A001-A0048 CDRLs DD 1423.pdf
PDF 964 KB Posted
- Solicitation number
- W91CRB23R0005
About this file
This draft solicitation seeks proposals for environmental remediation services at Rocky Mountain Arsenal. Over a potential nine-year contract consisting of a three-year base period and two three-year option periods, the contractor shall provide personnel, equipment, facilities, transportation, and other resources to operate and maintain Comprehensive Environmental Response, Compensation, and Liability Act and Resource Conservation and Recovery Act remediation systems. Specific work includes operating groundwater treatment plants, sampling and monitoring groundwater and surface water, maintaining landfills and covers, sustaining infrastructure and facilities, assisting with regulatory interfaces, conducting program records and reporting, ensuring land use control compliance, optimizing environmental remediation systems, and adhering to environmental compliance requirements. Interested parties may submit comments on this draft solicitation by March 26, 2023 prior to release of the final solicitation on the System for Award Management website. The resulting contract will be set aside for small businesses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W91CRB23R0005 DRAFT RFP 23MAR23.pdf | ||
| Draft RFP RMA ERS Cost Model 2023.xlsx | XLSX spreadsheet | |
| Draft RFP Attachment A15.docx | DOCX document | |
| Draft RFP Attachments A11-A14.docx | DOCX document | |
| Draft RFP Attachments A1-A9.docx | DOCX document | |
| Draft RFP Attachment A10.docx | DOCX document | |
| W91CRB23R0005 DRAFT RFP.pdf | ||
| Draft RFP A16 Attachment SUMMARY OF EXPERIENCE FORM.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DD FORM 1423, AUG 96
CONTRACT DATA REQUIREMENTS LIST
PREVIOUS EDITION MAY BE USED.
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ________ TM _______ OTHER _________________________
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Page ____ of ____ Pages
A001 Quality Control Plan
C1.7.1 Rocky Mountain Arsenal
Annual Updates 1 Jan 2022
1 Jan 2023 Army (digital) 1 1
1 1 0
Required Submittals: Client Draft, Final Copy Distribution to Army COR by electronic submittal in Word and pdf format
A002 Health and Safety Plan
C1.14.2 Rocky Mountain Arsenal
Annual Updates 1 Jan 2022
1 Jan 2023 Army (digital) 1 1
1 1 0
Required Submittals: Client Draft, Final Copy Distribution to Army COR by electronic submittal in Word and pdf format
A003 Transition Plan
C1.21 Rocky Mountain Arsenal w/Proposal w/Proposal
N/A
0 0 0
Submit with Proposal
A004 RCRA Landfills and Groundwater Monitoring Report
C5.4.7 Rocky Mountain Arsenal
Annual 30 Jun 2022
30 Jun 2023 Army (digital) 1 1 EDTC (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution to Army COR by electronic submittal in Word and pdf format
Adobe Professional 8.0
PREVIOUS EDITION MAY BE USED.
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ________ TM _______ OTHER _________________________
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Page ____ of ____ Pages
A005 Annual Covers Report for ICS
C5.4.7 Rocky Mountain Arsenal
Annual Updates 30 Nov 2022
30 Nov 2023 EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution to Army COR by electronic submittal in Word and pdf format
A006 Annual Basin F Cover and Groundwater Monitoring Rep
C5.4.7 Rocky Mountain Arsenal
Annual Updates 30 Nov 2022
30 Nov 2023 EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution to Army COR by electronic submittal in Word and pdf format
A007 Annual Summary Report for GW and SW
C5.9.1 Rocky Mountain Arsenal
Annual 30 Sep 2022
30 Sep 2023 EDTC (digital) 1 1 0 Army (hard copy) 6 6 Army (digital) 1 1
8 8 0
Required Submittals: Client Draft, Final Draft, Final Copy Distribution to Army COR by electronic submittal in Word, pdf, and hard copy format Provide 1 hard copy of Client Draft to Army for review
A008 Annual Street Sanding Report
C1.23 Rocky Mountain Arsenal
Annual 30 Jun 2022
30 Jun 2023 EDTC (digital) 1 Army (digital) 1
0 2 0
Required Submittals: Final Copy
PREVIOUS EDITION MAY BE USED.
