A00808-611940.pdf

PDF 1 MB Posted

Attached to
611940 SOMERVILLE FAP No. HIP(NGB)-003S(987)X Bridge Replacement, S-17-016 (3GF), Webster Avenue o
Solicitation number
BD-27-1030-0H100-0H002-133205
Issued by
Middlesex County, Massachusetts

About this file

Summary

This is a Project Utility Coordination (PUC) Form for the Massachusetts Department of Transportation (MassDOT) Highway Division related to Proposal No. 611940-136645, a bridge replacement project in Somerville, Massachusetts. The document details the relocation and coordination of multiple utility systems required for the replacement of the Webster Avenue bridge over the MBTA and Boston & Maine Railroad (BMRR). The project involves extensive coordination among numerous utility companies including Eversource Electric and Gas, Verizon, Comcast, MBTA systems, MWRA, NGrid, AT&T, and various municipal departments. The scope encompasses relocation of electrical duct banks, gas mains, water and sewer lines, telecommunications conduits, and PTC (Positive Train Control) cable systems. The document establishes a phased approach with multiple sequential and concurrent utility relocation tasks, including advance work, temporary pole installations, underground-to-overhead conversions, and final installations following bridge demolition and reconstruction. The project involves seven utility poles to be relocated, with work scheduled between February 2024 and August 2026.

The utility relocation work is structured across two main stages with multiple phases and tasks, with estimated durations ranging from one to 208 work days depending on the specific utility operation. Key requirements include obtaining MBTA Utility Licenses, Eversource Grants of Location, street opening permits, and compliance with the 8M permit for work affecting MWRA facilities. The contractor must provide seven calendar days advance notification before utility mobilization and comply with seasonal restrictions on gas line work (prohibited November 15 to March 15). Critical coordination includes winter bypass requirements for gas service, temporary shoring and support systems during bridge demolition, tree trimming by line clearance qualified personnel, and comprehensive traffic control and access provisions. The document indicates that utilities will work concurrently where feasible and establishes clear responsibility assignments between the contractor, utility companies, MassDOT, and the City of Somerville for each task component.

View the file

Other files

File Type Posted
A00813-611940.pdf PDF
611940 Bid Items List.txt TXT text file
A00801-611940.pdf PDF
A00811-611940.pdf PDF
A00814-611940.pdf PDF
A00802-611940.pdf PDF
A00875-611940.pdf PDF
611940 - Notice to Contractors.pdf PDF
A00844-611940.pdf PDF
A00815-611940.pdf PDF
611940 - Plan Holders List 9-22-2026.pdf PDF
A00812-611940.pdf PDF
A00820-611940.pdf PDF
SOMERVILLE-611940-136645-A-1.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Massachusetts Department Of Transportation Highway Division Proposal No. 611940-136645

A00808 - 1

DOCUMENT A00808

PROJECT UTILITY COORDINATION FORM

Massachusetts Department Of Transportation Highway Division

A00808 - 2

THIS PAGE INTENTIONALLY LEFT BLANK

7/31/2025

Revision Date:

Mass DOT PM: Total Poles Relocated: 7/31/2026

PRINTED

Yes No Agreement YES NO YES NO UG OH

Eversource Electric Luis Escobar

Ned Sadowski

(617) 629-3203

(617) 541-5714

(413) 537-6594 luis.escobar@eversource.com ned.sadowski@eversource.com x x x x x

Eversource Gas Jeffrey Evans-Mongeon (508) 305-6970 (802) 505-5253 Jeffrey.Evans-Mongeon@eversource.com x x x x

Somerville Fire

Sean Tierney (Deputy Chief) Charles Breen (Chief)

Jeff Barbier Kristofer Cali (DPW)

(617) 623-1700 x

(617) 666-3311 x

(617) 666-3311 x

(857) 274-2280 stierney@somervillema.gov cbreen@somervillema.gov jbarbiere@somervillema.gov Kcali@somervillema.gov x x x x

Somerville Street Lights Fire alarm

Eric Weisman Kristofer Cali

(617) 625-6600 x5165

(617) 666-3311 x5607 eweisman@somervillema.gov Kcali@somervillema.gov x x x x x

Verizon Paul Diamantopoulos (978) 382-2855 (508) 245-5522 paul.e.diamantopoulos@verizon.com x x x x x

