Enclosure 3 Quality Assurance Surveillance Plan.pdf
PDF 658 KB Posted
- Attached to
- Enterprise Multimedia and Integrated Technical Services (eMITS) Federal contract opportunity
- Solicitation number
- 80TECH22R0001
About this file
This document provides a Quality Assurance Surveillance Plan (QASP) for the Enterprise Multimedia and Integrated Technical Services (eMITS) contract. The QASP defines the NASA surveillance approach for the eMITS contract to provide multimedia, communication, and IT management services to the NASA Office of Chief Information Officer and Office of Communications. The surveillance strategy focuses on insight over oversight, leveraging the contractor's quality management system. Key surveillance activities include work area checks, performance monitoring against requirements, property administration, and safety reviews. The plan identifies risk areas like system availability, IT security, and schedule, and associated surveillance methods like documentation reviews, audits, and reporting.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP 80TECH22R001
GOVERNMENT QUALITY ASSURANCE SURVEILLANCE
PLAN
ENTERPRISE MULTIMEDIA AND INTEGRATED TECHNICAL
SERVICES (eMITS)
CONTRACT NO. TBD
FEBRUARY 2022
FOR INFORMATION PURPOSES ONLY
FOREWARD
Under performance-based acquisitions such as this, the Contractor assumes more responsibility and greater risk in exchange for more flexibility and less direct Government involvement in contract activities. However, the Government still has a responsibility to conduct surveillance.
Surveillance spans a spectrum of Government involvement. Surveillance may be as simple as inspecting a delivered support or service at acceptance or as complex as continually monitoring contractor performance. To meet this responsibility, the Government needs to understand the risks involved in the Contractor's activity and how the Contractor is managing those risks.
This Government Quality Assurance Surveillance Plan has been prepared to describe the Government’s surveillance of this contract. It is a “living” document that will be tailored to the contractor selected. The Government welcomes suggestions for improving this Plan. Of particular interest are ideas on what information the Government should monitor (i.e., metrics) and how the Government can most cost-effectively obtain the relevant performance data it needs.
ENTERPRISE MULTIMEDIA AND INTEGRATED TECHNICAL SERVICES
(eMITS)
GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN
1.0 INTRODUCTION
1.1 Purpose
The purpose of this Government Quality Assurance Surveillance Plan (QASP) is to define the overall approach that NASA intends to use to monitor and survey Contractor onsite performance under the Enterprise Multimedia and Integrated Technical Services (eMITS) Contract No. TBD.
This QASP defines the process the Government expects to follow to obtain data, evaluate the Contractor, and determine if contract performance conforms to contract requirements. The goal is to balance the level of Government surveillance with perceived impacts and risks associated with performance hereunder. The QASP can be changed unilaterally by the Government at any time during the contract.
NASA plans to utilize a surveillance team to evaluate Contractor performance and direct surveillance activities. The team will establish and rely on objective and subjective performance metrics based on the contract Performance Work Statement (PWS), work packages, and task orders issued thereunder to evaluate Contractor performance against requirements.
The QASP is a Government-developed surveillance tool prepared in accordance with FAR 46.4 and NFS 1846.4. It shall not be included in the contract, per NFS 1846.401(a)(iii), but provided to the Contractor for informational purposes only.
1.2 Scope
This QASP identifies the program requirements, strategies, resources, review and control processes, surveillance activities, and metrics for continuous measurement of Contractor performance. This plan provides effective and systematic surveillance methods for evaluating the Contractor services, processes, and products provided under this contract. The Government may evaluate work at any time during the Contractor’s work performance.
The intent of the QASP is to ensure that the Contractor performs in accordance with acceptable quality levels and the Government receives the quality of services and products called for in the contract. This QASP does not detail how the Contractor accomplishes the work. Rather, the QASP is based on the premise that the contractor, not the Government, is responsible for managing its quality controls and ensuring that performance meets the terms of the contract. The role of the Government is quality assurance to ensure contract standards are achieved.
The QASP is intended to be a “living” document from which resources and activities will evolve from one phase to another during the life of the contract, and will be updated as required and defined in this document.
This plan is applicable to all services performed or products provided by the eMITS Contractor(s). Throughout this QASP, the term “Contractor” is used. In terms of this plan, it should be known that unless explicitly stated, the term “Contractor” is applicable to both the eMITS Contractor and any and all of its subcontractors.
