A00801-616302.pdf
PDF 690 KB Posted
- Attached to
- 616302 BELCHERTOWN-HAMPDEN-MONSON-SOUTH HADLEY-SOUTHWICK Maintenance and Preservation of Municipal
- Solicitation number
- BD-27-1030-0H100-0H002-130918
- Issued by
- Hampden County, Massachusetts
About this file
This is a Special Provisions document issued by the Massachusetts Department of Transportation Highway Division for a bridge maintenance and preservation project (Proposal No. 616302-134929, Contract A00801) spanning five municipalities: Belchertown, Hampden, Monson, South Hadley, and Southwick. The project encompasses maintenance and preservation work on five municipal bridges, including removal and replacement of structural steel, cleaning and painting, bearing repairs, deck repairs, railing repairs, substructure repairs, wearing surface repairs, and maintenance of traffic during all operations. Work locations include Bridge B-05-009 (Allen Road, Belchertown), Bridge H-04-001 (Mill Road, Hampden), Bridge M-27-002 (Cushman Street, Monson), Bridge S-18-010 (Morgan Street, South Hadley), and Bridge S-22-001 (North Loomis Street, Southwick), with specific repair requirements varying by location. The project is scheduled for day work (Monday through Saturday, 7:00 a.m. to 3:30 p.m.) with all work to be completed within one construction season. Prospective bidders must submit questions by 3:00 p.m. on the Tuesday before the bid opening date and are required to hold MassDOT pre-qualification in the Bridge Construction category; proposals are due electronically through www.bidx.com on August 11, 2026 at 2:00 p.m.
The project has an estimated value of $2.166 million and is subject to prevailing wage rates as determined by the Massachusetts Department of Labor and Workforce Development. Labor participation goals are established at 15.3% for minorities and 6.9% for women across all job categories for both contractors and subcontractors. A Proposal Guaranty equal to 5% of the bid value is required. Price adjustments apply to hot mix asphalt, Portland cement mixtures, diesel fuel, gasoline, and structural and reinforcing steel based on base prices of $712.50 per ton for liquid asphalt, $452.13 per ton for Portland cement, $4.497 per gallon for diesel fuel, $3.752 per gallon for gasoline, and a Steel Base Price Index of 362.0. The contract includes specific access restraints requiring one-lane alternating staged construction at four bridge locations and full closure at the Monson bridge location, with work restrictions mandating 30-day advance notification to municipalities, completion within one construction season, and temporary traffic control lasting no longer than 12 weeks. The work must comply with the 2026 Standard Specifications for Highways and Bridges, includes environmental compliance requirements such as contaminated soil evaluation and Policy Directive P-22-001 for soil stockpiling, and incorporates protection measures for Northern Long-Eared Bats and Tricolored Bats under the Endangered Species Act.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BELCHERTOWN-HAMPDEN-MONSON-SOUTH_HADLEY-SOUTHWICK-616302-134929-A-1.pdf | ||
| 616302 - Notice to Contractors.pdf | ||
| A00820-616302.pdf | ||
| A00870-616302.pdf | ||
| 616302 - Plan Holders List 7-28-2026.pdf | ||
| 616302 Bid Items List.txt | TXT text file | |
| A00803-616302.pdf | ||
| A00875-616302.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Massachusetts Department Of Transportation Highway Division Proposal No. 616302-134929
A00801 - 1
DOCUMENT A00801
SPECIAL PROVISIONS
BELCHERTOWN-HAMPDEN-MONSON-
SOUTH HADLEY-SOUTHWICK
Maintenance and Preservation of Municipal Bridges at Multiple Locations (D2 Contract 2)
Labor participation goals for this Project shall be 15.3% for minorities and 6.9% for women for each job category. The goals are applicable to both Contractor’s and Subcontractor’s on-site construction workforce. Refer to Document 00820 for details.
SCOPE OF WORK
All work under this Contract shall be done in conformance with the 2026 Standard Specifications for Highways and Bridges, the Supplemental Specifications contained in this book, the Construction Standard Details in effect as of May 2026, the 1990 Standard Drawings for Signs and Supports, the 2015 Overhead Signal Structure and Foundation Standard Drawings, the 11th Edition of the Manual on Uniform Traffic Control Devices (MUTCD) and the January 2026 Massachusetts Amendments to the MUTCD, the 1968 Standard Drawings for Traffic Signals and Highway Lighting, the latest edition of The American Standard for Nursery Stock, the Plans and these Special Provisions.
The work to be done under this Contact consists of removal and replacement of cleaning and painting of structural steel, bearing repairs, structural steel repairs, deck repairs, railing repairs, substructure repairs and wearing surface repairs.
The scope of work also includes maintenance of traffic during all operations according to the Temporary Traffic Control Plans as well as all other work as may be indicated on the design sketches (Document A00803) or within these specifications.
The extent of the work is location dependent; locations of work are listed below under the heading “Location of Work”.
All work shall be performed within, and accessed by, existing State, City or Town roadway layouts. No rights to enter on or occupy private property have been acquired for this project.
A00801 - 2
CONTRACTOR QUESTIONS AND ADDENDUM ACKNOWLEDGEMENTS
Prospective bidders are required to submit all questions to the Construction Contracts Engineer by 3:00 P.M. on the Tuesday of the previous week before the scheduled bid opening date. Any questions received after this time will not be considered for review by the Department.
Contractors should email questions and addendum acknowledgements to the following email address massdotspecifications@dot.state.ma.us The MassDOT proposal number and municipality is to be placed in the subject line.
LOCATION OF WORK
The following specific bridges are to have worked performed as follows.
BRIDGE
NO.
