4-26-02_Cal883229BN & BS_Bid_Bond_DocEE (UPLOAD).pdf
PDF 207 KB Posted
- Attached to
- Cal883229BN & BS (Calhoun)
- Solicitation number
- 0009-RFB-WRBLW-CY26-02
- Issued by
- Carroll County, Iowa
About this file
This is a Proposal Guarantee (Bid Bond) document issued by the Iowa Department of Agriculture and Land Stewardship, Division of Soil Conservation and Water Quality, for Bid No. 26-2 (also referenced as Bid No. 25-17). The document pertains to the Cal883229BN-North & Cal883229BS-South Nutrient Reduction Wetland Project located in Section 29, Township 88 North, Range 32 West, Calhoun County, Iowa. The project encompasses two concurrent nutrient reduction wetland construction initiatives: the North project requires approximately 31,200 cubic yards of earthwork and 16.6 acres of seeding, while the South project requires approximately 10,300 cubic yards of earthwork and 1.0 acre of seeding. Deliverables include excavation, grading, lift station installation with solar-powered pumps, water control structures, riprap placement, and seeding. Sealed bids were due by 3:00 PM CDT on May 20, 2026, with a public bid opening scheduled the same day. A non-mandatory pre-bid conference was held on April 24, 2026 at 10:00 AM at the Calhoun County Conservation Board in Rockwell City, Iowa. Construction must commence within 14 days of the preconstruction meeting, with a construction deadline of December 31, 2026, a seeding deadline for structures by May 15, 2027, and a buffer seeding deadline of June 30, 2027.
Bidders must submit a bid bond equal to ten percent (10%) of the bid amount, with the successful contractor required to furnish a Performance/Payment Bond equal to one hundred percent (100%) of the contract price. The estimated total construction cost range is $375,000 to $475,000 for the North project and $175,000 to $275,000 for the South project, with a combined potential award value between $550,000 and $750,000. The bid bond obligation becomes null and void if the proposal is rejected or if the proposal is accepted and the principal enters into the contract and furnishes the performance bond within fourteen (14) days of award approval. If the principal fails to meet these conditions, the principal and surety agree to forfeit the penal sum to the Division. Bidders must be registered with the Iowa Department of Inspections, Appeals & Licensing and the Iowa Management of Procurement and Contracts System (IMPACS). Non-Iowa corporations must provide proof of authorization from the Secretary of State to do business in Iowa prior to contract execution. No specific set-aside designations, disadvantaged enterprise restrictions, or incumbent vendors are identified in this procurement.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cal883229BN-North & BS-South Nutrient Reduction Wetland Project DOCUMENT EE Bid No. 25-17 PROPOSAL GUARANTEE (BID BOND)
EE-1
State of Iowa Iowa Department of Agriculture and Land Stewardship
DIVISION OF SOIL CONSERVATION AND WATER QUALITY
KNOW ALL PERSONS BY THESE PRESENTS:
That we, of as PRINCIPAL, and of as SURETY(S), are hereby held and firmly bound unto the State of Iowa in the penal sum of
______ /100 Dollars ($ . ) for the payment, whereof, the said PRINCIPAL and SURETY(S) bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
The conditions of this obligation are such that whereas the PRINCIPAL is herewith submitting to the Iowa Department of
Agriculture and Land Stewardship, Division of Soil Conservation and Water Quality, hereinafter called the DIVISION its sealed contract for the following:
Nutrient Reduction Wetland Project
Section 29, Township 88 North, Range 32 West, Calhoun County, Iowa
Project ID: Cal883229BN-North & BS-South
Bid No. 26-2
NOW THEREFORE,
the conditions of this obligation are such that, if said proposal is rejected by the DIVISION, or if said proposal is accepted by the DIVISION and the PRINCIPAL shall enter into a contract in the form specified by the DIVISION in accordance with the terms of the Proposal and Schedule of Prices (Document CC) and shall furnish a bond for the faithful performance of said contract in the form specified by the DIVISION, this obligation shall be null and void. Otherwise, it shall remain in full force and effect.
In the event that the said proposal is accepted by the DIVISION and the PRINCIPAL fails to enter into the contract as defined herein or fails to furnish the performance bond as noted above, within fourteen (14) days of the approval of the award, the
PRINCIPAL and SURETY(S) agree to forfeit to the DIVISION the penal sum herein mentioned, it being understood that the liability of the SURETY(S) shall in no event exceed the penal sum or this obligation.
IN WITNESS WHEREOF,
the above bounden parties have executed this instrument under their several seals this day of
, 20_______, the name and corporate seal of each party being hereto affixed and these presents duly signed by its undersigned representative pursuant to authority of its governing body.
PRINCIPAL SURETY
By By
Print Name:
If a partnership, all partners must sign.
END OF DOCUMENT EE