About this file

This document is Addendum 1 for Invitation to Bid (ITB) 2026002 issued by Clayton County Public Schools (CCPS) for W.A. Fountain Elementary School Abatement and Demolition Services. The project involves abatement and demolition services with an estimated construction value of $2,000,000. The mandatory pre-bid meeting and site visit occurred on Wednesday, October 8, 2025, at 10:00 A.M. at W.A. Fountain Elementary School. Key dates include a questions deadline of October 16, 2025, answers posting on October 23, 2025, and the bid submission deadline on October 30, 2025. The anticipated construction timeline runs from December 15, 2025, to April 13, 2026, with a final completion date of July 13, 2026.

The addendum includes several modifications to the original bidding documents, such as changes to the SLBE (Small Local Business Enterprise) Program requirements and procedural details. The bid process includes provisions for SLBE-Clayton preferences, with the lowest SLBE-Clayton bidder allowed to match the low bid of a non-SLBE-Clayton bidder if within 5% of the original bid. Bidders must submit documentation showing compliance with SLBE contracting percentage goals, including a Subcontractor/Supplier Utilization Plan and a Letter of Intent. The public bid opening will be conducted via Zoom on October 30, 2025, at 3:00 P.M. Eastern Standard Time, with specific meeting details provided in the addendum.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum 1, ITB W.A. Fountain ES Abatement and Demolition Services Page 1 of 10

Clayton County Public Schools

Construction Department 6635 Lake Drive • Morrow, Georgia 30260 • (770) 473-2706

DR. ANTHONY W. SMITH RONICK JOSEPH

Superintendent of Schools Chief Capital Improvement Officer

ADDENDUM # 1

ITB 2026002

W.A. Fountain Elementary School Abatement and Demolition Services for Clayton County Public Schools

Solicitation Released: October 3, 2025

Where any original item, term, or requirement is not specifically amended, voided or superseded by this addendum, it will remain in effect. This clarification is being provided to all known respondents.

1. The Pre-Bid Conference Agenda and Sign-in Sheet pertaining to this ITB are attached hereto as Attachment 1.

2. CCPS has change Invitations for Bids (IFB) to Invitation to Bids (ITB ) on the SLBE Program-Required Document, Appendix D, on Page 2 of 3. The revised Page 2 of 3 is attached hereto as Attachment 2.

3. CCPS has added Item Number 4.3.7 on Page 11, Bonfirehub.com Portal at Vendor Discussions. The revised Page 11 is attached hereto as Attachment 3.

4. CCPS has change the Procurement-Construction address in Item Number 5.4.2 from 66635 Lake Drive to 6635 Lake Drive on Page 12. The revised Page 11 is attached hereto as Attachment 4.

5. CCPS has replaced Page 19 in its entirety to include the time for the question deadline, when the answers will be posted and the time for the bid submission deadline. The revised Page 19 is attached hereto as Attachment 5.

6. CCPS has added the Zoom meeting link for the public bid opening of ITB

2026002 – W.A. Fountain Elementary Demolition Services. The public bid opening is scheduled for October 30, 2025, at 3:00 P.M. Eastern Standard Time.

The Zoom Meeting Link below:

ITB 2026002 W.A. Fountain Elementary School Abatement and Demolition Services for Clayton County Public Schools Public Bid Opening

Meeting ID: 987 0688 4676

Passcode: 937162

Telephone Number: +14702509358, 98706884676# US (Atlanta) https://claytonk12ga.bonfirehub.com/portal/?tab=login

Addendum 1, ITB W.A. Fountain ES Abatement and Demolition Services Page 2 of 10

Drexal Paulk MBA, CPM, CPPO, CPPB Issue Date Director of Procurement-Construction/Capital Projects

This sheet must be completed, signed, and returned with any bid to acknowledge receipt of this Addendum. Failure to do so may result in the rejection of any bid submitted.

