Final Plans and Bid Documents for Pumped Wetlands Construction in Rockwell City, Iowa

This document set consists of final construction plans and specifications prepared by Shive-Hattery, Inc. for the Iowa Department of Agriculture and Land Stewardship's Division of Soil Conservation and Water Quality for two pumped nutrient reduction wetlands projects (Cal883229B North and South) located in Calhoun County near Rockwell City, Iowa. The North wetland project involves construction of a 7.35-acre pool with dual pump stations, requiring approximately 7,232 cubic yards of excavation and 6,761 cubic yards of general earthfill, plus 11,887 cubic yards of clay liner material, 5,322 cubic yards of topsoil placement, and 1.9 acres of structure seeding and 15.7 acres of buffer seeding. The South wetland project involves construction of a 4.65-acre pool with a single pump station, requiring approximately 1,056 cubic yards of excavation, 1,355 cubic yards of earthfill and dam materials, 1,220 cubic yards of clay liner material, and seeding of 0.4 acres of structure areas and 0.6 acres of buffer. Both projects include installation of water control structures with 48-inch corrugated metal risers, drawdown pipes, gravity intake pipes from Lake Creek, solar-powered submersible pump systems with variable frequency drives, 8-inch schedule 80 PVC forcemains, riprap placement, silt fence pollution control, and related appurtenances. Construction must commence within 14 days of the preconstruction meeting, with a deadline of December 31, 2026, and seeding deadlines of May 15, 2027 for structures and June 30, 2027 for buffer areas.

The plans specify that both pump stations utilize photovoltaic solar panels with lithium battery storage systems to power submersible axial-flow pumps with design capacities of 1.6 cubic feet per second at 14.5 feet of total dynamic head for the North site and 1.7 cubic feet per second at 12.8 feet of head for the South site, each capable of pumping 600,000 to 700,000 gallons daily and 300,000 to 360,000 gallons daily respectively. All work is subject to NRCS standards and requirements, with construction survey staking provided by the owner at no additional cost to the contractor. The contractor is responsible for all construction dewatering, proper disposal of debris and trash, replacement of damaged property and facilities, and re-seeding of all disturbed areas. A 20 percent shrinkage factor has been incorporated into earthwork estimates, and contractors must comply with Iowa Code 480 for underground facility notification. The project site is located at 2579 Preston Avenue, Rockwell City, Iowa, with the North construction entrance and South construction entrance marked on the plans, and landowner easements involving Joel Wuebker and Calhoun County Conservation. The plans note that neither Shive-Hattery nor IDALS guarantee the wetlands will maintain a permanent pool of water.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF IOWA

ROCKWELL CITY, IOWA

ENGINEER

SHIVE-HATTERY, INC

ATTN: DAN JENSEN

4125 WESTOWN PARKWAY, SUITE 100

WEST DES MOINES, IOWA 50266

PH: (515) 223-8104

FX: (515) 223-0622

SITE ADDRESS:

2579 PRESTON AVE

ROCKWELL CITY, IA, 50579

CONTACT INFORMATION:

IOWA DEPARTMENT OF AGRICULTURE AND LAND STEWARDSHIP

MIKE BOURLAND

502 E 9TH ST

DES MOINES, IA, 50319

OFFICE PH: (515) 242-6130

MIKE.BOURLAND@IOWAAGRICULTURE.GOV

CAL883229B PUMPED WETLANDS

IDALS

PROJECT

LOCATION

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d: C000

BI

D

DO

CU

M

EN

TS

1/

/2

C

AL

B

PU

M

PE

D

W

ET

LA

N

D S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

- C

O

VE

R

SH

EE

T.

dw g

3/

/2

:3 4:

A

M

PROJECT DRAWING COORDINATE SYSTEM:

HORIZONTAL: NAD83 IOWA STATE PLANE

NORTH ZONE (1401)

VERTICAL: NAVD88

UNITS: U.S. SURVEY FEET

PAGES, SHEETS OR DIVISIONS COVERED BY THIS SEAL:

My License Renewal Date is: DECEMBER 31, Printed or typed name:

License Number:

Signature: Date

I HEREBY CERTIFY THAT THIS ENGINEERING DOCUMENT DESCRIBED

BELOW WAS PREPARED BY ME OR UNDER MY DIRECT PERSONAL

SUPERVISION AND THAT I AM A DULY LICENSED PROFESSIONAL ENGINEER

UNDER THE LAWS OF THE STATE OF IOWA.

ALL 'C' SHEETS

DANIEL JENSEN

25063

CIVIL ENGINEER

NRCS NEM PART 505 CERTIFICATION

THE SIGNING PROFESSIONALS HEREBY

CERTIFY THAT, TO THE BEST OF THEIR

PROFESSIONAL KNOWLEDGE,

JUDGEMENT, AND BELIEF, THESE PLANS

MEET APPLICABLE NRCS STANDARDS.

I O

W A D E P A R T M E NT O F

AGR

I C U L T UR E & L A N D S T EWA R D

SH

IP

PROJECT

LOCATION

CALHOUN COUNTY

NORTH CONSTRUCTION

ENTRANCE

LANDOWNERS

JOEL WUEBKER

2588 QUINTON AVE

ROCKWELL CITY, IA 50579

PH: (712) 297-8609

LOHRVILLE

ROCKWELL CITY

POMEROY

MANSON

FARNHAMVILLE

LAKE CITY

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

PR

ES

TO

N

A

VE

LAKE CREEK

PAGES, SHEETS OR DIVISIONS COVERED BY THIS SEAL:

My License Renewal Date is: DECEMBER 31, Printed or typed name:

License Number:

Signature: Date

I HEREBY CERTIFY THAT THIS ENGINEERING DOCUMENT DESCRIBED

BELOW WAS PREPARED BY ME OR UNDER MY DIRECT PERSONAL

SUPERVISION AND THAT I AM A DULY LICENSED PROFESSIONAL ENGINEER

UNDER THE LAWS OF THE STATE OF IOWA.

ALL 'E' SHEETS

KEVIN J. BRUXVOORT

19927

ELECTRICAL ENGINEER

NORTH WETLAND

PROJECT EASEMENT

LANDOWNER: JOEL WUEBKER

CALHOUN COUNTY CONSERVATION

CURTIS VANDERHEIDEN

1228 HIGH ST

ROCKWELL CITY, IA, 50579

OFFICE PH: (712) 297-7131

CONSERVATION@CALHOHNCOUNTY.IOWA.GOV

SOUTH WETLAND

PROJECT EASEMENT

LANDOWNER: CALHOUN

COUNTY CONSERVATION

Sheet List Table Sheet Number Sheet Title

C000 COVER SHEET

C001 PROJECT QUANTITIES

C002 PROJECT NOTES

CD01 EXISTING CONDITIONS AND REMOVALS

C101 NORTH WETLAND GRADING PLAN

C102 NORTH WETLAND CUT-FILL PLAN

C103 NORTH WETLAND DRAWDOWN PLAN AND PROFILE

C104 NORTH WETLAND PUMP STATION 1 PLAN AND PROFILE

C105 NORTH WETLAND PUMP STATION 2 PLAN AND PROFILE

C106 NORTH SEEDING PLAN

C201 SOUTH WETLAND GRADING PLAN

C202 SOUTH WETLAND CUT-FILL PLAN

C203 SOUTH EMBANKMENT PLAN AND PROFILE

C204 SOUTH WETLAND DRAWDOWN PLAN AND PROFILE

C205 SOUTH WETLAND PUMP STATION PLAN AND PROFILE

C206 SOUTH SEEDING PLAN

C301 CONSTRUCTION DETAILS

C302 CONSTRUCTION DETAILS

C303 CONSTRUCTION DETAILS

C304 NORTH WETLAND DUPLEX PUMP DETAILS

C305 SOUTH WETLAND SIMPLEX PUMP DETAILS

E101 NORTH WETLAND PUMP STATION

E102 SOUTH WETLAND PUMP STATION

NORTH WETLAND

PROJECT EASEMENT

LANDOWNER: CALHOUN COUNTY

CONSERVATION

THE ENGINEERING JOB CLASS IS IV

SOUTH CONSTRUCTION

ENTRANCE

04-03-2026

04-03-2026

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d: C001

PR

O

JE

CT

Q

UA

NT

IT

IE

S

G

HK

DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

C

AL

B

PU

M

PE

D

W

ET

LA

N

D S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

Q

UA

NT

IT

IE

S.

dw g 3/

/2

:3

4:

A M

ESTIMATED QUANTITIES:

GENERAL NOTES:

1. THE LOCATIONS OF UTILITY MAINS, STRUCTURES AND SERVICE

CONNECTIONS PLOTTED ON THIS DRAWING ARE APPROXIMATE ONLY AND

WERE OBTAINED FROM RECORDS MADE AVAILABLE TO SHIVE-HATTERY,

INC. THERE MAY BE OTHER EXISTING UTILITY MAINS, STRUCTURES AND

SERVICE CONNECTIONS NOT KNOWN TO SHIVE-HATTERY, INC. AND NOT

SHOWN ON THIS DRAWING. THE VERIFICATION OF EXISTENCE OF, AND THE

DETERMINATION OF THE EXACT LOCATION OF, UTILITY MAINS,

STRUCTURES AND SERVICE CONNECTIONS SHALL BE THE RESPONSIBILITY

OF THE CONSTRUCTION CONTRACTOR(S).

2. IOWA CODE 480, UNDERGROUND FACILITIES INFORMATION, REQUIRES

VERBAL NOTICE TO IOWA ONE-CALL 1-800-292-8989, NOT LESS THAN 48

HOURS BEFORE EXCAVATING, EXCLUDING WEEKENDS AND HOLIDAYS.

3. THE MEANS OF THE WORK AND THE SAFETY OF THE CONTRACTOR'S

EMPLOYEES ARE SOLELY THE RESPONSIBILITY OF THE CONTRACTOR.

4. NO WORK SHALL BE PERFORMED BEYOND THE PROJECT LIMITS WITHOUT

PRIOR AUTHORIZATION FROM THE OWNER'S REPRESENTATIVE.

5. REPLACE ANY PROPERTY MONUMENTS REMOVED OR DESTROYED BY

CONSTRUCTION. MONUMENTS SHALL BE SET BY A LAND SURVEYOR

REGISTERED TO PRACTICE IN THE STATE OF IOWA.

6. ALL DEBRIS AND TRASH ENCOUNTERED DURING CONSTRUCTION WITHIN

THE PROJECT LIMITS, OR DIRECTED BY THE ENGINEER, SHALL BE

PROPERLY DISPOSED OF.

7. CONTRACTOR IS RESPONSIBLE FOR ALL CONSTRUCTION DE-WATERING

THAT IS REQUIRED AT NO ADDITIONAL COST TO THE DIVISION.

8. REPAIR OR REPLACE DAMAGE TO EXISTING FACILITIES (TILE, UTILITIES,

FENCES, ETC.) DESIGNATED TO REMAIN, AT NO ADDITIONAL EXPENSE TO

THE OWNER. ALL AREAS DISTURBED BY CONSTRUCTION, INCLUDING

STAGING AREAS AND HAUL ROUTES, ARE TO BE REWORKED TO THEIR

EXISTING CONDITIONS AND SEEDED AT NO ADDITIONAL COST TO THE

DIVISION IF OUTSIDE OF PROJECT LIMITS AND NOT APPROVED BY

ENGINEER.