CITY /
TOWN
FACILITY
CARRIED/
FACILITY
INTERSECTED W
E
A R
IN
G
S U
R
FA
C E
R
PA
IR
S
D E
C K
R E
PA
IR
S
SU
B
ST
R
U C
T U
PA
IR
S
C L
E A
N
IN
G
PA
IN
T
IN
G
ST
U
C T
U R
A L
S T
EL
PA
IR
S
B E
A R
IN
G
R E
PA
IR
S
R A
IL
IN
G R
E
PA
IR
S
A
PP
R O
A C
H
SI
D
E W
A L
K R
E
PA
IR
S
B-05-009
(0PD)
BELCHER-
TOWN
ALLEN RD/
JABISH BROOK YES YES1 YES YES2 YES
H-04-001
(0QG) HAMPDEN
MILL RD/
SCANTIC
RIVER
YES YES 1 2 YES YES
M-27-
002 (172) MONSON
CUSHMAN ST/
CHICOPEE
BROOK
YES1 YES YES2 YES 3 YES
S-18-010 (0N1)
SOUTH
HADLEY
MORGAN ST/
STONY BROOK YES1 YES 2
S-22-001
(0RX) SOUTHWICK N LOOMIS ST/
MUNN BROOK 1 YES YES2 YES
1 Contractor shall hammer sound all abutment surfaces within Right-of-Way to determine whether additional spall and delamination repairs are required. Wingwalls are only to be sounded where repairs are included in the drawings.
2 After steel cleaning has been completed, steel shall be re-evaluated and additional steel repairs shall be developed, if required by the Engineer.
3. Clean and paint railings.
mailto:MassDOTSpecifications@dot.state.ma.us
A00801 - 3
SCHEDULE OF WORK
All proposed work hours shall conform to Subsection 7.09 and be subject to the written approval of the Engineer.
For specific locations, allowable work hours will be determined by the District Highway Director or designated representative.
Day Time Work at B-05-009 (0PD), H-04-001 (0QG), M-27-002 (172), S-18-010 (0N1), and
S-22-001 (0RX).
The work on this project is scheduled for a day work schedule based on a normal 8-hour day, 6-day week (M-Sa) from 7:00 AM to 3:30 PM, with the Contractor and all Subcontractors working the same shift, unless otherwise approved by the Engineer.
Work may not proceed beyond the normal 8-hour day unless prior approval is obtained from the Engineer for that day. Approval to work beyond the scheduled work will only be given when special conditions exist that warrant working beyond the scheduled work, as determined by the Engineer.
Work areas shall not be left overnight without safety precautions. All pertinent traffic warning devices shall be in place along with safety items, traffic barrier, etc.
These time periods include the "set-up" and "breakdown" of the traffic pattern employed. No operations, personnel, or equipment will be allowed on the roadways except during working hours.
The Engineer may direct the Contractor to cease any operation that is deemed unsafe, or which unduly impedes traffic, with no additional expense to the Commonwealth.
MassDOT has determined that the Contractor shall schedule work to expedite bridge work with a minimum disruption to road users and minimal impact to environmental resources while providing work zone safety. As a result, the Contractor is encouraged to perform concurrent work to facilitate on-time, on-budget project completion.
The Contractor shall schedule work to ensure the final coat of paint is not damaged by other operations. Any damage to coatings due to other Contractor’s operations shall be repaired at the Contractor’s expense.
The Contractor shall schedule operations such that any beam requiring temporary support or jacking shall be performed efficiently and will be paid once per location. This may require concurrent substructure and superstructure repairs.
A00801 - 4
SUBSECTION 8.06 LIMITATIONS OF OPERATIONS
Add/amend the following at the end of the Section:
Access Restraints:
An Access Restraint is a restriction of physical work, of a specific area or operation in the Contract, to allow all bidders to evaluate anticipated work restrictions, equally, during the pre-bid planning stages.
This Contract contains the following Access Restraints that shall be included in the Contractor’s Baseline Schedule submission, in accordance with the terms and conditions of the contract that identifies the Access Restraints noted below:
• AR#1 – Access Restraint #01: The Contractor shall use one lane alternating staged construction for Bridge Structure Number B-05-009 (0PD), Allen Road in Belchertown.
• AR#2 – Access Restraint #02: The Contractor shall use one lane alternating staged construction for Bridge Structure Number H-04-001 (0QG), Mill Road in Hampden.
• AR#3 – Access Restraint #03: The Contractor shall use one lane alternating staged construction for Bridge Structure Number S-18-010 (0N1), Morgan Street in South Hadley.
• AR#4 – Access Restraint #04: The Contractor shall use one lane alternating staged construction for Bridge Structure Number S-22-001 (0RX), North Loomis Street in Southwick.
Work Restrictions:
Additionally, this contract contains the following work restrictions:
• Bridge Structure Numbers M-27-002 (172) shall be closed to traffic, to accomplish the work described to repair and reopen the bridge to traffic.
• Proposed work must be completed in one construction season, no set ups are to be in place during winter shutdowns.
• All work must be scheduled and coordinated with the respective municipalities. The municipalities must be notified a minimum of 30 days prior to the work commencing.
• Each long term temporary traffic control shall be in place no longer than 12 weeks.
A00801 - 5
HOLIDAY WORK RESTRICTIONS
(Supplementing Subsection 7.09)
The District Highway Director (DHD) may authorize work to continue during these specified time periods if it is determined by the District that the work will not negatively impact the traveling public. DHD may allow work in those areas on a case-by-case basis and where work is behind barrier and will not impact traffic
Below are the holiday work restrictions:
New Years Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day. No work on local roadways on the holiday without permission by the DHD and the local police chief.
Martin Luther King's Birthday (Federal Holiday) No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.
President's Day (Federal Holiday) No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.
Evacuation Day (Suffolk County State Holiday) No work restrictions due to traffic concerns.
Patriot's Day (State Holiday) Work restrictions will be in place for Districts 3 and 6 along the entire Boston Marathon route and any other locations that the DHD in those districts determine are warranted so as to not to impact the marathon. All other districts work restrictions will be as per DHD.