The above addendum is hereby acknowledged:

Signature

Title

Company Name

Date

10/9/2025 | 3:20:59 PM EDT

Addendum 1, ITB W.A. Fountain ES Abatement and Demolition Services Page 3 of 10

ATTACHMENT 1

CLAYTON COUNTY PUBLIC SCHOOLS

“BUILDING A BETTER TOMORROW, TODAY”

ITB 2026002

W.A. Fountain Elementary Abatement and Demolition Services

Mandatory Pre-Bid Meeting and Site Visit Agenda

Wednesday, October 8, 2025 at 10:00 A.M.

W. A. Fountain Elementary School - Media Center 5215 West Street

Forest Park, GA 30297

Agenda

1. Opening Remarks Rose Tookes

Procurement Specialist – Construction Department Introduction of CCPS Staff Purpose of the Meeting

End User Department Christy Crawford

Capital Projects Executive – Construction Department

2. Bid Overview Rose Tookes

2.1 Important Dates

2.2 CCPS Required Forms and SLBE Forms

2.3 CCPS Insurance

2.3 Performance and Payment Bonding

2.4 Submission of Written Questions

2.5 Prohibited Contact

3. Scope of Work Cody Lanman, PE

3.1 Abatement Project Manager – Eberly & Associates

3.2 Demolition

3.3 Substitutions

3.4 Schedule

3.5 Permits

5. Questions and Answers Cody Lanman, PE

6. Conclusion and Adjournment

Responses to this ITB will be received by Clayton County Public Schools (CCPS), Procurement Construction Department, 6635 Lake Drive, Morrow, Georgia, 30260 until 3:00 P.M., Eastern Standard Time (EST) on Thursday, October 30, 2025.

All questions or inquiries pertaining to the project are due no later than 3:00 p.m. on Thursday, October 16, 2025. All questions must be submitted for this ITB in the Bonfirehub.com Portal at Vendor Discussions. All replies will be made in writing via addendum to the CCPS Bonfire website. Oral responses are not authoritative. It shall be the responsibility of each Bidder to monitor the CCPS Bonfire website at:

https://claytonk12ga.bonfirehub.com/portal/?tab=openOpportunities and obtain a copy of any addendum issued for this ITB.

Addendum 1, ITB W.A. Fountain ES Abatement and Demolition Services Page 4 of 10

“BUILDING A BETTER TOMORROW, TODAY”

ITB 2026002

W.A. Fountain Elementary Abatement and Demolition Services

Mandatory Pre-Bid Meeting and Site Visit Agenda

Wednesday, October 8, 2025 at 10:00 A.M.

W. A. Fountain Elementary School - Media Center

5215 West Street Forest Park, GA 30297

QUESTIONS

Please print your question (s) below. Any question not answered today will be answered by addendum as stated below*

Name: Title:

Company/Firm:

Email Address:

*Attendees will be permitted to ask questions during the pre-bid meeting, however, any oral responses to questions are not authoritative and may not be relied upon for any matter. It shall be the responsibility of each Bidder to monitor the CCPS Bonfire website at:

https://claytonk12ga.bonfirehub.com/portal/?tab=openOpportunities and obtain a copy of any addendum issued for this IFB. Please do not contact the end user department or any elected officials about this ITB.

Addendum 1, ITB W.A. Fountain ES Abatement and Demolition Services Page 5 of 10

“BUILDING A BETTER TOMORROW, TODAY”

ITB NO. 2026002 W.A. Fountain ES Abatement and Demolition Services

Mandatory Pre-Bid Meeting and Site Visit

Wednesday, October 8, 2025, 10:00 A.M.

Attendance Sheet

Print Name Title Company Name Email Address

1 Jean Paul Goulet Project Manager Thompson Building Wrecking

James L. Prior Project Manager Jermaine Enterprises, Inc.

3 James Morehead Pres. Complete Demolition

4 Tim Thomas Project Manager Johnson Enterprise, Inc.

5 Jesse J. Jenkins CEO Jermaine Enterprises, Inc.

6 Henry Sajdivar Project Manager

American Property Restoration

Rick Arndt

Pres.

First Environmental Services

Al Diallo

Pres.