9. WORK WHICH DOES NOT CONFORM TO THE REQUIREMENTS OF THE

CONTRACT WILL BE CONSIDERED UNACCEPTABLE. UNACCEPTABLE WORK,

WHETHER THE RESULT OF POOR WORKMANSHIP, USE OF DEFECTIVE

MATERIALS, DAMAGE THROUGH CARELESSNESS OR ANY OTHER CAUSE,

FOUND TO EXIST PRIOR TO THE FINAL ACCEPTANCE OF THE WORK, SHALL

BE REMOVED AND REPLACED IN AN ACCEPTABLE MANNER, AS REQUIRED

BY THE OWNER AT THE CONTRACTOR'S EXPENSE.

10. WORK DONE CONTRARY TO THE INSTRUCTIONS OF THE OWNERS

REPRESENTATIVE, WORK DONE BEYOND THE LINES SHOWN ON THE PLANS

OR ANY EXTRA WORK DONE WITHOUT AUTHORITY WILL NOT BE PAID FOR.

11. A SHRINKAGE FACTOR OF 20% WAS ESTIMATED FOR THIS PROJECT. THE

CONTRACTOR SHALL MAKE CHANGES IN EARTHWORK AS NEEDED TO

ADJUST FOR INACCURACIES INHERENT WITH ESTIMATING THE SHRINKAGE

FACTOR. THESE CHANGES SHALL ONLY BE MADE AFTER CONSULTATION

AND APPROVAL BY THE ENGINEER AND DIVISION.

12. CONTOURS AND SPOT ELEVATIONS SHOWN ARE TO FINISHED GRADE.

13. THE CONTRACTOR SHALL KEEP ALL ROADS OPEN TO THROUGH TRAFFIC

AT ALL TIMES.

14. ALL WORK WITHIN THE PUBLIC RIGHT OF WAY SHALL BE COORDINATED

WITH THE GOVERNING AUTHORITY AND SHALL BE DONE IN ACCORDANCE

WITH THEIR STANDARDS.

15. SUBMIT MANUFACTURER'S CERTIFICATION AND MATERIAL DATA FOR ALL

MATERIALS DELIVERED TO THE PROJECT SITE AS REQUESTED BY THE

OWNERS REPRESENTATIVE.

16. CONSTRUCTION SURVEY STAKING WILL BE PAID FOR BY THE OWNER AND

PROVIDED BY THE ENGINEER. CONTROL POINTS WILL BE SET FOR USE

WITH GPS CONTROLLED GRADING, IF DESIRED. CONTRACTOR SHALL

PRESERVE STAKES TO THE EXTENT FEASIBLE. ANY RE-STAKING COSTS

WILL BE THE RESPONSIBILITY OF THE CONTRACTOR.

17. NEITHER SHIVE-HATTERY NOR IDALS GUARANTEE THIS PRACTICE WILL

HOLD A PERMANENT POOL OF WATER.

CULTURAL RESOURCES NOTE:

1. IF A CULTURAL RESOURCE IS IDENTIFIED

DURING CONSTRUCTION, STOP IMMEDIATELY

AND NOTIFY LOCAL NATURAL RESOURCES

CONSERVATION SERVICE OFFICE.

NORTH WETLAND DESIGN DATA:

PROJECT ID CAL883229B (NORTH) -----

LANDOWNER(S) JOEL WUEBKER & CALHOHN COUNTY CONSERVATION -----

PRELIMINARY OR FINAL DESIGN FINAL -----

DRAINAGE AREA 34,496 (DRAINAGE DITCH) 32.6 (OVERLAND FLOW) ACRES

WETLAND POOL AREA 7.35 ACRES

DEEP WATER AREA (>3 FT DEEP) 0.05 ACRES

NORMAL POOL ELEVATION 1186.00 FEET

AVERAGE POOL DEPTH 0.85 FEET

MAXIMUM POOL DEPTH 2.2 FEET

POOL STORAGE 6.17 ACRE-FEET

BERM ELEVATION N/A FEET

BERM STORAGE N/A ACRE-FEET

LENGTH OF BERM N/A FEET

AUXILIARY SPILLWAY ELEVATION N/A FEET

AUXILIARY SPILLWAY WIDTH N/A FEET

WEIR WIDTH N/A FEET

DROP HEIGHT N/A FEET

TIME OF CONCENTRATION 0.179 HOURS

WEIGHTED RUNOFF CURVE NUMBER 85 -----

5-YEAR STORM DESIGN FLOW 112.04 CFS

5-YEAR FLOOD SURF. ELEVATION 1186.81 FEET

25-YEAR STORM DESIGN FLOW 191.27 CFS

25-YEAR FLOOD SURF. ELEVATION 1186.97 FEET

100-YEAR STORM DESIGN FLOW 280.62 CFS

100-YEAR FLOOD SURF. ELEVATION 1187.09 FEET

TOTAL EASEMENT AREA 24.04 ACRES

PUMP INFORMATION

TOTAL DYNAMIC HEAD 14.5 FEET

DESIGN MAXIMUM DISCHARGE 3.2 CFS (Two Pumps) CFS

DESIGN DAILY FLOW VOLUME 600,000 - 700,00 GAL/DAY

# ITEM DESCRIPTION NORTH SITE

QUANTITY

SOUTH SITE

QUANTITY TOTAL QUANTITY UNITS

1 SITE STRIPPING & PREPARATION 1 1 1 LS

2 CROP DAMAGE 0 0 0 AC

3 STRUCTURE & CHANNEL SEEDING 1.5 0.4 1.9 AC

4 BUFFER SEEDING 15.1 0.6 15.7 AC

5 MOBILIZATION AND DEMOBILIZATION 1 1 1 LS

6 DRAIN TILE INVESTIGATION AND REMOVAL 2270 65 2335 LF

7 EXCAVATION (GENERAL (P)) 6176 1056 7232 CY

8 EARTHFILL (GENERAL (P)) 6176 585 6761 CY

9 EARTHFILL (GENERAL DAM (P)) 0 579 579 CY

10 EARTHFILL (DAM CORE (P)) 0 191 191 CY

11 EARTHFILL (18" CLAY LINER, WETLAND BOTTOM, TWO 9" LIFTS (P)): 9841 2046 11887 CY

12 EARTHFILL (SCARIFY AND RECOMPACT 9" LAYER OF WETLAND BOTTOM (P)): 4494 4607 9101 CY

13 TOPSOIL PLACEMENT, 6 INCH 4535 787 5322 CY

14 TOPSOIL PLACEMENT, 12 INCH 0 433 433 CY

15 8" PVC PIPE, SCHEDULE 80, FORECMAIN 92 27 119 LF

16 4" PERFORATED POLYETHYLENE PIPE WITH POROUS BACKFILL, SINGLE WALL 279 0 279 LF

17 6" NON-PERFORTATED POLYETHYLENE PIPE, SINGLE WALL 187 0 187 LF

18 24" SDR 26 PVC 367 210 577 LF

19 24" RISER INLET STRUCTURE 1 1 2 EA

20 48" CMP WATER CONTROL STRUCTURE 1 1 2 EA

21 18" ALUMINIZED CMP WETLAND DRAWDOWN PIPE, 14GA 177 114 291 LF

22 8" CMP TILE OUTLETS (20 LF EACH) 2 0 2 EA

23 RIP RAP, CLASS E 150 150 300 TON

24 1" CLEAN STONE 150 70 220 TON

25 2" CLEAN STONE 30 30 60 TON

26 POLLUTION CONTROL, SILT FENCE 472 304 776 LF

27 POLLUTION CONTROL, TYPE 2B RECP 560 395 955 SY

28 SOLAR, BATTERY, ELECTRICAL AND CONTROLS (COMPLETE SYSTEM) 2 1 3 LS

29 PUMP STATION (PUMP, CONTROLS, ELECTRICAL, STRUCTURE, APPURENTANCES (COMPLETE SYSTEM)) 2 1 3 LS

SOUTH WETLAND DESIGN DATA:

PROJECT ID CAL883229B (SOUTH) -----

LANDOWNER(S) CALHOUN COUNTY CONSERVATION -----

PRELIMINARY OR FINAL DESIGN FINAL -----

DRAINAGE AREA 10,560 (DRAINAGE DTICH) 9.8 (OVERLAND FLOW) ACRES

WETLAND POOL AREA 4.65 ACRES

DEEP WATER AREA (>3 FT DEEP) 0.09 ACRES

NORMAL POOL ELEVATION 1186.00 FEET

AVERAGE POOL DEPTH 0.63 FEET

MAXIMUM POOL DEPTH 3.0 FEET

POOL STORAGE 2.71 ACRE-FEET

BERM ELEVATION 1187 FEET

BERM STORAGE 8.78 ACRE-FEET

LENGTH OF BERM 305 FEET

AUXILIARY SPILLWAY ELEVATION N/A FEET

AUXILIARY SPILLWAY WIDTH N/A FEET

WEIR WIDTH N/A FEET

DROP HEIGHT N/A FEET

TIME OF CONCENTRATION 0.083 HOURS

WEIGHTED RUNOFF CURVE NUMBER 85 -----

2-YEAR STORM DESIGN FLOW 31.32 CFS

2-YEAR FLOOD SURF. ELEVATION 1186.33 FEET

25-YEAR STORM DESIGN FLOW 72.07 CFS

25-YEAR FLOOD SURF. ELEVATION 1186.56 FEET

100-YEAR STORM DESIGN FLOW 105.13 CFS

100-YEAR FLOOD SURF. ELEVATION 1186.71 FEET

TOTAL EASEMENT AREA 8.83 ACRES

PUMP INFORMATION

TOTAL DYNAMIC HEAD 12.8 FEET

DESIGN MAXIMUM DISCHARGE 1.7 CFS (One Pump) CFS

DESIGN DAILY FLOW VOLUME 300,000 - 360,000 GAL/DAY

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

T M

EN T O F

A G R I C U L T UR E

L A

ND

S

TEWARDSHIP

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d: C002

PR

O

JE

CT

N O

TE

S

G

HK

DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

C

AL

B

PU

M

PE

D

W

ET

LA

N

D S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

Q

UA

NT

IT

IE

S.

dw g 3/

/2

:3

4:

A M

GENERAL NOTES:

1. THE LOCATIONS OF UTILITY MAINS, STRUCTURES AND SERVICE

CONNECTIONS PLOTTED ON THIS DRAWING ARE APPROXIMATE ONLY AND

WERE OBTAINED FROM RECORDS MADE AVAILABLE TO SHIVE-HATTERY,

INC. THERE MAY BE OTHER EXISTING UTILITY MAINS, STRUCTURES AND

SERVICE CONNECTIONS NOT KNOWN TO SHIVE-HATTERY, INC. AND NOT

SHOWN ON THIS DRAWING. THE VERIFICATION OF EXISTENCE OF, AND THE

DETERMINATION OF THE EXACT LOCATION OF, UTILITY MAINS,

STRUCTURES AND SERVICE CONNECTIONS SHALL BE THE RESPONSIBILITY

OF THE CONSTRUCTION CONTRACTOR(S).