Astound/RCN Jennifer O'Neill

Alex Ortiz

(781) 316-8890

(781) 316-8878

(617) 756-9881

(617) 839-2845 jennifer.oneill@astound.com Alex.Ortiz@astound.com X x x x

MWRA Water Ralph Francesconi

Inspector (617)461-3573

(617) 305-5833

* Ralph.Francesconi@mwra.com x x x x x

MBTA Christine Bresnahan (617) 222-3361 (617) 455-7087 CBresnahan@mbta.com

MBTA RROPS Robert Proulx (617) 222-8364 (857) 330-2813 rproulx@mbta.com

Keolis - Signals Steve Merrill Mario Pinto

(617) 222-8445

(617) 438-2899 steve.merrill@keoliscs.com mario.pinto@keoliscs.com

Keolis Flagmen James Welch

Stephen Boran William Wallace

(617) 222-8428

(617) 438-2899

(857) 260-4871

James.Welch@KeolisCS.com Stephen.Boran@keoliscs.com William.Wallace@keoliscs.com

MBTA - PTC Cable Lee Remi

Kevin Ford Ryan Metcalf

(617) 519-9122 lremi@mbta.com kford2@mbta.com RMetcalf@MBTA.com

MBTA BUS

ESTIMATOR

Alexander Anhwere-James (617) 595-9635 aanhwerejames@mbta.com

Reimbursement

COAX & FIBER OH service R&R -P# 253/6 – Coax and Fiber needs to be rebuilt from reset pole (253/6). Will transfer if possible

8M Permit #3668 - ADJ MWRA Water Gates and Cathodic Protection Stations - Inspection required, follow 8M permit.

Route/Street: Asst. Dist Const /Dist Utility Reimb. Eng Scheduled Ad Date:

(339) 364-1855

Michael Winnick 857 368 4000 Br. Replacement S-17-16 Webster Ave over MBTA Alwin Ramirez

Contact Office #

MassDOT Consultant - CHA Consulting, Inc. Michael Sullivan Molly Dempsey

Consultant: Contact: Office #

Utility Company

City/Town: PUC Completed by:Project File #: Utility Pole Set:

CONTACTS AND GENERAL UTILITY INFORMATION

Project Utilities Coordination (PUC) Form

Somerville Ghita Ridadarajat Eversource

Non-Reimb'le Notes

No Power, Signal or Comm Disruptions anticipated

Coordinate with Keolis -for Flagging a Contract Allowance Items for PTC Cable R&R.

No Greenline flagging Required

Full closure, difficullt - Fitchburg line Riders take Redline to Porter St.

Cell # Email

MBTA

Utilities On Bridge/Structure

MSullivan@chasolutions.com mdempsey@chasolutions.com

611940

Amanda.Klemm@dot.state.ma.us/781-570-1154

Email

Utilities Underground (UG)

/Aerial (OH)

Potential for District Initiated Early Relocation *

Contract Item. Fire Alarm in VZ duct to be relocated over track on OHW, and later installed back into Vz Conduit. Hard wired Fire Alarm Box R&S and Repalced with New Radio Box

2 Somerville Street Lights Repalced with New - Contract Item

Scope, Budget, Duration Submitted

Cell #

8/15/2026

Relocation of Eversource ug Duct bank on Bridge - EV to Cut in Bypas over Prospect (ongoing) so they can cut and cap 2-13Kv circuit.

New 8" also requested in 12" casing

Relocation of 8" w/12" Casing low Pressure 1949 line over Bridge. May be temp Cut and Capped, but need a temp 2" bypass over winter - Also add a new 12" Casing pipe for future use.

Eversource would have a minimum shutdown temperature of 10 degF. If the job can be done in one season there no need to a temporary 2" relay over winter season(4/30/2024)

Temp Relocation of all cables overhead, to Poles (Contract Item and Contract Items for all ug Conduit, then final relocaton into bridge w/Fire alarm 2 fiber cables and 1 copper)

(857-368-9368)

Proposal No. 611940-136645

A00808 - 3 https://hwyapps.massdot.trans.internal/ProjectInfoNET/(S(ejmxidde0qjdbojkayqw5gib))/ProjectSummary.aspx?ProjectNumber=611940 mailto:Ghita.a.ridadarajat@dot.state.ma.us mailto:Michael.Winnick@dot.state.ma.us mailto:Alwin.Ramirez@dot.state.ma.us mailto:Amanda.Klemm@dot.state.ma.us/781-570-1154 mailto:terence.doonan1@eversource.com mailto:terence.doonan1@eversource.com mailto:Jeffrey.Evans-Mongeon@eversource.com mailto:jlathan@somervillema.gov mailto:jlathan@somervillema.gov mailto:jlathan@somervillema.gov mailto:jlathan@somervillema.gov mailto:eweisman@somervillema.gov mailto:eweisman@somervillema.gov mailto:eweisman@somervillema.gov mailto:paul.e.diamantopoulos@verizon.com mailto:jennifer.oneill@astound.com mailto:jennifer.oneill@astound.com mailto:Ralph.Francesconi@mwra.com mailto:CBresnahan@mbta.com mailto:rproulx@mbta.com mailto:steve.merrill@keoliscs.com mailto:steve.merrill@keoliscs.com mailto:James.Welch@KeolisCS.com mailto:James.Welch@KeolisCS.com mailto:James.Welch@KeolisCS.com mailto:lremi@mbta.com mailto:lremi@mbta.com mailto:lremi@mbta.com mailto:aanhwerejames@mbta.com mailto:aanhwerejames@mbta.com mailto:Michael.Winnick@dot.state.ma.us mailto:Alwin.Ramirez@dot.state.ma.us mailto:Ghita.a.ridadarajat@dot.state.ma.us https://hwyapps.massdot.trans.internal/ProjectInfoNET/(S(ejmxidde0qjdbojkayqw5gib))/ProjectSummary.aspx?ProjectNumber=611940 mailto:Amanda.Klemm@dot.state.ma.us/781-570-1154