The surveillance program shall be a collaborative and integrated effort that includes all areas of contract management, including the following:
a. Engineering & Technology
b. Quality Assurance
c. Procurement/Subcontracting/Purchasing
d. Finance
e. Property
f. Environmental
g. Export Control
h. Safety and Health
i. Security
1.3 Program Definition and Contract Description
1.3.1 Program Background and Definition
The National Aeronautics and Space Administration (NASA) Office of Chief Information Officer (OCIO) and Office of Communications (OCOMM) are transitioning to Agency level, or enterprise, contracts for multimedia and technical communications services. The two organizations are consolidating services currently provided by individual contractors at separate field centers with the dual intent of finding synergies and reducing duplication. Although the services themselves are dissimilar, the service solutions and skills required to perform the contracted tasks are similar. All the services employ or pertain to information technology (IT) and other electronic equipment. Further, creating and delivering multimedia and technical communications requires the use of the internet, digital platforms, and IT.
1.3.2 Contract Goals and Objectives:
The intent of the eMITS contract is to support customer organizations through a single provider of digital multimedia and technical communications services. The transformation and migration of services to Agency contracts is expected to last at three to four years. As part of this effort, the eMITS contract will eventually provide all services in this Performance Work Statement (PWS) for the OCIO and OCOMM organizations, including all Center and Agency level customers. Not all the services of eMITS will be provided to all customers on the start date of the contract.
Initially, a small number of Centers will begin receiving the services in the eMITS PWS at contract start, with other Centers and customers migrating their requirements at later dates. The eMITS contractor will facilitate this effort and effectively and efficiently provide eMITS services to all customers according to schedule. The eMITS contractor will also provide cost effective services from both onsite and remote support approaches to best provide the required eMITS services to all customers
1.4 Guiding Directives
The guiding documents for this surveillance effort include the Contract PWS, performance standards, Performance Evaluation Plan, Work Package/Task Order requirements as specified in issued Work Packages/Task Orders, and deliverable requirements. The contract identifies general requirements and the Work Packages/Task Orders identify specific objectives or results desired for each issued Work Package/Task Order requirement.
1.5 References and Applicable Documents
All applicable references and documents are listed in the applicable and document section of the contract.
2.0 SURVEILLANCE STRATEGY AND APPROACH
2.1 General
There exists a wide-ranging spectrum associated with surveillance, ranging from oversight to insight. The strategy and approach to surveillance by NASA for the eMITS contract, as detailed in this plan, is one that concentrates primarily on insight as opposed to oversight.
However, some limited areas do exist where oversight is conducted either via NASA exercising approval authority on contract-deliverable documentation in critical areas of performance or participation in the Contractor's configuration management process. Regardless, the Government reserves the right to initiate additional surveillance activities (insight or oversight) on an ‘as-needed’ basis, based upon circumstances and data collected (adverse trends, negative data points, lack of corrective action, etc.) via the surveillance activities defined in this plan. As applicable, any and all oversight activities would be communicated and coordinated with the Contractor and subsequently documented within this QASP.
The level of risk and the impact of failure are major determinants in helping define the type of surveillance to be conducted. Clearly, if the impact of failure is minor and the level of risk is low, only a small amount of insight-driven surveillance would normally be needed. Conversely, if the impact of failure could be significant and the level of risk is high, more extensive surveillance (including possible oversight surveillance) is warranted.
This insight-based approach to surveillance will utilize and leverage the Contractor's Quality Management System (QMS). Definitions, requirements, and specifications contained in the contract, PWS, and referenced documents will establish a baseline for the surveillance activities.
This insight-based approach will seek objective evidence and data that the Contractor's program and processes are functioning as intended in accordance with the terms of the contract. The focus will be on trusting the Contractor's QMS, and verifying that the Contractor is performing according to the policies, procedures, plans, and processes defined by their QMS.
NASA will strive to use an insight-driven surveillance approach throughout the performance of this contract. The overall surveillance goal will be to obtain objective evidence and data that enable the Government to determine whether the Contractor's program and processes are functioning as intended in accordance with the terms of the contract. The focus will be on prevention rather than detection, i.e., emphasizing controlled processes and methods of operation, as opposed to relying solely upon inspection and test to identify problems.