2. IOWA CODE 480, UNDERGROUND FACILITIES INFORMATION, REQUIRES

VERBAL NOTICE TO IOWA ONE-CALL 1-800-292-8989, NOT LESS THAN 48

HOURS BEFORE EXCAVATING, EXCLUDING WEEKENDS AND HOLIDAYS.

3. THE MEANS OF THE WORK AND THE SAFETY OF THE CONTRACTOR'S

EMPLOYEES ARE SOLELY THE RESPONSIBILITY OF THE CONTRACTOR.

4. NO WORK SHALL BE PERFORMED BEYOND THE PROJECT LIMITS WITHOUT

PRIOR AUTHORIZATION FROM THE OWNER'S REPRESENTATIVE.

5. REPLACE ANY PROPERTY MONUMENTS REMOVED OR DESTROYED BY

CONSTRUCTION. MONUMENTS SHALL BE SET BY A LAND SURVEYOR

REGISTERED TO PRACTICE IN THE STATE OF IOWA.

6. ALL DEBRIS AND TRASH ENCOUNTERED DURING CONSTRUCTION WITHIN

THE PROJECT LIMITS, OR DIRECTED BY THE ENGINEER, SHALL BE

PROPERLY DISPOSED OF.

7. CONTRACTOR IS RESPONSIBLE FOR ALL CONSTRUCTION DE-WATERING

THAT IS REQUIRED AT NO ADDITIONAL COST TO THE DIVISION.

8. REPAIR OR REPLACE DAMAGE TO EXISTING FACILITIES (TILE, UTILITIES,

FENCES, ETC.) DESIGNATED TO REMAIN, AT NO ADDITIONAL EXPENSE TO

THE OWNER. ALL AREAS DISTURBED BY CONSTRUCTION, INCLUDING

STAGING AREAS AND HAUL ROUTES, ARE TO BE REWORKED TO THEIR

EXISTING CONDITIONS AND SEEDED AT NO ADDITIONAL COST TO THE

DIVISION IF OUTSIDE OF PROJECT LIMITS AND NOT APPROVED BY

ENGINEER.

9. WORK WHICH DOES NOT CONFORM TO THE REQUIREMENTS OF THE

CONTRACT WILL BE CONSIDERED UNACCEPTABLE. UNACCEPTABLE WORK,

WHETHER THE RESULT OF POOR WORKMANSHIP, USE OF DEFECTIVE

MATERIALS, DAMAGE THROUGH CARELESSNESS OR ANY OTHER CAUSE,

FOUND TO EXIST PRIOR TO THE FINAL ACCEPTANCE OF THE WORK, SHALL

BE REMOVED AND REPLACED IN AN ACCEPTABLE MANNER, AS REQUIRED

BY THE OWNER AT THE CONTRACTOR'S EXPENSE.

10. WORK DONE CONTRARY TO THE INSTRUCTIONS OF THE OWNERS

REPRESENTATIVE, WORK DONE BEYOND THE LINES SHOWN ON THE PLANS

OR ANY EXTRA WORK DONE WITHOUT AUTHORITY WILL NOT BE PAID FOR.

11. A SHRINKAGE FACTOR OF 20% WAS ESTIMATED FOR THIS PROJECT. THE

CONTRACTOR SHALL MAKE CHANGES IN EARTHWORK AS NEEDED TO

ADJUST FOR INACCURACIES INHERENT WITH ESTIMATING THE SHRINKAGE

FACTOR. THESE CHANGES SHALL ONLY BE MADE AFTER CONSULTATION

AND APPROVAL BY THE ENGINEER AND DIVISION.

12. CONTOURS AND SPOT ELEVATIONS SHOWN ARE TO FINISHED GRADE.

13. THE CONTRACTOR SHALL KEEP ALL ROADS OPEN TO THROUGH TRAFFIC

AT ALL TIMES.

14. ALL WORK WITHIN THE PUBLIC RIGHT OF WAY SHALL BE COORDINATED

WITH THE GOVERNING AUTHORITY AND SHALL BE DONE IN ACCORDANCE

WITH THEIR STANDARDS.

15. SUBMIT MANUFACTURER'S CERTIFICATION AND MATERIAL DATA FOR ALL

MATERIALS DELIVERED TO THE PROJECT SITE AS REQUESTED BY THE

OWNERS REPRESENTATIVE.

16. CONSTRUCTION SURVEY STAKING WILL BE PAID FOR BY THE OWNER AND

PROVIDED BY THE ENGINEER. CONTROL POINTS WILL BE SET FOR USE

WITH GPS CONTROLLED GRADING, IF DESIRED. CONTRACTOR SHALL

PRESERVE STAKES TO THE EXTENT FEASIBLE. ANY RE-STAKING COSTS

WILL BE THE RESPONSIBILITY OF THE CONTRACTOR.

17. NEITHER SHIVE-HATTERY NOR IDALS GUARANTEE THIS PRACTICE WILL

HOLD A PERMANENT POOL OF WATER.

CULTURAL RESOURCES NOTE:

1. IF A CULTURAL RESOURCE IS IDENTIFIED

DURING CONSTRUCTION, STOP IMMEDIATELY

AND NOTIFY LOCAL NATURAL RESOURCES

CONSERVATION SERVICE OFFICE.

ESTIMATE REFERENCE NOTES:

ITEM # SPEC # DESCRIPTION

1 IA CS-001 SITE STRIPPING & PREPARATION : THIS ITEM WILL CONSIST OF WORK TO REMOVE AND DISPOSE OF EXISTING MATERIAL OR WASTE ONE SITE AND TO TO REMOVE VEGETATION ON AREAS TO BE EXCAVATED OR FILLED. TOTAL DEPTH OF VEGETATIVE STRIPPING AND TOPSOIL STRIPPING SHALL EQUAL A COMBINED DEPTH OF 12". THE TOPSOIL REPLACEMENT QUANTITY SHALL BE PAID SEPARATELY. THIS ITEM WILL ALSO INCLUDE ANY TREE AND BRUSH REMOVAL ALONG WITH ANY FENCES.

2 IA CS-001 CROP DAMAGE: THIS ITEM CONSISTS OF CROP DAMAGE THAT RESULTS FROM CONSTRUCTION ACTIVITIES. IT IS RECOMMENDED CONTRACTOR REMOVE CORN RESIDUE RATHER THAN KNOCK IT DOWN. PAYMENT FOR CROP DAMAGE WILL BE MADE TO THE NEAREST 0.1 ACRE AS MEASURED BY THE ENGINEER OR THEIR REPRESENTATIVE. THE UNIT RATE FOR CROP DAMAGE WILL BE DETERMINED BY THE DIVISION NEAR THE COMPLETION OF CONSTRUCTION AND ADDED TO THE CONTRACT WITH A CHANGE ORDER. PAYMENT WILL BE MADE TO CONTRACTOR WHO WILL PAY LANDOWNER.

3 IA CS-006 STRUCTURE & CHANNEL SEEDING: THIS ITEM INCLUDES SEEDING AND RELATED ACTIVITIES FOR STUCTURE SEEDING AREAS AS SHOWN ON THE PLANS. INCLUDES SEEDBED PREP, SEEDING, STRAW MULCH, AND FERTILIZER.

4 IA CS-006 BUFFER SEEDING: THIS ITEM INCLUDES SEEDING AND RETAED ACTVITIES FOR BUFFER SEEDING AREAS AS SHOWN ON THE PLANS. NO MULCH OR FERTILIZER SHALL BE APPLIED.

5 CS-008 MOBILIZATION AND DEMOBILIZATION: THIS ITEM SHALL BE CONSIDERED FULL COMPENSATION TO MOBILIZE AND DEMOBILIZE THE CONTRACTOR'S FORCES AND EQUIPMENT FOR THE PROJECT. ALL OTHER WORK NECESSARY TO COMPLETE THE PROJECT AS REPRESENTED HEREIN BUT NOT INCLUDED IN THE ITEMS LISTED BELOW SHALL BE INCIDENTAL TO THIS ITEM. THIS ITEM SHALL INCLUDE ALL LABOR, MATERIALS, EQUIPMENT AND IOWA ONE CALL NOTIFICATIONS TO INSTALL SIGN PROVIDED BY IOWA DEPARTMENT OF AGRICULTURE AND LAND STEWARDSHIP IN AND OWNER APPROVED LOCATION.

6 IA CS-009 DRAIN TILE INVESTIGATION AND REMOVAL: THIS ITEM INCLUDES THE EXPLORATORY EXCAVATIONS REQUIRED TO LOCATE AND REMOVE TILES SHOWN ON THE PLANS. THIS IS FULL COMPENSATION FOR EXCAVATION, BACKFILLING, AND REMOVAL OF THE TILE TRENCHES. CONTRACTOR SHALL PROVIDE DOCUMENTATION

FOR ALL TILE LOCATED AND REMOVED.

7 IA CS-021

EXCAVATION (GENERAL (P)): THIS ITEM INCLUDES THE EXCAVATION OF MATERIAL REQUIRED TO FORM THE WETLAND POOL, EXCAVATION OF THE CORE TRENCH BELOW THE EXISTING GROUND LEVEL, AS DETAILED, AND EXCAVATION FOR BORROW MATERIAL FOR PUMP EQUIPMENT PADS. COHESIVE MATERIAL FOUND DURING GENERAL GRADING MUST BE RESERVED FOR WETLAND CLAY LINER CONSTRUCTION, CORE TRENCH FILL, AND THE DAM CORE. SAND AND GRAVEL FOUND ON SITE SHALL NOT BE USED FOR THIS EARTHFILL WITHIN THE WETLAND AND MUST BE WASTED IN THE AREAS SHOWN ON THE PLANS OR MAY BE USED FOR

THE EQUIPMENT PADS IF REQUIRED.

8 IA CS-023

EARTHFILL (GENERAL (P)): THIS ITEM INCLUDES THE SOIL MATERIAL REQUIRED TO CONSTRUCT THE SUBMERGED BERMS, ADDITIONAL FILL TO BE PLACED OVER TILE COVER BERMS, FILL FOR PUMP EQUIPMENT PADS, AND WASTE SOIL. COHESIVE MATERIAL FOUND DURING GENERAL GRADING MUST BE RESERVE FOR CLAY LINER CONSTRUCTION, CORE TRENCH FILL, AND THE DAM CORE. SAND AND GRAVEL FOUND ON SITE SHALL NOT BE USED FOR THIS EARTHFILL WITHIN THE WETLAND AND MUST BE WASTED IN THE AREAS SHOWN ON THE PLANS. THE REQUIRED FILL INCLUDES A 20% SHRINKAGE FACTOR. COMPACTION SHALL BE NRCS METHOD 1. MEASUREMENT AND PAYMENT FOR PLACEMENT AND COMPACTION OF ALL FILL MATERIAL IS INCLUDED IN THIS ITEM AND WILL BE PAID BASED ON PLAN QUANTITY.

