9609 Bid Tab.xlsx
XLSX spreadsheet 13 KB Posted
- Solicitation number
- S-63400-00006620
- Issued by
- Marion County, Oregon
About this file
This document is a bid tabulation for ITB 9609 - Forest Improvement at Silver Falls State Park, a state and local contract opportunity in Oregon. The project involves forest improvement work at Silver Falls State Park, located in Marion County and Sumpter City. The contract was bid by three vendors: Eugene Drescher, O'Malley Brothers Corporation, and Trees Plus Northwest. The bid opening date was May 5, 2023. The bid tabulation includes the timber volumes, timber bid prices per thousand board feet (mbf), total timber values, and the cost of operations for each vendor. The vendor with the lowest total bid price was Trees Plus Northwest at $61,859.35.
Regarding pricing, the bid prices ranged from $175/mbf to $648.56/mbf for the timber, and the cost of operations ranged from $215,090 to $394,000. There is no information provided about any set-asides, incumbents, funding sources, or other salient details. The contract appears to be for a one-time forest improvement project at Silver Falls State Park.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
05-08-23
| OPRD #9609 |
| OregonBuys #S-63400-00006620 |
| Closing: 05/05/2023 |
| Title: Forest Improvement at Silver Falls State Park |
| Eugene Drescher | O'Malley Brothers Corporation | Trees Plus Northwest | ||||||
| 13703 Hobart Rd | 7842 SE 282nd Ave | 6605 Wallace Rd Nw | ||||||
| Silverton, OR 97381 | Gresham, OR 97080 | Salem, OR 97304 | ||||||
| Volume (mbf) | Timber Bid = $/mbf | Total Timber Value | Volume (mbf) | Timber Bid = $/mbf | Total Timber Value | Volume (mbf) | Timber Bid = $/mbf | Total Timber Value |
| 430.18 | $ 250.00 | $ 107,545.00 | 430.18 | $ 175.00 | $ 75,281.50 | 430.18 | $ 648.56 | 279,000.00 |
Cost of Operations: $215,090 Cost of Operations: $394,000.00 Cost of Operations: $217,140.65
| Total Timber Value | Cost of Operations | Total Bid Price | Total Timber Value | Cost of Operations | Total Bid Price | Total Timber Value | Cost of Operations | Total Bid Price |
| $ 107,545.00 | $ 215,090.00 | -107,545 | $ 75,281.50 | $ 394,000.00 | -318718.5 | $ 279,000.00 | $ 217,140.65 | 61859.35 |