Mother’s Day No work on Western Turnpike and Metropolitan Highway System from 5:00 AM on the Friday before, until the normal start of business on the following day.
Memorial Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the Friday before, until the normal start of business on the following day.
Bunker Hill Day (Suffolk County State Holiday) No work restrictions due to traffic concerns.
Juneteenth No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.
A00801 - 6
HOLIDAY WORK RESTRICTIONS (Continued)
Independence Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day. No work on local roadways on the holiday without permission by the DHD and the local police chief.
Labor Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the Friday before, until the normal start of business on the following day.
Columbus Day (Federal Holiday) No work on major arterials from 5:00 AM on the Friday before, until the normal start of business on the following day
Veterans' Day (Federal Holiday) No work restrictions due to traffic concerns.
Thanksgiving Day (Federal Holiday) No work on major arterials from 5:00 AM two days before until the normal start of business on the following Monday.
Christmas Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day.
SUBSECTION 8.02 SCHEDULE OF OPERATIONS
Replace this subsection with the following:
An integrated cost and schedule controls program shall be implemented by the Contractor to track and document the progress of the Work from Notice to Proceed (NTP) through the Contractor Field Completion (CFC) Milestone. The Contractor’s schedules will be used by the Engineer to monitor project progress, plan the level-of-effort required by the Department’s work force and consultants and as a critical decision-making tool. Accordingly, the Contractor shall ensure that it complies fully with the requirements specified herein and that its schedules are both accurate and updated as required by the specification throughout the life of the project. Detailed requirements are provided in Division II, Section 722 Construction Scheduling.
A00801 - 7
SUBSECTION 8.14 UTILITY COORDINATION, DOCUMENTATION, AND
MONITORING RESPONSIBILITIES
A. GENERAL
In accordance with the provisions of Section 8.00 Prosecution and Progress, utility coordination is a critical aspect to this Contract. This section defines the responsibility of the Contractor and MassDOT, with regard to the initial utility relocation plan and changes that occur as the prosecution of the Work progresses. The Engineer, with assistance from the Contractor shall coordinate with Utility companies that are impacted by the Contractor’s operations. To support this effort, the Contractor shall provide routine and accurate schedule updates, provide notification of delays, and provide documentation of the steps taken to resolve any conflicts for the temporary and/or permanent relocations of the impacted utilities. The Contractor shall provide copies to the Engineer of the Contractor communication with the Utility companies, including but not limited to:
• Providing advanced notice, for all utility-related meetings initiated by the Contractor.
• Providing meeting minutes for all utility-related meetings that the Contractor attends.
• Providing all test pit records.
• Request for Early Utility work requirements of this section (see below).
• Notification letters for any proposed changes to Utility start dates and/or sequencing.
• Written notification to the Engineer of all apparent utility delays within seven (7) Calendar
Days after a recognized delay to actual work in the field – either caused by a Utility or the Contractor.
• Any communication, initiated by the Contractor, associated with additional Right-of-Way needs in support of utility work.
• Submission of completed Utility Completion Forms.
B. PROJECT UTILITY COORDINATION (PUC) FORM
The utility schedule and sequence information provided in the Project Utility Coordination Form (if applicable) is the best available information at the time of the bid and has been considered in setting the contract duration. The Contractor shall use all of this information in developing the bid price and the Baseline Schedule Submission, inclusive of the individual utility durations sequencing requirements, and any work that has been noted as potentially concurrent utility installations.
C. INITIATION OF UTILITY WORK
The Engineer will issue all initial notice-to-proceed dates to each Utility company based on either the:
1) Contractor’s accepted Baseline Schedule
2) An approved Early Utility Request in the form of an Early Utility sub-net schedule (in accordance with the requirements of this Subsection)
3) An approved Proposal Schedule
C.1 - BASELINE SCHEDULE – UTILITY BASIS
The Contractor shall provide a Baseline Schedule submission in accordance with the requirements of Subsection 8.02 and inclusive of all of the information provided in the PUC Form that has been issued in the Contract documents. This is to include the utility durations, sequencing of work, allowable concurrent work, and all applicable considerations that have been depicted on the PUC Form.
A00801 - 8
SUBSECTION 8.14 (Continued)
C.2 – EARLY UTILITY REQUEST – (aka SUBNET SCHEDULE) PRIOR TO THE BASELINE All early utility work is defined as any anticipated/required utility relocations that need to occur prior to the Baseline Schedule acceptance. In all cases of proposed early utility relocation, the Contractor shall present all known information at the pre-construction conference in the form of a ‘sub-net’ schedule showing when each early utility activity needs to be issued a notice-to-proceed. The Contractor shall provide advance notification of this intent to request early utility work in writing at or prior to the Pre-Construction meeting. Prior to officially requesting approval for early utility work, the Contractor shall also coordinate with MassDOT and all utility companies (private, state or municipal) which may be impacted by the Contract. If this request is acceptable to the Utilities and to MassDOT, the Engineer will issue a notice-to-proceed to the affected Utilities, based on these accepted dates.
C.3 – PROPOSAL SCHEDULE - CHANGES TO THE PUC FORM
If the Contractor intends to submit a schedule (in accordance with MassDOT Standard Specifications, Division I, Subsection 8.02) that contains durations or sequencing that vary from those provided in the Project Utility Coordination (PUC) Form, the Contactor must submit this as an intended change, in the form of a Proposal Schedule and in accordance with MassDOT Standard Specifications, Division I, Subsection 8.02. These proposed changes are subject to the approval of the Engineer and the impacted utilities, in the form of this Proposal Schedule and a proposed revision to the PUC form. The Contractor shall not proceed with any changes of this type without written authorization from the Engineer, that references the approved Proposal Schedule and PUC form changes. The submission of the Baseline Schedule should not include any of these types of proposed utility changes and should not delay the submission of the Baseline Schedule. As a prerequisite to the Proposal Schedule submission, and in advance of the utility notification(s) period, the Contractor shall coordinate the proposed utility changes with the Engineer and the utility companies, to develop a mutually agreed upon schedule, prior to the start of construction.
