9-Appendix G- Interoperability Testing Schedule.pdf

PDF 220 KB Posted

Attached to
NGCS & ESInet Fairfax VA & Regional 911 Authorities
Solicitation number
RFP 2000004244
Issued by
Fairfax County, Virginia

About this file

This document is an Interoperability Testing Schedule (Appendix G) for RFP 2000004244, which concerns Next Generation 9-1-1 Core Services and Emergency Services IP Network solutions for Fairfax County, Virginia, and regional 911 authorities across Virginia, Maryland, the District of Columbia, and other authorized jurisdictions. The testing schedule outlines a standardized process for evaluating vendor solutions for NG9-1-1 compliance and functionality. Each vendor undergoes approximately a 30-calendar-day test cycle, with up to three vendors testing concurrently depending on laboratory availability. The pre-test preparation phase (weeks -3 to 0) requires vendors to execute non-disclosure and data-sharing agreements, complete self-assessments using approved scripts, provide technical data exchanges, and finalize test plans. The formal test cycle spans four weeks, including onboarding and validation, cybersecurity testing against NIST/CISA baselines, interoperability testing using NENA i3 functional scripts covering call routing, ECRF/ESRP, failover, redundancy, and CAD/CHE integration, and adjudication with reporting. Post-test activities include final report submission by Netmaker Communications Interoperability Lab (NMC) and Ashburn Consulting, LLC, stakeholder review meetings, and optional vendor retesting within 90 days at the vendor's expense if deficiencies are identified.

The aggregate testing schedule anticipates approximately three months to complete testing for six vendors using two concurrent testing streams. All vendors access documentation, frequently asked questions, self-assessment tools, and secure portal resources through the Netmaker Communications Interoperability Lab at www.NMCLabs.net, which serves as the central repository for onboarding materials and test guidance. Fairfax County (Sponsor) and Ashburn Consulting, LLC (Prime) coordinate the sequencing and administration of all testing activities, with vendors required to request secure access credentials prior to testing initiation.

View the file

Other files

File Type Posted
8-Appendix F- SLA Summary Matrices.pdf PDF
7-Appendix E - Narrative Responses.docx DOCX document
3-Attachment B.pdf PDF
2-Attachment A1-A7.pdf PDF
4-Appendix B.pdf PDF
1-DPMM Coversheet.pdf PDF
5-Appendix C - Technical Requirements.xlsx XLSX spreadsheet
6-Appendix D - Cost Proposal.xlsx XLSX spreadsheet
10-RFP 2000004244.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP 2000004244

APPENDIX G - NG9-1-1 Interoperability Testing Schedule

G-1

Assumptions

• Each vendor test cycle lasts approximately 30 calendar days. Weeks shown below are independent of the RFP procurement schedule and represent relative times for the Interop Testing schedule.

• Up to three vendors may test concurrently (depending on lab availability).

• Fairfax County (Sponsor) and Ashburn Consulting, LLC (Prime) will coordinate sequencing.

• Each vendor shall complete a pre-test self-assessment using approved scripts and submit results via the Netmaker Communications Interoperability Lab portal (www.NMCLabs.net) prior to formal testing.

1. Pre-Test Preparation (Weeks – 3 to 0)

Task Responsible Party Duration / Timing Description / Output

NDA & Access Agreements

Fairfax / Vendors /

NMC

Week –3 to –2 Execute non-disclosure, data-sharing, and network access agreements.

Vendor Self- Assessment Submission

Vendor / NMC Week –3 to –2

Vendors complete self-assessment using approved scripts (e.g., NENA i3 conformance, Nessus cybersecurity scans) and upload results to NMCLabs.net portal.

Technical Data Exchange

Vendors / NMC Week –2 Vendors provide network diagrams, interface definitions, and configuration data.

Test Environment Readiness

NMC Week –2 to 0 Configure testbed (NGCS components, CHE, CAD, LIS/GIS, cybersecurity tools).

Baseline Test Plan Finalization

NMC / Ashburn Week 0 Deliver and approve test scripts and schedule for vendor execution.

2. Test Cycle (30 Calendar Days per Vendor)

Phase Duration Key Activities Primary Deliverables

Week 1 – Onboarding & Validation

5 days Confirm environment setup, validate connectivity, review vendor self-assessment results, and perform pre-test checks.

Test Readiness Checklist

Week 2 – Cybersecurity Testing

5 days Conduct vulnerability scanning, penetration testing, and configuration review per NIST / CISA baselines.

Cybersecurity Test Log

Week 3 – Interoperability Testing

5 days Execute NENA i3 functional test scripts: call routing, ECRF/ESRP, failover, redundancy, CAD / CHE integration.

Interoperability Test Results Log

Week 4 – Adjudication & Reporting

5 days

Review findings with vendor, capture remediations, compile reports and scorecard. If deficiencies are identified, issue retest notice and define 90-day remediation window.

Draft Reports and Completion Scorecard

3. Post-Test Activities (Weeks +1 to +2)

Task Responsible Party Output

Final Report Submission NMC → Ashburn / Fairfax Final Cybersecurity + Interoperability Reports; Scorecard

Stakeholder Review Meeting

Fairfax / Ashburn / Vendor / NMC Presentation of findings and resolution discussion

Optional Vendor Retest (if required)

Vendor / NMC Follow-up testing must be completed within 90 days of deficiency notification at the vendor’s expense.

RFP 2000004244

APPENDIX G - NG9-1-1 Interoperability Testing Schedule

G-2

4. Example Aggregate Schedule (Six Vendors, Two Concurrent Streams)

Month Stream A Stream B

Month 1 Vendor 1 Testing Vendor 2 Testing

Month 2 Vendor 3 Testing Vendor 4 Testing

Month 3 Vendor 5 Testing Vendor 6 Testing

Total Estimated Duration: ~3 months to complete all six vendors, assuming overlapping test streams and standard 30-day cycles.

5. Vendor Portal Resources

All documentation, FAQs, and self-assessment tools are available via the Netmaker Communications Interoperability Lab at www.NMCLabs.net. (Vendors must request secure access credentials prior to testing. The portal serves as the central repository for onboarding materials, test guidance, and updates.)

http://www.nmclabs.net/