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ________ TM _______ OTHER _________________________
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Page ____ of ____ Pages
A009 Annual Snow Removal Plan
C5.5.1.2 Rocky Mountain Arsenal
Annual 31 Oct 2021
31 Oct 2022 Army (digital) 1 1
1 1 0
Required Submittals: Client Draft, Final Copy Distribution to Army COR by electronic submittal in Word and pdf format
A010 RCRA Annual Activity Report
C1.23 Rocky Mountain Arsenal
Annual 15 Feb 2022
15 Feb 2023 EDTC (digital) 1 Army (digital) 1
0 2 0
Required Submittals: Final Copy Distribution to Army COR by electronic submittal in Word and pdf format
A011 SARA Title III, Tier II Emergency and Hazardous Chem
C1.23 Rocky Mountain Arsenal
Annual 22 Feb 2022
22 Feb 2023 EDTC (digital) 1 Army (digital) 1
0 2 0
Required Submittals: Final Copy Distribution to Army COR by electronic submittal in Word, pdf, and hard copy format
A012 Land Use Control Monitoring Report
C5.10.2 Rocky Mountain Arsenal
Annual 31 Dec 2021
31 Dec 2022 EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy
PREVIOUS EDITION MAY BE USED.
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ________ TM _______ OTHER _________________________
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Page ____ of ____ Pages
A013 Army Contractor Manpower Report
C1.22 Rocky Mountain Arsenal
Annual 31 Oct 2022
31 Oct 2023 Army (digital) 1
0 1 0
Required Submittals: Final Copy Distribution to Army COR by electronic submittal in Word and pdf format
A014 Annual Work Plan
C1.5.2 Rocky Mountain Arsenal
Annual 30 Jun 2022
30 Jun 2023 Army (digital) 1 1
1 1 0
Required Submittals: Draft, Final Draft, Final Copy Distribution to Army COR by electronic submittal in Word and pdf format
A015 Voluntary Protection Program (VPP) Annual Evaluation
C1.14 Rocky Mountain Arsenal
Annual 15 Feb 2022
15 Feb 2023 EDTC (digital) 1 1 0 Army (digital) 1 1 OSHA (digital) 1
2 3 0
Required Submittals: Draft, Final Copy Distribution to Army COR by electronic submittal in Word, pdf, and hard copy format Report required if Contractor participates in VPP.
A016 Annual GFE Inventory Reports
C3.4 Rocky Mountain Arsenal
Annual 31 Dec 2021
31 Dec 2022 EDTC (digital) 1 Army (digital) 1
0 2 0
Required Submittals: Final Copy Distribution to Army COR, PIEE, GCSS by electronic submittal
PREVIOUS EDITION MAY BE USED.
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ________ TM _______ OTHER _________________________
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Page ____ of ____ Pages
A017 ERSC Performance Incentive Fee Criteria Proposal
C1.23 Rocky Mountain Arsenal
Semi-Annual w/ Proposal
1 May 2022 Army (digital) 1 1
1 1 0
Required Submittals: Draft, Final Draft, Final Copy Distribution to Army COR by electronic submittal in Word and pdf format
A018 ICS and Basin F Cover Lysimeter Monitoring Data
C5.9.1 Rocky Mountain Arsenal
Quarterly 15 Jan 2022
15 Apr 2022 EDTC (digital) 1 Army (digital) 1
0 2 0
Required Submittals: Final Copy Distribution to Army COR by electronic submittal
A019 Treatment Plant Effluent Water Quality Data Report
C5.9.1 Rocky Mountain Arsenal
Quarterly 28 Feb 2022
31 May 2022 Army (digital) 1 1 0 EDTC (digital) 1 1
2 2 0
Required Submittals: Client Draft, Final Copy Distribution to Army COR by electronic submittal in Word (client draft) and pdf (final)
A020 RCRA Biennial Hazardous Waste Report
C1.23 Rocky Mountain Arsenal
Every 2 Years 15 Feb 2022
15 Feb 2024 EDTC (digital) 1 Army (digital) 1
0 2 0
Required Submittals: Final Copy
PREVIOUS EDITION MAY BE USED.