D. UTILITY DELAYS
The Contractor shall notify the Engineer upon becoming aware that a Utility owner is not advancing the work in accordance with the approved utility schedule. Such notice shall be provided to the Engineer no later than seven (7) calendar days after the occurrence of the event that the Contractor believes to be a utility delay. After such notice, the Engineer and the Contractor shall continue to diligently seek the Utility Owner’s cooperation in performing their scope of Work.
In order to demonstrate that a critical path delay has been caused by a third-party Utility, the Contractor must demonstrate, through the requirements of the monthly Progress Schedule submissions and the supporting contract records associated with Subsection 8.02, 8.10 and 8.14, that the delays were beyond the control of the Contractor.
A00801 - 9
SUBSECTION 8.14 (Continued)
All documentation provided in this section is subject to the review and verification of the Engineer and, if required, the Utility Owner. In accordance with MassDOT Specifications, Division I, Subsection 8.10, a Time Extension will be granted for a delay caused by a Utility, only if the actual duration of the utility work is in excess of that shown on the Project Utility Coordination Form, and only if;
1) proper Notification of Delay was provided to MassDOT in accordance with the time requirements that are specified in this Section
2) the utility delay is a critical path impact to the Baseline Schedule (or most recently approved Progress Schedule)
E. LOCATION OF UTILITIES
The locations of existing utilities are shown on the Contract drawings as an approximation only.
The Contractor shall perform a pre-construction utility survey, including any required test pits, to determine the location of all known utilities no later than thirty (30) calendar days before commencing physical site work in the affected area.
F. POST UTILITY SURVEY – NOTIFICATION
Following completion of a utility survey of existing locations, the Contractor will be responsible to notify the Engineer of any known conflicts associated with the actual location of utilities prior to the start of the work. The Engineer and the Contractor will coordinate with any utility whose assets are to be affected by the Work of this Contract. A partial list of utility contact information is provided in the Project Utility Coordination Form.
G. MEETINGS AND COOPERATION WITH UTILITY OWNERS
The Contractor shall notify the Engineer in advance of any meeting they initiate with a Utility Owner’s representative to allow MassDOT to participate in the meeting if needed.
Prior to the Pre-Construction Meeting, the Contractor should meet with all Utility Owners who will be required to perform utility relocations within the first 6 months of the project, to update the affected utilities of the Project Utility Coordination Form and all other applicable Contract requirements that impact the Utilities. The Contractor shall copy the Engineer on any correspondence between the Utility Owner and the Contractor.
H. FORCE ACCOUNT / UTILITY MONITORING REQUIREMENTS
The Engineer will be responsible for recording daily Utility work force reports. The start, suspension, re-start, and completion dates of each of the Utilities, within each phase of the utility relocation work, will be monitored and agreed to by the Engineer and the Contractor as the work progresses.
I. ACCESS AND INSPECTION
The Contractor shall be responsible for allowing Utility owners access to their own utilities to perform the relocations and/or inspections. The Contractor shall schedule their work accordingly so as not to delay or prevent each utility from maintaining their relocation schedule.
A00801 - 10
PREPARATION OF CONCRETE SURFACES:
All concrete surfaces to be patched shall be roughened, cleaned of all laitance, dirt, grease, oil, other contaminants and all standing water. All reinforcing steel encountered in the excavation shall be thoroughly cleaned by abrasive blasting and coated with a zinc-rich primer conforming to MassDOT Standard Specification M7.04.11 before being covered with new concrete.
The excavated areas shall then be presoaked with a water hose for 24 hours or as long as site constraints permit. At time of repair concrete placement, substrate shall be saturated surface dry with no standing water. At the discretion of the Engineer, epoxy bonding compound may be used.
Any remaining water should be blown out to produce a saturated surface dry (SSD) condition using oil free compressed air.
NONCONFORMING COMPRESSIVE STRENGTH OF CEMENT CONCRETE
Concrete with compressive strength test results failing to attain the limits specified in Table 901.64-3 of 901.64.B: Acceptance Testing shall be evaluated for structural adequacy and serviceability at the Contractors’ expense. The Department will review all production records, the concrete test records, petrographic analysis report, field notes, and the placement records for the concrete in question. If the Engineer determines the material is found to be adequate to remain in place, payment shall be adjusted in accordance with the following formula:
𝑃𝑃 =
2(𝑓𝑓𝑓𝑓 − 𝑓𝑓′𝑐𝑐)(𝑈𝑈𝑈𝑈)(𝑄𝑄)
𝑓𝑓′𝑐𝑐
Where:
𝑃𝑃 = 𝑝𝑝𝑝𝑝𝑝𝑝 𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝑓𝑓𝑓𝑓𝑓𝑓 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐
𝑓𝑓′𝑐𝑐 = 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠ℎ 𝑎𝑎𝑎𝑎 28 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 𝑓𝑓𝑓𝑓 = 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠ℎ 𝑎𝑎𝑎𝑎 56 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 𝑄𝑄 = 𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞 𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 𝑏𝑏𝑏𝑏 𝑡𝑡ℎ𝑒𝑒 𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 𝑈𝑈𝑈𝑈 = 𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑜𝑜𝑜𝑜 𝑡𝑡ℎ𝑒𝑒 𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 𝑠𝑠𝑠𝑠𝑠𝑠 𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑝𝑝𝑝𝑝𝑝𝑝 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦 𝑓𝑓𝑓𝑓𝑓𝑓 𝑡𝑡ℎ𝑒𝑒 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑖𝑖𝑖𝑖 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝
A00801 - 11
ENVIRONMENTAL PERMITTING
The proposed work does not occur in jurisdictional wetland resources subject to section 401 or section 404 of the Clean Water Act; therefore, the project does not require a Water Quality Certification from the Massachusetts Department of Environmental Protection or authorization from the US Army Corps of Engineers. The proposed work qualifies for the bridge exemption authorized in the Transportation Bond Bill and is therefore not subject to the Massachusetts Wetlands Protection Act, the Massachusetts Public Waterfront Act (Chapter 91), or the Massachusetts Environmental Policy Act.
