM
K-1 30/25 LIGHTING STANDARDS AND DETAILS
K-1 30/26 LOCK ELECTRICAL MISC. DETAILS
K-1 50/1.5 DAM ELECTRICAL PLAN AND DETAILS
K-1 50/2.4 DAM ELECTRICAL DETAILS 1
K-1 50/3.4 DAM ELECTRICAL DETAILS 2
E-004 LIGHTING PANELBOARD SCHEDULE
E-008 LIGHTING SCHEMATIC DIAGRAMS SHEET 1
E-009 LIGHTING SCHEMATIC DIAGRAMS SHEET 2
E-010 LIGHTING SCHEMATIC DIAGRAMS SHEET 3
S-3561 SUMP PUMP CONTROLLER DIAGRAM
TRANSFORMERXFMR
TRANSDUCERXDCR
VOLTS DIRECT CURRENTVDC
VALVEVLV
CURRENT
VOLTS ALTERNATING VAC
PAIR
UNSHIELDED TWISTED UTP
INDICATED
UNLESS OTHERWISE U.O.I.
UPSTREAMU/S
TYPICALTYP
SURGE SUPPRESSION
TRANSIENT VOLTAGE TVSS
SWITCHGEARSWGR
STANDBYSTDBY
STROBESTRB
SHIELDEDSH
SELECTOR SWITCHSEL SW
RESETRST
ROOMRM
RIGID GALVANIZED STEELRGS
RECEPTACLEREC
RED R
POWERPWR
CONTROLLER
PROGRAMMABLE LOGIC PLC
OVER TRAVELOT
OVERLOADOL
NOT TO SCALENTS
NORMALLY OPENNO
NORMALLY CLOSEDNC
MOTORMTR
MISSOURIMO
MEDIUM VOLTAGEMV
MANHOLEMH
MOTOR CONTROL CENTERMCC
METAL-CLADMC
MACHINERYMACH
LOWERLWR
LIGHTINGLTG
LIMIT SWITCHLS
LIGHTING PANEL NO. #LP#
LIFT GATELG
LIGHT EMITTING DIODELED
CC
L
IC
IT
A
T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S I Z
E
S U
B M
IT
T
E D
B Y
D A
T E
C O
N T
R A
C T
N O
C
H E
C K
E D
B Y
D R
A W
N B
Y
IS
S
U E
D A
T E
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
SHEET ID
of Engineers
S K
A S
K
IA
R
IV
E R
M O
D O
C
IL
L
IN
O
IS
L E
D L
IG
H
T
IN
G U
P G
R A
D E
S
JE
R
R Y
F C
O S
T E
L L
O L
O C
K
D A
M
S T
L
O U
IS
M
IS
S O
U R
I
S T
L
O U
IS
D
IS
T
R
IC
T
U .S
A
R M
Y C
O R
P S
O F
E N
G
IN
E E
R S
M A
Y
A N
S I
D
B L
E W
IS
P
.E
2023/04/24
E-001
R
G
D R
G
N M
C
S
IT
E P
L A
N
E L
E C
T R
IC
A
L
CUTOFF WALL
PIER 3
TAINTER GATE NO. 2
PIER 2
TAINTER GATE NO. 1
STAIRS
CUTOFF WALL
K A S K A S K I A R I V E R
PIER
GUIDEWALL
SEE SHEET E-102
UPSTREAM FLOATING GUIDEWALL
FLOW
(IN GALLERY UNDER CONTROL HOUSE)
UPSTREAM SUMP PUMP CONTROLLER
CENTRAL CONTROL HOUSE (CCH)
SEE SHEET E-101
PARKING AREA
VEHICLE ACCESS GATE
MAINTENANCE BUILDING
GATE SILL
GALLERY AT UPPER
UPSTREAM CROSSOVER
MITER GATE (#2)
UPSTREAM LANDWALL
MITER GATE (#4)
UPSTREAM RIVERWALL
BUILDING
FUEL STORAGE
GENERAL STORAGE BUILDING
A C
C E S S R
O A
D
LANDWALL
LOCK CHAMBER
RIVERWALL
MITER GATE (#3)
DOWNSTREAM RIVERWALL
MITER GATE (#1)
DOWNSTREAM LANDWALL
DOWNSTREAM SUMP PUMP CONTROLLER (IN GALLERY)
DOWNSTREAM CONTROL SHELTER
CROSSOVER GALLERY
DOWNSTREAM
EXISTING
EQUIPMENT PLATFORM
ELECTRICAL MAIN SERVICE
ADMINISTRATION BUILDING &
PIER 1
PULL BOX
REPLACE (TYP.)