This insight-based approach to surveillance as applied to the contract will result in lower levels of Government intervention, thus allowing the Contractor to assume full accountability and responsibility for integrity of processes. Although less obtrusive than oversight, this insight-based approach to surveillance continues to provide the Government with visibility into the Contractor's programmatic processes, technical processes, progress, and issues at all levels.
As required by FAR 42.1502 and GPR 5100.2, Supplier Performance Evaluations, the Contracting Officer (CO), in collaboration with the Contracting Officer’s Representative (COR) and Deputy COR, will annually complete a Contractor Performance Assessment Reporting System (CPARS) evaluation, which will also be reviewed by the Contractor, and become a part of the Past Performance Information Retrieval System (PPIRS).
2.2 Surveillance Activity Limitations and Guidance
2.2.1 General
Surveillance of the eMITS contract, will be conducted on a non-interference basis and in a manner that will not unduly delay work being performed by the Contractor.
2.2.2 Insight
Insight is an assurance process that uses performance requirements and, if definable, performance metrics to ensure process capability, product quality and end-item effectiveness.
Insight relies on gathering a minimum set of product or process data that provides adequate visibility into the integrity of the product or process. The data may be acquired from Contractor records, usually in a non-intrusive parallel method.
Insight as applied to this contract will result in lower levels of Government surveillance and allow the Contractor to assume increased responsibility and accountability for the integrity of processes. Insight will rely heavily on evaluating planned contract deliverables, performance standards, and existing Contractor procedures and working documents, if available.
2.2.3 Oversight
Oversight as applied to this contract will result in higher levels of Government surveillance. The Government will gather information pertaining to the Contractor’s process through on-site involvement and/or inspection in the process and will monitor the process itself. The Government’s involvement in the Contractor’s performance, through oversight, will be determined necessary by the COR or Deputy COR.
2.3 Surveillance Organization and Resources
2.3.1 General
The activities detailed in this plan will be supported and performed by a group of individuals, many with differing levels of responsibilities, but all maintaining a level of consistency in terms of the surveillance strategy, approach, and activities in general. Specific entities supporting the eMITS contract surveillance activities include the identified NASA personnel; Contractor QA Department personnel (including their subcontractors); and contractor support services and delegated agency personnel, if applicable. Each of these entities and their associated responsibilities/input to the surveillance activities on the eMITS contract are described in the following paragraphs.
2.3.2 Surveillance Team
2.3.2.1 General Organization and Responsibilities
General organization and responsibilities of the Surveillance Team are as follows:
a. The surveillance team will be composed of key Government personnel. All surveillance activities will be implemented using NASA and NASA support-contractor personnel, a delegated agency (e.g., Defense Contract Management Agency (DCMA)), and/or a surveillance support contractor(s). The surveillance team may be composed of:
1. NASA Information Technology Procurement Office Personnel (i.e., CO, Contract
Specialist)
2. NASA Personnel (i.e., COR, Deputy COR, Task Monitor(s) and Technical
Monitor(s), and Resource/Financial Analyst(s));
3. NASA Safety, Health and Security Personnel (both physical and Information
Technology (IT) Security);
4. NASA Property Administrator Personnel;
5. eMITS Performance Evaluation Board
b. The team’s primary purpose will be to provide direction for contract surveillance activities and to serve as the Government’s focal point in reviewing and evaluating overall Contractor performance under the eMITS contract. The team will obtain information from various sources, including deliverable Contractor documents, communications with the Contractor, and reports by other personnel or representatives (e.g., Task Monitor(s) and Technical Monitor(s); Safety, Health, or Security personnel;
DCMA) who interact with the Contractor.
The NASA OCIO and OCOMM has the responsibility for independently assuring that the Contractor's operations meet NASA's contract performance requirements and enable success. As such, surveillance team members will have open access to all areas in which this contract is being performed and will interface directly with their Contractor counterparts. Government expertise with regards to the eMITS contract may be applied in the form of technical consultants and/or providing assistance at working group meetings, design/development and specification reviews, review board meetings, surveys, audits, program reviews, and as in-plant representatives. The team will document problems, concerns and issues, and take note of Contractor accomplishments.
They will collect performance metric data, where applicable, and will participate in Contractor review meetings, such as those described herein. Information will flow from individual team members through the COR or Deputy COR to surveillance team representatives, who will present issues and achievements at surveillance team meetings.