The Contractor is responsible for identifying and avoiding impacts to adjacent wetland resource areas, if applicable. If field conditions and/or Contractor-proposed erection, demolition, staging, or other procedures require work to occur in or otherwise impact water or wetland resource areas, the Contractor is advised that no associated work can occur until all required environmental permits have been obtained allowing such work. The Contractor must notify the District 2 Highway Director and Resident Engineer in writing at least 60 days prior to desire commencement of the proposed activity. All environmental submittals, including any Contract with Local, State, or Federal environmental agencies, must be coordinated with the District 2 Environmental Engineer. The Contractor is expected to fully cooperate with requests for information and provide same in a timely manner. The Contractor is further advised that the Department will not entertain a delay claim due to the time required to obtain the environmental permits.
CONTAMINATED SOIL
Soil to be removed from the project area shall not be assumed to be uncontaminated and must be evaluated prior to off-site management for potential contamination with hazardous materials. No soil may be disposed of off-site without proper assessment by the contractor and approval from the Resident Engineer (RE), District Environmental Engineer (DEE), or the project designee.
SOIL STOCKPILING DIRECTIVE P-22-001
Any stockpiling of soil must be performed in compliance with Policy Directive P-22-001, Off- Site Stockpiling of Soil from MassDOT Construction Projects. This directive limits the allowable locations for off-site stockpiling of soil generated during MassDOT projects and includes various requirements that must be satisfied by the contractor prior to off-site stockpiling. The Contractor is responsible for identifying a suitable stockpile location.
A00801 - 12
TRUCK SAFETY DEVICES
(Supplementing Subsection 7.04: Motor Vehicles)
All motor vehicles subject to Section 7 of Chapter 90 to be operated under this Contract shall be equipped with safety devices as provided therein and in 540 CMR 4.00.
The Contractor shall certify to the Registry of Motor Vehicles, in a manner prescribed by the Registrar, that all applicable vehicles are equipped with Lateral Protective Devices, Convex Mirrors, Cross Over Mirror(s) and Back Up Cameras in accordance with the requirements of 540
CMR 4.00.
The Contractor shall provide evidence satisfactory to the Department to demonstrate compliance with the above certification requirement for all applicable vehicles operated under this Contract by the Contractor and its subcontractors and vendors in a manner set forth by the Department.
Thereafter, the Contractor shall have an affirmative obligation to continue to provide such evidence of compliance on an ongoing basis and no later than 7 days after certification with the Registry of Motor Vehicles of any additional vehicles operated under this Contract by the Contractor and its subcontractors and vendors.
Non-compliance with respect to a vehicle that is subject to 540 CMR 4.00 may subject the Contractor to statutory fines as established in M.G.L. c. 90, § 7 and/or contractual remedies up to and including termination of the Contract.
PIGEON WASTE
The Contractor shall remove and dispose of the pigeon waste and any other debris accumulated on the steel members and bridge seats in areas where work is being performed. Pigeon waste and debris material contaminants will require special handling and disposal in accordance with all Federal, state, and local requirements. No separate payment will be made for removal and disposal of pigeon waste. Cost shall be incidental to the contract pay items.
EMERALD ASH BORER ADVISORY
To the extent possible, all trees and brush shall be disposed on site, typically chipped and spread in place. When trees or brush must be removed, such as in urban, or otherwise populated areas, Contractor shall identify proposed location for disposal, and provide written notification to the Engineer for approval. Disposal shall be in city or town of project, or at minimum, within county, of construction operations.
A00801 - 13
GENERAL REQUIREMENTS FOR DEMOLITION AND
WORK INVOLVING PAINTED STEEL
(02/06/2020)
Demolition and work involving painted steel shall conform to the requirements of Subsection 961 of the Standard Specifications.
Work Involving Painted Steel
Hazardous materials shall be removed in the immediate area of any intended welding, heating, saw cutting or burning of steel. Hazardous material removal is required to allow the demolition of structural steel, railings, drainage systems, utility supports, steel lamp posts, etc.
The contractor shall assume that the coatings on the steel contain lead (Pb), unless otherwise determined by testing. The contractor shall certify in writing to the Engineer the results of all testing, and shall also certify that any lead (Pb) coated steel removed from the project was not reused or buried, but was sent to a scrap metal recycling facility.
Implement and maintain programs and procedures, which comply with the requirements of this specification and all applicable standards and regulations. Comply with all applicable regulations even if the regulation is not specifically referenced herein. If a state or local regulation is more restrictive than the regulation of this specification, follow the more restrictive requirements.
This requirement is intended only for the demolition and preparation prior to repair and does not include provisions for recoating of steel.
Environmental
All applicable portions of Subsections 961.65 “Worker Protection” and 961.66 “Environmental Protection and Monitoring” shall be followed when performing this work.
During chemical stripping a hand washing facility may be used in lieu of a decontamination/changing facility.
Hazardous material shall be collected during the disassembly and disposed of as outlined in Subsection 961.68 “Handling of Hazardous Waste and Reporting Release Programs”.
The applicable submittals shall be according to Subsection 961.69 “Submittals”.
A00801 - 14
GENERAL REQUIREMENTS FOR DEMOLITION AND
WORK INVOLVING PAINTED STEEL (Continued)
Cleaning/Removal
Cutting Or Burning Of Steel
All surfaces to be welded, heated, saw cut or burned shall be cleaned so as to remove all contaminants and/or hazardous materials, which could be discharged to the environment as a function of the subsequent operations.
