Solicitation Amendment 80KSC026R00120001 SF 30.pdf
PDF 144 KB Posted
- Solicitation number
- 80KSC026R0012
About this file
This is Amendment 0001 to a solicitation for a Design-Build Construction Services contract issued by NASA Kennedy Space Center. The amendment addresses pre-proposal Requests for Information (RFIs) and incorporates resulting revisions into the Request for Proposal (RFP) and supporting documents. The contract (80KSC026R0012) is for the NASA Kennedy Space Center Construction and Checkout (STOCC II) program and will be awarded as multiple Indefinite Delivery/Indefinite Quantity (IDIQ) contracts with task orders issued for specific construction projects. The Government intends to reserve three of eight awards for contractors demonstrating experience with mechanical construction (HVAC, plumbing, piping) valued below the Simplified Acquisition Threshold (SAT). Eligibility is limited to Small Business firms (CLINs 0001-0003) and 8(a) firms (CLINs 0004-0006) classified under NAICS code 236220. The selection process is a two-phase evaluation: Phase 1 evaluates technical approach and past performance on an acceptable/unacceptable basis with focus on program management, project planning and execution, and past performance confidence ratings; Phase 2 evaluates price and technical factors for a design-build seed project. Offerors must submit proposals electronically via email to three NASA points of contact by Monday, February 16, 2026, no later than 2:00 PM EST, with the deadline for questions preceding proposal submission by the same date. Up to five 8(a) and three Small Business IDIQ contract awards may be made based on best value determination, with only one offeror selected for the seed project award.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Amendment 0001 addresses the pre-proposal Requests for Information (RFIs) and provides responses in attachment 13. The Request for Proposal (RFP) and Attachment 8 have been updated to incorporate revisions resulting from the submitted RFIs.
Section G - Contract Administration Data
Miscellaneous text in this section has been modified to:
G.1 CONTRACT ADMINISTRATION
a. Following award, this contract will be administered by the NASA/KSC Office of Procurement. The address, telephone number, and email of the Contracting Officer are:
National Aeronautics Space Administration
Office of Procurement
John F. Kennedy Space Center
Kennedy Space Center, 32899
Phone: (321) 867-5294
Email: Aaron.L.Kelley@nasa.gov
b. The Contracting Officer is the only person authorized to issue Task Orders, approve changes or modify any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract, the authority remains solely with the Contracting Officer. In the event the Contractor effects any change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in cost incurred as a result thereof.
c. Contractual problems, of any nature, which might occur during the performance of the contract must be handled in accordance with very specific public laws and regulations (e.g. Federal Acquisition Regulation), and must be referred to the Contracting Officer for resolution. Therefore, the Contractor is directed to submit all such contractual problems to the immediate attention of the Contracting Officer.
d. Any request for contract changes/modifications shall be submitted to the Contracting Officer.
e. All correspondence concerning this contract, such as requests for information, explanation of terms, and contract interpretations, shall be submitted to the Contracting Officer.
G.2 SUBMISSION OF VOUCHERS/INVOICES FOR PAYMENT (NFS 1852.232-80) (APR 2018)
(a) The designated payment office is the NASA Shared Services Center (NSSC) located at FMD Accounts Payable, Bldg. 1111, Jerry Hlass Road, Stennis Space Center, MS 39529.
80KSC026R00120001
(b) Except for classified vouchers, the Contractor shall submit all vouchers and invoices using the steps described at NSSC's Vendor Payment information web site at: . https://www.nssc.nasa.gov/vendorpayment Please contact the NSSC Customer Contact Center at 1-877-NSSC123 (1-877-677-2123) with any additional questions or comments.
(c) Payment requests.
(1) The payment periods are stipulated in the payment clause(s) contained in this contract.
(2) Vouchers submitted under cost-type contracts and invoices submitted under fixed-price contracts shall include the items delineated in FAR 32.905(b) supported by relevant back-up documentation. Back-up documentation shall include at a minimum, the following information:
(i) Vouchers.
(A) Breakdown of billed labor costs and associated contractor generated supporting documentation for billed direct labor costs to include rates used and number of hours incurred.
(B) Breakdown of billed other direct costs (ODCs) and associated contractor generated supporting documentation for billed ODCs. (C) Indirect rate(s) used to calculate the amount of billed indirect expenses.
(D) Progress reports, as required.
(ii) Invoices.
(A) Description of goods and services delivered as part of the contract's terms and conditions, including the dates of delivery/performance.
(B) Progress reports, as required.
(C) Date goods and services were performed.
(iii) Fee vouchers.
(A) Listing of all provisionally-billed fee by period or date earned since contract award.
(B) A reconciliation of all billed and earned fee.
(C) A clear explanation of the fee calculations.
(d) Non-electronic payment requests. The Contractor may submit a non-electronic voucher/invoice using the steps for non-electronic payment requests described at , when any of https://www.nssc.nasa.gov/vendorpayment the following conditions are met:
(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor.