9 IA CS-023

EARTHFILL (GENERAL DAM (P)): THIS ITEM INCLUDES THE EARTHFILL PLACEMENT AND COMPACTION NECESSARY TO CONSTRUCTION THE PORTION OF THE EMBANKMENT THAT IS NOT THE EMBANKMENT CORE. COHESIVE MATERIAL FOUND DURING GENERAL GRADING AND COMPACTED LINER CAN BE USED FOR THIS AREA. SAND AND GRAVEL FOUND ON SITE SHALL NOT BE USED FOR FILL IN THESE AREAS. THE REQUIRED FILL INCLUDES A 20% SHRINKAGE FACTOR. COMPACTION SHALL BE METHOD 1 OR METHOD 2. MEASUREMENT AND PAYMENT FOR PLACEMENT AND COMPACTION OF ALL FILL MATERIAL IS INCLUDED IN THIS ITEM

AND WILL BE PAID BASED ON PLAN QUANTITY.

10 IA CS-023 EARTHFILL (DAM CORE (P)): THIS ITEM INCLUDES THE EARTHFILL PLACEMENT AND COMPACTION NECESSARY TO CONSTRUCT THE EMBANKMENT CORE WITHIN THE EMBANKMENT. SELECT COHESIVE MATERIAL TAKEN FROM DESIGNATED BORROW AREA SHOULD BE USED FOR THIS AREA. SAND AND GRAVEL SHALL NOT BE USED FOR THIS AREA. THE REQUIRED FILL INCLUDES A 20% SHRINKAGE FACTOR. COMPACTION SHALL BE NRCS METHOD 2. MEASUREMENT AND PAYMENT FOR PLACEMENT AND COMPACTION OF ALL FILL MATERIAL IS INCLUDED IN THIS ITEM AND WILL BE PAID BASED ON PLAN QUANTITY.

11 IA CS-023

EARTHFILL (18" RE-COMPACTED CLAY LINER, WETLAND BOTTOM (P)): THIS ITEM INCLUDES CONSTRUCTION OF A COMPACTED CLAY LINER WITHIN THE WETLAND POOL IN AREAS WHERE EXCAVATION OCCURS. SEQUENCING SHALL INCLUDE OVEREXCAVATION AND STOCKPILE OF 9" OF SOIL, SCARIFICATION TO A DEPTH OF 9 INCHES, AND RECOMPACTION (LIFT 1). AN ADDITIONAL 9 INCH CLAY LIFT WILL BE REPLACED ABOVE LIFT ONE AND COMPACTED, FORMING A TOTAL OF 18 INCHES OF CLAY LINER PRIOR TO RESPREADIN TOPSOIL. PROPOSED CONTOURS SHOWN ARE TO FINSHED SURFACE, POST TOPSOIL RESPREAD. MOISTURE CONDITIONING MAY BE REQUIRED AND COMPACTION SHALL BE NRCS METHOD 2. RESERVE SELECT CLAY SOILS FOR CONSTRUCTION OF THE CLAY LINER AND NOTIFY THE ENGINEER IS SANDY SOILS ARE LOCATED. CONTRACTOR SHALL REMOVE ROCKS LARGER THAN 6 INCHES. NOTIFY ENGINEER IMMEDIATELY IF SANDY

SOILS ARE ENCOUNTERED. ITEM WILL BE PAID BASED ON PLAN QUANTITY.

12 IA CS-023 EARTHFILL (SCARIFY AND RECOMPACT 9" LAYER OF WETLAND BOTTOM (P)): THIS ITEM INCLUDES SCARIFICATION AND LOOSENING OF A 9 INCH SURFACE LAYER OF SOIL IN UNDISTURBED AREAS OF THE WETLAND POOL BOTTOM , MOISTURE CONDITIONING, AND COMPACTION OF THE WETLAND BOTTOM TO FORM A SEAL.

CONTRACTOR SHALL REMOVE ROCKS LARGER THAN 6 INCHES. NOTIFY ENGINEER IMMEDIATELY IF SANDY SOILS ARE ENCOUNTERED. ITEM WILL BE PAID BASED ON PLAN QUANTITY.

13 IA CS-026 TOPSOIL PLACEMENT. 6 INCH: THIS ITEM INCLUDES THE RESPREAD OF TOPSOIL STOCKPILED DURING SITE STIRPPING. RESPREAD 6" TOPSOIL IN ALL DISTURBED AREAS INCLDUNG EXCAVATION, BORROW, AND EARTHFILL FOOTPRINTS. ITEM WILL BE PAID BASED ON PLAN QUANTITY.

14 IA CS-026 TOPSOIL PLACEMENT, 12 INCH: THIS ITEM INCLUDES THE RESPREAD OF TOPSOIL STOCKPILED DURING SITE STIRPPING. RESPREAD 12" TOPSOIL ON THE EMBANKMENT FOOTPRINT ON THE SOUTH WETLAND SITE. ITEM WILL BE PAID BASED ON PLAN QUANTITY.

15 IA CS-045 8" SCHEDULE 80 PVC PIPE: THIS ITEM INCLUDES THE MATERIAL, EXCAVATION, PLACEMENT, JOINTING, FITTINGS, AND BACKFILL OF THE BURIED 8" SCHEDULE 80 PVC PIPE AS SHOWN ON THE PLANS. PIPING WITHIN THE PUMP STATION IS NOT INCLUDED WITH THIS BID ITEM AND SHALL BE INCIDENTAL TO BID ITEM 30.

16 IA CS-046 4" PERFORATED POLYETHYLENE PIPE WITH POROUS BACKFILL, SINGLE WALL : THIS ITEM INCLUDES THE MATERIAL, EXCAVATION, PLACEMENT, JOINTING, AND BACKFILL OF THE 4" PERFORATED HDPE DRAIN TILE WITH POROUS BACKFILL.

17 IA CS-046 6" PERFORATED POLYETHYLENE PIPE, NON PERFORATED, SINGLE WALL: THIS ITEM INCLUDES THE MATERIAL, EXCAVATION, PLACEMENT, JOINTING, AND BACKFILL OF THE 6" NON-PERFORATED HDPE DRAIN TILE.

18 IA CS-046 24" SDR 26 PVC PIPE: THIS ITEM INCLUDES THE MATERIAL, EXCAVATION, PLACEMENT, JOINTING, AND BACKFILL OF THE 24" SDR 26 PVC PIPE WITH GASKETED BELL AND SPIGOT JOINTS FROM THE DRAINAGE DITCH TO THE PUMP STATION STUCTURES. PIPE SHALL BE BEDDED IN CLASS 1 AGGREGATE. CONCRETE COLLR

CONNECTIONS AT THE PUMP STUCTURE ARE REQUIRED.

19 IA CS-051 24" RISER INLET STRUCTURE: THIS ITEM INCLUDES COSTS FOR THE MATERIAL AND INSTALLATION OF 24" CMP RISER INLET STRUCTURE PIPE, TRASH RACK, AND BASE A DETAILED.

20 IA CS-051 48" CMP WATER CONTROL STRUCTURE : THIS ITEM INCLUDES ALL LABOR, EQUIPMENT, AND MATERIALS FOR THE PLACEMENT OF THE 48" CMP WATER CONTROL STRUCTURE, FOOTING, STEEL, FABRICATION, PIPE CONNECTIONS, STOP LOGS, STOP LOG STORAGE STRUCTURE, AND LOCKABLE LID.

21 IA CS-051 18" CMP DRAWDOWN WETLAND OUTLET PIPE: THIS ITEM INCLUDES ALL LABOR, EQUIPMENT, MATERIALS REQUIRED FOR THE EXCAVATION, AND THE PLACEMENT OF THE CORRUGATE METAL PIPE, INCLUDING ANTI-SEEPAGAE COLLARS.

22 IA CS-051 8" CMP TILE OUTLETS (20 LF EACH): THIS ITEM INCLUDES THE COSTS FOR MATERIAL, EXCAVATION, PLACEMENT, JOINTING, BEDDING, RODENT GUARDS, AND BACKFILLING OF THE 20 LF 8" CMP END SECTION FOR THE PROPOSED FIELD TILE OUTLET TO THE WETLAND. 8" CMP OUTLET SECTIONS ARE FOR 6 INCH TILES.

23 IA CS-061 RIP RAP: THIS ITEM INCLUDES THE EXCAVATION AND PLACEMENT OF CLASS 'E' REVETMENT OVER GEOTEXTILE FABRIC AT THE LOCATIONS SHOWN ON THE PLANS. GEOTEXTILE FABRIC IS INCIDENTAL TO THIS ITEM. QUANTITY DETERMINATION IS BASED ON A UNIT WEIGHT OF 105 POUNDS PER CUBIC FOOT. PROVIDE

WEIGHT TICKETS TO OWNER'S REPRESENTATIVE.

24 IA CS-061 1" CLEAN STONE: THIS ITEMS INCLUDES PROCUREMENT, PLACEMENT AND SPREADING OF 1 INCH CLEAN STONE OVER GEOTEXTILE FABRIC AT THE PUMP PADS. QUANTITY DETERMINATION IS BASED ON A UNIT WEIGHT OF 130 POUNDS PER CUBIC FOOT.

25 IA CS-061 2" CLEAN STONE: THIS ITEMS INCLUDES PROCUREMENT, PLACEMENT AND SPREADING OF 2 INCH CLEAN STONE AT THE STABILIZED CONSTRUCTION ENTRANCE.

26 CS-008 POLLUTION CONTROL, SILT FENCE: THIS ITEM INCLUDES PROCUREMENT AND INSTALLATION OF SILT FENCE AS SHOWN ON THE PLANS AND AS DETAILED.

27 IA CS-005 POLLUTION CONTROL, TYPE 2B RECP: THIS ITEM INCLUDES PROCUREMENT AND INSTALLATION OF TYPE 2B RECP TURF REINFORCING MAT IN ACOORDANCE WITH SUDAS 9040. INSTALLATION SHALL BE PER THE MANUFACTURER’S RECOMMENDATIONS.

28 DIVISION

SOLAR, BATTERY, ELECTRICAL AND CONTROLS (COMPLETE SYSTEM); THIS ITEM INCLUDES PROCUREMENT, INSTALLATION, START UP AND WARRANTYY OF ALL COMPONENTS FOR THE PHOTOVOLTAIC AND BATTERY SYSTEM AS SHOWN IN THE PLANS AND AS DESCRIBED IN THE SPECIFICATIONS INCLUDING CONNECTION

TO THE PUMP SYSTEM AND CONTROLS.

29 DIVISION

33 & 26

PUMP STATION (PUMP, CONTROLS, ELECTRICAL, STRUCTURE, APPURENTANCES (COMPLETE SYSTEM)) : THIS ITEM INCLUDES PROCUREMENT, INSTALLATION, START UP AND WARRANTY ALL COMPONENTS FOR THE PUMPING SYSTEMS AS SHOWN IN THE PLANS AND AS DESCRIBED IN THE SPECIFICATIONS INCLUDING THE CONCRETE STUCTURE, CONNECTIONS, CONTROLS, FLOATS, ELECTRICAL, VARIABLE FREQUENCY DRIVE, PUMPS, INTERIOR PIPING, WATER METER, AND REMOTE MONITORING SYSTEM. REFER TO DRAWINGS AND SPECIFICATIONS.