Lead paint shall be removed in its entirety in an area prescribed by a 6 inch (15 cm) minimum offset from the required work. The paint removal operation may be dry abrasive blasting, wet abrasive blasting or chemical stripping.
Proper level of containment shall be used when performing this work in accordance with Subsection 961.67 “Containment”. Full containment is not required during chemical stripping operation however; the Contractor shall install proper shielding and/or tarpaulins under the chemical stripping operations in order to catch all debris generated during this procedure. A cleaned area must be inspected and approved before the demolition operations are started.
During cleaning operations the Contractor shall be required to furnish and erect temporary floodlights illuminating the steel surface at a minimum of 30-foot candles. This lighting shall be used in areas where there is insufficient lighting for proper cleaning operations and inspection.
The Contractor shall supply electrical power.
The Contractor shall provide support for interim and final inspection of the bridge during cleaning operations. This support shall include the necessary traffic controls and safe access to the work.
Mechanical Disassembly Of Steel
All surfaces to be mechanically disassembled by shear cutting or removing bolts or rivets shall not require deleading. When shear cutting or removing bolts or rivets, the Contractor shall not use any method that will cause dust and/or particles to be emitted and/or dispersed into the environment to an extent that would expose the workers above the Action Levels of 30µg/m3.
For purposes of limiting the lead (Pb) dust, the Contractor will be required to dampen the lead paint work areas.
The contractor shall install a proper shielding and/or tarpaulins under all lead-paint-coated surfaces to be shear cut or bolts or rivets ordered removed in order to catch any loose lead paint chips, dust or particles.
A00801 - 15
EQUIVALENT SINGLE AXLE LOADS (ESALS)
The estimated traffic level to be used for SUPERPAVE HMA mixture designs for this contract, expressed in Equivalent Single Axle Loads (ESALs) for the design travel lane over a 20-year period, is traffic level 2 (0.3-10.0 million 18-kip (80-kn) ESALs).
NORTHERN LONG-EARED BAT AND TRICOLORED BAT PROTECTION
The northern long-eared bat (Myotis septentrionalis; NLEB) and tricolored bat (Perimyotis subflavus; TCB) are listed as federally endangered or proposed endangered, respectfully, under the Endangered Species Act (ESA). The U.S. Fish and Wildlife Service (USFWS) developed this guidance to address ESA compliance and promote conservation of NLEB and TCB. As there is no Federal nexus (Federal funding or permits) for this project, Section 7 consultation was not required or conducted. However, Section 9 of the ESA prohibits anyone from “taking” or harming an endangered species, and the below language shall be adhered to in order to maintain compliance with the ESA.
If any of the project locations require work within U.S. Army Corps of Engineers (ACOE) jurisdictional wetlands, the ACOE will be the lead federal agency for ESA consultation with the U.S. Fish & Wildlife Service (USFWS). Most consultations for the NLEB take 30 days.
The following Avoidance and Minimization Measures (AMMs) must be strictly adhered to in order to protect NLEB and TCB and to be in compliance with the ESA. Contact MassDOT Environmental Services - Wildlife & Endangered Species Unit Supervisor (David Paulson, david.j.paulson@dot.state.ma.us, 857-262-3378) for questions about project limits, restrictions, or conservation measures.
The Resident Engineer can check on the status of AMM applicability by sending a locus map of the proposed work to MassDOT Highway Division’s Environmental Services Section - Wildlife & Endangered Species Unit Supervisor for review and a determination if some of the AMMs and TOY restriction can be waived.
Required AMM for all projects:
• The Contractor shall ensure all personnel working in on the project site are aware of all environmental commitments related to NLEB and TCB, including all applicable AMMs.
NLEB Bat information (https://www.fws.gov/midwest/endangered/mammals/nleb/and https://www.fws.gov/species/tricolored-bat-perimyotis-subflavus) shall be made available to all personnel.
If temporary lighting is proposed within the project scope, the following AMM is applicable:
Lighting AMM:
• Direct temporary lighting away from suitable habitat during the active season: April 15 to
October 31.
mailto:david.j.paulson@dot.state.ma.us https://www.fws.gov/midwest/endangered/mammals/nleb/and%20https:/www.fws.gov/species/tricolored-bat-perimyotis-subflavus https://www.fws.gov/midwest/endangered/mammals/nleb/and%20https:/www.fws.gov/species/tricolored-bat-perimyotis-subflavus
A00801 - 16
NORTHERN LONG-EARED BAT AND TRICOLORED BAT PROTECTION (Continued)
If the Removal of Trees and/or Woody Vegetation >3-inch in diameter is proposed within the project scope, the following AMMs are applicable:
Tree AMMs:
• If additional cutting is proposed by the Contractor that is outside the scope of this contract, additional review is required by the MassDOT Highway Division’s Environmental Services Section, and additional review and restrictions may be required by the USFWS.
• Ensure tree removal is limited to that specified in project plans and ensure that contractors understand clearing limits and how they are marked in the field (e.g., install bright colored flagging/fencing prior to any tree clearing to ensure contractors stay within clearing limits).
• In order to protect northern long-eared bats and their young during their active season, no tree cutting shall be conducted during the Time of Year (TOY) restriction of April 15 to October 31.
• Do not remove documented or NLEB roosts that are still suitable for roosting, or trees within
0.25 miles of roosts, or documented foraging habitat any time of year (http://www.mass.gov/eea/agencies/dfg/dfw/natural-heritage/species-information-and-conservation/rare-mammals/northern-long-eared-bat.html).
• The Contractor shall ensure all personnel working in on the project site are aware of all environmental commitments related to NLEB and TCB, including the TOY restriction.
If the Bridge Work is proposed within the project scope, the following AMMs are applicable:
Bridge AMMs:
• Bridge AMM 1 - To completely avoid direct effects to roosting bats, perform any bridge removal, replacement, and/or maintenance work during the winter hibernation period unless a hibernating colony of bats is present (contact your local USFWS Field Office for exact dates).
