This statement of work document outlines requirements for bridge and historic repairs at the Salisbury National Cemetery in North Carolina. The contractor will perform work in accordance with contract drawings and specifications across multiple construction divisions, including concrete, masonry, metals, thermal and moisture protection, earthwork, exterior improvements, utilities, and historic stonework cleaning and restoration. Key tasks involve repairing a brick culvert, box culvert area, and materials storage area. The solicitation includes a 180-day performance period and requires the contractor to submit documentation like shop drawings, samples, and payment requests to the contracting officer's representative and project engineer for review and approval. Bidders must inspect the site and direct any questions to the cemetery director or foreman. The price schedule requests a lump sum bid to complete all work for the project under control number 876-MM24-02.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Location: SALISBURY NATIONAL CEMETERY (HISTORIC)

202 GOVERNMENT RD, SALISBURY, NC 28144

Project Title: Bridge and Historic Repairs

Project Control #: 876-MM24-02

Statement of Work Summary:

Contractor shall furnish all tools, labor, materials, equipment, and services to perform work described below, in the specification sections, and on the drawings at the Salisbury

National Cemetery.

A. General

1. Contractor is strongly encouraged to survey the project area prior to bidding to adequately understand the full scope of work and all requirements. Contractor is required to submit any questions or clarifications prior to bid. A bid submitted will be taken as agreement that the work shall be performed to meet the requirements herein based on the existing conditions in the field.

2. The specifications and drawings have the following project number on them which corresponds to the design project number: 876-MM21-06. Contractor shall note that this differs from the scope of work project control number listed above which is being used for this construction project: 876-MM24-02.

3. The contractor shall submit submittals including shop drawings and any other specification requirements to the COR for review and approval prior to fabrication/installation. Submittals approved by the owner (VA/NCA) are required prior to starting on the corresponding work.

4. The contractor shall submit a draft invoice/payment request concurrently to the field COR and the Project Engineer for dual approval. Only when the field COR and the Project Engineer approve of the draft invoice may it then be submitted for formal payment.

B. Specific work items:

1. Perform all work in accordance with the contract drawings and specifications below and attached.

SPECIFICATION SECTIONS:

DIVISION 00 - SPECIAL SECTIONS

00 01 07 Professional Seals & Signatures 00 01 15 List of Drawing Sheets

DIVISION 01 - GENERAL REQUIREMENTS

01 00 02 General Requirements (Minor NCA Projects) 01 33 23 Shop Drawings, Product Data, and Samples 01 42 19 Reference Standards

01 45 29 Testing Laboratory Services 01 57 19 Temporary Environmental Controls 01 74 19 Construction Waste Management 01 81 13 Sustainable Construction Requirements

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete

DIVISION 04 – MASONRY

04 05 13 Masonry Mortaring 04 05 16 Masonry Grouting 04 05 31 Masonry Tuck Pointing

04 20 00 Unit Masonry

DIVISION 05 – METALS

05 50 00 Metal Fabrications

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 92 00 Joint Sealants

DIVISION 31 – EARTHWORK

31 20 11 Earth Moving (Short Form)

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 32 12 16 Asphalt Paving 32 31 13 Chain Link Fences 32 90 00 Planting

DIVISION 33 – UTILITIES

33 40 00 Storm Sewer Utilities

DIVISION 45 - SPECIALTIES

45 10 00 Historic Stonework and Metalwork Cleaning and Restoration

APPENDICES

Asphalt Roadway Structure Evaluation Report

DRAWINGS:

Drawing No. Title

SITE PLANNING

V-001 SITE SURVEY

GC001 OVERALL DEVELOPMENT PLAN

CD001 ROADWAY PREPARATION AND REMOVALS PLAN

CP001 PAVEMENT REPLACEMENT PLAN

CI201 MAIN CEMETERY ENTRANCE ELEVATION

CI202 FLOOD GATE ELEVATIONS AND RESTORATION

CI501 SITE DETAILS

STRUCTURAL

S-100 STRUCTURAL EXISTING CONDITIONS PLAN

S-101 REPAIR BRICK CULVERT

S-102 REPAIR BOX CULVERT AREA

S-103 MATERIALS STORAGE AREA RENOVATION

S-501 BRICK CULVERT RELINE DETAILS – 1

S-502 BRICK CULVERT RELINE DETAILS – 2

S-503 STRUCTURAL DETAILS

Pre-Bid Site Visit: Bidders are strongly urged to inspect, site investigate by observation, and Request for Information (RFI) and responses through the Contracting Office to satisfy their understanding of the work to be done, all general, local and technical conditions that may affect the cost and the feasibility of their proposal. In no event shall failure to inspect the site constitute grounds for a claim after award. Visitors planning to conduct a site visit shall contact the Cemetery Director or Foreman to make arrangements:

Cemetery POC(s):

Salisbury National Cemetery Director....... (704) 636-2661 or Philip Smyre at john.smyre@va.gov

Technical POC (Submit all submittals concurrently to the COR and Technical POC below):

Rico J. Silvetti, North Atlantic District (NAD) Engineer....... rico.silvetti@va.gov mailto:john.smyre@va.gov

PRICE SCHEDULE

DESCRIPTION QTY UNIT TOTAL PRICE

Contractor shall provide all labor, tools, materials, equipment, and supervision necessary to perform all work in accordance with the attached specifications and drawings at the Salisbury National Cemetery (Historic).

1 JOB $ _____________

Duration: Term of the contract shall be one hundred and eighty days (180 days) from date of award. The Contractor shall complete all work within 180 calendar days after receipt of Notice to Proceed, subject to all terms, conditions, provisions and schedules of the contract.

(END OF PRICE SCHEDULE)