This mechanical equipment schedule and related solicitation provide specifications for replacing the HVAC system in Building 2 at the VA medical center located in Pineville, Louisiana. Offerors must submit proposals by August 21, 2020 at 3:30pm CST for Project #502-16-104. The scope of work involves installing new fan coil units, air separators, chilled water pumps, and air handling units. The equipment schedule specifies requirements for the fan coil units such as electronically commutated motors, filter types, and control valves. The chilled water pump package must be skid-mounted with an N+1 redundant design no taller than 63 inches. The air handling units must meet specified throw patterns. Amendment 0002 provides a brand name justification and instructs offerors to obtain all amendments and submit proposals following the instructions in the solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--Proj. # 502-16-104 Replace HVAC System in Bldg. 2, newest first.
File Type Posted
A0002 Att 3 MP101 REV 2.pdf PDF
A0002 Att 6 JA.pdf PDF
36C25620R0079 0002.docx DOCX document
A0002 Att 4 RFI Register.docx DOCX document
A0002 Att 2 MH104 REV 2.pdf PDF
A0002 Att 5 Sign in Sheet.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

Office of

Construction and Facilities

Management

CONSULTANTS: PROJECT MANAGER:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120

Cary, North Carolina 27511 www.acg-pa.com 919-858-7420

U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

# 2

502-16-104

TAMEKA J. TAYLOR

1-9-2020

100% CONSTRUCTION DOCUMENTS

17-108

2495 SHREVEPORT HWY. PINEVILLE, LA 71360

REPLACE HVAC SYSTEM

VA COMMENTS 5/15/20201

FAN COIL UNIT SCHEDULE REMARKS:

1. UNIT SHALL HAVE ELECTRONICALLY COMMUTATED (EC) MOTOR.

2. UNIT SHALL BE CAPABLE OF MEETING THE REQUIRE AIRFLOWS, CAPACITIES, ETC. AT LOW OR MEDIUM FAN SPEED.

3. PROVIDE FACTORY-MOUNTED FUSED DISCONNECT SWITCH.

4. PROVIDE 1" MERV 8 FILTER. FOR DUCTED UNITS, THE PERMANENT FILTER SHALL BE IN THE FILTER RETURN GRILLE.

5. PROVIDE SUPPLY AND RETURN DUCT COLLARS.

6. PROVIDE BOTTOM ACCESS PANEL RETURN INLET GRILLE AND FRONT STAMPED LOUVER SUPPLY OUTLET.

7. PROVIDE UNIT WITH FACTORY-INSTALLED 24V MODULATING CONTROL VALVES. VALVES SHALL BE PROVIDED BY THE CONTROLS CONTRACTOR.

MECHANICAL EQUIPMENT SCHEDULES

M-601

SMPLH

M-601

19 21

1. INSTALL PER MANUFACTURER'S INSTRUCTIONS.

2. AIR SEPARATOR SHALL BE ASME STAMPED, RATED TO 125 PSIG.

1. INSTALL PER MANUFACTURER'S INSTRUCTIONS.

2. MAXIMUM WORKING PRESSURE IS AT 200 DEGREES F OPERATING TEMPERATURE.

3. INITIAL FILTER USED FOR CLEANING THE CHILLED WATER SYSTEM SHALL BE A 20 MICRON PLEATED FILTER. AFTER SYSTEM IS

CLEAN, INSTALL A 5 MICRON PLEATED FILTER FOR USE DURING SYSTEM OPERATION.

REMARKS:

1. UNIT SHALL BE A PACKAGED, PRE-PIPED SYSTEM WITH A N+1 REDUNDANT DESIGN (IE, FOR A QUADRIPLEX PUMP PACKAGE, 3 PUMPS WOULD

HANDLE THE FULL LOAD WITH ONE ACTING AS AN EMERGENCY BACKUP), MOUNTED ON A SKID. PACKAGE SHALL COMPLETE WITH VENTED

CONDENSATE RECEIVER, STEAM TRAP, STRAINERS, AND CHECK VALVES ON THE INLET AND DISCHARGE OF EACH PUMP.

2. UNIT MUST BE NO MORE THAN 63 INCHES TALL FULLY CONSTRUCTED. PROVIDE WITH SIDE RECEIVER CONDENSATE INLET TO REDUCE HEIGHT

UNIT IS NEEDED TO BE DEPRESSED INTO THE CRAWLSPACE.

REMARKS:

REMARKS:

1. INSTALL PER MANUFACTURER'S INSTRUCTIONS.

2. PROVIDE 1" FILTER FRAME AND 1" THICK MERV 8 FILTER.

REMARKS:

1. INSTALL PER MANUFACTURER'S INSTRUCTIONS.

2. SEE FLOOR PLAN FOR THROW PATTERN.

3. SEE DETAIL FOR DAMPER IN SUPPLY DUCT BRANCHES.

4. PROVIDE SQUARE TO ROUND ADAPTER AS REQUIRED.

REMARKS:

PRE - BID RFI RESPONSES 7/31/20202

DocuSign Envelope ID: 50215E3C-4A46-4E24-BEB4-7E1B422EEEB3

7/31/2020

Sheets and Views
MECHANICAL EQUIPMENT SCHEDULES