Information gained from these formal and informal exchanges of ideas and collection of data will be compiled and evaluated as a continuous measure of contract performance.
c. All available information will be evaluated, and any action by NASA will be determined based upon the scope and magnitude of any particular issue or problem. The surveillance team chairperson, the COR or Deputy COR, will formally notify the CO of situations where it is perceived that the Contractor has failed to take prudent corrective or preventive action, of situations that increase risk, or of findings of continued contractual non-compliance.
2.3.2.2 eMITS Contracting Officer eMITS CO responsibilities are as follows:
a. The CO is responsible for ensuring performance of all necessary actions for effective contracting, ensuring compliance with the terms of the contract, issuing task orders, and safeguarding the interests of the United States in its contractual relationships. Within the surveillance area the CO takes inputs from the Program/Project managers, COR, Deputy COR, Safety, Health, Office of Safety and Mission Assurance, eMITS Performance Evaluation Board, and others to establish the detailed surveillance requirements to be performed by NASA personnel, delegated to another Federal agency via a NASA Letter of Delegation, or to be performed under contract by a surveillance support Contractor.
The CO will also assure that the Contractor receives impartial, fair, and equitable treatment under this contract. The CO is ultimately responsible for the final determination of the adequacy of the contractor’s performance.
b. The CO will complete an annual Contractor performance assessment report using the
CPARS that will also be reviewed by the Contractor and become a part of the PPIRS.
2.3.2.3 eMITS Contracting Officer’s Representative eMITS COR and Deputy COR responsibilities are as follows:
a. The COR and Deputy COR are designated in writing by the CO to act as his or her authorized technical representative to assist in administering the contract. The COR and Deputy COR monitor the technical work performed under the contract, evaluates Contractor performance, serves as the primary interface for the Contractor and the CO for all technical matters, reports on contract status to Program/Project Management, and recommends corrective action when necessary. The COR and Deputy COR are not empowered to make any contractual commitments, authorize any contractual changes on the Government’s behalf, or in any way direct the Contractor to operate in conflict with the contract terms and conditions. Any changes that the Contractor deems may affect the contract or task order value, terms, or conditions shall be referred to the CO for action.
The COR and Deputy COR’s limitations of authority are contained in the NASA Form 1634, COR Delegation.
b. The COR and Deputy COR jointly assume full responsibility for directing the surveillance activities identified in this plan. The COR and Deputy COR also trains Task Monitor(s) and Technical Monitor(s) on evaluation procedures for evaluating contractor performance.
c. The COR and Deputy COR will assist the CO in the completion of the contract’s annual performance assessment report using CPARS.
2.3.2.4 Task Monitors
Task Monitors are individuals appointed by the COR or Deputy COR for developing Work Packages/Task Orders, reviewing the Contractor’s Task Plans and Work Package/Task Order reports, and monitoring Work Package/Task Order performance. Work Packages/Task Orders will include quantitative metrics, as appropriate. Task Monitors provide detailed technical oversight of the Contractor’s performance and report findings to the COR and Deputy COR in a timely, complete and impartial fashion. While the Task Monitors may serve as a direct conduit to provide Government guidance and feedback to the Contractor on technical matters, the Task Monitors are not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf.
2.3.2.5 Technical Monitors
Technical Monitors are individuals appointed by the COR or Deputy COR for the oversight of specific technical work on the contract. Technical Monitors provide detailed technical oversight of the Contractor’s performance and report findings to the COR or Deputy COR in a timely, complete and impartial fashion. While the Technical Monitors may serve as a direct conduit to provide Government guidance and feedback to the Contractor on technical matters, the Technical Monitors are not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf.
2.3.2.6 eMITS Contractor Quality Assurance
It is expected that the Contractor will maintain a QA lead as part of its QMS. It is expected that the QA lead will perform QA-related activities for the eMITS contract efforts. The Contractor's QA lead will serve a vital role in the success of the surveillance efforts detailed in this plan. In particular, it is expected that the Contractor will task its QA lead to serve as a focal point for the Government in several areas including but not limited to provision of and access to all requested insight data/lifecycle-related assets and artifacts as they pertain to the insight areas described in this plan, and all QA-related activities conducted by this group.
