This document is a Past Performance Questionnaire template for the NASA Rechargers solicitation (80KSC026R0022) issued by Kennedy Space Center.

The questionnaire is designed to be distributed by offerors to their previous customers to gather structured feedback on contractor performance. Completed questionnaires must be submitted to NASA contracting officers Hillary P. Heard (hillary.p.heard@NASA.gov) and Ryan M. Miller (ryan.m.miller@NASA.gov) at Kennedy Space Center, Florida 32899, no later than September 14, 2026. The document consists of two sections: Section I, completed by the offeror with contract details (contractor name, project name, contract number, performance period, location, contract value, and customer contact information), and Section II, completed confidentially by the rater with information about work performed and performance ratings.

Raters evaluate contractors on an eight-question scale using ratings of 1 (Unsatisfactory) through 5 (Exceptional), with N/A for inapplicable items. Evaluation criteria include overall project management effectiveness; schedule and performance completion; technical requirement understanding; personnel management and quality workmanship; deliverable completeness; safety compliance; discrepancy resolution and corrective action timeliness; and a yes/no question regarding whether cure notices, show cause letters, or terminations for cause were issued. A final yes/no question asks whether the rater would select the contractor again. Raters are instructed to complete the form as written to ensure consistent evaluation, and completed questionnaires are designated for government use only and will not be disclosed outside the government.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

80KSC026R0022

NASA Rechargers Attachment L-02

Past Performance Questionnaire

KENNEDY SPACE CENTER

NASA/KSC SOLICITATION 80KSC026R0022

ATTACHMENT L-02

PAST PERFORMANCE QUESTIONNAIRE

NASA Kennedy Space Center’s solicitation requires offerors to provide this Past Performance Questionnaire to customers to complete and return to NASA. Past performance raters are requested to submit the completed questionnaires to the contracting officer and contract specialist identified below via e-mail, to arrive not later than September 14, 2026.

Completed questionnaires should be sent to:

Name: Hillary P. Heard Email: hillary.p.heard@NASA.gov Address: NASA John F. Kennedy Space Center

Kennedy Space Center, Florida 32899

Name: Ryan M. Miller Email: ryan.m.miller@NASA.gov Address: NASA John F. Kennedy Space Center

Kennedy Space Center, Florida 32899

Raters are requested to complete the questionnaire forms as written since altered or substituted questionnaires may not adequately address the information NASA will be evaluating.

SECTION I. THIS SECTION TO BE COMPLETED BY THE OFFEROR

Name of Contractor Being Evaluated:

Name of Project and Contract/Order Number:

Period of Contract Performance (dates):

Place of Contract Performance:

Contract Value at Award:

Contract Value at Completion or Current Contract Amount:

Contract Status (Prime or Subcontract?):

Point of Contact: (Rater) Name/Address/Office Phone Number/E-Mail Address:

mailto:hillary.p.heard@NASA.gov mailto:ryan.m.miller@NASA.gov

INTENTIONALLY LEFT BLANK

THIS SECTION TO BE COMPLETED BY THE RATER

(THIS QUESTIONNAIRE, WHEN COMPLETED, WILL NOT BE DISCLOSED TO

ANYONE OUTSIDE THE GOVERNMENT)

Name of Contractor Being Evaluated:

Name of Project and Contract/Order Number:

Period of Contract Performance (dates):

Place of Contract Performance:

Contract Value at Award:

Contract Value at Completion or Current Contract Amount:

Contractor’s Status (Prime or Subcontractor?):

Percentage and Dollar Value of Work Performed by the Contractor:

Dates of Rater’s Involvement in Program/Contract:

Brief Description of Work Performed:

Point of Contact: (Rater) Name/Address/Office Phone Number/E-Mail Address:

RATING DEFINITIONS:

On a scale of 1 to 5, with 1 being unsatisfactory and 5 being exceptional, please rate the contractor on the past performance areas included in this questionnaire. A rating of N/A should be used if the question is not applicable or the answer is unknown. Space is provided for any additional comments raters may want to provide. The definitions associated with the 1 to 5 ratings are provided below:

1. UNSATISFACTORY: Performance does (did) not meet most contractual requirements and recovery is not likely (did not occur). The contractual performance contains (contained) serious problem(s) for which the contractor’s corrective actions appear ineffective (were ineffective).

2. MARGINAL: Performance does (did) not meet some contractual requirements. The contractual performance reflects (reflected) serious problem(s) for which the contractor has not yet identified acceptable corrective actions (did not provide acceptable corrective actions).

3. SATISFACTORY: Performance meets (met) contractual requirements. The contractual performance reflects (reflected) some minor problems. Corrective actions being taken by the contractor appear to be effective (Corrective actions taken were effective).

4. VERY GOOD: Performance meets (met) contractual requirements and exceeds (exceeded) some of the Government’s expectations. The contractual performance reflects (reflected) some minor problems and corrective actions being taken by the contractor appear to be effective (Corrective actions taken were effective).

5. EXCEPTIONAL: Performance meets (met) contractual requirements and exceeds (exceeded) many of the Government’s expectations. The contractual performance reflects (reflected) few minor problems and corrective actions taken by the contractor appear to be highly effective (corrective actions taken were effective).

N/A: Not applicable or rater has not observed performance in this area.

CONTRACTOR’S PERFORMANCE QUESTIONS

1. The effectiveness of the contractor’s overall project management ability (including but not limited to project managers, quality control managers, safety managers, and superintendents); labor (skilled and unskilled workers); equipment; supplies; tools; and financial resources to successfully perform, provide contract deliverables and complete work in a safe and timely manner.

1 2 3 4 5 NA

Comments:

2. The contractor’s ability to complete the project according to the contractor’s provided schedule and within the period of performance.

3. The contractor’s ability to understand and meet customer’s technical requirements.

4. The contractor’s ability to manage personnel to ensure quality workmanship.

5. The contractor’s ability to provide complete deliverables (reports, records) quality records as required.

6. The Contractor’s ability to comply with safety requirements.

7. The Contractor’s ability to resolve discrepancies in a timely and effective manner and the ability to report, investigate, and take corrective actions in a timely and effective manner.

8. Has the contractor’s performance required the issuance of any cure notices, show cause letters, or terminations for cause/default? (Please circle Yes or No).

Yes No

8. Would you select this contractor again?

Yes No

THIS COMPLETED QUESTIONNAIRE WILL NOT BE DISCLOSED TO ANYONE

OUTSIDE THE GOVERNMENT. THANK YOU FOR TAKING THE TIME TO

COMPLETE THIS QUESTIONNAIRE.

80KSC026R0022 Attachment L-02 Past Performance Questionnaire.pdf
Address: NASA John F. Kennedy Space Center
Address: NASA John F. Kennedy Space Center
SECTION I. THIS SECTION TO BE COMPLETED BY THE OFFEROR
THIS SECTION TO BE COMPLETED BY THE RATER
CONTRACTOR’S PERFORMANCE QUESTIONS
THIS COMPLETED QUESTIONNAIRE WILL NOT BE DISCLOSED TO ANYONE OUTSIDE THE GOVERNMENT. THANK YOU FOR TAKING THE TIME TO COMPLETE THIS QUESTIONNAIRE.