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

T M

EN T O F

A G R I C U L T UR E

L A

ND

S

TEWARDSHIP

C

ALH

O U

N C

O U

N

TY

C

ALH

O U

N C

O U

N

TY

D

&J LAN

D

TR

U

ST

C

ALH

O U

N C

O U

N

TY

W U

EBKER

, JO

EL & M

O

N

IC

A

D

&J LAN

D

TR

U

ST

D

&J LAN

D

TR

U

ST

11801180

PROJECT GRADING LIMITS AND TILE INSTALLATION LIMITS

STRIP AND STOCKPILE 12 INCHES OF TOPSOIL IN EMBANKMENT

FOOTPRINT AND ALONG PROPOSED DIVERSION TILE LENGTH

OUTSIDE THE PROPOSED EASEMENT. STRIP 6 INCHES OF

TOPSOIL IN ALL OTHER DISTURBED AREAS. RESPREAD TOPSOIL

PRIOR TO SEED BED PREPARATION AND SEEDING.

NO CONTRACTOR

TRAFFIC OUTSIDE OF

EASEMENT UNLESS

APPROVED BY OWNER

EXISTING STREAM

CENTERLINE

100-YEAR FEMA

FLOODPLAIN

LOCATE AND REMOVE

900' OF EXISTING TILE

LOCATE, CRUSH, AND BURY ALL TILE

WITHIN PROPOSED WETLAND POOL.

LOCATED AND REMOVE

TILE OUTLETS TO CREEK

LOCATE EXISTING FIELD TILE FOR

CONNECTIONS TO PROPOSED TILE TO

BE DAYLIGHTED TO THE POOL (TYP).

3 LOCATIONS ANTICIPATED.

PROTECT ALL TILE TO REMAIN IN PLACE.

CONTRACTOR RESPONSIBLE FOR REPAIR OF

ANY DAMAGE CAUSED BY CONSTRUCTION AT

NO ADDITIONAL COST TO THE DIVISION.

EXISTING 12" CMP

LOCATE AND REMOVE

1,020' OF EXISTING TILE

LOCATE AND REMOVE

218' OF EXISTING TILE

EASEMENT BOUNDARY

EASEMENT BOUNDARY (TYP)

REMOVE & DISPOSE

EXISTING 12" CMP OUTLET

REMOVE & DISPOSE

EXISTING 12" CMP OUTLET

APPROXIMATE PROPERTY

BOUNDARY (TYP.)

EMBANKMENT DAM

GRADING LIMITS

STRIP 12 INCHES

FEMA FLOODWAY

REMOVE AND DISPOSE

EXISTING 18" CMP OUTLET

CONSTRUCTION ACCESS ROUTE SHALL BE

WITHIN EASEMENT, COORDINATE WITH THE

OWNER. DISK COMPACTED AREAS AS

REQUIRED PRIOR TO SEED BED PREPARATION.

STABILIZED CONSTRUCTION

ENTRANCE, 30 TONS 2" CLEAN STONE

PRESTON AVE

LAKE CREEK

STABILIZED CONSTRUCTION

ENTRANCE, 30 TONS 2" CLEAN STONE

EXCAVATION LIMITS

STRIP 12 INCHES

N O

R

TH

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

TM

EN T O F

A G R I C U L T UR E

L A

ND

S

TEWARDSHIP

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d:

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d: CD01

EX

IS

TI

NG

CO

ND

IT

IO

NS

A

ND

RE

M O

VA

LS

G

HK

DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

C

AL

B

PU

M

PE

D

W

ET

LA

N

D S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C D0

- E

XI

ST

IN

G

C O

ND

IT

IO

NS

A

ND

R

EM

O

VA

LS

.d wg 3/

/2

:3

4:

A M

PROPERTY LINE (APPROX)

EXISTING CONTOUR - MAJOR

EXISTING CONTOUR - MINOR

LEGEND SURVEY NOTES:

1. LIMITED TOPOGRAPHIC SURVEY COMPLETED BY SHIVE-HATTERY ON

FEBRUARY 22, 2024.

2. SUPPLEMENTAL EXISTING SURFACE INFORMATION SHOWN WAS

BASED ON LIGHT DETECTION AND RANGING (LIDAR) INFORMATION

FROM IOWA DNR (2020).

3. CONTRACTOR SHALL VERIFY BASE SURFACE PRIOR TO

CONSTRUCTION AND COORDINATE WITH ENGINEER.

COORDINATE SYSTEM AND DATUM:

HORIZONTAL DATUM - NAD83, IOWA STATE PLANE, NORTH ZONE

VERTICAL DATUM - NAVD88

TILE INFORMATION

EXISTING TILE INFORMATION IS APPROXIMATE AND WAS PROVIDED BY

THE LANDOWNER.

EXISTING DRAIN TILE

EXISTING TILE REMOVAL

SOIL BORING SB

EASEMENT BOUNDARY

100-YEAR FLOODPLAIN

SOILS NOTES:

1. STRIP EXISTING VEGETATION AND TOPSOIL WITHIN ALL DISTURBED

AREAS. STRIPPING DEPTH SHALL BE 12 INCHES. STOCKPILE CLEAN

TOPSOIL FREE OF VEGETATION FOR RESPREAD.

2. LIMITED SOIL PROBING WAS COMPLETED BY SHIVE-HATTERY ON

OCTOBER 26, 2023. PROBING WAS DONE TO A DEPTH OF

APPROXIMATELY 42 INCHES IN PROPOSED POOL AREAS.

3. SOILS CONSIST OF A SURFACE LAYER OF DARK ORGANIC TOPSOIL

FOLLOWED BY A LEAN CLAY LAYER. SOME SILT AND SAND SEAMS WERE

PRESENT AS IS TYPICAL IN FLOODPLAN AREAS. THE CLAY LAYER WAS

OBSERVED DOWN TO DEPTHS OF ABOUT 42 INCHES. SOILS AT DEEPER

DEPTHS ARE UNKNOWN. EXCAVATION IS LIMITS TO 3 FEET IN POOL

AREAS AND SELECT SOILS SHALL BE RESERVED FOR CLAY LINER

CONSTRUCTION. SOIL CONDITIONS MAY VARY.

4. NOTIFY ENGINEER IMMEDIATELY IF SAND IS ENCOUNTERED IN LARGE

QUANTITIES. GRADING MAY REQUIRE MODIFICATION IN THE FIELD

BASED ON SOIL CONDITIONS. COORDINATE WITH THE ENGINEER.

500-YEAR FLOODPLAIN

FLOODWAY

0+00

1+00 2+00

2+50

0+

1+

2+

11801180

9:1

:1

43:1

4:1

4:1

0:

3:1

3:

85 11

:1

INSTALL 30 LF OF

6" HDPE @ 3.28%

START IE = 1189.0

END IE = 1188.0

INSTALL 74 LF OF

6" HDPE @ 0.47%

START IE = 1188.0

END IE = 1187.7

INSTALL 90 LF OF

6" HDPE @ 1.12%

START IE = 1189.0

END IE = 1188.0

IE = 1188.0

24" CMP RISER

RIM = 1185.50

NORTH WETLAND DRAWDOWN PIPE

146 LF 18" CMP @ 0.69%

48" CMP WATER CONTROL STRUCTURE

RIM = 1188.60

NORTH WETLAND OUTLET PIPE

31 LF 18" CMP @ 0.00%

PRESTON AVE

LAKE CREEK

INSTALL 34 LF OF

6" HDPE @ 0.47%

START IE = 1187.7

END IE = 1187.5

IE = 1187.5

TWO PUMP STATION SUMPS, SOLAR PANELS,

BATTERY AND CONTROLS. WATER METER TO

BE INSTALLED ON EACH DISCHARGE PIPE

- SEE DETAIL ON C304

GRAVITY INTAKE PIPE FROM

STREAM TO SUMP. TWIN 24"

SDR 26 PVC TO EACH VAULT

BURIED WATER FORCEMAIN

8 INCH SCHEDULE 80 PVC.

PROPOSED NORMAL WATER LEVEL

ELEVATION = 1186.0

AREA = 7.35 ACRES

AVERAGE DEPTH = 0.85 FT

MAX DEPTH = 2.2 FT

FEMA ZONE A

100-YEAR FLOODPLAIN

APPROXIMATE PROPERTY

BOUNDARY (TYP.)

WETLAND EXCAVATION LIMITS

AREA = 4.1 ACRES

EQUIPMENT PAD

TOP ELEV = 1191.50

EXCESS SOIL PLACEMENT LIMITS

AREA = 1.3 ACRES

EXCAVATED CHANNEL

GRADE TO DRAIN TOWARDS OUTLET

TILE COVER BERM

TOP WIDTH = 12 FEET

SIDE SLOPES = 4:1

TILE COVER BERM

TOP WIDTH = 12 FEET

SIDE SLOPES = 4:1

SEE SHEETS C201 AND C202 FOR

SOUTH WETLAND GRADING PLANS

DELINEATED

FLOODWAY

TILE OUTLET SWALE TO WETLAND POOL

PLACE 35 TONS CLASS 'E' RIPRAP 1.5' THICK

INSTALL 279 LF 4"

PERFORATED DRAIN TILE

WITH POROUS BACKFILL.

0.5% MIN SLOPE.

TILE OUTLET SWALE TO WETLAND POOL

PLACE 25 TONS CLASS 'E' RIPRAP 1.5' THICK

EASEMENT BOUNDARY (TYP.)