The Government expects that as necessary and applicable, the QA lead may direct the Government to other groups/individuals supporting the eMITS contract effort in order to obtain requested insight data. These groups/individuals may include the Contractor's Program/Business Management office and/or representatives, discipline engineers, Configuration Management representatives, etc.
2.3.2.7 eMITS Performance Evaluation Board
The eMITS Performance Evaluation Board (PEB) is made up of voting members appointed by the Fee Determination Official (FDO) to evaluate the Contractor's performance according to the standards and criteria stated in the eMITS Performance Evaluation Plan. The PEB will submit an award fee letter to the FDO for signature, which addresses the PEB's findings and recommendations for each award-fee evaluation period.
2.4 Forms of Surveillance
2.4.1 General
Surveillance on the eMITS contract will be performed using any of the primary surveillance forms applied to the insight areas described in Section 3 of this document, during applicable stages of the contract. These primary forms of surveillance are described below.
2.4.2 Communications
Communications is a general surveillance activity. Communications is a two-way process and includes both written and oral communication. Examples of written communications activities that may be used in conducting surveillance include:
a. Exchanges from the Contractor to the Government of plans, procedures, quality records, reports, etc., and/or provision of read-only access to repositories which retain these items.
b. Exchanges from the Government to Contractor of letters, reports, review results, etc.
c. Ad hoc information submitted by the COR or Deputy COR and/or Task
Monitor(s) and Technical Monitor(s) to the CO related to the Contractor’s electronic mail.
Examples of oral communications activities that may be used in conducting include:
a. Informal telephone calls, teleconferences.
b. Informal verbal inquiries, discussions, engineering consultations.
c. Working group meetings, IPT participation, technical/status briefings, progress reviews, technical information meetings, and formal and informal reviews.
d. Informal discussions.
2.4.3 Management Reviews and Reporting
Examples of management review and reporting activities that may be used in conducting surveillance include:
a. Formal, process, and progress reviews
b. Review of contract deliverables
c. Documentation of problems, issues and concerns
d. Data collection reporting
e. Review of task order deliverables, products, and documentation
2.4.4 Participation in Contractor Configuration Management Processes
NASA's Configuration Control Boards’ (CCB)s’, which includes OCSS and the local NASA Centers, approvals are required for changes that affect eMITS contract capabilities and external interfaces. The Contractor is required to facilitate the applicable CCBs’ insight into the contractor configuration management process. This process will be accomplished through the Enterprise participation in the Contractor configuration management process and insight into Contractor configuration controlled documentation. NASA personnel monitor performance and activities with metrics. These metrics are used to assess contractor performance, as well as, to ensure mission customer requirements are met.
3. SURVEILLANCE ACTIVITIES
3.1 General
There exist specific insight areas that the Government and the Contractor shall concentrate on during applicable stages of contract performance. Each of these insight areas and the Government’s expectations for these areas are described in Table 1.
Table 1. Surveillance Insight Areas
Area of Risk Identified Impact to Government Surveillance Team Activity
System Maintenance and Availability
System downtime or loss of functionality could result in loss of service to the user community
Review Contractor-developed maintenance plan for improvements. Review data and trouble data. Review corrective action performance.
Information Technology (IT) Security
Computer Security: Potential corruption and loss of data;
disruption of schedule
Annual review of IT security plans and contingency test results and controls.
Review compliance with policies, firewalls, protection software, vulnerability scans and external systems.
Configuration Management (CM) Documentation
Uncontrolled models, hardware, software, or documents could lead to erroneous results, incompatible interfaces, wasted resources, and/or mission failure
Periodically sample current documentation, and active management documents to verify compliance with the Contractor’s CM System and CM Plan.
Property Management, Control, and Maintenance
Loss of or damage to equipment;
potential schedule impact
Review Contractor property management techniques, compliance with policies, and record-keeping.
Safety Loss of work-time or equipment, with schedule or cost impact
Evaluate compliance with the Contractor's Safety and Health Plan and safety requirements.
Technical Documentation and Control
Loss of knowledge of processes and results
Periodically sample documents (review for accuracy) and ensure they are under CM control.
Process Controls Degradation of work products;
increase in safety risk; potential schedule impact
Periodically monitor the Contractor’s adherence to key processes and their internal audit schedules/results.
Continuous Risk Management Technical, cost, schedule, safety, and program success
Periodically ensure that the Contractor is performing a Continuous Risk Management program that identifies, analyzes, tracks, mitigates, controls and reports on related risks.