POWER RECPT
480V, 3-PHASE
A1
SCALE: 1" = 50"
SITE PLAN - GENERAL OVERVIEW
SEE SHEET E-102
FLOATING GUIDWALL
DOWNSTREAM
SHEET KEYNOTES
ALL ELECTRICAL WORK SHALL BE IN ACCORDANCE WITH NFPA 70.4.
WORK ITEM TO BE PERFORMED UNDER THIS CONTRACT.
"TECHNICAL SPECIFICATIONS" FOR DETAILED REQUIREMENTS OF EACH
OF THE LOCATIONS OF EQUIPMENT AND FEATURES. SEE SECTION C
DETAILS, RATHER IT IS INTENDED TO PROVIDE A GENERAL OVERVIEW
THIS DRAWING IS NOT INTENDED TO DEFINE ANY SPECIFIC WORK ITEM3.
INCLUDING PUMP MOTOR FEEDER CONDUCTORS AND RACEWAY.
- REPLACE AND RELOCATE TWO (2) DUPLEX SUMP PUMP CONTROLLERS
- REPLACE FIFTEEN (15) EXISTING 480V, 3-PHASE POWER RECEPTACLES.
LIGHT FIXTURES ON THE LOCK CHAMBER WALLS.
- REPLACE FOUR (4) EXISTING MITER GATE (MG) LOCK RECESS AREA
LIGHT FIXTURES ON THE LOCK CHAMBER WALLS.
- REPLACE THIRTEEN (13) EXISTING FLOATING MOORING BIT (FMB) AREA
- REPLACE EXISTING DAM LOW-VOLTAGE DISTRIBUTION EQUIPMENT.
- REPLACE EXISTING LOCK GALLERY LIGHTING SYSTEM.
OPTIONAL WORK TO BE PERFORMED BY THE CONTRACTOR OUTLINED BELOW:2.
EQUIPMENT FOR DAM TAINTER GATE BAY AREAS.
INCLUDING CIRCUIT CONDUCTORS, RACEWAY, AND MOUNTING
- PROVIDE FOUR (4) NEW LED TYPE FLOOD LIGHTING LUMINAIRES
TYPE LUMINAIRES.
- REPLACE NINE (9) EXISTING DAM CANOPY LUMINAIRES WITH NEW LED
LUMINAIRES WITH NEW LED TYPE LUMINAIRES.
- REPLACE TWENTY-SIX (26) EXISTING POLE-MOUNTED LOCK LIGHTING
WITH NEW LED TYPE LUMINAIRES IN PARKING AREA.
- REPLACE FIVE (5) EXISTING LIGHT STANDARD POLES AND LUMINAIRES
- DEVELOP LIGHTING ANALYSIS PER SECTION C, PARA. 3.1.
CONTRACTOR OUTLINED BELOW:
MAJOR FEATURES OF ELECTRICAL WORK TO BE PERFORMED BY THE 1.
CCH PLAN VIEW.
REFERENCE DRAWING S-3561 FOR EXISTING SCHEMATIC. SEE SHEET E-105 FOR
SAME FUNCTIONALITY AS THE EXISTING CONTROLLERS. SEE APPENDIX B,
PER NFPA 70. NEW CONTROLLERS SHALL BE FABRICATED TO PROVIDE THE
CABLES SHALL BE FIELD ROUTED BY THE CONTRACTOR IN EXISTING RACEWAY
OFFICE" ON THE 2ND FLOOR OF THE CENTRAL CONTROL HOUSE (CCH). NEW
NEW DUPLEX CONTROLLERS SHALL BE INSTALLED IN THE "LOCKMASTER'S
CIRCUIT CABLES TO EACH PUMP MOTOR LOCAL DISCONNECT SWITCH.