Eversource UG Transmission

Aaron Welles Jack Strollo

Cornerstone Energy Inc. - Kirby Brown (Transmission ROW)

Merideth, Eamon

(781) 441-3973

(509) 923-8713

(339) 225-5463 aaron.welles@eversource.com jack.strollo@eversource.com kirby.brown@eversourceenergy.com

Somerville Water Virginia Adams (PM)

Neil Viner (Superintendent) Carlos Perez

(617) 625-6600 x5816

(617) 625-6600 x5812

(617) 625-6600 x5815 vadams@somervillema.gov nviner@somervillema.gov CPerez@somervillema.gov

Somerville Sewer Jay Hayden (Superintendent)

(617) 625-6600 x 5854 jhayden@somervillema.gov

Somerville DPW Engineering

Kristofer Cali Jonathan Smith

Jill Lathan (Commissioner) Brian Postlewaite

Jeffrey Barbiere (Hwy)

(617) 666-3311 x

(617) 625-6600 x

(617) 625-6600 x kcali@somervillema.gov jsmith@somervillema.gov jlathan@somervillema.gov bpostlewaite@somervillema.gov jbarbiere@somervillema.gov engineering@somervillema.gov

Somerville OSPCD- Mobility Div

Brad Rawson (Director) Viola Augustin

(617) 625-6600 x

(781) 254-3947 brawson@somervillema.gov vaugustin@somervillema.gov

CSX Michael Sliper (518) 767-6081 Michael_Sliper@csx.com

MBTA - Plans Requests

Silvia Walsh archives@mbta.com

MBTA - PTC Cable Lee Remi

Kevin Ford Ryan Metcalf

(617) 519-9122 lremi@mbta.com kford2@mbta.com RMetcalf@MBTA.com

MBTA Parking Operation

Curt Chiverton CChiverton@MBTA.com

MBTA Bus Michael Seegers

Nicholas Tomkavage MSeegers@MBTA.com ntomkavage@MBTA.com

MBTA Robert Zmudzinski (212) 377-8549 robert.zmudzinski@aecom.com

PTC & ATC

Jaime Garmendia

Greg Gooden Nicole Bulger

(617) 293-9234

(540) 292-5428 jgarmendia@mbta.com william.gooden@wsp.com Nikole.Bulger@wsp.com

Keolis - Track William Wallace (857) 260-4871 William.Wallace@keoliscs.com

Keolis Estimator Swarna Arza Swarna.Arza@keoliscs.com

Keolis- Communications

Christopher Bruno christopher.bruno@keoliscs.com

Comcast James Fitzpatrick

Michael Cook

(860) 304-3909 James_Fltzpatrick@comcast.com Michael_Cook7@comcast.com

MWRA Sewer Kevin McKenna (617) 305-5956 Kevin.McKenna@mwra.com

NGrid Gas Melissa Owens Ryan Cormier

(781) 907-2845

(617) 592-7850

(781) 392-4782

Melissa.Owens@nationalgrid.com Ryan.Cormier@nationalgrid.com

ZAYO Richard Moran (978) 844-7525 richard.moran@zayo.com

Light Path Jeff Harrington

Daniel Colon

(617) 999-5371

(603) 320-5120 jeff.harrington@lightpathfiber.com daniel.colon@lightpathfiber.com

First Light Heather Araujo (207) 432-2045 (978) 302-9334 FirstLight_MA@firstlight.net haraujo@firstlight.net

Enbridge Kathy M. Aruda (508) 938-7728 (617) 921-4910 kathleen.aruda@enbridge.com

AT&T

Erica Hudson Bob Jordan

(781) 221-8400 x7041

(781) 221-8400 x7014

(781) 640-3357 erica.hudson@sienaengineeringgroup.com bob.jordan@sienaengineeringgroup.com

Vz SM Cell Liz Glidden

Sean Conway

(508) 245-8832

(508) 320-2017 elizabeth.glidden@verizonwireless.com Sean.Conway@verizonwireless.com