(2) The contract includes provisions allowing the contractor to submit vouchers or invoices using the steps for non-electronic payment requests. In such instances the Contractor agrees to submit non-electronic payment requests using the method or methods specified in Section G of the contract.
80KSC026R00120001
https://www.nssc.nasa.gov/vendorpayment https://www.nssc.nasa.gov/vendorpayment
(e) Improper vouchers/invoices. The NSSC Payment Office will notify the contractor of any apparent error, defect, or impropriety in a voucher/invoices within seven calendar days of receipt by the NSSC Payment Office.
Inquiries regarding requests for payment should be directed to the NSSC as specified in paragraph (b) of this section.
(f) Other payment clauses. In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payment requests.
(g) In the event that amounts are withheld from payment in accordance with provisions of this contract, a separate payment request for the amount withheld will be required before payment for that amount may be made.
(End of clause)
G.3 CONSTRUCTION PROGRESS PAYMENTS
In compliance with FAR Clause 52.232-5, Payments Under Fixed-Price Construction Contracts, the Contractor shall submit a breakdown using the items, major parts, and components that were approved by the Contracting Officer's Technical Representative (COR) for the approved schedule of construction (e.g. Bar Chart). The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on percentages of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer. The Contracting Officer authorize material payments only for materials that are delivered to the site. MAY SUBMIT
PROGRESS PAYMENTS IN THE FORMAT IDENTIFIED IN SECTION J - ATTACHMENT 5.
G.4 LIST OF GOVERNMENT PROPERTY FURNISHED PURSUANT TO FAR 52.245-1 (NFS
1852.245-76) (JAN 2011)
For performance of work under this contract, the Government will make available Government property identified below or in Attachment * of this contract on a no charge-for-use basis pursuant to the clause at FAR 52.245-1, Government Property, as incorporated in this contract. The Contractor shall use this property in the performance of this contract at Kennedy Space Center and at other location(s) as may be approved by the Contracting Officer. Under FAR 52.245-1, the Contractor is accountable for the identified property.
(End of clause)
* (Future Task Orders shall identify if Government Furnished Property will be provided.)
G.5 OCCUPANCY MANAGEMENT REQUIREMENTS (NFS 1852.245-82) (SEP 2017)
(a) In addition to the requirements of the clause at FAR 52.245-1, Government Property, as included in this contract, the Contractor shall comply with the following in performance of work in and around Government real property:
(1) NPD 8800.14, Policy for Real Estate Management.
(2) NPR 8831.2, Facilities Maintenance and Operations Management.
(b) The Contractor shall obtain the written approval of the Contracting Officer before installing or removing Contractor-owned property onto or into any Government real property or when movement of Contractor-owned property may damage or destroy Government-owned property. The Contractor shall restore damaged property to its original condition at the Contractor's expense.
(c) The Contractor shall not acquire, construct or install any fixed improvement or structural alterations in Government buildings or other real property without the advance, written approval of the Contracting Officer.
Fixed improvement or structural alterations, as used herein, means any alteration or improvement in the nature of the building or other real property that, after completion, cannot be removed without substantial loss of value or damage to the premises. Title to such property shall vest in the Government.
(d) The Contractor shall report any real property or any portion thereof when it is no longer required for performance under the contract, as directed by the Contracting Officer.
(End of clause)
G.6 REAL PROPERTY MANAGEMENT REQUIREMENTS (NFS 1852.245-83) (JAN 2011)
(a) In addition to the requirements of the FAR Government Property Clause incorporated in this contract (FAR 52.245-1), the Contractor shall comply with the following in performance of any maintenance, construction, modification, demolition, or management activities of any Government real property:
(1) NPD 8800.14, Policy for Real Estate Management.
(2) NPR 8831.2, Facilities Maintenance and Operations Management.
(b) Within 30 calendar days following award, the Contractor shall provide a plan for maintenance of Government real property provided for use under this contract. The Contractor's maintenance program shall enable the identification, disclosure, and performance of normal and routine preventative maintenance and repair. The Contractor shall disclose and report to the Contracting Officer the need for replacement and/or capital rehabilitation. Upon acceptance by the Contracting Officer, the program shall become a requirement under this contract.
(c) Title to parts replaced by the Contractor in carrying out its normal maintenance obligations shall pass to and vest in the Government upon completion of their installation in the facilities. The Contractor shall keep the property free and clear of all liens and encumbrances.
(d) The Contractor shall keep records of all work done to real property, including plans, drawings, charts, warranties, and manuals. Records shall be complete and current. Record of all transactions shall be auditable.
The Government shall have access to these records at all reasonable times, for the purposes of reviewing, inspecting, and evaluating the Contractor's real property management effectiveness. When real property is disposed of under this contract, the Contractor shall deliver the related records to the Government.