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ________ TM _______ OTHER _________________________
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Page ____ of ____ Pages
A021 Five-Year Review Report
C5.9.1 Rocky Mountain Arsenal
Every Five Years 30 Sep 2025
30 Sep 2030 EDTC (digital) 1 1 Army (hard copy) 6 6 Army (digital) 1 1
8 8 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution to Army COR by electronic submittal in Word, pdf, and hard copy format Provide 1 hard copy of Client Draft to Army for review
A022 Five-Year GW and SW Summary Report
C5.9.1 Rocky Mountain Arsenal
Every Five Years 31 Dec 2025
31 Dec 2030 Army (digital) 1 1 Army (hard copy) 6 6 Army (digital) 1 1
8 8 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution to Army COR by electronic submittal in Word, pdf, and hard copy format Provide 1 hard copy of Client Draft to Army for review
A023 Monthly Operations Report
C3.3 Rocky Mountain Arsenal
Monthly 5 Jan 2022
5 Feb 2022 EDTC (digital) 1 0 Army (digital) 1
0 2 0
Required Submittals: Final Copy Distribution to Army COR by electronic submittal in Word and pdf format Submittal shall be made by 5th of each month
A024 Monthly Contract Status Report
C5.1.1 Rocky Mountain Arsenal
Monthly 5 Jan 2022
5 Jan 2022 EDTC (digital) 1 Army (digital) 1
0 2 0
Required Submittals: Final Copy Distribution to Army COR by electronic submittal in Word and pdf format Submittal shall be made by 5th of each month
PREVIOUS EDITION MAY BE USED.
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ________ TM _______ OTHER _________________________
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Page ____ of ____ Pages
A025 Document Delivery Schedule
C5.1.2 Rocky Mountain Arsenal
Monthly 5 Jan 2022
5 Feb 2022 EDTC (digital) 1 Army (digital) 1
0 2 0
Required Submittals: Final Copy Distribution to Army COR by electronic submittal in Word and pdf format Submittal shall be made by 5th of each month
A026 Monthly Cost Report
C5.1.2 Rocky Mountain Arsenal
Monthly 5 Jan 2022
5 Feb 2022 EDTC (digital) 1 Army (digital) 1
0 2 0
Required Submittals: Final Copy Distribution to Army COR by electronic submittal in Word and pdf format Submittal shall be made by 5th of each month
A027 Monthly Unliquidated Obligations (ULO) Report
C5.1.2 Rocky Mountain Arsenal
Monthly 5 Jan 2022
5 Feb 2022 EDTC (digital) 1 0 Army (digital) 1
0 2 0
Required Submittals: Final Copy Distribution to Army COR by electronic submittal in Word and pdf format Submittal shall be made by 5th of each month
A028 Weekly Activities Report
C5.1.1 Rocky Mountain Arsenal
Weekly 9 Dec 2021
16 Dec 2021 EDTC (digital) 1 Army (digital) 1
0 2 0
Required Submittals: Final Copy Distribution to Army COR by electronic submittal in Word and pdf format Submittal shall be made by Tuesday of each week
PREVIOUS EDITION MAY BE USED.
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ________ TM _______ OTHER _________________________
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Page ____ of ____ Pages
A037
C5.9.1 Rocky Mountain Arsenal
2X Every 5 Years 30 Sep 2022
30 Sep 2024 EDTC (digital) 1 1 Army (digital) 1 1 State Engineer 1
2 3 0
Required Submittals: Draft, Final Copy Distribution by electronic submittal in pdf format
A030 On-post Plume Map
C5.9.1 Rocky Mountain Arsenal
Every 20 Years
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Final Copy Distribution by electronic submittal in pdf format
0 0 0
0 0 0
PREVIOUS EDITION MAY BE USED.