BREAKERS IN PANEL 'P' OF THE EXISTING MCC AND NEW PUMP MOTOR
INCLUDING NEW FEEDER CIRCUIT CABLES FROM EXISTING 15A, 480V/3P
CONTRACTOR SHALL PROVIDE TWO NEW DUPLEX SUMP PUMP CONTROLLERS
INCLUDING FEEDER CIRCUIT CABLES AND PUMP MOTOR CIRCUIT CABLES.
SHALL REMOVE BOTH EXISTING U/S AND D/S SUMP PUMP CONTROLLERS
REPLACE AND RELOCATE LOCK SUMP PUMP CONTROLLERS: CONTRACTOR
(OPTIONAL BID ITEM 11)4.
REFERENCE DRAWING K-1 30/19-1 FOR GUIDE WALL PLAN.
LOCATIONS OF EXISTING RECPTACLES TO BE REPLACED. SEE APPENDIX B,
POWER RECPTACLES. SEE SHEETS E-101, E-102, AND E-103 FOR ADDITIONAL
480V POWER RECEPTACLE: CONTRACTOR SHALL REPLACE EXISTING 480V
(OPTIONAL BID ITEM 10)3.
STRUCTURE IN ACCORDANCE WITH NFPA 70. SEE SHEET E-103.
NEW DISTRIBUTION EQUIPMENT SHALL BE INSTALLED ON EXISTING MOUNTING
'X', PANEL 'Y', PANEL 'Z', STEP-DOWN XFMR, AND PHOTOELECTRIC CONTROL BOX.
EXISTING DISTRIBUTION EQUIPMENT INCLUDING BUT NOT LIMITED TO: PANEL
DAM LOW VOLTAGE DISTRIBUTION EQUIPMENT: CONTRACTOR SHALL REPLACE
(OPTIONAL BID ITEM 07)2.
- REF DWG E-004: PANEL SCHEDULE - LIGHTING PANEL 'L'
- REF DWG K-1 30/20: GALLERY LIGHTING PLAN
- REF DWG E-009: GALLERY LIGHTING SCHEMATIC
LIGHTING SYSTEM DETAILS:
SEE APPENDIX B, REFERENCE DRAWINGS FOR ADDITIONAL LOCK GALLERY
REPLACEMENT LIGHTING SYSTEM SHALL BE AS SPECIFICED IN SECTION C.
POWER CABLES, WATERTIGHT FIXTURES, LED LAMPS, AND HARDWARE.
EXISTING LOCK GALLERY LIGHTING SYSTEM INCLUDING BUT NOT LIMITED TO:
LOCK WALL GALLERIES: CONTRACTOR SHALL REPLACE THE COMPLETE
1. (OPTIONAL BID ITEM 06)
GENERAL ELECTRICAL NOTES
L
IC
IT
A
T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S I Z
E
S U
B M
IT
T
E D
B Y
D A
T E
C O
N T
R A
C T
N O
C
H E
C K
E D
B Y
D R
A W
N B
Y
IS
S
U E
D A
T E
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
SHEET ID
of Engineers
S K
A S
K
IA
R
IV
E R
M O
D O
C
IL
L
IN
O
IS
L E
D L
IG
H
T
IN
G U
P G
R A
D E
S
JE
R
R Y
F C
O S
T E
L L
O L
O C
K
D A
M
S T
L
O U
IS
M
IS
S O
U R
I
S T
L
O U
IS
D
IS
T
R
IC
T
U .S
A
R M
Y C
O R
P S
O F
E N
G
IN
E E
R S
M A
Y
A N
S I
D
B L
E W
IS
P
.E
E-101
R
G
D R
G
N M
C
E L
E C
T R
IC
A
L
P A
R K
IN
G
A R
E A
L
IG
H T
IN
G
P L
N
SHEET KEYNOTES
GENERAL SHEET NOTES
REPLACE
LIGHT STANDARD
OPTIONS.MODEL INCLUDING MANUFACTURER
NEW LED LIGHT STANDARDS AND LUMINAIRES SHALL MATCH THIS EXISTING
- STANDARD: LITHONIA SSA-25-5G-DM28AS-VD-ADB-USPOM
- LUMINAIRE: LITHONIA DSX0-LED-P5-40K-TFTM-480-SPA-PIRH-DDBXD-USPOM.