(e) The Contracting Officer may direct the Contractor in writing to reduce the work required by the maintenance program authorized in paragraph (b) of this clause at any time.
(End of clause)
G.7 CONTRACTOR'S CONTRACT ADMINISTRATION
To Be Completed By The Contractor:
Name and Title: _____________________________________
Responsible Office: __________________________________
Address: ___________________________________________
Telephone Number ___________________________________
Email: _____________________________________________
Cage Code: _________________________________________
Unique Entity Identifier (UEI): _______________________________________
Tax Identification Number: _____________________________
INDIVIDUAL(S) AUTHORIZED TO NEGOTIATE OR DISCUSS PROPOSALS
Name of Primary:_____________________ Name of Alternate: __________________
Address: ____________________________ Address: __________________________
Telephone #: _________________________Telephone #: _______________________
Alternate #:__________________________ Alternate #: ________________________
Fax No: ____________________________ Fax No: ___________________________
Email:______________________________ Email: ____________________________
Section J - List of Attachments
The following attachments were added:
Attachment 13 - Pre-Proposal Questions and Answers_Phase 1 Attachment 8 - Proposal Submission Checklist
The following attachments were deleted:
Attachment 8 Proposal Submission Checklist
Section L - Instructions, Conditions, & Notices to Offerors or Quoters
Miscellaneous text in this section has been modified to:
L.1 COMMUNICATIONS REGARDING SOLICITATION
(1) Questions or comments regarding this solicitation must be submitted in writing via email using the format included in Section J, Attachment 7 and be directed to the following Government POC's:
National Aeronautics Space Administration
Office of Procurement, Kennedy Space Center, FL 32988
Aaron.L.Kelley@nasa.gov
Benjamin.P.Crafton@nasa.gov
Jacqueline.A.Brooks@nasa.gov
Oral questions will not be answered due to the possibility of misunderstanding or misinterpretation.
Questions regarding this solicitation shall be submitted via e-mail to the Government Representatives by Monday, February 16, 2026 no later than 2:00PM EST.
(2) Questions or comments should be submitted in accordance with above to allow for analysis and dissemination of responses. Late questions or comments are not guaranteed a response prior to the proposal due date. The Contracting Officer will issue a written amendment to this solicitation to answer questions. Offerors are ENCOURAGED to submit questions the last date for questions.prior to
L.2 PROPOSAL PAGE LIMITATIONS (NFS 1852.215-81)(APR 2015)
(a) The following page limitations are established for each portion of the proposal submitted in response to this solicitation.
VOLUME TITLE COPIES REQUIRED PAGE LIMITATION
Volume I Administrative 1 Unlimited
Volume II Factor 1 - Technical Approach
1 25 Pages
Volume III Factor 2 - Past Performance
1 25 Pages
(b) A page is defined as one side of a sheet, 8 1/2" x 11", with at least one inch margins on all sides, using not smaller than 12 point type. Foldouts count as an equivalent number of 8 1/2" x 11" pages. The metric standard format most closely approximating the described standard 8 1/2" x 11" size may also be used. Other limitations /instructions identified as follows: N/A.
(c) Identify any exclusions to the page limits that are excluded from the page counts specified in paragraph (a) of this provision (e.g. title pages, table of contents) as follows: Table of contents, cover page, and title page. In addition, the Cost section of your proposal is not page limited. However, this section is to be strictly limited to cost and price information. Information that can be construed as belonging in one of the other sections of the proposal will be so construed and counted against that section's page limitation.
(d) If final revisions are requested, separate page limitations will be specified in the Government's request for that submission.
(e) Pages submitted in excess of the limitations specified in this provision will not be evaluated by the Government and will be returned to the offeror.
(End of provision)
L.3 ELECTRONIC SUBMISSION OF OFFERS
Offerors are required to submit electronic offers in response to this solicitation. Email is the only acceptable means of submission. Proposals sent by United States mail, commercial package delivery, hand delivery or facsimile will not be accepted. The electronic offer must arrive at Aaron.L.Kelley@nasa.gov, Benjamin.P.
Crafton@nasa.gov and Jacqueline.A.Brooks@nasa.gov by the time specified in the solicitation. (Note: The NASA/KSC e-mail box is limited to 15MB of unencrypted and 10MB of encrypted data on a PC and 12 MB of unencrypted and 7 MB of encrypted data on a MAC. Additionally, the server may reject files within these size limits due to an array of unforeseen conditions.) Electronic offers that fail to furnish the required representations or information or that rejects any of the terms, conditions, and provisions of the solicitation may be excluded from consideration. Electronic offers must contain the required signatures and must be in a searchable PDF format. The Government reserves the right to make award solely on the electronic offer. However, if requested to do so by the Contracting Officer, the apparent successful offeror agrees to promptly submit the complete original signed offer. If an offer received at the Government facility by electronic data interchange is unreadable to the degree that conformance to the essential requirements of the solicitation cannot be ascertained, the Contracting Officer will immediately notify the offeror that the offer will be rejected unless the offeror provides clear and convincing evidence -
(a) Of the content of the offer as originally submitted;
(b) That the unreadable condition of the offer was caused by the Government software or hardware error, malfunction, or other Government mishandling.