Eversource Fiber Bechir Khoury

Farzin Tahmasbi (Lead Egr) Tomi Fadipe

(781) 441-3864

(858) 449-5456

(781) 441-3864 bechir.khoury@eversource.com farzin.tahmasbi@eversource.com oloruntomi.fadipe@eversource.com

ZAYO

Mark Bonanno Mark Vegnani

(508) 616-7818

(508) 208-9117

(617) 828-1415 mark.bonanno@zayo.com Mark.Vegnani@zayo.com

Lumen Michael Mugo (857) 706-6414 (978) 908-0313 michael.mugo@lumen.com

MCI Verizon Stephen Parretti

Tremain Ferandes

(508) 248-1305

(508) 248-1309

(508) 892-3381

(617) 953-9575 stephen.parretti@verizon.com tremain.k.fernandes@verizon.com

Suggested Sequence of Relocation ( Based on Consultant proposed construction staging)

No Facilities or No Conflicts

Set Up Bi Weekly

No Facilities - RCS

No Facilities No Conflicts 2024 02 23

No Facilities, No Conflict 2024 02 23

2026 2 13 No Facilities

Bus Routes Detour

2025 2 19 No FACILITIES

No Facilities No Conflicts 2024 02 23

026 2 13 No facilities

The sequence as detailed on the following pages is based on the consultants proposed staging plan. This information was compiled through meetings that included all of the utilities listed below along with the designer and the City of Somerville. The information provided is the best available information prior to project advertisement.

No Facilities 2 26 2025 old trolly tracks on Webster - unknown remaining facilities MWRA 8M Permit 3668 - Note this is only a prelim permit initiated for liability the Contractor must Complete the provisions and include additional information such as crane placement etc. Comply with 8M Permit, RE: Vibration Monitoring, Personell, Equipment, Activities requiring Inspection, Replacement MH Frames and Covers, etc R&S massDOT Temp Shoring Towers under bridge to the massDOT Peabody Depot - Contact Bridge Section to confirm stacking requirements, schedule and precise location, Cribbing, etc., Christopher.Leahy@dot.state.ma.us

Utility Relocation Notes for MassDOT Contractor Unless otherwise noted by Contract, the MassDOT Contractor is to provide the District Construction Office with 7 Calendar Days advance notification in order to validate the current progress and provide the required 30 Days advance

Additional notes:

No Facilities No Conflicts 2024 02 26

No Facilities

No Facilities 2 20 2025

No Facilites on Webster St - But Ng has a 36" CI 22# 1898 Gas Main on Prospect over MBTA

No Facilities- Ghita

Existing PTC on OHW over tracks

Contract Items for 20" water Relocation on approach - Next to MWRA on utility bridge

For Information Only

Sewer Under MBTA - Contract Item to Adj

SMH

Substation on Site - Request for screening fence on Bridge - Existin and Prop 115kV line on Prescott - Review any Excavation carefully for PTC at the corner of Webster and Prescott. New transmission alternatives to this substation are being evaluated.

Proposal No. 611940-136645

A00808 - 4 mailto:aaron.welles@eversource.com mailto:aaron.welles@eversource.com mailto:aaron.welles@eversource.com mailto:aaron.welles@eversource.com mailto:water@somervillema.gov mailto:water@somervillema.gov mailto:water@somervillema.gov mailto:jhayden@somervillema.gov mailto:kcali@somervillema.go mailto:kcali@somervillema.go mailto:kcali@somervillema.go mailto:kcali@somervillema.go mailto:kcali@somervillema.go mailto:kcali@somervillema.go mailto:vaugustin@somervillema.gov mailto:vaugustin@somervillema.gov mailto:Michael_Sliper@csx.com mailto:archives@mbta.com mailto:lremi@mbta.com mailto:lremi@mbta.com mailto:lremi@mbta.com mailto:CChiverton@MBTA.com mailto:robert.zmudzinski@aecom.com mailto:William.Wallace@keoliscs.com mailto:Swarna.Arza@keoliscs.com mailto:christopher.bruno@keoliscs.com mailto:Wendy_Brown@comcast.com mailto:Wendy_Brown@comcast.com mailto:Kevin.McKenna@mwra.com mailto:Melissa.Owens@nationalgrid.com mailto:Melissa.Owens@nationalgrid.com mailto:richard.moran@zayo.com mailto:jharrington@cambridgenetsolutions.com mailto:jharrington@cambridgenetsolutions.com mailto:haraujo@firstlight.net mailto:haraujo@firstlight.net mailto:kathleen.aruda@enbridge.com mailto:erica.hudson@sienaengineeringgroup.com mailto:erica.hudson@sienaengineeringgroup.com mailto:mark.bonanno@crowncastle.com mailto:mark.bonanno@crowncastle.com mailto:stephen.parretti@verizon.com mailto:stephen.parretti@verizon.com

Yes No 7/31/2026 x PRINTED

Yes No x

Exclusive Utility on site

Concurrent Utilities

Contractor Off-Site

Contractor Concurrent

C

Co nt ra ct or U

U til ity

C o.