American Property Restoration

Addendum 1, ITB W.A. Fountain ES Abatement and Demolition Services Page 6 of 10

Print Name Title Company Name Email Address

9 Alaih Komono() Pres. American Property Restoration

10 Cody Lanman PM – Civil Engineer Eberly

11 Kobe Heffner Operator Wrecking Corp, LLC

12 Sarah Zuniga Supervisor Green Source Environmental, Inc, 13 Ashley Butterfield Env. Director Oasis Consulting

Yader Vilchez

Project Manager

Southern Env. Serv. Inc.

Joe Barillari

Owner

Tristar America, LLC

16 John Wilson PM 316 Cleaning & Grading

17 Rose Tookes Procurement Specialist Construction Dept.

18 Christy Crawford Capital Projects

Executive

Construction Dept.

ITB NO. 2026002 – W.A. Fountain ES Abatement and Demo Services, Wed, October 8, 2025

Mandatory Pre-Bid Meeting and Site Visit – Attendance Sheet, Page 2 of 2

Addendum 1, ITB W.A. Fountain ES Abatement and Demolition Services Page 7 of 10

ATTACHMENT 2

APPENDIX D

SLBE PROGRAM-REQUIRED DOCUMENTS

business license must be submitted with Bidder’s/Proposer’s response to any qualified solicitation.

Certified SLBEs located and operating within Clayton County, Georgia that contribute to the local tax base are granted a preference on bids and proposals submitted in response to qualified solicitations.

SLBE-CLAYTON PREFERENCES

The preference/bid-match provisions do not apply to solicitations or bids where applicable procurement laws prohibit or restrict these types of preferences, including construction projects covered by the Georgia Local Government Public Works Construction Law.

Request for Proposals (RFP) 5 Points in Initial Evaluation

Invitations to Bids (ITB) Bid Match

Lowest SLBE-CLAYTON bidder will be allowed to match the low bid of a Non SLBE-CLAYTON bidder if such bid is responsible and responsive and within five (5) percent of the low bid submitted by a Non SLBE-CLAYTON bidder. The SLBE-CLAYTON must match the bid in timeframe prescribed by CCPS.

Without exception all bidders/proponents, including those that are SLBEs, must comply with all

SLBE program requirements. Each bidder/proponent, including SLBE bidders/proponents, must submit documentation showing that the required SLBE contracting percentage goal will be performed by a certified SLBE. Please find attached hereto the mandatory forms and requirements for this particular solicitation. The mandatory documents include:

1. SLBE Subcontractor/Supplier Utilization Plan;

2. Letter of Intent describing the work, material, equipment and/or services to be provided by each SLBE and the agreed percentage of participation; and

3. Subcontractor/Supplier Contact List and Documentation of Good Faith Efforts (GFE).

Bidders/Proponents failing to meet the SLBE contracting goal must document contacts and demonstrate GFE on the prescribed form. GFE may include, but are not limited to, the following:

a) Identifying scope(s) of work which may be available for the inclusion of SLBEs or making efforts to divide work into subcontracting areas wherein SLBEs are likely to be successful;

b) Assisting potential SLBEs with bonding, insurance or other contracting requirements;

c) Attending pre-solicitation meetings to meet potential SLBEs;

d) Reviewing SLBE registry and contacting those that can perform a Commercially

Useful Function on a specific project;

e) Advertisement in a trade publication or journal to target SLBEs for a specific project.

f) Hosting a virtual or in-person event to solicit SLBEs; and

g) Outreach to advocacy groups/trade associations where SLBEs might be members.