Late proposals will be reviewed in accordance with FAR 15.107(b).
(End of Provision)
L.4 PROPOSAL PREPARATION INSTRUCTIONS
Offerors shall utilize the Proposal Checklist provided in Section J, Attachment 8 to ensure a complete and compliant submission. All proposal files shall be submitted in Adobe Portable Document Format (PDF).
Each volume shall be:
Submitted as a separate PDF file
Organized as detailed below
Sequentially numbered throughout
Accompanied by a cover sheet that includes:
Offeror's name
Complete address (including 9-digit ZIP code)
Phone number
Facsimile number
Email address
Date of offer
Volume number and title
Copy number
Solicitation identification number
Each volume shall also include a table of contents for easy reference to sections, figures, and illustrations.
Information that is not directly stated within the proposal may not be included by reference to other sources.
Proposal Volumes shall be consistent with the following structure and tabbed accordingly:
1. VOLUME I - Administrative (Required Documentation)
a. Executive Summary: Each offeror shall submit an Executive Summary of no more than three pages total, which summarizes the key points from the offeror's Technical Capabilities and Past Performance.
b. Solicitation/Model Contract Representations and Certifications. Complete blocks of the SF 1442; in doing so, the offeror accedes to the contract terms and conditions as written in the Request for Proposal (RFP) Sections A through K. These sections constitute the model contract. An official having the authority to bind the offeror contractually must sign the SF 1442. One copy of SF 1442 must bear a signature. (Enter the "Cage Code" and "Unique Entity ID" in Block 14 on page 2).
c. Section G - Contract Administrative Data. Complete any fill-ins required; Paragraph G.7.
d. Section K - Representations, Certifications, and other Statements of Offerors. Complete representations, certifications, acknowledgments and statements. (Note: Offerors must also comply with the System Management for Award (SAM) requirements of FAR 52.204-7).
e. Acknowledgment of all amendments issued (if applicable);
f. Statement of the period for which the proposal is valid (not less than 180 calendar days);
g. BONDING CAPACITY
Offeror shall provide a letter, from an approved surety, stating the offeror has, as a minimum:
For Small Business offerors: A current bonding capacity for this acquisition of at least the Simplified Acquisition Threshold (SAT) (per project) and at least $1 million for the aggregate project amount. The letter shall include the name and telephone number of the Bonding Company(s). Such bonding capacity should meet the requirements of FAR 52.228-15, Performance and Payment Bonds - Construction.
For 8(a) offerors: Due to the anticipated size and complexity of task orders under the 8(a) pool, offerors in this category shall provide evidence of bonding capacity at a minimum of $5 million (per project) and at least $10 million for the aggregate project amount. The letter shall include the name and telephone number of the Bonding Company(s). Such bonding capacity should meet the requirements of FAR 52.228-15, Performance and Payment Bonds - Construction. This requirement reflects the larger share of the overall contract value allocated to the 8(a) pool.
2. VOLUME II - Factor 1 - Technical Approach
a. The purpose of the Technical Approach Volume is to demonstrate the plan on how the requirements of this acquisition will be managed. The technical approach should consider the estimated quantities and construction magnitudes included in Section B as well as the Statement of Work included as Attachment 1 in Section J. The measures of merit for acceptability for each of the sub-factors and elements are outlined in Section M. The following sub-factors and elements shall be included in the Technical Approach:
i. Sub-Factor 1 - Program Management
Element 1 - Overall Management Approach
Element 2 - Management Organization
Element 3 - Quality Control
ii. Sub-Factor 2 - Project Planning and Execution
Element 1 - Workload Management
Element 2 - Subcontract Management
b. Design-Build: The sub-factors and elements must address information on the offeror's design-build team, including management/ organizational structure, qualifications of architects, engineers, accredited professionals, contractual arrangements, and lines of authority. The technical approach should address the design-build implementation approach to addressing H.1. Paragraph 5 (Design-Build 100%).
i. Discuss approach used to ensure the as-built construction satisfies all approved design requirements, including shop drawing review and approval process, and inspection, testing, and quality control procedures.
Discuss the design team's associated interactions with and on behalf of the owner.
ii. Discuss approach used to maintain control of project costs without compromising technical requirements and standards.
3. VOLUME III - Factor 2 - Past Performance
a. The purpose of the Past Performance Volume is to provide a summary of recent and relevant efforts essentially comparable to this acquisition. The Government will use this information to perform a past performance evaluation as described in Section M. Current contracts or subcontracts performed, in whole or part, within the past five (5) years immediately preceding the issuance of this solicitation will be considered RECENT. RELEVANCY is described in detail in Section M paragraph 4(c).
b. Recent and Relevant Contracts. Provide a comprehensive list of up to five recent and relevant contracts to include the information listed below. If you believe a classified project is significant for this proposal, then simply state "Classified" where appropriate and provide points of contact.