EXISTING LED LIGHT STANDARD MODEL (TO REMAIN): 2.
SECTION C "TECHNICAL SPECIFICATIONS".
EXISTING LED LIGHT STANDARD SHOWN AND SHALL BE AS SPECIFIED IN
LUMINAIRES. NEW LIGHT STANDARDS AND LED LUMINAIRES SHALL MATCH
400W LUMINAIRE FIXTURE WITH NEW LIGHT STANDARD POLES AND LED TYPE
SHALL REPLACE FIVE (5) EXISTING PARKING AREA LIGHT STANDARDS AND
NEW LED LIGHT STANDARD AND AREA LIGHTING LUMINAIRE: CONTRACTOR
(BID ITEM 02)1.
REPLACE
REPLACE
REPLACE
TO REMAIN
EXISTING
LED LIGHT STANDARD
EXISTING
480V
PANEL 'A'
ON EXISTING PARKING AREA LIGHTING.
SEE APPENDIX B, REFERENCE DRAWING K-1 29/15.2 FOR ADDITIONAL DETAILS6.
FEDERAL REGULATIONS.
REPLACED OFF-SITE IN ACCORDANCE WITH ALL LOCAL, ENVIRONMENTAL, AND
CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL LIGHT STANDARDS TO BE5.
NEW LED LIGHT FIXTURES.
CONTRACTOR SHALL USE EXISTING CIRCUIT CABLES AND RACEWAY TO ALL 4.
RECOMMENDATIONS.
TO PROPERLY INSTALL NEW LED LIGHT STANDARDS PER MANUFACTURER'S
CONTRACTOR SHALL PROVIDE ALL NECESSARY PLANT, LABOR, AND MATERIAL3.
ARE COMPATIBLE WITH EXISTING LIGHT POLES.
ENSURE ALL NEW LIGHT FIXTURES TO BE INSTALLED BY THE CONTRACTOR
MOUNTING CONNECTIONS AND ELECTRICAL CONNECTIONS, AND SHALL
2. CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING ALL EXISTING
WORK ITEM TO BE PERFORMED UNDER THIS CONTRACT.
"TECHNICAL SPECIFICATIONS" FOR DETAILED REQUIREMENTS OF EACH
OF THE LOCATIONS OF EQUIPMENT AND FEATURES. SEE SECTION C
DETAILS, RATHER IT IS INTENDED TO PROVIDE A GENERAL OVERVIEW
THIS DRAWING IS NOT INTENDED TO DEFINE ANY SPECIFIC WORK ITEM1.
REPLACE
EXISTING
EQUIPMENT PLATFORM
MAIN ELECTRICAL SERVICE
A1
SCALE: 1" = 20'
LIGHTING PLAN - PARKING AREA
L
IC
IT
A
T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S I Z
E
S U
B M
IT
T
E D
B Y
D A
T E
C O
N T
R A
C T
N O
C
H E
C K
E D
B Y
D R
A W
N B
Y
IS
S
U E
D A
T E
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
SHEET ID
of Engineers
S K
A S
K
IA
R
IV
E R
M O
D O
C
IL
L
IN
O
IS
L E
D L
IG
H
T
IN
G U
P G
R A
D E
S
JE
R
R Y
F C
O S
T E
L L
O L
O C
K
D A
M
S T
L
O U
IS
M
IS
S O
U R
I
S T
L
O U
IS
D
IS
T
R
IC
T
U .S
A
R M
Y C
O R
P S
O F
E N
G
IN
E E
R S
M A
Y
A N
S I
D
B L
E W
IS
P
.E
E-102
R
G
D R
G
N M
C
E L
E C
T R
IC
A
L
L
IG
H T
IN
G
P L
A N
SHEET KEYNOTES
V
IG
A T
IO
N
L O
C K
G
U
ID
E W
A L
L S
UPSTREAM GUIDE WALL DOWNSTREAM GUIDE WALL
NAVIGATION LOCK
GUIDE WALL
TO DOWNSTREAM
GUIDE WALL
TO UPSTREAM
NAVIGATION LOCK
TO DOWNSTREAM
NAVIGATION LOCK
TO UPSTREAM
EXISTING (TYP)
SINGLE FIXTURE
AREA LIGHT POLE
EXISTING (TYP)
DOUBLE FIXTURE
AREA LIGHT POLE
EXISTING TO REMAIN (TYP)
GUIDE WALL LIGHT FIXTURE
LOCATIONS OF EXISTING RECPTACLES TO BE REPLACED.
