36C78624B0009 A0002.docx
DOCX document 25 KB Posted
- Solicitation number
- 36C78624B0009
About this file
This document contains an amendment and questions and answers related to a solicitation for bridge and historic repairs at the Salisbury National Cemetery (Historic) in Salisbury, North Carolina. The project includes repairing the cemetery bridge and performing historic masonry work. The amendment provides the government's responses to Request for Information Number 2, answering questions about the bridge's weight rating, required experience for stone contractors, permitting requirements, and methods for cleaning concrete gutters and relining pipes. It clarifies that contractors are responsible for obtaining permits and determining their means and methods. The solicitation requires contractors to submit pricing for contract line items, complete cost estimate worksheets, and sign amendments by the specified due date. The Department of Veterans Affairs National Cemetery Administration is the contracting agency.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 876-MM24-02 Full Drawings - Salisbury Natl Cem.pdf | ||
| Virtual Bid Opening Salisbury National Cemetery.pdf | ||
| 36C78624B0009 A0001.docx | DOCX document | |
| IFB Cost Estimate Worksheet Salisbury Natl Cem FY24.xlsx | XLSX spreadsheet | |
| 876-MM24-02 SOW.pdf | ||
| 36C78624B0009_1.docx | DOCX document | |
| Wage Determination Rowan County Salisbury NC.pdf | ||
| 876-MM24-02 Full Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) A0002
876-MM24-02
36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle
VA
22172 36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle
VA
22172 To all Offerors/Bidders
A0002 36C78624B0009 02-01-2024 A0002
X X X
X AMENDMENT (A0002) | Salisbury National Cemetery | Bridge and Historic Repairs | Project No. 876-MM24-02 The Purpose of Amendment (A0002) is to Notify the Public of the Government's Response to RFI No. 2.
NOTE: Please See Page. #3 for Content
**All Factors & Content of This IFB Solicitations Remains the Same** Sheryl Palacio-Davis Contracting Officer A.1 AMENDMENT (A0002) FOR IFB SOLICITATION SALISBURY NATIONAL CEMETERY (HISTORIC)
AMENDMENT A0001
PROJECT LOCATION: Salisbury National Cemetery (Historic) Salisbury National Cemetery (Historic) 202 Government Rd.
Salisbury, NC 28144
PROJECT TITLE: Bridge and Historic Repairs
PROJECT NUMBER: 876-MM24-02
STATEMENT OF WORK SUMMARY:
· Contractor shall furnish all tools, labor, materials, equipment, and professional supervision to perform work described in the Statement of Work (SOW), Specification & Drawings, for the Bridge and Historic Repairs, located at the Salisbury National Cemetery (Historic), North Carolina.
Rowan County, in the State of North Carolina.
CONTINUATION PAGE
QUESTIONS AND ANSWERS TO RFI #2
AMENDMENT A0002: SALISBURY NATIONAL CEMETERY (HISTORIC) | IFB SOLICITATION NO. 36C78624B0009 | PROJECT NO. 876-MM24-02 | BRIDGE AND HISTORIC REPAIRS.
· CEMETERY’S ADDRESS
Salisbury National Cemetery (Historic) 202 Government Rd Salisbury, NC 28144
Amendment A0002 is the Government’s Response to RFI No. 2 as Follows:
The RFP, page 14 states the following is all that is required for submission:
· Company’s cover letter with Solicitation number, POC name, phone number, email address, and DUNS number.
· Completed front and back blocks 14-20 of the SF 1442 and signed block 20b
· Completed Price Cost Schedule “A.4” Pricing for each CLIN and grand total.
· Completed Attachment of the IFB Contractor Cost Estimate Worksheet.
· Complete and signed SF30 Amendments.
· Scanned digital copy of the Bid Bond. (Ensure to lightly darken all raised seals)
QUESTION #1? Please confirm no other documents are required for submission such as Reps and Certs.
· ANSWER: Review the entire solicitation package and submit all items required.
QUESTION #2? Per Section 45 10 00, please confirm the Stone Contractor is required to provide documentation showing a minimum of 5 years experience doing Historic Masonry work.
· ANSWER: Perform work as described in specification sections.
QUESTION #3? With the size of the project, please confirm one individual can perform the duties of Superintendent, SSHO, and QCM if qualified.
· ANSWER: This is not a question for the Government to answer.
QUESTION #4? Is the Contractor required to obtain any permits for this project?
· ANSWER: This is the contractor’s responsibility to obtain any permits required.
QUESTION #5? What is the anticipated amount of days the contractor can anticipate for work stoppage due to funerals?
· ANSWER: Typically, a funeral requires only a short (30 minutes) stoppage of loud equipment. The Number of internments per day and per week will be provide to the Awardee.
RFI NO. 2 CONTINUATION……
AMENDMENT A0002: SALISBURY NATIONAL CEMETERY (HISTORIC) | IFB SOLICITATION NO. 36C78624B0009 | PROJECT NO. 876-MM24-02 | BRIDGE AND HISTORIC REPAIRS.
QUESTION #1? Is the bridge weight rated? We are concerned about moving heavy equipment/vehicles.
ANSWER: We do not have this information.
QUESTION #2? Would you agree that once we peel away asphalt from the curbs, using a grader, we can’t guarantee any pre-existing conditions we cannot see beforehand?
ANSWER: This answer is covered by the relevant FAR clauses and the existing conditions section of the specifications.
QUESTION #3? When cleaning the concrete gutter pans to remove asphalt [C1501]to what level should we strive? Are we just freshening, or should we consider blasting, soda blasting or dustless blasting?
ANSWER: This is your means and methods to determine the best method.
QUESTION #4? Gathering estimates for the Ultra Flo Pipe Polymer Coated Steel for Reline is proving a bit difficult. Should you have any sources it would be greatly appreciated.
ANSWER: This is contractor’s responsibility.
QUESTION #5? In discussing preserving the historical look of our final product we wish to know what level of scrutiny will be placed on repair of replacement stonework and restoration? We reached out and found members of the North Carolina Historical Society and quickly realized, for example, using period informed skilled iron or masonry workers could be quite expensive.
ANSWER: See relevant specifications and drawings for this information.
QUESTION #6? We question the direction to “remove asphalt, stone and soil to a depth of 14.5” below finished grade” [Roadway Preparation & Removals Plan - Drawing CD001] We feel this might cause the curve in the road to collapse. Would you consider 7-inch dig at the head of the curve transitioning to a 4 inch intermediate area and finally flattening out to a 2-inch dig to finish off?
ANSWER: No, perform work per design documents.
End of Document