1. Contract Number
2. Total dollar value (original and final)
3. Contracting Agency
4. Title of Contract
5. Government program manager (name, address, phone number)
6. Description of program/project
7. PCO and ACO (name, address, and phone number)
8. Period of performance
9. Type of Contract (Firm Fixed Price, Fixed Price Incentive, Cost Plus Fixed Fee, Cost Plus Award Fee, etc.)
c. Performance Evaluation Questionnaire (PEQ). The Government requests the offeror send out the questionnaire (see Attachment 6) for each contract listed above. Offerors shall request the customer to complete the questionnaire and return it to the Contracting Officer AT LEAST 10 DAYS prior to the proposal closing date /time, earlier if possible, but NO LATER THAN the proposal closing date. Once the questionnaires are completed by the Points of Contact (POC), the information contained therein shall be considered sensitive and shall not be released to you, the offeror. A cover letter for transmitting the questionnaire to each POC is included. You may include your own cover letter requesting completion of the questionnaire in addition to the cover letter provided. The Past Performance Volume shall include a list of questionnaire recipients to include two current POCs and phone numbers for each contract reference provided. The offeror is solely responsible for the accuracy of the contact information provided. Contractor Performance Assessment Reporting System (CPARS) Reports may be provided in lieu of the PEQ if available.
The completed PEQs shall be emailed by respondent directly to , Aaron.L.Kelley@nasa.gov Benjamin.P.
and .Crafton@nasa.gov Jacqueline.A.Brooks@nasa.gov
d. Design-Build Past Performance: A past performance evaluation on each offeror's overall Design-Build experience as it relates to recent and relevant contracts identified in the offeror's Construction Project Listing will be performed. Offerors must ensure the past performance submitted highlights any Design-Build experience.
e. Safety and Health Program: The contractor MUST submit copy of Section J, Attachment 9. Attachment 9 shall contain the prime contractor's OSHA Total Recordable Incidence Rate (TRIR), OSHA Days Away, Restricted, Transfer, (DART) Rate, and designated Experience Modification Rate (EMR) used to calculate Workmen's Compensation Insurance. These rates will be considered in the past performance confidence assessment. Attachment 9, Safety and Health Program, is excluded from the 25-page limit for volume III.
The acquisition forecast for the next 5 years at KSC shows an increased need to execute mechanical requirements valued less than the simplified acquisition threshold (SAT).
Targeted Past Performance Submission for Mechanical Requirements:
In support of the Government's intent to reserve three (3) of the eight (8) total awards for offerors with demonstrated experience in mechanical construction requirements under the Simplified Acquisition Threshold (SAT), offerors are encouraged to clearly identify and highlight relevant past performance examples that meet the following criteria:
- Mechanical scopes of work (e.g., HVAC, plumbing, piping, mechanical systems integration)
- Projects valued below the SAT
- Work performed in similar operational environments (e.g., NASA centers, federal facilities)
Offerors should include sufficient detail to demonstrate the recency, relevancy, and quality of performance on these projects. These examples should be clearly labeled within Volume III - Past Performance Information to facilitate evaluation.
Offerors who do not possess relevant mechanical experience under the SAT are still encouraged to submit proposals, as the remaining awards will be based on overall best value considering the full range of construction capabilities within The Statement of Work.
Past Performance Information: When submitting past performance information, offerors should highlight relevant aspects of their own, their teaming partners', and joint venture participants' contract histories that best demonstrate their ability to successfully perform the current requirement. Past performance should reflect how previous work met or exceeded contract expectations. In evaluating this information, the Government will place greater weight on the experience of the prime offeror, unless the teaming arrangement indicates otherwise, to emphasize the capabilities of the entity with primary responsibility for contract execution (Attachment 10: "Past .
Performance Assessment" is a tool used by NASA to record information regarding the past performance. No action required from offerors for this form.)
Section M - Evaluation Factors for Award
Miscellaneous text in this section has been modified to:
SECTION M - EVALUATION FACTORS FOR AWARD
M.1 GENERAL
Proposals will be evaluated by the evaluation team in accordance with applicable regulations, including the Federal Acquisition Regulation (FAR) and the NASA FAR Supplement (NFS). The evaluation team will conduct the evaluation activities and report its findings to the Source Selection Authority (SSA), who is responsible for making the source selection decision. Acceptable proposals will be evaluated against the evaluation factors set forth in paragraph M.4 below. Offerors must meet all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements, as well as the evaluation factors. Incomplete proposals may be deemed unacceptable and removed from further consideration.
M.2 BASIS FOR AWARD
This acquisition will follow a two-phase selection process in accordance with FAR 36.101-2 and the procedures of FAR Part 15, Contracting by Negotiation.