POWER RECPTACLES. SEE SHEETS E-001, E-101, AND E-103 FOR ADDITIONAL
480V POWER RECEPTACLE: CONTRACTOR SHALL REPLACE EXISTING 480V
(OPTIONAL BID ITEM 10)5.
- REF DWG K-1 30/25: FMB LIGHTING DETAILS
- REF DWG E-010: FMB LIGHT SCHEMATIC
SEE APPENDIX B, REFERENCE DRAWINGS:
FOR CONNECTION TO EXISTING CIRCUIT CONDUCTORS. TYPICAL OF THIRTEEN.
SHALL BE PROVIDED WITH NEW WATERTIGHT CABLE CONNECTOR FOR
SPECIFIED IN SECTION C TECHNICAL SPECIFICATIONS. NEW FMB LED FIXTURES
SHALL REPLACE EXISTING LOCK FMB LIGHT FIXTURES WITH NEW LED TYPE AS
NEW FLOATING MOORING BIT (FMB) LIGHT FIXTURE: CONTRACTOR
(OPTIONAL BID ITEM 08)4.
- REF DWG K-1 30/25: MG RECESS LIGHTING DETAILS
- REF DWG E-008: MG RECESS LIGHT SCHEMATIC
TYPICAL OF FOUR. SEE APPENDIX B, REFERENCE DRAWINGS:
FLOOD LIGHTS AS SPECIFIED IN SECTION C TECHNICAL SPECIFICATIONS.
SHALL REPLACE EXISTING MG RECESS FLOOD LIGHTS WITH NEW LED TYPE
NEW SURFACE-MOUNT MITER GATE (MG) RECESS FLOOD LIGHT: CONTRACTOR
(OPTIONAL BID ITEM 09)3.
- REF DWG K-1 30/25: LOCK LIGHTING DETAILS
- REF DWG E-010: LOCK LIGHTING SCHEMATIC
MANUFACTURER. TYPICAL OF EIGHT. SEE APPENDIX B, REFERENCE DRAWINGS:
BRACKET ARM OF THE MAKE/MODEL RECOMMENDED BY THE NEW LED LIGHT
EXISTING BRACKET ARM SHALL BE REPLACED WITH NEW HORIZONTAL
TYPE LUMINAIRES AS SPECIFIED IN SECTION C TECHNICAL SPECIFICATIONS.
SHALL REPLACE EXISTING 400W LUMINAIRE FIXTURE WITH NEW LED
NEW POLE-MOUNT LED LUMINAIRE (DOUBLE): CONTRACTOR
(BID ITEM 03)2.
- REF DWG K-1 30/25: LOCK LIGHTING DETAILS
- REF DWG E-010: LOCK LIGHTING SCHEMATIC
MANUFACTURER. TYPICAL OF TEN. SEE APPENDIX B, REFERENCE DRAWINGS:
BRACKET ARM OF THE MAKE/MODEL RECOMMENDED BY THE NEW LED LIGHT
EXISTING BRACKET ARM SHALL BE REPLACED WITH NEW HORIZONTAL
TYPE LUMINAIRES AS SPECIFIED IN SECTION C TECHNICAL SPECIFICATIONS.
SHALL REPLACE EXISTING 400W LUMINAIRE FIXTURES WITH NEW LED
NEW POLE-MOUNT LED LUMINAIRE (SINGLE): CONTRACTOR
(BID ITEM 03)1.
EXISTING NAVIGATION LOCK AND GUIDE WALL LIGHTING PLANS & DETAILS.
SEE APPENDIX B, REFERENCE DRAWINGS K-1 30/20, 25, AND 26 FOR 6.
NEW LED LIGHT FIXTURES SHOWN.