Also, follow Bridge AMM 4.
a. Note: Bridge AMM 1 is an avoidance measure for direct effects; the full implementation of which may not always be practicable. If bridge removal, replacement, and/or maintenance work must be performed outside of the winter hibernation period, then follow Bridge AMMs 2-4.
• Bridge AMM 2 - Colony or Assuming Presence of Bats
a. If assuming presence of bats or if bridge assessment or P/A surveys suggest presence of a colony of bats, and work is conducted during the active season, ensure activity will not disturb bats. The following types of bridge work can generally be conducted with the presence of bats:
i. above deck work where construction equipment or materials do not extend to the underside of deck where bats may be located (e.g., materials that may drip down to underside of deck), or does not include percussives (vibration) or noise levels above general traffic (e.g., road line painting, wing-wall work).
ii. below deck work that is conducted away from roosting bats and does not involve percussives or noise level above general traffic (e.g., wing-wall work, some abutment, beam end, scour, or pier repair).
http://www.mass.gov/eea/agencies/dfg/dfw/natural-heritage/species-information-and-conservation/rare-mammals/northern-long-eared-bat.html http://www.mass.gov/eea/agencies/dfg/dfw/natural-heritage/species-information-and-conservation/rare-mammals/northern-long-eared-bat.html
A00801 - 17
NORTHERN LONG-EARED BAT AND TRICOLORED BAT PROTECTION (Continued)
• Bridge AMM 3 - Small Number of Bats
a. If bridge assessment or P/A surveys suggest presence of a small number of bats (<5 – not a colony), and work is conducted during the active season, the following types of bridge work can generally be conducted with the presence of bats:
i. above deck work where construction equipment or materials do not extend to the underside of deck where bats may be located (e.g., materials that may drip down to underside of deck), or does not include percussives (vibration) or noise levels above general traffic (e.g., road line painting, wing-wall work).
ii. below deck work that is conducted away from roosting bats and does not involve percussives or noise level above general traffic (e.g., wing-wall work, some abutment, beam end, scour, or pier repair).
iii. any other bridge removal, replacement, and/or maintenance work (which may include activities with percussives) conducted in the evening while the bats are feeding, starting one hour after sunset, and ending one hour before daylight excluding the hours between 10 p.m. and midnight and keep the light localized.
• Bridge AMM 4 - If assuming presence of bats, or if bridge assessment or P/A surveys suggest presence of bats, ensure suitable roosting habitat is maintained. Suitable roosting sites may be incorporated into the design of a new bridge.
PAINTED CONCRETE
If the project involves work that will impact coated concrete, this coating may contain lead. The contractor must test the coating to determine whether lead is present. If lead is present, all work shall be performed in accordance with the OSHA standards contained in 29 CFR Part 1926.62 – Lead. Dust and debris shall be prevented from entering the environment (including but not limited to soil, air, and water). The contract shall comply with all applicable conditions of Subsection
961.68 “Handling of Hazardous Waste and Reporting Release Programs” and Subsection 961.69 “Submittals” of the 2026 MassDOT Standard Specifications for Highways and Bridges.
NOTICE TO OWNERS OF UTILITIES
(Supplementing Subsection 7.13)
District 2 Utility/Constructability Engineer Paul Kelly Paul.Kelly@DOT.state.ma.us
The existing plans indicate the location of the existing known utilities in the vicinity of the work.
As the accuracy and completeness of the plans are not guaranteed in any manner, it is the Contractor’s responsibility to make their own investigation to assure that no damage to existing structures, drainage lines, traffic signal conduits, etc., will occur.
mailto:Paul.Kelly@DOT.state.ma.us
A00801 - 18
NOTICE TO OWNERS OF UTILITIES (Continued)
Written notice shall be given by the Contractor to all public service corporations or officials owning or having charge of publicly or privately owned utilities of the Contractor’s intention to commence operations affecting such utilities at least one week in advance of the commencement of such operations and the Contractor shall at that time file a copy of such notice with the Engineer.
A list of public and private utilities can be found on the MassDOT website at:
https://www.mass.gov/info-details/utility-contacts-by-district-and-municipality Select District 2 Select the Town, and then locate the utility The utility contact list is for guidance only and is not guaranteed to be complete or up to date.
NOTIFICATION OF PUBLIC OFFICIALS
Town officials are shown at website https://www.mass.gov/lists/massachusetts-cities-and-towns and select the required City/Town website.
State Police are shown at website https://www.mass.gov/info-details/massachusetts-state-police-troop-boundaries. Select the area of jurisdiction to find the local station.
The Contractor shall be responsible for informing the following officials in each area that he is assigned to work in:
Superintendent, Department of Public Works, or Town Engineer. Superintendent, Water Department, Superintendent, Sewer Departments. Police Department, Fire Department, Electric Company.
NATIONAL GRID EMERGENCY TELEPHONE NUMBERS
ELECTRIC:
Outage/ Emergency: 1-800-465-1212 New Service: 1-800-375-7405 Customer Support: 1-800-322-3223
EVERSOURCE EMERGENCY TELEPHONE NUMBERS
GAS:
Outage/ Emergency: 800-592-2000 New Service: 866-678-2744 Customer Support: 800-592-2000
ELECTRIC:
Outage/ Emergency: 800-592-2000 or 844-726-7562 New Service: 1-888-633-3797 (1-888-need pwr) Customer Support: 1-800-340-9822 https://www.mass.gov/info-details/utility-contacts-by-district-and-municipality https://www.mass.gov/info-details/utility-contacts-by-district-and-municipality https://www.mass.gov/lists/massachusetts-cities-and-towns https://www.mass.gov/info-details/massachusetts-state-police-troop-boundaries https://www.mass.gov/info-details/massachusetts-state-police-troop-boundaries
A00801 - 19
PROPRIETARY PRODUCTS
A letter discussing the HILTI HIT RE-500V3 EPOXY ANCHOR as a proprietary specification pursuant to M.G.L. c. 30, sec. 39M(b) has been placed in the Project file. The HILTI HIT RE- 500V3 EPOXY ANCHOR shall be manufactured by HILTI CORPORATION or approved equal.