Phase 1 will evaluate non-price factors, specifically technical approach and past performance.
Phase 2 will evaluate price based on offerors' proposals for the design-build 'seed' project, which is a task order included in the phase 2 solicitation. The seed project consists of a statement of objectives and supporting documentation that reflects the type of construction anticipated under the contract and will be awarded as the initial task order.
This is a competitive best value source selection conducted in accordance with FAR Part 15 and NFS
1815.305. Awards will be made to offerors who are determined to be responsible under FAR Part 9, whose proposals conform to the solicitation requirements, and who, based on an integrated assessment of the evaluation criteria, represent the best value to the Government, as described in paragraph M.5.
M.3 AWARD WITHOUT DISCUSSIONS
In accordance with FAR 52.215-1, the Government intends to evaluate proposals and make awards without discussions (except for clarifications as described in FAR 15.202(a)(2)). Therefore, offerors are encouraged to submit their best proposal in the initial submission. However, the Government reserves the right to conduct discussions if the Contracting Officer determines them to be necessary. Multiple awards may be made as a result of this solicitation.
M.4 EVALUATION PROCESS
The evaluation process will consist of a two-step process for both the pool of general contractors and the pool of mechanical discipline contractors. Phase 1 will consider the non-price factors of technical approach and past performance. Price will be evaluated during Phase 2 based on the offerors' proposals in response to the design build "seed" project.
Offerors will be checked in the System for Award Management (SAM) for current entity registration, representations and certifications, and the exclusions. Proposals will also be checked for minor informalities or irregularities.
PHASE 1
EVALUATION OF NON-PRICE/TECHNICAL FACTORS
Offerors will be evaluated on the non-price/technical factors of Technical Approach and Past Performance.
FACTOR 1 - TECHNICAL APPROACH
The Government technical evaluation team will evaluate technical proposals on an acceptable/unacceptable basis. The following sub-factors will be evaluated:
Sub-Factor 1 - Program Management
Element 1 - Management Approach
Description: This element assesses how well the offeror's approach manages the overall contract and the resulting Task Orders
Measure of Merit: The element is satisfied when the offeror's proposal clearly and logically addresses and meets the requirements specified below and within the contract Statement of Work (SOW). The standard is met when the proposal:
Management Approach: Describes how the offeror plans to manage the entire contract, and the Task Orders issued for each Contract Line-Item Number (CLIN), including Design/Build requirements.
Organizational Diagram: Includes a diagram that clearly shows the lines of authority from the Program Manager to subcontracting management. This should cover areas such as site investigation, site superintendence, and quality control.
Subcontracting Plan: Specifies the offeror's proposed level of subcontracting to complete the work, clearly outlining the tasks that will not be handled by in-house resources.
Partnering Approach: Describes the strategy for collaborating with accredited Architectural and Engineering (A&E) firms and construction contractors simultaneously for Design/Build projects.
Element 2 - Management Organization
Description: This element assesses the adequacy of the offeror's key staff personnel and their overall composition.
Measure of Merit: The element is satisfied when the offeror's proposal clearly and logically addresses and meets the requirements specified below and within the contract Statement of Work (SOW). The standard is met when the proposal:
Key Staff Qualifications: Identifies key program and project management staff along with their qualifications, such as education, training, licenses, and relevant experience for the tasks they will perform if awarded the contract.
Decision-Making Authority: Defines clear lines of decision-making authority between management and staff members, with an emphasis on the authority of the local Program Manager for on-site decisions.
Element 3 - Quality Control
Description: The Government will assess the adequacy of the offeror's quality control procedures.
Measure of Merit: The element is satisfied when the offeror's proposal clearly and logically addresses and meets the requirements specified below and within the contract Statement of Work (SOW). The standard is met when the proposal:
Quality Control Approach: Describes the offeror's quality control strategy for the STOCC II and explains how it will mitigate risks on individual Task Orders.
Surveillance Responsibility: Specifies who is responsible for overseeing the work of both subcontractors and in-house personnel.
Deficiency Management: Outlines the process for accepting or rejecting work, documenting and resolving deficiencies for tasks performed by in-house staff or subcontractors, and implementing corrective actions to address poor performance by any in-house staff or subcontractor staff.
Superintendence Requirements: Explains how the requirements of FAR 52.236-6, titled "Superintendence by the Contractor," will be met. This includes detailing how the superintendent will be qualified to supervise various trades to ensure quality workmanship.
Sub-Factor 2 - Project Planning and Execution
Element 1 - Workload Management
Description: This element assesses the adequacy of the offeror's ability to manage the contract and the resulting Task Order workload.
Measure of Merit: The element is satisfied when the offeror's proposal clearly and logically addresses and meets the requirements specified below and within the contract Statement of Work (SOW). The standard is met when the proposal:
Documented Experience: Provides evidence of experience in performing at least three construction projects simultaneously.