CONTRACTOR SHALL USE EXISTING CIRCUIT CABLES AND RACEWAY TO 5.
LIGHT POLES.
MOUNTING HARDWARE TO MOUNT NEW LED LIGHT FIXTURES TO EXISTING
CONTRACTOR SHALL PROVIDE ALL NECESSARY ACCESSORIES AND 4.
CONNECTIONS ARE SUITABLE FOR USE WITH NEW LIGHT FIXTURES.
MOUNTING CONNECTIONS, CABLE LENGTHS, AND ELECTRICAL
CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING ALL EXISTING 3.
CONTRACT. ALL OTHER ITEMS ARE EXISTING AND SHALL REMAIN.
ITEMS SHOWN IN BOLD IS WORK TO BE PERFORMED UNDER THIS 2.
WORK ITEM TO BE PERFORMED UNDER THIS CONTRACT.
"TECHNICAL SPECIFICATIONS" FOR DETAILED REQUIREMENTS OF EACH
OF THE LOCATIONS OF EQUIPMENT AND FEATURES. SEE SECTION C
DETAILS, RATHER IT IS INTENDED TO PROVIDE A GENERAL OVERVIEW
1. THIS DRAWING IS NOT INTENDED TO DEFINE ANY SPECIFIC WORK ITEM
REPLACE (TYP)
FMB LIGHT FIXTURE
REPLACE (TYP.)
POWER RECPT
480V, 3-PHASE
REPLACE (TYP.)
POWER RECPT
480V, 3-PHASE 55
A1
SCALE: 1" = 60'
LIGHTING PLAN - NAVIGATION LOCK & GUIDE WALLS
L
IC
IT
A
T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S I Z
E
S U
B M
IT
T
E D
B Y
D A
T E
C O
N T
R A
C T
N O
C
H E
C K
E D
B Y
D R
A W
N B
Y
IS
S
U E
D A
T E
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
SHEET ID
of Engineers
S K
A S
K
IA
R
IV
E R
M O
D O
C
IL
L
IN
O
IS
L E
D L
IG
H
T
IN
G U
P G
R A
D E
S
JE
R
R Y
F C
O S
T E
L L
O L
O C
K
D A
M
S T
L
O U
IS
M
IS
S O
U R
I
S T
L
O U
IS
D
IS
T
R
IC
T
U .S
A
R M
Y C
O R
P S
O F
E N
G
IN
E E
R S
M A
Y
A N
S I
D
B L
E W
IS
P
.E
E-103
R
G
D R
G
N M
C
E L
E C
T R
IC
A
L
L
IG
H T
IN
G
P L
SHEET KEYNOTES
D A
M
LOCATIONS OF EXISTING RECPTACLES TO BE REPLACED.
POWER RECPTACLES. SEE SHEETS E-001, E-101, AND E-102 FOR ADDITIONAL
480V POWER RECEPTACLE: CONTRACTOR SHALL REPLACE EXISTING 480V
(OPTIONAL BID ITEM 10)4.
- REF DWG K-1 50/2.4: DAM LOW-VOLTAGE DISTRIBUTION EQUIPMENT DETAIL
- REF DWG K-1 50/1.5: DAM ELECTRICAL PLAN AND DETAILS
DRAWINGS:
STRUCTURE IN ACCORDANCE WITH NFPA 70. SEE APPENDIX B, REFERENCE
NEW DISTRIBUTION EQUIPMENT SHALL BE INSTALLED ON EXISTING MOUNTING
'X', PANEL 'Y', PANEL 'Z', STEP-DOWN XFMR, AND PHOTOELECTRIC CONTROL BOX.
EXISTING DISTRIBUTION EQUIPMENT INCLUDING BUT NOT LIMITED TO: PANEL
DAM LOW VOLTAGE DISTRIBUTION EQUIPMENT: CONTRACTOR SHALL REPLACE
(OPTIONAL BID ITEM 07)3.
AND DETAILS.
DRAWING K-1 50/1.5 FOR DAM ELECTRICAL PLAN SEE APPENDIX B, REFERENCE
PROPERLY INSTALL NEW FLOOD LIGHT FIXTURES IN ACCORDANCE WITH NFPA 70.