U til ity w or ki ng w ith n o ot he r U til iti es in v ic in ity

U til ity w or o th er iti es o n si te

N o

Co nt ra ct or ph ys ic al co ns tr uc tio n op er at io ns o n-si te

(w hi le U til ity is Co nt ra ct or a nd ity re or ki ng o n-si te bu t N

O T in th e sa m e vi ci ni ty

Stage : 1 Phase : A

Task: 1 C

Task: 2a U 200 x x * Advance Work DUCE EST*

U 3 x x U 13 x x U 3 x x U 7 x x

Task: 3a C U 120 x c *DUCE EST * C 30 x c *DUCE EST * C C C C C C C

Task: 3b C U 100 x x * DUCE EST * C

U 2 x x U 4 x x U 12 x x U 31 x x U 5 x x

C

Task: 4 C

C

K 5 x x *DUCE Est -

K x x *DUCE Est -

Contractor Fire Line Crew to remove dead cables.

MBTA Utility License, Somerville Street opening 20' Conduit Permit - Start this 1 year in advance

Sub-Total

Contractor provide wire as specified by Keolis to the next Splice to the west (Eng Est 2500'!)

OHW will run underground from Sta 53+80 LT to Sta 51+00 LT only - and 2500' overhead.

Keolis Splices over and Removes old OHW. Contractor reimburses Keolis through Contract Allowance item 999.860 2 Sub-Total 7

Meeting with Res Eng DURE

1st Relocation of Verizon Duct Bank - Temp Poles on MBTA for Vz and Fire Alarm - Contract Item

Utility Co. MBTA OHW to UG

Meeting with Res. Eng. DURE, and Fire Dept - Contractor must do all the Work and have all the Wire approved

Installs Utility Poles, strand, guys and anchors as req, conduit and risers, from TMHs through walls and spans to Poles for Fire

Contractor fire to splice Contractor Fire Crew to rod and rope conduit and place cables

Contractor to install 2-4"conduits, 2 sweeps, handholds, plus spare , risers, etc. as detailed in Specials, & 2 Guy Anchors, ground rods, Keolis to install the wire underground & approx. 2500 feet overhead to the west

Utility Co. Verizon Install new cable overhead and cut away cables in bridge to allow for bridge demo

UTILITY OPERATIONS - Eversource Electric - Cut and Cap 2- 13.8 kV lines and R&R 3x3 Lighting, UP R&R, And 2 - Light Poles R&R

Cut cables & remove existing primary within the Webster Ave Bridge

Vz Abandons old conduit for removal by Contractor - Contractor Tests for Haz Mat

Vz Contractor to perform TMH tie ins Vz to install strand and guying Vz Line Crew to rod and rope conduit and place cables Vz Splice Crew to Splice in Cables Vz Line Crew to remove dead cables.

Sub-Total 154

Utility Co. Somerville Fire Alarm Install new cable overhead and cut away cables in bridge to allow for bridge demo

RE

SP

O N

SI

BL

E

PA

RT

Y

Is 'enabling' (prep) work, by the Contractor, necessary prior to the start of the first series of utility relocations:

Has any of the Utility work been identified to work concurrently

Concurrent / Exclusive Utility Work Contractor note: In planning and executing the work, the Access Restraints listed in the Special Provisions, takes precedence over the checklist in these 4 columns.

Access Restraint & Limitations of Operations Notes

Should an AR be considered for the Contractor ?

Es tim at ed

D ur at io n (W or k

D ay

s) b y U til iti es

(L ea d tim e no t i nc lu de d)

PUC FORM - CONTINUED

DESCRIPTION - Utility Relocation Phases, Tasks and Activities

Po te nt ia l A cc es s R es tr ai nt

(Y

/N o)

Re as on /N ot e

(o pt io na l)

Route/Street:

Project File #:

SomervilleCity/Town:

611940

Br. Replacement S-17-16 Webster Ave over MBTA

Sub-Total

UTILITY OPERATIONS - Work Required to Close & Demo Bridge Utility Co. Water 12" Main on South Abutment

Contractor Fire Abandons old conduit to Verizon

Street opening for all Conduit at Webster and Prospect, and on MBTA - start 60 days min in advance

MBTA Utility License, - Start this 1 year in advance

Contractor to install deep Water main on South abutment - This is early action as it is very deep.