Response Plan: Describes a plan for responding to Task Order RFPs issued for each CLIN within the timelines specified in the Master Statement of Work (SOW).
Execution Plan: Outlines a strategy for handling many Task Orders within a highly compressed time frame due to funding surges and emerging requirements.
Support Plan: Describes a strategy for obtaining additional subcontractor support and/or enhancing existing in-house project supervision for Task Orders during peak workload periods in any contract period.
Scheduling Methods: Describes the methods and procedures for scheduling work to ensure that performance periods are met.
Project Tracking and Communication: Identifies the methods and tools used to track project progress and outlines how to interface with the Government Contract Officer and COR/technical personnel regarding project status.
Element 2 Subcontract Management
Description: The Government will assess the adequacy of the offeror's ability to acquire qualified subcontractor support and the policies/procedures for managing subcontractor resources required for all Task Orders issued.
Measure of Merit: The element is satisfied when the offeror's proposal clearly and logically addresses and meets the requirements specified below and within the contract Statement of Work (SOW). The standard is met when the proposal:
Subcontract Management Experience: Provides evidence of experience in managing subcontracts and multiple subcontractors for at least three projects (design and/or construction) simultaneously.
Subcontractor Plan: Clearly and logically describes the methods and criteria for acquiring qualified subcontractors. This includes considering their previous experience, current capabilities, and the quality of their past work.
Subcontractor Management Policies and Procedures: Proposal clearly describes methods of surveillance, quality control, scheduling, performance, and administrative issues such as payroll submission and Davis-Bacon Act Enforcement.
Failure to meet all requirements under the Technical Approach Factor will result in an "UNACCEPTABLE" rating, leading to elimination from further consideration for the contract award.
FACTOR 2 - PAST PERFORMANCE
The Government will evaluate the offeror's demonstrated record of performance in providing construction services that meet customer needs, with a focus on work relevant to the STOCC II requirements. This evaluation will consider how well recent, relevant efforts were performed and will serve as an indicator of the offeror's ability to perform under the prospective contract.
NASA will assess past performance using information submitted in accordance with Section L, Past Performance Information - Volume III, as well as any other information available to the Government from independent sources. The evaluation will focus on how effectively contract objectives--such as technical performance, management, safety/quality control, and cost--were achieved on related projects.
The evaluation team will integrate the recency, relevancy, and quality of performance across all evaluated efforts to develop an overall past performance confidence assessment rating. This rating reflects an integrated assessment of:
The offeror's recent and relevant performance; and
The recent and relevant performance of any joint venture participants whose efforts will significantly influence contract performance.
Past performance of joint venture partners will be included in the aggregate evaluation.
Note: Targeted Selection for Mechanical Requirements
To ensure the award pool includes contractors with demonstrated capability to support anticipated mechanical construction requirements under the Simplified Acquisition Threshold (SAT), the Government intends to reserve for offerors whose past performance demonstrates:three (3) of the eight (8) total awards
Successful execution of mechanical scopes of work (e.g., HVAC, plumbing, piping)
Experience with projects valued below the SAT
Performance in similar operational environments (e.g., NASA centers, federal facilities)
These three awards will be made to the highest-rated offerors in this category, based on the evaluation criteria outlined in this section. The remaining five awards will be made based on overall best value to the Government, considering the full range of relevant construction experience.
The following areas will be evaluated:
Recency Assessment: An assessment of the past performance information will be made to determine if it is recent. To be recent, the effort must have been completed or performed during the past five years from the date of the issuance of this solicitation. Efforts that have not yet been completed shall have had at least six months of performance prior to the date of issuance of this solicitation. Past performance information that fails these conditions shall not be evaluated. If the removal of one or more projects from the past performance evaluation pool results in the number of evaluated projects to fall below the minimum project requirement of three, the offeror will be removed from further consideration for award.
Relevance Assessment: The Government will conduct an evaluation of all recent performance information obtained to determine how closely the effort relates to the STOCC II. The past performance summary and information that may be obtained from other sources will be used to establish the degree of relevance of the past performance.
The Government will use the following degrees of relevance when assessing recent contracts:
Degree Description
RELEVANT (R) Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
NOT RELEVANT (NR) Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
Safety Past Performance: The evaluation of past performance will include assessment of the overall safety record of the offeror during the performance of previous contracts, to include maintaining acceptable TCIR, EMR, and DART rates. A contractor with a lower EMR and DART rates will receive better rating of confidence, while a contractor with a higher EMR and DART rates will receive a lower rating of confidence. A contractor's EMR rating less than 1.0 is needed to be rated a Very High Level of Confidence.
Performance Quality: In conducting the Past Performance evaluation, the Government reserves the right to use both the information provided in the offeror's Past Performance Proposal and information obtained from other sources, to include but not limited to, Contractor Performance Assessment Reporting System (CPARS), Defense Contract Management Agency (DCMA), commercial sources, and interviews with previous customers.