COMPLIANCE WITH THE NATIONAL DEFENSE AUTHORIZATION ACT
(Supplementing Subsection 7.01)
On all projects, the “Prohibition on Certain Telecommunications and Video Surveillance Services or Equipment” Regulation (2 CFR 200.216) prohibits the Contractor from using or furnishing the following telecommunications equipment or services:
• Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities).
• For the purpose of public safety, security of government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities).
• Telecommunications or video surveillance services provided by such entities or using such equipment.
• Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of the National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.
This prohibition applies to all products manufactured by the aforementioned companies, including any individual components or parts.
By submitting a bid on a project, the Contractor certifies that all work will be in compliance with the terms of 2 CFR 200.216. The Contractor shall submit a COC indicating compliance with the above provisions for all telecommunications equipment or services included in the Contract.
Payment for the item in which the materials are incorporated may be withheld until these COCs are received. Any cost involved in furnishing the certificate(s) shall be borne by the Contractor.
A00801 - 20
ITEM 101.01 CLEARING AND GRUBBING AT BRIDGES SQUARE YARD
The work under this Item shall conform to the relevant provisions of Subsection 101 of the Standard Specifications, and the following:
The work under this item consists of clearing trees and shrubs outside the proposed parapet face of the wingwall and other selected areas directed by the Engineer to provide access for repair and inspection work.
Areas along the wingwall, abutments, and along the ten (10) feet of approach sidewalks or curblines of the bridges shall be cleared and grubbed for a width of fifteen (15) feet from the face of feature or to the edge of the right of way if less than fifteen (15) feet from the face of feature and as directed by the Engineer.
All debris shall be removed and properly disposed from the site.
METHOD OF MEASUREMENTS
Item 101.01 will be measured for payment by the Square Yard of clearing and grubbing, by the horizontal plane area, complete in place.
BASIS OF PAYMENT
Item 101.01 will be paid for at the Contract unit price per Square Yard, which price shall include clearing, grubbing, removal of all brush, trees, stumps, and roots within the designated areas, all labor, tools, materials, equipment, and all incidental costs required to complete the work.
No separate payment will be made for any individual trees or stumps removed within the area.
A00801 - 21
ITEM 106.101 BEARING ADJUSTMENT EACH
The work under this Item shall conform to the relevant provisions of Subsection M4.04.5 of the Standard Specifications, and the following:
This work shall consist of removing all existing grout from the indicated bearings on Bridge M- 27-002 (172) and placement of new non-shrink grout.
METHOD OF MEASUREMENTS
Item 106.101 will be measured for payment by the Each bearing adjustment, complete in place.
BASIS OF PAYMENT
Item 106.101 will be paid for at the Contract unit price per Each, which price shall include removal of existing grout, placement of new non-shrink grout, all labor, materials, tools, equipment, and all incidental costs required to complete the work.
A00801 - 22
ITEM 106.88 JACKING AND SHORING EACH
The work under this Item consists of supporting existing beams of Bridge No. M-27-002 (172), as shown on the sketches and as required by the Engineer.
Shoring materials may be new or second hand, as approved by the Engineer. The Contractor shall submit a plan of the proposed work showing the details and indicating the materials to be used.
The submittal shall include the jacking load calculations and shoring design computations, based on the bridge configurations and the working stresses of the materials used, sequence of operations, and all details incidental thereto. Unless otherwise directed by the Engineer, the proposed jacking and shoring system shall be designed to apply force in increments to the existing beam/girder to relieve load from the existing substructure. The jack(s) shall have a locking mechanism preventing the beam/girder from lowering in the event of loss of hydraulic pressure. All components of the system shall have load capacity greater than the total calculated load carried by the existing beam/girder during normal traffic operation, which includes but not limited to, dead load, live load, and impact load.
Bridge Loads: The Contractor shall be responsible for calculating loads (live and impact loads, dead loads...etc.) necessary to design shoring paid under this Item. Soil bearing values shall be determined per section 2.5.2 of the AASHTO Guide Design Specifications for Bridge Temporary Works. All materials (except jacks) shall be designed by working stress design (ASD).
Type of jacks used, and factor of safety shall be per industry standards.
Approval of this submission by the Engineer shall be obtained prior to the commencement of any work under this item. The above plan and computations shall bear the seal and signature of a Professional Engineer of the appropriate discipline registered in Massachusetts.
Materials shall meet the following:
• Anchor Bolts, Nuts and Washers: M8.01.5
• Bridge Related Structural Steel: M8.05.0
• Wood Products: M9.05.1
All treated wood supplied by the Contractor shall meet the requirements of M9.05.1 for Wood Products, including the most recent versions of AWPA U1 and M4 which are incorporated by reference. No new wood shall be treated with inorganic arsenic (including chromated copper arsenate (CCA), ammoniacal copper arsenate (ACA), and ammoniacal copper zinc arsenate (ACZA)), creosote or pentachlorophenol in all project construction.
When, determined by the Engineer, extensive repairs require temporarily supporting some of the beams/girders on one or both sides of an abutment(s), those beams/girders shall be jacked/shored all at once as one unit for the length of time required.
The work shall be performed as follows:
Erect timber cribbing under each end diaphragm as directed by the Engineer. Timber cribbing shall be shimmed tight. In lieu of timber cribbing, hydraulic jacks with locking collars may be used.
A00801 - 23
ITEM 106.88 (Continued)
The successful prosecution, safety, and completion of the work in an acceptable manner is the responsibility of the Contractor.