CONFIGURATION/EQUIPMENT AND TO PROVIDE ALL NECESSARY EQUIPMENT TO
RESPONSIBILITY OF THE CONTRACTOR TO DETERMINE MOUNTING
UNDER THE EXISTING OVERHEAD CANOPY STRUCTURES. IT SHALL BE THE
DAM OPERATIONS. NEW CIRCUIT CONDUCTORS AND CONDUIT SHALL BE ROUTED
LOCATIONS SHOWN AND SHALL NOT INTERFERE WITH EXISTING EQUIPMENT OR
NEW FLOOD LIGHT FIXTURES SHALL BE MOUNTED IN THE APPROXIMATE
SHALL BE FIELD ROUTED FROM PANEL 'Z' TO EACH NEW FLOOD LIGHT FIXTURE.
EQUIPMENT FOR EACH NEW FIXTURE. CIRCUIT CONDUCTORS AND CONDUIT
SHALL PROVIDE NEW CIRCUIT CONDUCTORS, CONDUIT, AND MOUNTING
FLOOD LIGHT FIXTURES TO ILLUMINATE EACH DAM TG BAY AREA. CONTRACTOR
DAM TG FLOOD LIGHTING (NEW): CONTRACTOR SHALL PROVIDE FOUR NEW
(BID ITEM 05)2.
LIGHTING.
REFERENCE DRAWING K-1 50/1.5 FOR ADDITIONAL DETAILS ON DAM CANOPY
WITH SECTION C "TECHNICAL SPECIFICATIONS". SEE APPENDIX B,
DAM CANOPY FIXTURES WITH NEW LED TYPE FIXTURES IN ACCORDANCE
DAM CANOPY LIGHT FIXTURE: CONTRACTOR SHALL REPLACE NINE EXISTING
(BID ITEM 04)1.
PLANS & DETAILS.
SEE APPENDIX B "REFERENCE DRAWINGS" FOR EXISTING DAM LIGHTING 5.
MOUNTING HARDWARE TO INSTALL NEW LIGHT FIXTURES.
CONTRACTOR SHALL PROVIDE ALL NECESSARY ACCESSORIES AND 4.
CONNECTIONS ARE SUITABLE FOR USE WITH NEW LIGHT FIXTURES.
MOUNTING CONNECTIONS, CABLE LENGTHS, AND ELECTRICAL
CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING ALL EXISTING 3.
CONTRACT. ALL OTHER ITEMS ARE EXISTING AND SHALL REMAIN.
ITEMS SHOWN IN BOLD IS WORK TO BE PERFORMED UNDER THIS 2.
WORK ITEM TO BE PERFORMED UNDER THIS CONTRACT.
"TECHNICAL SPECIFICATIONS" FOR DETAILED REQUIREMENTS OF EACH
OF THE LOCATIONS OF EQUIPMENT AND FEATURES. SEE SECTION C
DETAILS, RATHER IT IS INTENDED TO PROVIDE A GENERAL OVERVIEW
1. THIS DRAWING IS NOT INTENDED TO DEFINE ANY SPECIFIC WORK ITEM
REPLACE (TYP)
LIGHT FIXTURE
DAM CANOPY
REPLACE (TYP)
LIGHT FIXTURE
DAM CANOPY
NEW
2-#12 W/ GND
PANEL 'Z'
NEW
2-#12 W/ GND
PANEL 'Z'
NEW
2-#12 W/ GND
PANEL 'Z'
NEW
2-#12 W/ GND
PANEL 'Z'
MANUAL CONTROL
CONTROL BOX W/
PHOTOELECTRIC
120/240V, 1-PHASE
PANEL 'Z'
480V, 3-PHASE
PANEL 'Y'
480V DISCONNECTS
PANEL 'X'
EXISTING
MOUNTING STRUCTURE
REPLACE
POWER RECPT.
480V, 3-PHASE
A1
SCALE: 1/4" = 1'
LIGHTING PLAN - DAM SHEET 1 OF 2
E1
SCALE: N.T.S.
DETAIL - DAM CANOPY LIGHT FIXTURE (EXISTING)
1-PHASE
480V-120/240V
LIGHTING XFMR
File details come from the government source that posted it. Updated .