Sub-Total

UTILITY OPERATIONS -MBTA PTC Relocation - Before Demo to Protect OHW

Enabling' work by the Contractor: Pre-bridge closure all utilities must precure MBTA utility and access Licenses. Call in dig safe to mark out UG, MWRA 8M Permit requires an on site inspector, and for Contractor submit Prop. Equipment, Personnel and procedures for approval and to meet on site, etc., Coordinate with DURE and meet all Utilities and walk site to confirm Prop. Pole Re-Locations and delineation of work. Coord with DURE to send 30 day notices for force account work. Note - Meet in advance with Eversource, tree warden and Contractor to review tree trimming required. Request quote from Keolis for splicing PTC. to be reimbursed by contract allowance item.

Contractor installs new Radio Controlled Fire Box.

Utility Co. Eversource Electric 2-13.8kv Circuits MBTA Utility License and MassDOT Permit for Conduit on Prospect St Bridge - Start this 1 year in advance(Start in Design) Install 60ft. of 6-4" conduit MH4121->MH25391 - Install 20 sections of 3-700FS cable Make straight splices in 2 MH's

A00808 - 5

Exclusive Utility on site

Concurrent Utilities

Contractor Off-Site

Contractor Concurrent

C

Co nt ra ct or U

U til ity

C o.

U til ity w or n o ot he r U til iti es in v ic ity w or o iti es o n si te

N o

Co nt ra ct or ph ys tr uc tio n op er at io ns o n-le U til ity is Co nt ra ct or ity ki ng o n-si te bu t N

O T in th e sa m e vi ci

RE

SP

O N

SI

BL

E

PA

RT

Y Concurrent / Exclusive Utility Work

Contractor note: In planning and executing the work, the Access Restraints listed in the Special Provisions, takes precedence over the checklist in these 4 columns.

Access Restraint & Limitations of Operations Notes

Should an AR be considered for the Contractor ?

Es tim at ed

D ur at io n (W or k

D ay

s) b y U til d tim e no t i nc lu de d)

DESCRIPTION - Utility Relocation Phases, Tasks and Activities

Po te nt ia l A cc es s R es tr on /N ot e

(o pt io na l)

Task: 5a C

C

C

C

U

U 3 x x U 3 x x U 6 x x U 2 x x U 2 x x

Task: 5b

C x x

*DUCE Est -

C 2 x x *DUCE Est -

U 3 x x U 10 x x U 2 x x U 1 x x U 1 x x U 4 x x U 2 x x

Stage : 2 Phase : _

Task: 5c C C C

C

U 4 x x U 15 x x

U 5 x x

U 5 x x

U 2 x x

U 2 x x

U 8 x x

U 4 x x

Task: 2b C

U 2 x x * DUCE Est>

C

U 5 x x * DUCE Est>

Task: 2c C 100 * DUCE Est>

C 2 * DUCE Est>

C 2

* DUCE Est>

U 1 x x

U 1 x x

C 100 * DUCE Est>

U 1 x x

C 1

* DUCE Est>

Install 8" PL LP main: Excavate trench on either side of Webster Ave Bridge, install 8" PL main up to bridge abutments

Install 2" PL LP bypass: Install 2" PL through 4" STL casing across temporary utility bridge Pig new main

Backfill and restore excavations

Pressure test new main Excavate, tie-in and activate new main at two locations

Sub-Total 208

Contractor submits the prop Gas work Casing Pipes and Gas Plans as MBTA Access permit.

Relocation of Ev 9 duct bank -

Receive Notice to Proceed and Mobilize crew to site Mobilize, materials delivery and project planning Excavate test holes to confirm main material and isolation locations Excavate isolation holes, shore and prepare mains for retirement Isolate and abandon existing 12" CI LP main Backfill and restore excavations

Mobilize, materials delivery and project planning

Install 8" PL LP main: Insert 8" PL LP main into 12" STL casing (by others) Non-FA Work: Insert 8" PL main into 12" STL casing (by others) Pig new main Pressure test new main Excavate, tie-in and activate new main at two locations

Contractor provides Approved Shop Drawing to Ev so Ev may complete design and submit to DPU (9Months)

Install steel carrier pipe across bridge. Fasten Roller supports. Provide work area for EV at Approaches to install plastic Gas Main with all main connections/ties.

Once Power's cut - Contractor coordinates with Somerville Lights and Lines to R&D or Stack Light Poles, Arms, &/or LED & remove old charge from Existing Account.

Contractor coordinate with gas to ensure EV gas has 8M permit and MBTA licenses as required

Sub-Total

Eversource to live break EMH4116, EMH 25108

Ev pull new cables, Splice, cut any cable in old duct near S. Abutment and abandon old duct- Likely no work required as backup works fine

Contractor to install conduit(Contract Item-1-4" PVC Sched 80"/Sched 40 concrete encased) Conduit from EMH to Prop St Light Foundation - The Material and size of Conduit is as approved by the Ev WO - the Measurement and Payment is under the Contract Item. The WO fees and permit/Inspection is under Hwy Light Pole 821.01 Ev cuts out a hole in EMH for new conduit to street light -

Contractor installs new City of Somerville approved foundation and Street light Contractor applies for a Eversource WO# acting for Somerville to add new Light poles, end old account and starts a new account

Contractor applies for a Eversource WO acting for Somerville disconnect two old Street Light poles, and remove those from the Somerville account.

