Tab 4 4 SOW Revised.pdf
PDF 153 KB Posted
- Attached to
- Wallops Flight Facility Chlorinator Upgrade Federal contract opportunity
- Solicitation number
- 80NSSC843390Q
About this file
This statement of work outlines requirements for a chlorinator upgrade project for two drinking water systems operated by NASA's Wallops Flight Facility. The project involves replacing chlorination equipment at the Main Base and Island systems to improve disinfection and monitoring. Key requirements include installing new duplex chlorine dosing systems, bulk chemical storage, and secondary containment. Training and commissioning are also specified. The contractor must be located within an hour of Wallops Flight Facility. The performance period is from October 2023 to June 2024. The related federal contract opportunity is solicitation number 80NSSC843390Q for the Wallops Flight Facility Chlorinator Upgrade issued by the National Aeronautics and Space Administration Shared Services Center.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Tab 4 SOW Revised 2.pdf | ||
| Tab 12 RFQ 80NSSC843390Q Revised 2.pdf | ||
| Tab 12 RFQ 80NSSC843390Q Revised SOW.pdf | ||
| Chlorinator Site Visit.pdf | ||
| Tab 12 RFQ 80NSSC843390Q.pdf | ||
| chlorination RFI pictures.pdf | ||
| Tab 12 Technical Questions and Answers.pdf | ||
| Tab 12 RFQ 80NSSC843390Q.pdf | ||
| Tab 4 4 SOW.pdf | ||
| Tab 12 RFQ 80NSSC843390Q.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Wallops Flight Facility Chlorinator Upgrade SOW
NASA Wallops Flight Facility 34200 Fulton Street
Wallops Island, Virginia
1.0 STATEMENT OF WORK
Goddard Space Flight Center’s Wallops Flight Facility operates two public drinking water systems. A community waterworks located on the Main Base and a Non‐Transient, Non‐Community water system located on Wallops Island. Both systems utilize liquid sodium hypochlorite for disinfection and are currently operating with a single chlorine injection point to chlorinate raw well water prior to a ground‐ based water storage tank. The water systems are also coupled with extensive fire suppression systems and water age is an operational issue with the current chlorination systems. The current chlorination systems have also experienced several failures and require updating and renovation to eliminate failure points.
NASA is seeking services provide installation and commissioning of equipment for improvements for a public drinking water systems.
The purpose of this project is to upgrade the existing chlorination station and chlorine monitoring and to upgrade the existing chlorination equipment for the Wallops Island drinking water system. The chlorination stations will facilitate the disinfection of water to ensure the delivery of safe drinking water to the public and help reduce the formation of disinfection byproducts through improvements to the chlorine dosing control.
1.1 MAIN BASE CHLORINATION SYSTEM
Include necessary services to provide replacement of chlorination equipment and installation of new chlorine injection station, including all necessary design and permitting for the Wallops Flight Facility
Main Base drinking water system.
Ensure compliance with applicable Virginia Waterworks Regulations and applicable codes and standards.
1.1.1 Replace existing dosing station
Install new Grundfos pre‐engineered duplex dosing skid or equal to include two digital diaphragm dosing pumps with stepper motors, remote start/stop, analog inputs, analog outputs, relay outputs, graphical display, flow control monitoring and switch control panel to replace existing chlorine dosing pump system.
Inspect and secure or replace all upstream and downstream chlorine dosing lines and remove abandoned components.
Connect dosing skid to existing (Johnson Controls) building supervisory control device to provide monitoring, alarming, and control.
Provide flow‐paced chlorine dosing using existing well flowmeter signal.
Replace existing automatic chlorine analyzer system with new Hach Cl‐17s and SC4500 digital controller or equal.
1.1.2 Bulk chemical storage equipment
Install 55 gallon drum chlorine containment system to include portable ramp for material handling and secondary spill containment with integrated scale connected to NASA building automation system and local display.
Replace all existing ductwork, control devices, and wiring. All devices inside the room shall be corrosive resistant.
Install new secondary spill containment with integrated scale with local display for existing zinc orthophosphate system.