Quality Management Technical, cost, schedule, safety, and program success
Monitor the Contractor’s internal and external audits for compliance with the Contractor’s established Quality Management Systems, including CMMI® or ANSI/ISO/ASQ Q9001:2000 or AS 9100.
Area of Risk Identified Impact to Government Surveillance Team Activity Quality of Work Force a. Inability to fill positions and meet commitments on scheduled deliverables or science results,
a. Monitor time required to fill positions, and evaluate Contractor efforts and approaches used to fill vacancies.
including NASA Performance Metrics
b. Additional cost resulting from decreased productivity of other staff reliant on unfilled positions
c. Lack of expertise or inadequate experience in key areas
d. Delayed data delivery and/or poor data quality
b. Assess Contractor efforts to train staff in areas of required expertise.
c. Evaluate Contractor technical performance
d. Monitor progress and timeliness and evaluate the quality of data received.
Quality of Workmanship (End-Items)
a. Inability to meet commitments of scheduled deliverables
b. Additional cost and time resulting from rework, nonconforming, latent defects
a. Monitor and track schedules and delivery due dates.
b. Conduct/witness testing and inspections, when necessary. Ensure end-item deliverables conform prior to acceptance.
Schedule Services or products not provided in a timely manner can impact project schedule and cost
Monitor progress via management reviews and reporting.
Cost and Funding Cost Overrun:
a. Inability to implement contract requirements within negotiated costs may lead to erosion of technical performance, delay, or deletion of work
b. Reduction of work due to funding limitations/fluctuations
Monitor and track costs incurred through the NASA Form 533, NASA Contractor Financial Management Report submitted on a monthly and quarterly basis
Organizational Conflicts of Interest (OCI) Avoidance
Potential restrictions, ineligible to perform, and/or unfair competitive advantage on future work
Monitor submittal, enforcement and compliance with the Contractor’s OCI Avoidance Plan.
Environmental Environmental damage to local and remote sites
Conduct periodic inspections to ensure compliance with environmental requirements.
Export Control Violation of International Traffic in Arms Regulations (ITAR)
Ensure the Contractor has Technical Assistance Agreements as required by the NASA Export Control Program.
TBD (as designated on individual Work Packages/Task Orders)
TBD (as designated on individual Work Packages/Task Orders)
TBD (as designated on individual Work Packages/Task Orders)
3.2 Surveillance Team Activities
The surveillance team members will participate in review meetings, if applicable. They will provide support, as necessary, with the development and approval of technical requirements;
flow-down of requirements; and with design, development, production and test activities. They will also maintain insight into the Contractor’s compliance with relevant deliverables submitted under the contract and services performed. When the Government has concerns regarding Contractor performance, surveillance team members may conduct independent audits of the Contractor’s activities, processes, products, documentation and data, in order to provide assurance that the program is being implemented according to all requirements and specifications. These audits will normally be conducted with advance notification and coordinated with the Contractor. However, the Government reserves the right to conduct unscheduled audits when evidence indicates that Contractor performance is deficient.
The following selected surveillance team activities will be performed by various surveillance team members during applicable stages of contract performance:
3.2.1 Work Area/Floor Checks
The surveillance team members will make a physical inspection of the Contractor's onsite work area semi-annually. In addition, the COR or Deputy COR may make informal inspections, as required. These inspections are made to assure compliance with NASA and NASA Centers’ and Facilities’ regulations and procedures regarding:
a. All onsite Contractor employees have a NASA Personal Identify Verification (PIV) card
(badge).
b. The total number of Contractor employees provided onsite office space.
c. The Contractor’s office space is physically separated from the Government’s workspace and is properly identified by a sign with the contractor employee & company’s name clearly displayed.
d. The names and locations (buildings/room numbers) of the Contractor employees match their monthly onsite Personal Identity Verification (PIV) Report.
e. The Contractor knows who the building's Facilities Operation Manager (FOM) is, and what his/her functions are.
f. The Contractor is familiar with the building emergency evacuation procedures.
g. The Contractor employees are aware that work area checks may be conducted at any time.
h. The Contractor is familiar with NASA and NASA Centers’ and Facilties’ Policy Directives and Procedural Requirements as it pertains to ANSI/ISO/ASQ Q9001:2000 or
AS 9100 governing onsite performance. These procedures can be accessed via the following NASA Online Directive Information System Website:
http://nodis3.gsfc.nasa.gov/.