Eversource Cut power to old light from EMH # and also Disconnect OHW to LP#. Contractor to provide temp lighting if necessary

Ev Pull wire from EMH to Streetlight and powers up light.

Utility Co. Eversource Electric 9-5" Duct

Contractor submits the prop Gas work Casing Pipes and Gas Plans as Access permit.

MAG drill all roller support holes for EV on utility bridge supports. One hole must be slotted.

Backfill and restore excavations

Eversource Gas - Cut and Cap Lines over Bridge -5a) Ev cut gas line over Bridge, 5b.) Contractor design and build a 2" Bypass over Bridge-" Winter by Pass" this must be approved before 8" active line is cut, c.) Contractor Installs 12" Casing Pipe4.) Ev Installs new Plastic into the new bridge, and Cut winter by pass d.) Contractor removed abandoned winter bypass.

Sub-Total

Utility Co. Eversource gas 12"

Provide laydown area and traffic control for gas work

Complete conc encasement trench Backfill and Patch Roadway

Utility Co. Eversource Electric Street Lighting (2 Light poles may be Removed and replaced after bridge demo) Sub-Total

Install 9-5" Conduit from EMH 4116 to EMH 25108 - Coord with Ev to break into EMH

Propose a Temp Support for Gas, acquire MBTA Access permit, Build Support, and give the Ev Gas NTP

Utility Co. Eversource GAS 2"BYPASS

Mobilize, materials delivery and project planning Install 2" PL LP bypass: Excavate trench on either side of Webster Ave bridge, install 2" PL main up to temporary bridge abutments

Contractor provide shop drawing of the Steel casing pipe and rollers to Ev for Approval.

Winter By pass - Install all Casing pipe and Support for EVERSOURCE to install a 2" plastic/CS line to maintain the system for winter.

The 2" line will be approximately 200' in length and must be constructed prior to November of the year the 8" line is cut and capped.

UTILITY OPERATIONS -

Enabling' work by the Contractor: Bridge Closure/ Demo and New Beams are set. Contractor to coordinate with MBTA BUS a year in advance. Coordinate and get approval from Eversource gas for temp gas by pass work plan (temp gas supports, access at bridge abutments, shielding existing tracks/MBTA during demo, various work platforms, TMP's). Contractor to provide shielding and support to the utility bridge. During Demo Contractor will R&D all Gas, Vz and Electric Ducts and unravaged cable.

Utility Co. Eversource GAS

Sub-Total 45

A00808 - 6

Exclusive Utility on site

Concurrent Utilities

Contractor Off-Site

Contractor Concurrent

C

Co nt ra ct or U

U til ity

C o.

U til ity w or n o ot he r U til iti es in v ic ity w or o iti es o n si te

N o

Co nt ra ct or ph ys tr uc tio n op er at io ns o n-le U til ity is Co nt ra ct or ity ki ng o n-si te bu t N

O T in th e sa m e vi ci

RE

SP

O N

SI

BL

E

PA

RT

Y Concurrent / Exclusive Utility Work

Contractor note: In planning and executing the work, the Access Restraints listed in the Special Provisions, takes precedence over the checklist in these 4 columns.

Access Restraint & Limitations of Operations Notes

Should an AR be considered for the Contractor ?

Es tim at ed

D ur at io n (W or k

D ay

s) b y U til d tim e no t i nc lu de d)

DESCRIPTION - Utility Relocation Phases, Tasks and Activities

Po te nt ia l A cc es s R es tr on /N ot e

(o pt io na l)

Task: 2d1 U 2 x x *DUCE Est -

C 2 x x

U 5 x x *DUCE Est -

C 2 x x

Task: 2d2 U 21 x x

U 30 x x

Task: 2d3 U 2 x x *DUCE Est

Task: 4b C C

U x x *DUCE Est -

Task: 2b C

U 2 x x

C

U 10 x x

Task: 3c c U 3 X X

U 4 X X

U 12 X X

C 2 DUCE EST

Task: 3d_ c 1 *DUCE Est -c C U X X c

Task: 7_ C C

U 2 X X *duce est * U 2 X X *duce est * U 2 X X *duce est *

C C

Eversource gas.