The review may result in positive or adverse findings. An adverse finding is defined as past performance information that supports an unacceptable rating on any evaluation element or any unfavorable comment received from sources without a formal rating system. Offerors may be given the opportunity to clarify adverse past performance information to which the offeror has not previously had an opportunity to respond. For adverse information identified, the evaluation will consider the number and severity of the problem(s), mitigating circumstances, and the effectiveness of corrective actions that have resulted in sustained improvements. Process changes will only be considered when objectively measurable improvements in performance have been demonstrated.
Past Performance Ratings: The offeror's relevant experience and past performance will be reviewed, and an assessment made that reflects the Government's judgment of the probability of each offeror successfully accomplishing the proposed effort based on that offeror's demonstrated performance. Past performance shall be evaluated for each offeror using the following levels of confidence ratings:
Very High Level of Confidence
The offeror's relevant past performance is of exceptional merit and is very highly pertinent to this acquisition, indicates exemplary performance in a timely, efficient, and economical manner and very minor (if any) problems with no adverse effect on overall performance. Based on the offeror's performance record, there is a very high level of confidence that the offeror will successfully perform the required effort. (One or more significant strengths exist. No significant weaknesses exist.)
High Level of Confidence
The offeror's relevant past performance is highly pertinent to this acquisition; demonstrating very effective performance that would be fully responsive to contract requirements. Offeror's past performance indicates that contract requirements were accomplished in a timely, efficient, and economical manner for the most part, with only minor problems that had little identifiable effect on overall performance. Based on the offeror's performance record, there is a high level of confidence that the offeror will successfully perform the required effort. (One or more significant strengths exist. Strengths outbalance any weakness.)
Moderate Level of Confidence
The offeror's relevant past performance is pertinent to this acquisition, and it demonstrates effective performance. Performance was fully responsive to contract requirements; there may have been reportable problems, but with little identifiable effect on overall performance. Based on the offeror's performance record, there is a moderate level of confidence that the offeror will successfully perform the required effort. (There may be strengths or weaknesses, or both.)
Low Level of Confidence
The offeror's relevant past performance is at least somewhat pertinent to this acquisition, and it meets or slightly exceeds minimum acceptable standards. Offeror achieved adequate results; there may have been reportable problems with identifiable, but not substantial, effects on overall performance. Based on the offeror's performance record, there is a low level of confidence that the offeror will successfully perform the required effort. Changes to the offeror's existing processes may be necessary in order to achieve contract requirements.
(One or more weaknesses exist. Weaknesses outbalance strengths.
Very Low Level of Confidence
The offeror's relevant past performance does not meet minimum acceptable standards in one or more areas;
remedial action was required in one or more areas. Performance problems occurred in one or more areas which, adversely affected overall performance. Based on the offeror's performance record, there is a very low level of confidence that the offeror will successfully perform the required effort. (One or more deficiencies or significant weaknesses exist.)
Neutral
In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available, the offeror may not be evaluated favorably or unfavorably on past performance [see FAR 15.202(c)].
Offerors evaluated and assessed at anything less than a "High Confidence" rating for past performance, will not be considered for Phase 2.
PHASE 2
EVALUATION OF PRICE/TASK ORDER PROPOSAL
Only the top-rated offerors in Phase 1 (maximum of five general contractors and three mechanical contractors) will be selected to submit proposals in Phase 2. Offerors selected in Phase 2 will be evaluated on the price and technical factors of the Design/Build Task Orders. Evaluation criteria of each Task Order will be included per the ordering procedures outlined in the Ordering Procedures.
M.5 METHODOLOGY USED FOR PROPOSAL EVALUATION
STEP 1:
Review for Responsiveness: The Government will review all proposals to determine if each offeror has submitted a responsive proposal, and that all required documentation complies with the solicitation instructions. Review of the System for Award Management (SAM) will be conducted to determine if an offeror has an active exclusion, as well as a review of the Offerors Representations and Certifications to determine eligibility for award for both the Small Business (SB) firms (CLINs 0001 - 0003) and 8(a) firms (CLINs 0004 - 0006) assigned the NAICS code 236220. All other participants are deemed ineligible to submit offers. Any non-responsive proposal will be handled in accordance with NFS 1815.305- 70, "Identification of Unacceptable Proposals", Offerors whose proposals are found to be non-responsive in any area or offerors who has an active exclusion listed in SAM will be eliminated from the competition without further consideration, all other offers will be considered responsive and will move forward for further evaluation.
STEP 2:
Evaluate Technical Approach and Past Performance: All responsive proposals will be evaluated for technical acceptability and past performance.
Technical Approach Evaluation: Failure to meet all of the requirements under the Technical Approach Factor will result in an "UNACCEPTABLE" rating and elimination from further consideration for contract award.
Past Performance Evaluation: Offerors evaluated and assessed at anything less than a "High Confidence" rating for past performance, will not be considered for…