20 TONS CLASS 'E' RIPRAP

20 TONS CLASS 'E' RIPRAP

20 TONS CLASS 'E' RIPRAP

30 TONS CLASS 'E' RIPRAP

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

TM

E NT O F

A G R I C U L T U R E

L A

ND

S

TEWARDSHIP

D R

AW

N

B Y

AP

PR

O

VE

D B

Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

FI

EL

D B

O O

K

PR

O

JE

C

T N

U M

BE

R

Pr in te d: C101

N O

R

TH

W

ET

LA

N

D G

R

AD

IN

G

P

LA

N G

HK DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

50 --- ---C

AL

B

PU

M

PE

D W

ET

LA

N D

S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

G

RA

DI

NG

P

LA

N.

dw g

3/

/2

:3 4:

A

M

N O

R

TH

LEGEND

LINE TYPEDESCRIPTION

TOP OF DAM ELEVATION

GRADING LIMITS

MAJOR CONTOUR (PROPOSED)

MINOR CONTOUR (PROPOSED)

APPROX. PROPERTY BOUNDARY

MAJOR CONTOUR (EXISTING)

MINOR CONTOUR (EXISTING)

NORMAL WATER LEVEL

EASEMENT BOUNDARY

PROPOSED TILE

100-YEAR FLOODPLAIN

11801180

DELINEATED FLOODWAY

FEMA ZONE A

100-YEAR FLOODPLAIN

SCARIFY AND RECOMPACT 9"

OF ALL NON-EXCAVATED

AREAS WITHIN POOL LIMITS

WASTE SOIL AREA

18" RECOMPACTED CLAY

LINER WITHIN EXCAVATION

LIMITS OF POOL

SCARIFY AND RECOMPACT 9"

OF ALL NON-EXCAVATED

AREAS WITHIN POOL LIMITS

NORTH EQUIPMENT PAD

TILE COVERS

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

TM

EN T O F

A G R I C U L T UR E

L A

ND

S

TEWARDSHIP

D R

AW

N

B Y

AP

PR

O

VE

D B

Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

FI

EL

D B

O O

K

PR

O

JE

C

T N

U M

BE

R

Pr in te d: C102

N O

R

TH

W

ET

LA

N

D C

U T-

FI

LL

P

LA

N G

HK DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

50 --- ---C

AL

B

PU

M

PE

D W

ET

LA

N D

S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

G

RA

DI

NG

P

LA

N.

dw g

3/

/2

:3 4:

A

M

N O

R

TH

EARTHWORK TABLE

CLASSIFICATION CUT TOTAL FILL + 20% SHRINK

EXCAVATION, WETLAND 6,176 0

EARTHFILL, EQUIPMENT PAD 0 1,110

EARTHFILL, WASTE SOIL 0 4,046

EARTHFILL, TILE BERMS 0 1,020

TOTAL EARTHWORK 6,176 6,176

ELEVATIONS TABLE

CUT/FILL MINIMUM ELEVATION (FT.) MAXIMUM ELEVATION (FT.) COLOR

CUT -3.0 -2.5

CUT -2.5 -2.0

CUT -2.0 -1.5

CUT -1.5 -1.0

CUT -1.0 -0.5

CUT -0.5 0.0

FILL 0.0 0.5

FILL 0.5 1.0

FILL 1.0 1.5

FILL 1.5 2.0

FILL 2.0 2.5

FILL 2.5 3.0

FILL 3.0 3.5

FILL 3.5 4.0

FILL 4.0 4.5

FILL 4.5 5.0

FILL 5.0 5.5

0+00.00 1+00.00 2+00.00 2+50.00

NORTH WETLAND OUTLET PIPE

18" CMP 31 LF @ 0.00%

48" CMP WATER CONTROL STRUCTURE

RIM = 1188.60

IE = 1181.0

IE = 1181.0

24" CMP RISER

RIM = 1185.50

NORTH WETLAND DRAWDOWN PIPE

18" CMP 146 LF @ 0.69%

IE = 1181.0

IE = 1182.0

NWL = 1186.00

EXISTING GROUND

20 TONS CLASS 'E' RIP RAP MOUNDED

AROUND INTAKE RISER. PLACE WITH CARE

TO ENSURE INTEGRITY OF RISER

6' X 6' CMP

ANTI-SEEP COLLAR

- SEE DETAIL

20 TONS CLASS E RIP RAP

2' THICK OVER GEOTEXTILE

MATCH EXISTING STREAM AND BANK GRADES

7' X 7' CONCRETE BASE

TOP = 1180.67

BOTTOM = 1180.00

6' X 6' CMP

ANTI-SEEP COLLAR

- SEE DETAIL

0+00

1+00

2+00

2+50

146 LF OF 18" CMP @ 0.69%

48" CMP WATER CONTROL STRUCTURE

RIM = 1188.60

31 LF OF 18" CMP @ 0.00%

24" CMP RISER

RIM = 1185.50

STOP LOG STORAGE STRUCTURE

31 LF OF 18" CMP @ 0.00%

20 TONS CLASS E RIP RAP

2' THICK OVER GEOTEXTILE

MATCH EXISTING STREAM

AND BANK GRADES

20 TONS CLASS 'E' RIP RAP

MOUNDED AROUND INTAKE RISER

HORIZONTAL SCALE:

VERTICAL SCALE:

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

TM

E NT O F

A G R I C U L T U R E

L A

ND

S

TEWARDSHIP

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d: C103

NO

RT

H W

ET

LA

ND

DR

AW

DO

W N

PL

AN

AN

D

PR

O

FI

LE

G

HK

DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

C

AL

B

PU

M

PE

D

W

ET

LA

N

D S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

O

UT

LE

T

CH

AN

NE

L

PL

AN

A

ND

P

RO

FI

LE

.d wg 3/

/2

:3

5:

A M

NORTH

0+00

1+00

4:1

4:1

:1

UNISTRUT RACKING FOR

PUMP AND SOLAR CONTROLS

- SEE DETAIL

SOLAR PANELS

- SEE DETAILS

105 TONS 1" CLEAN

STONE, 6" THICK

OVER GEOTEXTILE

ACCESS RAMP

WIDTH = 12 FEET

560 SY TPE 2B RECP

20 TONS CLASS

'E' RIPRAP

NORTH WETLAND PUMP STATION #1

9' X 9' CONCRETE BOX STRUCTURE

RIM = 1191.50

SUMP = 1173.00

NORTH BURIED WATER FORCEMAIN 1A

8" SCH 80 PVC 26 LF @ 0.00%

12.00'

NORTH WETLAND GRAVITY INTAKE PIPE 1A.2

24" SDR 26 PVC 4 LF @ 0.00%

NORTH WETLAND GRAVITY INTAKE PIPE 1B.2

24" SDR 26 PVC 4 LF @ 0.00%

NORTH WETLAND GRAVITY INTAKE PIPE 1A.1

24" SDR 26 PVC 94 LF @ -1.02%

NORTH WETLAND GRAVITY INTAKE PIPE 1B.1

24" SDR 26 PVC 91 LF @ 1.03%

NORTH BURIED WATER FORCEMAIN 1B

8" SCH 80 PVC 9 LF @ 0.00%

30 TONS CLASS E RIP RAP 2'

THICK OVER GEOTEXTILE

MATCH EXISTING STREAM

AND BANK GRADES

0+00.00 1+00.00 2+00.00

NWL = 1186.00

EXISTING GROUND

LIGHT ALARM

DUCKBILL CHECK VALVE

PUMP STATION

- SEE DETAIL ON C304

20 TONS CLASS 'E' RIPRAP 2'

THICK OVER GEOTEXTILE FABRIC

SUMP = 1173.00

CONCRETE BASE AND

STONE SUBBASE

- SEE DETAIL

PROPOSED GROUND

IE = 1187.0

IE = 1187.0

IE = 1178.9

IE = 1178.0

8" SH 80 PVC FORCEMAIN

24" SDR 26 PVC

30 TONS CLASS 'E' RIPRAP 2'

THICK OVER GEOTEXTILE FABRIC

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

TM

E NT O F

A G R I C U L T U R E

L A

ND

S

TEWARDSHIP

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d: C104

NO

RT

H W

ET

LA

ND

PU

M P

ST

AT

IO

N

PL

AN

A

ND

P

RO

FI

LE

G

HK

DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

C

AL

B

PU

M

PE

D

W

ET

LA

N

D S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

O

UT

LE

T

CH

AN

NE

L

PL

AN

A

ND

P

RO

FI

LE

.d wg 3/

/2

:3

5:

A M

NO

RTH

HORIZONTAL SCALE:

VERTICAL SCALE:

0+00

1+00

4:1

4:1

:1

NORTH WETLAND PUMP STATION #2

9' X 9' CONCRETE BOX STRUCTURE

RIM = 1191.50

SUMP = 1173.00

UNISTRUT RACKING FOR

PUMP AND SOLAR CONTROLS

- SEE DETAIL

SOLAR PANELS

- SEE DETAILS

105 TONS 1" CLEAN

STONE, 6" THICK

OVER GEOTEXTILE

ACCESS RAMP

WIDTH = 12 FEET

560 SY TPE 2B RECP

20 TONS CLASS

'E' RIPRAP

12.00'

NORTH WETLAND GRAVITY INTAKE PIPE 2B.2

24" SDR 26 PVC 4 LF @ 0.00%

NORTH WETLAND GRAVITY INTAKE PIPE 2A.2

24" SDR 26 PVC 4 LF @ 0.00%

NORTH WETLAND GRAVITY INTAKE PIPE 2A.1

24" SDR 26 PVC 84 LF @ -1.19%

NORTH WETLAND GRAVITY INTAKE PIPE 2B.1

24" SDR 26 PVC 82 LF @ -1.22%

NORTH BURIED WATER FORCEMAIN 2B

8" SCH 80 PVC 20 LF @ -0.00%

NORTH BURIED WATER FORCEMAIN 2A

8" SCH 80 PVC 33 LF @ 0.00%

NORTH BURIED WATER FORCEMAIN 2C

8" SCH 80 PVC 3 LF @ 0.00%

30 TONS CLASS E RIP RAP 2'

THICK OVER GEOTEXTILE

MATCH EXISTING STREAM

AND BANK GRADES

0+00.00 1+00.00 2+00.00 2+25.13

IE = 1187.0 NWL = 1186.00

EXISTING GROUND

LIGHT ALARM

PUMP STATION

- SEE DETAIL ON C304

20 TONS CLASS 'E' RIPRAP 2'

THICK OVER GEOTEXTILE FABRIC

SUMP = 1173.00

CONCRETE BASE AND

STONE SUBBASE

- SEE DETAIL

PROPOSED GROUND

NORTH WETLAND PUMP STATION #2

9' X 9' CONCRETE BOX STRUCTURE

RIM = 1191.50

SUMP = 1173.00

8" SH 80 PVC FORCEMAIN

DUCKBILL CHECK VALVE

IE = 1179.0

24" SDR 26 PVC

IE = 1178.0

30 TONS CLASS 'E' RIPRAP 2'

THICK OVER GEOTEXTILE FABRIC

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

TM

E NT O F

A G R I C U L T U R E

L A

ND

S

TEWARDSHIP

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d: C105

NO

RT

H W

ET

LA

ND

PU

M P

ST

AT

IO

N

PL

AN

A

ND

P

RO

FI

LE

G

HK

DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

C

AL

B

PU

M

PE

D

W

ET

LA

N

D S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

O

UT

LE

T

CH

AN

NE

L

PL

AN

A

ND

P

RO

FI

LE

.d wg 3/

/2

:3

5:

A M

NO

RTH

HORIZONTAL SCALE:

VERTICAL SCALE:

2+00

11801180

C

ALH

O U

N C

O U

N

TY

D

&J LAN

D

TR

U

ST

W U

EBKER

, JO

EL & M

O

N

IC

A

D

&J LAN

D

TR

U

ST

PRESTON AVE

SEED FROM WETLAND POOL

TO EASEMENT BOUNDARY

BUFFER SEEDING

AREA = 15.1 ACRES

EASEMENT BOUNDARY

GRADING LIMITS (TYP)

EXISTING STREAM

CENTERLINE

SEED SPOIL AREA AND TILE COVER BERMS

STRUCTURE SEEDING

AREA = 1.3 ACRES

SEED PUMP STATION PAD

STRUCTURE SEEDING

AREA = 0.2 ACRES

SEE C206 FOR SOUTH

WETLAND SEEDING PLAN

560 SY TYPE

2B RECP

N O

R

TH

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

TM

E NT O F

A G R I C U L T U R E

L A

ND

S

TEWARDSHIP

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d:

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d: C106

NO

RT

H

SE

ED

IN

G

PL

AN

G

HK

DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

C

AL

B

PU

M

PE

D

W

ET

LA

N

D S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

1-

SE

EE

DI

NG

P

LA

N.

dw g

3/

/2

:3 5:

A

M

LEGEND

DESCRIPTION

FENCE

STRUCTURE SEEDING

BUFFER SEEDING

MAJOR CONTOUR (EXISTING)

MINOR CONTOUR (EXISTING)

LINE TYPE

EASEMENT BOUNDARY

GRADING LIMITS

0+

1+

2+

3+

4+

11801180

4:1

4:1

:1

:1

4:1 4:1

15:1

PRESTON AVE

LAKE CREEK

48" CMP WATER CONTROL STRUCTURE

RIM = 1187.00 SOUTH WETLAND DRAWDOWN PIPE

57 LF 18" CMP @ 0.88%

24" CMP RISER

RIM = 1185.50

SOUTH WETLAND OUTLET PIPE

57 LF 18" CMP @ 0.87%

PROTECT EXISTING

BURIED TELECOM LINE

GRAVITY INTAKE PIPE

FROM STREAM TO SUMP

TWIN 24" SDR 26 PVC

SEDIMENT FOREBAY GRADING LIMITS

BOTTOM = 1185.0

DEPTH = 2 FEET

TOP OF BERM

TOP WIDTH = 24 FEET

ELEVATION = 1187.0

MAINTAIN SWALE

DRAINAGE

PUMP STATION SUMP,SOLAR PANELS,

BATTERY, AND CONTROLS. WATER METER

TO BE INSTALLED ON DISCHARGE PIPE

- SEE DETAIL ON C305

BURIED WATER FORCEMAIN.

8 INCH C900 PVC

EASEMENT BOUNDARY (TYP.)

APPROXIMATE PROPERTY

BOUNDARY (TYP.)

ARMOR NATURAL FLOODPLAIN

INFLOW/OUTFLOW LOCATION

CREST = 1186.5

70 TONS CLASS 'E' RIPRAP

EXCAVATED CHANNEL GRADE TO

DRAIN TOWARDS OUTLET

SEE C101 AND C102 FOR

NORTH WETLAND

WETLAND EXCAVATION LIMITS

AREA = 1.1 ACRES

PROPOSED NORMAL WATER LEVEL

ELEVATION = 1186.0

AREA = 4.7 ACRES

AVERAGE DEPTH = 0.63 FT

MAX DEPTH = 3.0 FT

20 TONS CLASS 'E' RIPRAP

STABILIZED

CONSTRUCTION

ENTRANCE, 30 TONS 2

INCH CLEAN STONE

20 TONS CLASS 'E' RIPRAP

20 TONS CLASS 'E' RIPRAP

20 TONS CLASS 'E' RIPRAP

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

TM

EN T O F

A G R I C U L T UR E

L A

ND

S

TEWARDSHIP

D R

AW

N

B Y

AP

PR

O

VE

D B

Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

FI

EL

D B

O O

K

PR

O

JE

C

T N

U M

BE

R

Pr in te d: C201

SO

U

TH

W

ET

LA

N D

G R

AD

IN

G P

LA

N

G

HK DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

50 --- ---C

AL

B

PU

M

PE

D W

ET

LA

N D

S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

G

RA

DI

NG

P

LA

N.

dw g

3/

/2

:3 5:

A

M

N O

R

TH

LEGEND

LINE TYPEDESCRIPTION

TOP OF DAM ELEVATION

GRADING LIMITS

MAJOR CONTOUR (PROPOSED)

MINOR CONTOUR (PROPOSED)

APPROX. PROPERTY BOUNDARY

MAJOR CONTOUR (EXISTING)

MINOR CONTOUR (EXISTING)

NORMAL WATER LEVEL

EASEMENT BOUNDARY

PROPOSED TILE

100-YEAR FLOODPLAIN

0+

1+

2+

3+

4+

11801180

FEMA ZONE A

100-YEAR FLOODPLAIN

DELINEATED FLOODWAY

DELINEATED FLOODWAY

18" RECOMPACTED CLAY

LINER WITHIN EXCAVATION

LIMITS OF POOL

SCARIFY AND RECOMPACT 9"

OF ALL NON-EXCAVATED

AREAS WITHIN POOL LIMITS

SOUTH EMBANKMENT

SOUTH EQUIPMENT PAD

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

TM

EN T O F

A G R I C U L T UR E

L A

ND

S

TEWARDSHIP

D R

AW

N

B Y

AP

PR

O

VE

D B

Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

FI

EL

D B

O O

K

PR

O

JE

C

T N

U M

BE

R

Pr in te d: C202

SO

U

TH

W

ET

LA

N D

C U

T-

FI

LL

P

LA

N

G

HK DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

50 --- ---C

AL

B

PU

M

PE

D W

ET

LA

N D

S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

G

RA

DI

NG

P

LA

N.

dw g

3/

/2

:3 5:

A

M

N O

R

TH

ELEVATIONS TABLE

CUT/FILL MINIMUM ELEVATION (FT.) MAXIMUM ELEVATION (FT.) COLOR

CUT -2.5 -2.0

CUT -2.0 -1.5

CUT -1.5 -1.0

CUT -1.0 -0.5

CUT -0.5 0.0

FILL 0.0 0.5

FILL 0.5 1.0

FILL 1.0 1.5

FILL 1.5 2.0

FILL 2.0 2.5

FILL 2.5 3.0

FILL 3.0 3.5

FILL 3.5 4.0

FILL 4.0 4.5

EARTHWORK TABLE

CLASSIFICATION CUT TOTAL FILL + 20% SHRINK

EXCAVATION, WETLAND 1,056 0

EARTHFILL, EQUIPMENT PAD 0 578

EARTHFILL, WASTE SOIL 0 478

TOTAL EARTHWORK 1,056 1,056

0+00 1+00 2+00 3+00 4+00

4:

4:

24" CMP RISER

RIM = 1185.50

57 LF OF 18" CMP @ 0.88%

48" CMP WATER CONTROL STRUCTURE

RIM = 1187.00

57 LF OF 18" CMP @ 0.87%

0+00 1+00 2+00 3+00 4+00

PROPOSED TOP OF DAM

ELEVATION = 1187.00

EXISTING GROUND

OVERBUILD EMBANKMENT

TO ELEVATION OF 1187.10

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

TM

EN T O F

A G R I C U L T UR E

L A

ND

S

TEWARDSHIP

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d: C203

SO

UT

H

EM

BA

NK

M

EN

T

PL

AN

AN

D

PR

O

FI

LE

G

HK

DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

C

AL

B

PU

M

PE

D

W

ET

LA

N

D S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

O

UT

LE

T

CH

AN

NE

L

PL

AN

A

ND

P

RO

FI

LE

.d wg 3/

/2

:3

6:

A M

HORIZONTAL SCALE:VERTICAL SCALE:

1+50

4:1

24" CMP RISER

RIM = 1185.50

57 LF OF 18" CMP @ 0.88%

48" CMP WATER CONTROL STRUCTURE

RIM = 1187.00

57 LF OF 18" CMP @ 0.87%

STOP LOG STORAGE STRUCTURE

20 TONS CLASS E RIP RAP

2' THICK OVER GEOTEXTILE

MATCH EXISTING STREAM AND BANK GRADES

20 TONS CLASS 'E' RIP RAP

MOUNDED AROUND INTAKE RISER

0+00.00 1+00.00 1+50.00

24" CMP RISER

RIM = 1185.50

SOUTH WETLAND DRAWDOWN PIPE

18" CMP 57 LF @ 0.88%

SOUTH WETLAND OUTLET PIPE

18" CMP 57 LF @ 0.87%

48" CMP WATER CONTROL STRUCTURE

RIM = 1187.00

IE = 1180.5

IE = 1180.0

IE = 1181.0

IE = 1180.5

20 TONS CLASS 'E' RIP RAP MOUNDED

AROUND INTAKE RISER. PLACE WITH CARE

TO ENSURE INTEGRITY OF RISER

NWL = 1186.00

6' X 6' CMP

ANTI-SEEP COLLAR

- SEE DETAIL

20 TONS CLASS E RIP RAP

2' THICK OVER GEOTEXTILE

7' X 7' CONCRETE BASE

TOP = 1180.17

BOTTOM = 1179.50

6' X 6' CMP

ANTI-SEEP COLLAR

- SEE DETAIL

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

TM

EN T O F

A G R I C U L T UR E

L A

ND

S

TEWARDSHIP

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d: C204

SO

UT

H W

ET

LA

ND

DR

AW

DO

W N

PL

AN

AN

D

PR

O

FI

LE

G

HK

DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

C

AL

B

PU

M

PE

D

W

ET

LA

N

D S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

O

UT

LE

T

CH

AN

NE

L

PL

AN

A

ND

P

RO

FI

LE

.d wg 3/

/2

:3

6:

A M

1+00 2+00

4:

4:1

:1

SOUTH BURIED WATER FORCEMAIN

8" SCH 80 PVC 27 LF @ 0.00%

SOUTH GRAVITY INTAKE 2

24" SDR 26 PVC 105 LF @ -0.24%

SOUTH WETLAND PUMP STATION

9' X 9' CONCRETE BOX STRUCTURE

RIM = 1190.00

SUMP = 1175.50

SOUTH GRAVITY INTAKE 1

24" SDR 26 PVC 104 LF @ -0.24%

UNISTRUT RACKING FOR

PUMP AND SOLAR CONTROLS

- SEE DETAIL

SOLAR PANELS

- SEE DETAILS

70 TONS 2" CLEAN

STONE, 6" THICK

OVER GEOTEXTILE

ACCESS RAMP

WIDTH = 12 FEET

SIMPLEX PUMP STATION

- SEE DETAIL ON C305

395 SY TPE 2B RECP

20 TONS CLASS

'E' RIPRAP

20 TONS CLASS E RIP RAP

2' THICK OVER GEOTEXTILE

MATCH EXISTING STREAM

AND BANK GRADES

0+00.00 1+00.00 2+00.00

IE = 1180.3

IE = 1180.0

IE = 1187.0 IE = 1187.0

SOUTH WETLAND PUMP STATION

9' X 9' CONCRETE BOX STRUCTURE

RIM = 1190.00

SUMP = 1175.50

LIGHT ALARM

PUMP STATION

- SEE DETAIL ON C305

20 TONS CLASS 'E' RIPRAP 2'

THICK OVER GEOTEXTILE FABRIC

NWL = 1186.00

PROPOSED GROUND

EXISTING GROUND

SUMP = 1175.00

CONCRETE BASE AND

STONE SUBBASE

- SEE DETAIL

20 TONS CLASS 'E' RIPRAP 2'

THICK OVER GEOTEXTILE FABRIC

8" SH 80 PVC FORCEMAIN

24" SDR 26 PVC

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

TM

EN T O F

A G R I C U L T UR E

L A

ND

S

TEWARDSHIP

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d: C205

SO

UT

H W

ET

LA

ND

PU

M P

ST

AT

IO

N

PL

AN

A

ND

P

RO

FI

LE

G

HK

DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

C

AL

B

PU

M

PE

D

W

ET

LA

N

D S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

O

UT

LE

T

CH

AN

NE

L

PL

AN

A

ND

P

RO

FI

LE

.d wg 3/

/2

:3

6:

