About this file
This is a Construction Quality Assurance and Quality Control Inspection Plan prepared by Shive-Hattery Engineering for the Iowa Department of Agriculture and Land Stewardship (IDALS) for the CAL883229B wetland construction project in Calhoun County, Iowa. The plan establishes documented procedures for construction observation and quality assurance during the construction of a nutrient reduction wetland, with oversight provided by IDALS Engineer Sara Smith and Engineer of Record Dan Jensen. The document outlines the inspection requirements for various construction phases including tile exploration, soil confirmation, embankment construction, grading operations, pump station installation, water control structure installation, tile intercepts and outlets, and seeding activities. Inspection levels range from full-time observation for critical activities such as embankment construction, pump station installation, and water control structure installation to intermittent inspection for general grading, tile intercepts, and seeding operations. The plan specifies that site benchmarks and easement boundary stakes will be established by Shive-Hattery prior to construction commencement, and an as-built survey will be completed following topsoil placement to verify bid quantities and document final elevations and locations of all major project components.
The inspection plan establishes clear responsibility divisions whereby quality control is the contractor's responsibility while quality assurance remains with the Design Engineer of Record. The contractor must submit construction schedules, material certifications, and shop drawings for approval prior to implementation, including specifications for pipes, field tile, rock and riprap, pump stations, concrete mix designs, trash racks, drawdown structures, seeding, and fertilizer. Observers must be either the professional engineer of record or an engineer in training familiar with the project, with the engineer of record available by phone for consultation. The plan includes provisions for documenting contract changes and modifications through coordination between the construction observer, engineer of record, and IDALS. As-built records will include location and elevation data for sheet pile weirs, stilling basins, tile intercepts and outlets, sedimentation basins, drawdown structures, embankment features, and cross-sections to verify final construction elevations and quantities against bid specifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Inspection Plan
CAL883229B Wetland Iowa Department of Agriculture and Land Stewardship
Contact Information
Landowners: Joel Wuebker
(712) 297-8609
Calhoun County Conservation (Attn: Curtis Vanderheiden)
(712) 297-7131
IDALS Engineer: Sara Smith, PE
(515) 422-7335 sara.smith@iowaagriculture.com
Engineer of Record: Dan Jensen, PE
(641) 373-1068 djensen@shive-hattery.com
Purpose
This purpose of this construction observation plan is to provide a documented procedure for construction quality assurance for the above referenced wetland construction project. Procedures laid out in this plan are meant to be general procedures and should be modified as appropriate based on observations and discussions in the field as well as the skill and experience of the construction contractor and crew members.
Construction Submittals and Shop Drawings A schedule of construction submittals and shop drawings for the project will be provided by the engineer to the contractor. The contractor is responsible for providing all submittals to the engineer for review.
The Engineer will review and provide approval, reject, or provide other guidance (i.e., furnish as noted) for all shop drawings, materials, and submittals as soon as practical.
A typical schedule of submittals for wetland projects includes:
Construction Schedule Pipes, Field Tile and appurtenances Rock and Rip Rap Pump Station Concrete Mix Designs Trash Racks Drawdown Structures and appurtenances Seeding and fertilizer
More detailed information on items requiring submittals and observation are located in the contract documents.
Construction Observation Procedures The sequence of construction will be determined with the contractor after the contract is awarded, the start date planned and whether crops have been harvested. This will be discussed at the pre-construction meeting. The easement boundary stakes and at least 3 benchmarks to be used for construction will be placed by Shive-Hattery prior to construction commencing.
Project #2142206150 - CAL883229B Wetland
Quality Control (QC) is the responsibility of the contractor, but any work deemed to not be in accordance with the plans and specifications based on inspections completed shall be reworked.
Quality Assurance (QA) is the responsibility of the Design Engineer of Record. The Contractor is responsible to provide materials that meet or exceed the requirements provided on the plans and specification. The Design Engineer will review material certifications provided for all pipe/tile, geotextile, granular material, and riprap. Shop drawings shall also be submitted for approval for the sheet pile weir, drawdown structure, and outlet pipe. The grout mix and seed mix designs shall also be submitted and approved by the Design Engineer prior to placement.
Below is a list of anticipated tasks to be completed along with the amount of inspection required and the experience level of the inspector needed. Engineer refers to either the Design Engineer of Record or an Engineer designated by such. Qualified Technician refers to an individual with sufficient technical background and experience to properly assess the individual work items described below that will be completed by the Contractor.