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ________ TM _______ OTHER _________________________
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Page ____ of ____ Pages
A033 Well Abandonment/Well Installation Field Forms
C1.23 Rocky Mountain Arsenal
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Final Copy Distribution by electronic submittal in pdf format
A034 Design Submittals
C1.23 Rocky Mountain Arsenal
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution by electronic submittal in Word (Army Client Draft) and pdf format
A035 Work Plans
C1.23
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution by electronic submittal in Word (Army Client Draft) and pdf format
A036 Data Summary Reports
C1.23
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution by electronic submittal in Word (Army Client Draft) and pdf format
PREVIOUS EDITION MAY BE USED.
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ________ TM _______ OTHER _________________________
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Page ____ of ____ Pages
A037 Completion Reports
C1.23 Rocky Mountain Arsenal
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution by electronic submittal in Word (Army Client Draft) and pdf format
A038 ROD Revisions
C1.23 Rocky Mountain Arsenal
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution by electronic submittal in Word (Army Client Draft) and pdf format
A039 Closure Plans
C1.23
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution by electronic submittal in Word (Army Client Draft) and pdf format
A040 Operational Change Notices
C1.23
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy
PREVIOUS EDITION MAY BE USED.
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ________ TM _______ OTHER _________________________
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Page ____ of ____ Pages
A041 Design Change Notices
C1.23 Rocky Mountain Arsenal
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution by electronic submittal in Word (Army Client Draft) and pdf format
A042 Non-routine Action Plans
C1.23 Rocky Mountain Arsenal
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Final Copy Distribution by electronic submittal in Word (Army Client Draft) and pdf format
A043 Notice of Violation Triggers
C1.23
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution by electronic submittal in Word (Army Client Draft) and pdf format
A044 Consultative Process Triggers
C1.23
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy
PREVIOUS EDITION MAY BE USED.
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ________ TM _______ OTHER _________________________
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
SUBMISSION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Page ____ of ____ Pages
A045 Compliance Inspection Triggers
C1.23 Rocky Mountain Arsenal
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy Distribution by electronic submittal in Word (Army Client Draft) and pdf format
A046 Surveillance Reports
C1.23 Rocky Mountain Arsenal
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Final Copy Distribution by electronic submittal in Word (Army Client Draft) and pdf format
A047 Incident Reports
C1.23
As Needed
EDTC (digital) 1 Army (digital) 1
0 2 0
Required Submittals: Final Copy Distribution by electronic submittal in pdf format
A048 Deletion Reports
C1.23
As Needed
EDTC (digital) 1 1 Army (digital) 1 1
2 2 0
Required Submittals: Client Draft, Regulatory Agency Draft, Final Copy
INSTRUCTIONS FOR COMPLETING DD FORM 1423
(See DoD 5010.12-M for detailed instructions.)
FOR GOVERNMENT PERSONNEL
Item A. Self-explanatory.
Item B. Self-explanatory.
Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.
Item D. Enter name of system/item being acquired that data will support.
Item E. Self-explanatory (to be filled in after contract award).
Item F. Self-explanatory (to be filled in after contract award).
Item G. Signature of preparer of CDRL.
Item H. Date CDRL was prepared.
Item I. Signature of CDRL approval authority.
Item J. Date CDRL was approved.
Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.
Item 2. Enter title as it appears on data acquisition document cited in Item 4.
Item 3. Enter subtitle of data item for further definition of data item (optional entry).
Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.
Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).
Item 6. Enter technical office responsible for ensuring adequacy of the data item.
Item 7. Specify requirement for inspection/acceptance of the data item by the Government.
Item 8. Specify requirement for approval of a draft before preparation of the final data item.
Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.
DoDD 5230.24).
Item 10. Specify number of times data items are to be delivered.
Item 11. Specify as-of date of data item, when applicable.
Item 12. Specify when first submittal is required.
Item 13. Specify when subsequent submittals are required, when applicable.
Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.
Item 15. Enter total number of draft/final copies to be delivered.
Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13;
Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.
FOR THE CONTRACTOR
Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.
a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.
Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.
b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.
Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.
c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.
Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.
d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.
Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.
Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.
These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.
DD FORM 1423 (BACK), AUG 96