A M

11801180

C

ALH

O U

N C

O U

N

TY

PRESTON AVE

BUFFER SEEDING

AREA = 0.6 ACRES

EASEMENT BOUNDARY

GRADING LIMITS (TYP)

EXISTING STREAM

CENTERLINE

SEED WETLAND EMBANKMENT

STRUCTURE SEEDING

AREA = 0.3 ACRES

GRADING LIMITS (TYP)

SEED PUMP STATION PAD

STRUCTURE SEEDING

AREA = 0.1 ACRES

CONTRACTOR IS RESPONSIBLE FOR RE-SEEDING ALL DISTURBED

AREA WITHIN THE EASEMENT AND OUTSIDE OF THE POOL. SITE IS

CURRENTLY SEEDED TO NATIVE PRAIRIE. SEEDING AREA SHOWN

IS AN ESTIMATE OF NEEDED DISTURBANCE FOR STAGING AND

ACCESS. MINIMIZE DISTURBANCE TO ESTABLISHED VEGETATION

DESIGNATED TO REMAIN TO THE EXTENT PRACTICAL

395 SY TYPE

2B RECP

INSTALL 422 LF

OF SILT FENCE

SEE C106 FOR NORTH

WETLAND SEEDING PLAN

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

TM

E NT O F

A G R I C U L T U R E

L A

ND

S

TEWARDSHIP

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d:

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d: C206

SO

UT

H

SE

ED

IN

G

PL

AN

G

HK

DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

C

AL

B

PU

M

PE

D

W

ET

LA

N

D S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

1-

SE

EE

DI

NG

P

LA

N.

dw g

3/

/2

:3 6:

A

M

N O

R

TH

LEGEND

DESCRIPTION

FENCE

STRUCTURE SEEDING

BUFFER SEEDING

MAJOR CONTOUR (EXISTING)

MINOR CONTOUR (EXISTING)

LINE TYPE

EASEMENT BOUNDARY

GRADING LIMITS

EXISTING SOIL SURFACE

16" HOLES LOCATED AS SHOWN,

PRE-PUNCHED BY SIGN

FABRICATOR. FASTEN SIGN TO

POSTS WITH 3/8" DIA. STEEL BOLT &

NUT SET, SEE BOLT, WASHER, &

NUT FASTENER DETAIL THIS SHEET

(4 SETS REQ'D. PROVIDED AND

INSTALLED BY CONTRACTOR).

SIGN PANEL TO BE 0.080" THICK

ALUMINUM SUBSTRATE WITH 3M (OR

EQUAL) ENGINEER GRADE REFLECTIVE

SHEETING. SIGN PANELS FURNISHED BY

THE DIVISION OF SOIL CONSERVATION.

SIGN PANEL INSTALLED BY CONTRACTOR.

BACKFILL WITH CONCRETE

(PREFERRED), CLEAN STONE

(ACCEPTABLE), OR HAND-TAMPED

EARTH IN SMALL LIFTS (SUBJECT

TO ENGINEER'S APPROVAL)

2 EACH OF 4"x4"x12'

PRESSURE-TREATED POST

(TYP.). POSTS SEALED WITH

THOMPSON'S WATER SEAL OR

EQUAL. POSTS, SEALANT, AND

INSTALLATION PROVIDED BY

CONTRACTOR.

SIGNAGE NOTES:

1. DIVISION WILL FURNISH SIGN PANEL. CONTRACTOR IS RESPONSIBLE FOR PROVIDING POSTS, HARDWARE, AND INSTALLATION.

2. ALL EXPOSED WOOD SHALL BE SEALED WITH THOMPSON'S WATER SEAL OR EQUAL MEETING ASTM D-4446-08.

3. ALL STEEL HARDWARE PIECES SHALL BE GALVANIZED OR RUST RESISTANT.

4. NYLON AND STEEL WASHERS SHALL BE USED AS SHOWN ON THE BOLT, WASHER, NUT FASTENER

DETAIL ABOVE.

5. CLEAR UTILITIES WITH IOWA ONE-CALL (800) 292-8989 BEFORE EXCAVATING FOR POSTS.

6. SECURE DIVISION AND LANDOWNER APPROVAL FOR SIGN LOCATION BEFORE INSTALLATION.

7. COSTS FOR POSTS, HARDWARE, WOOD SEALANT AND SIGN INSTALLATION SHALL BE INCIDENTAL TO

MOBILIZATION.

8. CONTRACTOR SHALL INSTALL SIGN POSTS USING A PLYWOOD OR OTHER SUITABLE TEMPLATE TO MAINTAIN ACCURATE POST SPACING AND ALIGNMENT DURING BACKFILLING OF THE POST HOLES. TO AVOID BENDING OF THE SIGN PANELS, POSTS SHALL NOT BE INSTALLED OR BACKFILLED WITH SIGN

PANELS ATTACHED.

9. ONE (1) PROJECT SIGN IS REQUIRED UNLESS NOTED OTHERWISE.

TOP

PANEL

9"

30"

48" 9"

3" (T

YP

BOLT, WASHER, &

NUT

FASTENER DETAIL

NOT TO SCALE

STEEL

WASHER

HEAD

NYLON WASHER

AGAINST FACE OF SIGN

STEEL WASHER

BACK OF POST NUT

TH

IC

KN

ES

S

FO

R

SI

G N

P

O

ST

A B C D E F

W

ES

TO

W

N P

KW

Y, S U

IT

E

W

ES

T D

ES

M

O

IN

ES

, I

O W

A

5.

3.

S

H

IV

E- H

AT

TE

R Y.

C O

M

A B C D E F

IOWA D

EP

A R

T M

EN T O F

A G R I C U L T UR E

L A

ND

S

TEWARDSHIP

D R

AW

N

AP

PR

O

VE

D

IS

SU

ED

F

O R

D

AT

E:

FI

EL

D B

O O

K:

PR

O

JE

C

T N

O

C

LI

EN

T

N O

Pr in te d: C301

CO

NS

TR

UC

TI

O

N

DE

TA

IL

S G

HK

DJ

J

BI

D

DO

CU

M

EN

TS

1/

/2

C

AL

B

PU

M

PE

D

W

ET

LA

N

D S

ID

AL

S

RO

CK

W

EL

L

CI

TY

, I

O W

A

P:

\P ro je ct s\

DM

\2

0\ De liv er ab le s\ Dr aw in gs \1

_C ivi l\C

1-

CO

NS

TR

UC

TI

O N

DE

TA

IL

S.

dw g

3/

/2

:3 6:

A

M

NWL = 1186.00

PROPOSED GROUND

EXISTING GROUND (VARIES)

ELEV = 1185.75

10' MINIMUM

REFER TO GRADING PLAN

WAVE BENCH

A1 WAVE PROTECTION BENCH AT NWL

ELEV = 1186.25

EXISTING GROUND

TIE INTO EXISTING TILE AS

DETAILED -

FIELD VERIFY LOCATION

AND DEPTHSNWL = 1186.00

PROPOSED GROUND

LAST 20 LF SHALL BE CMP

WITH RODENT GUARD

1 SIZE LARGER THAN PROPOSED TILE

PE FIELD TILE -

SEE PLANS FOR LENGTHS AND

LOCATIONS

PROPOSED GROUND

CONCRETE CONNECTION

MATCH INVERTS

A3 TYPICAL TILE DAYLIGHT

MATCH INVERTS

D

2D INSTALL APPROPRIATELT SIZED FERNCO OR

APPROVED EQUIVALENT COUPLER AND

CONCRETE COLLAR OF 3,000 PSI MINIMUM STRENGTH

CONCRETE, MINIMUM 2D WIDE CENTERED ON JOINT,

MIN 6'' THICKNESS FOR FULL 2D WIDTH. THICKNESS

CAN TAPER DOWN BEYOND THE 2D WIDTH.

FlowFlow

NEW SECTION OF TILE

EXISTING TILE

A2 FIELD TILE REPAIR CONNECTION

IE = 1187.00

D4 PROJECT SIGN

A4 CMP PIPE BEDDING

1. SUBGRADE SHOULD BE EXCAVATED OR OVER EXCAVATED, IF

NECESSARY, SO A UNIFORM FOUNDATION FREE OF

PROTRUDING ROCKS MAY BE PROVIDED.

2. GRANULAR BEDDING IS NOT ALLOWED AS IT MAY CREATE A

SEEPAGE PATHWAY. BACK FILL WILL IMPERVIOUS COMPACTED

CLAY BY HAND.

NOTE:

2'-10"

21.5"

4"UNDISTRUBED

SOIL

IMPERVIOUS FILL HAND COMPACTED IN 6 INCH LIFTS

2.00''

6.

0.75'' NOTES:

1. ALUMINUM OR PVC STOP-LOGS SHALL BE PROVIDED BY CONTRACTOR.

ALUMINUM STOP LOGS ARE DETAILED, PVC STOP LOGS SUBJECT TO

APPROVAL BY ENGINEER.

2. CONTRACTOR IS RESPONSIBLE FOR CUTTING STOP-LOGS AS SHOWN.

THE 0.75'' DIMENSION IS CRITICAL AND NEEDS TO BE CENTERED IN THE

STOP-LOG TO AVOID LEAKAGE.

3. THE FINISHED SURFACE SHALL BE SMOOTH TO PROVIDE A FLAT

SURFACE FOR THE STOP-LOG ABOVE IT.

4. THE CONTRACTOR SHALL DELIVER A TOTAL OF 21 STOP-LOGS TO THE

SITE (10 FOR NORTH SITE AND 11 FOR SOUTH SITE).

5. THE COST OF THE STOP-LOG WORK IS INCIDENTAL TO THE OUTLET

CONTROL STRUCTURE.

12''

8.

2.25''

NOTE:

TWO (2) LIFTING HOOKS REQUIRED

2'' DIAMETER ROD

1 1/4'' DIAMETER INSIDE

BEND. HOOK TO BE IN

LINE WITH HANDLE.

WATER CONTROL STRUCTURE

L 3 X 3 X 3 8

GALVANIZED (TYP)

ALUMINUM STOP LOG 1'' LESS THAN

TIGHT FIT. FIELD VERIFY LENGTH.

CONTINUOUS WELD

2.

0"

2.

5'

2.

5'

6''3''1''3''

0.

LIFTING HOLES

LIFTING HOLES

NOTES:

1. CONTRACTOR TO DRILL 38" HOLES IN TOP OF STOP LOG

CHANNELS AND PROVIDE TWO (2) PAD LOCKS TO LOCK

THROUGH CHANNELS TO PREVENT LOGS FROM BEING

LIFTED OUT WHEN…