• Tile Exploration – Full time by Engineer or Qualified Technician The site has several tiles on site based on a map provided by the landowner. The Contractor shall complete the exploration to confirm the depth and location in the presence of the Engineer or Technician with survey equipment. This information will be used by design engineer to adjust the tile outlets as needed to provide suitable outlet based on this acquired information.
• Soil Confirmation – Full time by Engineer or Qualified Technician
The Contractor shall excavate test pits as needed to confirm suitable soils are available before beginning stripping operations.
• Site stripping - No observation required
Site stripping can occur without any site inspection being required. The contractor will need to implement storm water and sedimentation control measures.
• Embankment Construction – Intermittent to Full Time by Engineer or Qualified Technician
The dike shall be constructed to the design height consisting of suitable cohesive material. This critical item of work shall be inspected to assure proper material, moisture, and placement method. Full time inspection shall be implemented if the problems arise, or the rate of placement necessitates this level. If work is progressing well and the rate of placement allows, this work shall be inspected intermittently, but at regular intervals. The location and elevations of the dike shall be checked by Engineer or Qualified Technician with survey equipment when Contractor is nearing final construction grade and before topsoil placement. As-built survey shall be completed after topsoil placement has been completed.
• General Grading – Intermittent by Engineer or Qualified Technician
The site includes grading of sediment forebays and submerged berms, along with deeper pockets within the pool. In addition, primary and secondary borrow areas are located on the plans. The Engineer or Qualified Technician will verify the location and dimensions of the sediment forebays, submerged berms and deeper graded areas within the pool using survey equipment. The borrow area shall also be checked to make sure final grading allows for drainage and has adequate topsoil placement.
• Pump Station – Full time by Engineer or Qualified Technician
The pump station installation shall be inspected by a technician familiar with this type of work or the design engineer.
Project #2142206150 - CAL883229B Wetland
• Water Control Structure Installation – Full time and Intermittent by Engineer or Qualified Technician The location and elevation of the installation of the water control structure, inlet riser, and outlet pipes shall be verified by technician or surveyor prior to backfilling. The Engineer or Qualified Technician shall be on site full-time during the installation of the sand diaphragm.
• Tile Intercepts and Outlets – Intermittent by Engineer or Qualified Technician
The Engineer or Qualified Technician shall verify the tile intersection location and elevation.
Once established, the tile shall be placed to the designated outlet location by Contractor. The Engineer or Qualified Technician shall observe all joint connections prior to backfilling and shall measure the intercepts and outlet with surveying equipment. The Engineer or Qualified Technician shall also verify that adequate soil cover has been obtained and any riprap or erosion stone is properly placed at the outlet.
• Seeding – Intermittent by Engineer or Qualified Technician
Seed bed preparation shall be checked prior to seeding, along with the thickness of the topsoil over fill and borrow areas. Seed tags shall be verified.
Knowledge, Skill, and Ability of Observer A Shive-Hattery engineer familiar with the project and construction methods will be present at the project area during times detailed in this plan. The observer will either be the professional engineer of record for the project or an engineer in training (EIT) familiar with the project. The engineer of record will be available for discussions with the EIT via phone when not performing the construction observation.
Contract Changes At times, changes to the construction scope and fee may be needed. The observer is responsible for coordinating with the engineer of record to document changes or modification to the contract documents. All changes will be recorded and included in the record documents. The construction observer shall document the need for such changes and coordinate contract amendments as required with the engineer of record and IDALS prior to implementation of said modifications.
As-Built Records and Surveying Shive-Hattery is retained by IDALS to provide construction staking for the project as well as conduct an as-built survey. Site Benchmarks will be set prior to construction commencing for use by the contractor.
The as-built survey, benchmark installation, and construction staking will be completed by a professional land surveyor or under the direct supervision of a PLS. Record documents will be prepared and provided to IDALS using the construction observations and as-built survey information and will be used to verify bid quantities.
The record as-built drawings shall include the following information:
• Location and elevation along top of sheet pile weir
• Location and elevation of stilling basing and outlet channel
• Location and elevation of tile intercepts and outlets, along with pipe sizes
• Location and elevation of sedimentation basin
• Location and elevation of top of drawdown structure and inlet structure
• Cross section(s) near the center of the wetland to verify elevations
• Location and elevation of top and toes of the embankment, including the wave bench and auxiliary spillway