1.1.3 Training and Commissioning
Perform witness testing, commissioning, and calibration of the chlorination station components.
Provide training and documentation on the operation and maintenance of the chlorination stations to the designated personnel.
Purchase for government pump service kit for each installed chlorine pump.
1.2 ISLAND CHLORINATION SYSTEM
Include necessary services to provide the following requirements for the Wallops Flight Facility Island drinking water system. Virginia Department of Health permitting process will not be required for the
Wallops Island Chlorination System equipment installation.
1.2.1 Replace existing dosing station
Install new Grundfos pre‐engineered duplex dosing skid or equal to include two digital diaphragm dosing pumps with stepper motors, remote start/stop, analog inputs, analog outputs, relay outputs, graphical display, flow control monitoring and switch control panel to replace existing chlorine dosing pump system.
Connect dosing skid to existing (Johnson Controls) building supervisory control device to provide monitoring, alarming, and control.
Provide programming for flow‐paced chlorine dosing using existing well flowmeter signals.
Inspect and secure or replace all upstream and downstream chlorine dosing lines and remove abandoned components.
1.2.2 Bulk chemical storage equipment
Install 55 gallon drum chlorine containment system to include portable ramp for material handling and secondary spill containment with integrated scale connected to NASA building automation system and local display.
Install new secondary spill containment with integrated scale with local display for existing zinc orthophosphate system.
1.2.3 Training and Commissioning
Perform witness testing, commissioning, and calibration of the chlorination station components.
Provide training and documentation on the operation and maintenance of the chlorination station to the designated personnel.
2.0 Design
Follow all applicable codes and regulations, including AWWA standards, Virginia Department of
Environmental Quality regulations, and NASA standards.
2.1 Deliverables
2.1.1 Preliminary Deliverables
Functional description of alarms, controls, and backups
Cut sheets for all proposed equipment
2.1.2 Installation Deliverables
Systems tested and functional
Close‐out submittals
Punch list 100% complete
Areas cleaned and finished
Commissioning Plan
O&M manuals
Warranty and other documentation
3.0 Reviews and Meetings
3.1.1 Kick‐Off Meeting
The Contractor shall coordinate and conduct a Kick‐off meeting within two (2) weeks following contract award. The contractor should plan for a virtual Kickoff Meeting through Microsoft Teams. The meeting will be used for introductions, a Statement of Work review, development of an action plan to enable completion of tasks to meet the project milestones, and any other general discussions. The Contractor shall submit Kick‐off meeting minutes within two (2) business days following the Kick‐off meeting via the submittal process to include a summary of the discussions and action items.
3.1.2 Training
The contractor shall conduct onsite training to designated personnel for all aspects of system operation, including calibration, and adjustments.
3.1.3 Commissioning closeout meeting
The contractor shall attend a follow up meeting 90 days after operation begins to evaluate system performance in maintaining chlorine residuals in the water distribution system.
4.0 SAFETY AND SECURITY
The Contractor shall submit for approval by the government a safety plan prior to any work conducted.
Contractor shall assure that any job hazards are identified and discussed in a job hazard analysis prior conducting the associated work.
5.0 GEOGRAPHICAL LOCATION REQUIREMENT
This project is in response to regulatory violations with the Virginia Department of Health related to chlorine residual control and is a critical aspect to the functioning of the potable water system.
Contractor must be located within a 1 hour travel distance to Wallops Flight Facility to allow for prompt support during commissioning and warranty periods.
6.0 EXISTING WATER SYSTEM DETAILS
Main Base system Island system
Waterworks Operation Permit Class 5 Community Waterworks Non‐Transient, Non‐Community
Max anticipated daily water demand
60,000 gpd 60,000 gpd
Disinfectant Liquid Sodium hypochlorite (12.5%)
Liquid Sodium hypochlorite (12.5%)
Required free chlorine at entry point
0.29 mg/l 0.17 mg/l
Current Max chlorine delivery rate
90 ml/min 90 ml/min
7.0 PERIOD OF PERFORMANCE 10/01/23– 6/1/24
File details come from the government source that posted it. Updated .