Western Location Location Submittal In In
# Standards Project Specifications
STANDARD 1 STANDARD 1
1 Construction Schedule 1.1.4.1. (see project spec)
6 Breakdown of Contract Prices 1.1.6.1. NLT 30 days after NTP
10 Safety and Health Program 1.4.1.5.
NLT 10 days prior to start of construction
11 Copies of Certifications, Test Records & Technical Data 1.4.1.10. Prior to use
16 Material Safety Data Sheets 1.4.1.10.(5) Prior to use
17 Manufacturer's Load Rating For Hoists and Grips 1.4.1.10.(6) Prior to use
18 Certification of Fabricated Lifting and Rigging Devices 1.4.1.10.(7) & 1.4.11 Prior to use
19 Medical Examiner's Certificate 1.4.1.10.(8) & 1.4.3.3 Prior to use
21 Assurance of Competency in Equipment Operation 1.4.3.4. Prior to use
27 Protective Ground Lead Test Results & Certification 1.4.14.3. Prior to use
STANDARD 9 STANDARD 9
115 Contractor On-site Test Personnel 9.1.2.2.(2) Prior to working on-site
116 Electrical Test Reports & Documents 9.1.2.2.(3) NLT 7 days after testing
127 Revised Wiring Diagrams Table 9-1 & 9.1.3.9.
NLT 60 days after receipt of drawings
129 As-built Western Drawings Table 9-1 & 9.1.3.10.(2) NLT 60 days after equip.
checkout
130 Test Reports For Ground Tests 9.2.1.3.
NLT 15 days after completion of testing
STANDARD 13 STANDARD 13
179 Recycled Materials Quantity Report 13.2.1. & 13.7.2.
180 Products Containing Recovered Materials Report 13.2.2. & 13.8.3.
182 Spill Prevention Notification & Cleanup Plan 13.2.5. & 13.11.2.
188 Water Pollution Permits 13.2.12. & 13.17.2.
191 Cleanup Work Management Plan 13.2.16. & 13.19.2.
192 Post Cleanup Report 13.2.17. & 13.19.7.
STANDARD 15 STANDARD 15
193 As-Built Drawings 15.2.6.
ENVIRONMENTAL QUALITY PROTECTION
DRAWINGS
GENERAL REQUIREMENTS
SUBSTATION – ELECTRICAL
Submittal Item Date Due
Attachment D