Addendum 1, ITB W.A. Fountain ES Abatement and Demolition Services Page 8 of 10

Page 11 of 552 W.A. FOUNTAIN ELEMENTARY SCHOOL ABATEMENT AND DEMOLITION SERVICES – CCPS PROJECT NO 2026002

ATTACHMENT 3

4.3.5 The Bidder must complete, execute and include with the Bid, the following on forms identical to the forms provided in the Bidding Documents:

1. Bid Form;

2. Bid Bond;

3. Subcontractor Listing;

4. Corporate Certificate, Partnership Certificate, or Entity Certificate (as applicable); and

5. SBLE Subcontractor/Supplier Utilization Plan.

4.3.6 For any technical questions or difficulties, contact Bonfire Support at https://support.gobonfire.com/hc/en-us.

4.3.7 All questions must be submitted in Bonfire for this IFB in Bonfirehub.com Portal at Vendor Discussions.

4.4 Modification or Withdrawal of Bids

Except as otherwise expressly provided by applicable law, no Bid may be withdrawn for a period of one hundred and eighty (180) calendar days following the closing time and date for receipt of Bids, and all Bids are subject to acceptance by the Owner during said period, and each Bidder so agrees by submitting a Bid.

ARTICLE 5

CONSIDERATION OF BIDS

5.1 Opening of Bids. Unless stated otherwise in the Invitation to Bid, the properly identified timely Bids will be opened publicly and will be read aloud. All interested parties are invited to attend.

5.2 Rejection of Bids. Notwithstanding any other provision, the Owner shall have the right to reject any or all Bids, before or after opening, for any reason whatsoever including, but not limited to, any failure of any Bid to be accompanied by a Bid Bond or by other data required by the Bidding Documents, any incompleteness or irregularity of any Bid received, any evidence of collusion with the intent to defraud or other illegal practices on the part of the Bidder, failure to comply with the requirements of the Bidding Documents, or exceeding the funds available. Nothing shall limit or restrict the Owner's authority to reject any and all Bids.

5.3 Acceptance of Bid (Award)

5.3.1 It is the intent of the Owner to award a contract, at the sole option of the Owner, in due course and after a reasonable Bid evaluation period, on a lump sum basis and within the funds available, to the lowest responsive, responsible Bidder provided that the Bid otherwise fulfills the requirements of the Bidding Documents. The Owner shall have the right to waive technicalities and informalities in a Bid received and to accept the Bid which, in the Owner's judgment, is in the Owner's best interests.

5.3.2 Deductive Alternates may be used to reduce the Base Bid; however, they shall be prioritized and exercised, if at all, in numerical sequence as listed in the Bidding Documents. Additive Alternates shall not be https://support.gobonfire.com/hc/en-us https://claytonk12ga.bonfirehub.com/portal/?tab=login

Addendum 1, ITB W.A. Fountain ES Abatement and Demolition Services Page 9 of 10

Page 12 of 552 W.A. FOUNTAIN ELEMENTARY SCHOOL ABATEMENT AND DEMOLITION SERVICES – CCPS PROJECT NO 2026002

ATTACHMENT 4

used to determine the Low Bid. Low Bid shall be determined on the Base Bid less any deductive alternates exercised. Additive alternates may be exercised in any priority order and will be considered only after the Low Bid has been determined.

5.3.3 Each Bidder shall be prepared to commence Work upon the date it receives the Notice to Proceed to be issued by the Owner, or such later date as may be set forth therein.

5.4 Protest Procedures. This Section describes the mandatory administrative procedure whereby bidders may challenge procurement decisions or awards. The Owner will process protests in a timely and consistent manner to assure that all bidders are accorded equal consideration for the award of contracts.

5.4.1 A protest of any events or facts arising during the solicitation process shall be filed within three (3) business days of the occurrence of the event or fact giving rise to the protest. Notwithstanding the foregoing, any protest of event or facts arising during the solicitation process must be filed before the deadline for bids. A protest of the award of any contract shall be filed within three (3) business days of the posting of the Notice of Award/Notice of Intent to Award. If a protest is not filed by the applicable deadline, such failure shall be deemed as a waiver with prejudice of any grounds the bidder may have for a protest.

