This is Addendum No. 2 issued by St. Tammany Parish Government Procurement Department for Bid #26-27-2, regarding the St. Tammany Parish Library-Mandeville Branch Renovations project located at 844 Girod Street in Mandeville, Louisiana. The addendum clarifies contract document requirements and confirms that bidders must furnish all labor, materials, equipment, machinery, utilities, and other facilities necessary to complete the renovation work. Sealed bids are due on Wednesday, June 3, 2026, with a mandatory site visit previously scheduled for Wednesday, May 13, 2026 at 9:30 a.m. The project scope includes comprehensive renovations such as removal and replacement of the front entrance feature, installation of impact-resistant storefronts, new carpet tile flooring, concrete flatwork replacement, restroom renovations, new computer and data wiring, and mini-split HVAC installation. The contract term is limited to 180 calendar days from the Notice to Proceed, with two alternates available for carpet tile replacement and landscape installation.
The addendum specifically addresses prior product approvals, noting that the YHS 50 FI Impact Resistant and Blast Mitigating Storefront System has been approved for specification section 084100 Impact Resistant Storefront; however, this approval is limited to the specified manufacturer only, and all products must meet the original bid document specification requirements. The project is classified as Building Construction (IIIB construction type) and requires bidders to be properly licensed Louisiana contractors. Liquidated damages are assessed at $1,000 per day for projects in the $250,000–$1,000,000 range, with retainage held at 5 percent for contracts $500,000 and above and 10 percent for contracts under $500,000. The contract will be awarded to the lowest responsible bidder, with funding provided through St. Tammany Parish Government resources, subject to available funding and approval by designated parish members.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 923456-26-27-2-1.pdf | ||
| 923456-26-27-2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ST. TAMMANY PARISH
MICHAEL B. COOPER
PARISH PRESIDENT
PROCUREMENT DEPARTMENT
P.O. BOX 628 | COVINGTON, LOUISIANA | 70434 | PROCUREMENT@STPGOV.ORG | 985-898-2520
WWW.STPGOV.ORG
Version 2026.1
May 29, 2026
Please find the following addendum to the below-mentioned BID.
Addendum No.: 2
Bid#: 26-27-2
Project Name: St. Tammany Parish Library – Mandeville Branch Renovations
Bid Due Date: Wednesday, June 3, 2026
ATTACHMENTS:
1. Addendum No. 2 (Continued) http://www.stpgov.org/
235 Girod Street ● Mandeville, LA 70448
985 674 3077 ● kvs@kvsarchitecture.com
May 28, 2026
PPSL – VSF# 23-33-5
ST. TAMMANY PARISH – MANDEVILLE BRANCH LIBRARY RENOVATIONS
844 Girod Street Mandeville, LA 70448
ADDENDUM NO. TWO
The following items shall be considered part of the Contract Documents for the above referenced project, and shall take precedence over any conflicting statements contained therein. Revise all other drawings and specifications as required. The bidder hereby acknowledges and agrees to furnish all labor, materials, equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary to perform the work as indicated in the Addenda. The bidder is required to acknowledge Addenda in accordance with Instructions to Bidders.
1.0 CLARIFICATIONS:
Not Used.
2.0 ATTACHMENTS:
3.0 DRAWINGS:
4.0 SPECIFICATIONS:
Not Used.
5.0 PRIOR APPROVALS: (Products must meet all performance criteria in accordance with specifications).
5.1 YHS 50 FI Impact Resistant and Blast Mitigating Storefront System was submitted as a prior approval for 084100 Impact Resistant Storefront.
Please note that this prior approval is for the acceptance of the above captioned manufacturer only and that all products must meet the specification requirements in the Original Bid Documents regardless if listed as a Prior Approved Product.
END OF ADDENDUM NO. TWO