i. The Contractor is aware of the appropriate protection procedures for handling
Government planning data and other Contractor confidential or financial data.
j. The Contractor employees are aware that the use of Government telephones is for official business only.
k. The Contractor employees are following the proper Checkout Procedures when leaving
NASA Centers and Facilities (e.g., returning PIV card (badges), Government property, library books). The PIV data forms will be checked against the monthly Onsite Reports to identify exiting employees.
l. The Contractor employees are aware of the NASA and NASA Centers’ and Facilities’ IT
Security compliance requirements.
m. The Contractor employees are aware of the Contractor’s OCI Avoidance Plan and the appropriate Non-Disclosures.
In addition to checking conformance with NASA and NASA Centers’ and Facilities’ regulations listed above, the COR or Deputy COR may make periodic checks of the Contractor's workspace to assess adequacy of facilities, equipment, and materials.
3.2.2 Work Review and Performance Monitoring
The COR or Deputy COR, with the assistance of the Task Monitor(s) and Technical Monitor(s), will perform the following functions to evaluate the Contractor's performance:
a. Reviews individual Work Packages/Task Orders with the Task Monitors to assure that each Work Package/Task Order is technically within the scope of the contract and its personnel requirements and schedule are within the Contractor's capabilities. Reviews Contractor Task Plans to ensure that performance estimates are acceptable and that all milestones and deliverables have been identified.
b. Reviews specific PWS areas with the Technical Monitor(s) to assure that work being performed and deliverables are in accordance with the technical requirements of the PWS and timely.
c. Reviews the Contractor's monthly Progress Report for accuracy and completeness.
Consult with the Task Monitor(s) and Technical Monitor(s), as necessary, to assess the fidelity of reports.
d. Meets monthly, or more often if required, with the Contractor's Program Manager to discuss overall contract management and performance, review staffing and schedule issues, and review cost related issues.
e. Certifies the Contractor’s invoices for payment in accordance with NASA procedures.
f. Perform QA inspections and QA witnessing/monitoring of tests.
g. In the event of a discrepancy in the Contractor's performance, the COR or Deputy COR promptly notifies both the CO and the Contractor's Program Manager and arranges a meeting to rectify the situation.
h. Assesses the Contractor’s overall contract performance against the factors and criteria established in the contract’s Performance Evaluation Plan.
3.2.3 Government Property Administration
The COR or Deputy COR will carry out the following functions.
a. Review Contractor's request to purchase controlled property and facilities and make recommendations to the CO.
b. Validate that no property or facilities are being acquired without the CO's prior approval.
c. Review and approve Contractor's requests for acquisitions of supplies from NASA Centers’ and Facilities’ store stocks.
d. Validate that all Installation-Accountable Government Property (IAGP) is being properly utilized and maintained.
e. Conduct periodic inspection of equipment and its location, compared to the data on the property records.
f. Validate that all existing and new equipment is properly tagged.
g. Validate that Government property is made available in accordance with the terms of the contract.
h. Validate that the Contractor is maintaining records for all offsite Government-Furnished Property (GFP).
i. Review all requests to move IAGP to an offsite location for a period longer than 30 days ensure the required documentation has been properly completed and all required COR or Deputy COR/CO signatures obtained on the GSFC 20-4, Transfer/Shipping Request.
3.2.4 Performance Monitoring
The COR or Deputy COR will ensure that employer–employee relationships do not occur between Government and Contractor personnel. This is achieved if the following is adhered to:
a. Only the Contractor interviews prospective employees.
b. Only the Contractor’s Program Manager assigns work directly to the employees.
c. Only the Contractor approves timecards and absences.
d. Government personnel do not interfere with the Contractor regarding personnel and administrative prerogatives.
3.2.5 Safety
The responsibility for meeting all safety requirements rests with the Contractor. Surveillance team safety engineers and technical personnel will review Contractor-generated hazard analyses, safety compliance data packages or other safety-related documentation, as appropriate, to help ensure all safety requirements have been satisfied. Surveillance team personnel will also maintain insight into the Contractor’s safety activities through the review of the Contractor’s submitted Safety and Health Plan, and updates, as required by this contract.
File details come from the government source that posted it. Updated .