Contractor Does MWRA Water

R&R Utility Pole and Overhead Wires

UP Relocation Total Utility Co. MBTA UG at bungalow - possible conflict with Wing wall footing at North Abutment

Astound transfers to new Pole and runs new cable into property

Contractor to install conduit for the new fire alarm box Contractor pulls new -Approved ug Cable and makes splices in TMH Contractor to splice over the cable & Coordinate with City for Signal Check Contractor to remove old cable from pole & all pole attachments

Utility Co. Eversource Electric 2 new 6-5" Duct After Bridge Installation Install 2 new 6-5" Conduit from EMH 4116 to EMH 4115 - Coord with Ev to break into EMH

Sub-Total 2

Sub-Total

Contractor installs Conduit for MBTA

Utility Co. Fire Alarm

Astound removes attachment from old Pole

Utility Co. Eversource Electric R&R Utility Pole EV Removes old Pole

Keolis Splices over and removes old ug cable. Contractor reimburses Keolis through Contract Allowance item 999.860 Sub-Total

Contractor to install conduits, handholds, sweeps, and wires for PTC

Sub-Total

Eversource to live break MH4115 Complete conc encasement trench Backfill and Patch Roadway Ev pull new cables, Splice, cut any cable in old duct near s Abutment and abandon old Duct

VZ to remove cables from poles

The contractor performing the tree trimming within the electrical space must be Line Clearance Qualified

Water

Access - Unless otherwise noted in the Contract, and in addition to the 'enabling' notes above, the Contractor must provide safe and unimpeded access (for trucks, lifts, cranes, etc.) to the Utilities, to allow for the proposed relocation(s) - including but not limited to snow removal, clearing and grubbing, guard rail removal, barrier removal, tree removal, and grading. Any costs associated with these tasks are deemed to be incidental to the project.

For all MassDOT construction contracts issued after January 2014, the new Utility Coordination/documentation specification is required. This is Section 8.14 in Design-Bid-Build Contracts (see Design-Build index reference for applicable section #).

Prior to starting any and all enabling work for Utilities, the Contractor is to plan in advance with submittals and approved durations.

* Potential District Initiated Early Utility Relocation - if noted herein, the District reserves the right to initiate early utility relocation in advance of the Contract NTP. In submitting a bid price and in the development/basis of the Baseline Schedule, the Contractor shall not plan the Work with the potential benefit of any form of 'early utility relocation.' As a requirement of the Baseline submission, unless otherwise noted in this Specification, the earliest that the first Utility company is to receive the 30 days advance notification to mobilize to the site, will be 7 calendar days after the pre-construction meeting and never sooner than 7 days after the Contract NTP.

"Potential Access Restraints" noted within this PUC Form are for planning purposes. See MassDOT Contract for Contractual Access Restraints (refer to Subsections 8.02, 8.03, and/or 8.06 for Design Bid Build Contracts and Volume II Section 9 for Design Build Contracts).

Utility non-work periods - For planning purposes, the durations above contain some non work days (contingency) for New England conditions (precipitation, high temperatures, low temperatures, snow, ice). Gas line work however, typically has a seasonal restriction and can NOT be installed from 15-November to 15-March. Municipally Owned Electric and Gas Utilities are also restricted from proceeding from 15-November to 15-March. The Contractor shall (and the CTD plan) reflect this calendar restriction within the schedule (unless otherwise note).

IMPORTANT BASIS NOTES - FOR CONTRACTOR

Sub-Total

"Concurrent Utilities" operations noted herein, are to signify those Utility Company operations that can be worked concurrently (e.g. Utility A and Utility B work on-site together) - MassDOT and the Contractor are to prepare NTPs to Utilities accordingly.

Unless otherwise specified in the MassDOT Construction Contract, or unless specifically noted within this PUC Form, these durations (herein) are based upon the Contractor providing unimpeded access to the Utility company to perform Utility relocations (see Note 5 - Access).

Sub-Total 11

Utility Co. Eversource Electric R&R Utility Pole UP #253-6 - No Request for Reimbursement by Force Account submitted

Contractor performs Tree trimming, Stakes out UP(Line and Grade), meets in field with Res Eng, DURE, Ev, Astound, Vz… EV applies for a Grant of Location(90 work days - this must start before the 30 day NTP)

Ev Installs UP and Transfers Secondaries, & ohw service into business and Removes old OHW Contractor Coordinates with Property owner to remove private light facilities from UP

Utility Co. Astound _ (Coordinate in Advance this may be reduced)

Sewer inspection by the city

Sub-Total

Utility Co.

Telephone

UTILITY OPERATIONS - Adjustments - Multiple adjustments may be required for Full depth area.

Remove old OHW and guying

VZ line rod and rope conduits and place cables VZ splice to cut over the cable

Utility Co. Verizon

UTILITY OPERATIONS - Prop Conduits in Bridge (after Beams prior to Deck) Installation

VZ to perform manhole tie ins Contractor to install 6-4" new conduits on Webster ( PVC Conc Ended on Approaches, FRE with Hangers and Exp Joints on Bridge)

Sub-Total

Drainage

Eversource

A00808 - 7

THIS PAGE INTENTIONALLY LEFT BLANK

A00808 - 8