5.4.2 A protest is considered to be properly filed when it is in writing, signed by a company officer, and is received by the Construction Procurement Department. The protest should be marked "PROTEST" on the outside of the package and should be addressed to:

Clayton County Public Schools Attn: Procurement - Construction Director of Procurement 6635 Lake Drive

Morrow, GA 30260

5.4.3 At minimum, the written protest must include the following information:

1. Name and address of protestor;

2. Appropriate identification of the solicitation;

3. A statement of the reasons for the protest;

4. Supporting exhibits, evidence or documents to substantiate any claims, unless not available within the filing timeline (in which case the protestor should identify when such materials are expected to be available); and

5. The desired remedy.

5.4.4 The Director of Procurement shall review the protest and issue a written decision within five (5) business days. The decision of the Director of Procurement shall be final.

Addendum 1, ITB W.A. Fountain ES Abatement and Demolition Services Page 10 of 10

W. A. FOUNTAIN ES ABATEMENT AND DEMOLITION SERVICES PROCUREMENT SCHEDULE

Page 19 of 552 W.A. FOUNTAIN ELEMENTARY SCHOOL ABATEMENT AND DEMOLITION SERVICES – CCPS PROJECT NO 2026002

ATTACHMENT 5

ESTIMATED CONSTRUCTION VALUE: 2,000,000.

BID SUBMISSION DATE: THURSDAY, OCTOBER 30, 2025

ADVERTISEMENT FOR BID

FRIDAY, OCTOBER 3, 2025

MANDATORY PRE-BID MEETING WEDNESDAY, OCTOBER 8, 2025 @ 10:00 A.M.

MANDATORY SITE VISIT WEDNESDAY, OCTOBER 8, 2025 @ 10:00 A.M.

QUESTIONS DEADLINE THURSDAY, OCTOBER 16, 2025 @ 3:00 P.M.

ANSWERS POSTED THURSDAY, OCTOBER 23, 2025 @ 3:00 P.M.

BID SUBMISSION DEADLINE THURSDAY, OCTOBER 30, 2025 @ 3:00 P.M.

SLBE REVIEW

THURSDAY, OCTOBER 30 - 31, 2025

BOARD AGENDA ITEMS DUE

THURSDAY, NOVEMBER 6, 2025

BOARD WORK SESSION

MONDAY, NOVEMBER 17, 2025

BOARD MEETING

MONDAY, DECEMBER 1, 2025

CONSTRUCTION PHASE

ANTICIPATED PRE-CONSTRUCTION

MEETING DATE

THURSDAY, DECEMBER 11, 2025

ANTICIPATED START DATE FOR

CONSTRUCTION

MONDAY, DECEMBER 15, 2025

ANTICIPATED COMPLETE DATE

APRIL 13, 2026

ANTICIPATED FINAL COMPLETION DATE

JULY 13, 2026

ADDENDUM # 1
Where any original item, term, or requirement is not specifically amended, voided or superseded by this addendum, it will remain in effect. This clarification is being provided to all known respondents.
3. CCPS has added Item Number 4.3.7 on Page 11, Bonfirehub.com Portal at Vendor Discussions. The revised Page 11 is attached hereto as Attachment 3.
5. CCPS has replaced Page 19 in its entirety to include the time for the question deadline, when the answers will be posted and the time for the bid submission deadline. The revised Page 19 is attached hereto as Attachment 5.
CLAYTON COUNTY PUBLIC SCHOOLS
“BUILDING A BETTER TOMORROW, TODAY”
ITB 2026002
CLAYTON COUNTY PUBLIC SCHOOLS
“BUILDING A BETTER TOMORROW, TODAY”
ITB 2026002
*Attendees will be permitted to ask questions during the pre-bid meeting, however, any oral responses to questions are not authoritative and may not be relied upon for any matter. It shall be the responsibility of each Bidder to monitor the CCPS Bonfi...
ITB NO. 2026002 – W.A. Fountain ES Abatement and Demo Services, Wed, October 8, 2025
4.4 Modification or Withdrawal of Bids
ARTICLE 5 CONSIDERATION OF BIDS
5.3 Acceptance of Bid (Award)
ATTACHMENT 4
ATTACHMENT 5
2025-10-09T12:21:00-0700
Digitally verifiable PDF exported from www.docusign.com

File details come from the government source that posted it. Updated .