Attachment_08_Work_Plan.pdf
PDF 280 KB Posted
- Attached to
- Gateway Logistics Services Federal contract opportunity
- Solicitation number
- 80KSC019R0002
About this file
This document outlines work plans for Gateway Logistics Services to resupply the Gateway in cislunar orbit. The National Aeronautics and Space Administration Kennedy Space Center will issue a Request for Proposal for logistics capabilities to and from the Gateway, which will provide habitation space, docking, and logistics supply capabilities. The solicitation number is 80KSC019R0002. Offerors must monitor the Federal Business Opportunities website for release of the solicitation on or around August 15, 2019. The work plans provide milestone events and criteria for standard and initial Gateway Logistics Service missions, including reviews from launch-30 months to end of mission. Payments will be made upon completion of events like vehicle baselines reviews, integration reviews, launch, rendezvous and docking, on-orbit support, and end of mission review.
Attachment 08 Work Plan
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 08: Work Plans RFP 80KSC019R0002 Gateway Logistics Services
Attachment 08
Work Plans
ATTACHMENT 08: Work Plans
INITIAL GLS MISSION WORK PLAN
Payment Number Program Event (Launch +/- months) 1 Accomplishment Criteria1
1 L-“X” / L-48
ATP / Award Authority to Proceed received from the Contracting Officer.
Launch slot reserved.
2 L-42 System Requirements Review
(SRR)
System Requirement Review complete.
Applicable section in DRD GLS-101
3 L-33 Preliminary Design Review
(PDR)
Preliminary Design Review complete.
4 L-30 Critical Design Review (CDR) Critical Design Review complete.
5 L-20 System Certification Review
(SCR)
System Certification Review complete.
6 L-18 Vehicle Baseline Review (VBR) Vehicle Baseline Review complete.
Applicable section in DRD GLS-102
7 L-12 Mission Integration Review
(MIR)
Mission Integration Review complete.
8 L-10 Unpressurized Cargo Integration Review (UCIR) (if applicable)
Unpressurized Cargo Integration Review complete.
Number Program Event (Launch +/- months) 1 Accomplishment Criteria1
9 L-03 Pressurized Cargo Integration Review (PCIR)
Pressurized Cargo Integration Review
10 L-03 days
Flight Readiness Review (FRR) Flight Readiness Review (FRR) complete.
T-0 Launch Launch event occurred and documentation has been provided to NASA
11 TBP Delivery
Rendezvous and Docking Readiness Review (RDRR) complete.
Post-Delivery Review complete.
NASA verifies that cargo is delivered without any violation of the requirements and without any degradation of the cargo or ability of the logistic vehicle or payloads to perform all required functions.
Applicable sections in DRD GLS-102
12 TBP Docked Operations On-orbit operational support complete.
13 TBP End of Mission Review (EMR) Undocking Readiness Review (URR)
End of Mission Review complete.
Final Report submitted and the NASA Contracting Officer has determined mission success.
1 The “Program Event” and “Accomplishment Criteria” descriptions may be tailored to align with the contractor’s standard launch service process as long as the “Program Event” and “Accomplishment Criteria” descriptions remain substantially the same as is stated above.
STANDARD GLS MISSION WORK PLAN
Number Program Event (Launch +/- months) 1, 2 Accomplishment Criteria1
1 L-“X” / L-30
ATP / Award Authority to Proceed received from the Contracting Officer.
Launch slot reserved.
2 L-18 Vehicle Baseline Review (VBR) Vehicle Baseline Review complete.
3 L-12 Mission Integration Review
(MIR)
Mission Integration Review complete.
4 L-10 Unpressurized Cargo Integration Review (UCIR) (if applicable)
Unpressurized Cargo Integration Review
5 L-03 Pressurized Cargo Integration Review (PCIR)
Pressurized Cargo and Payloads Integration Review complete.
6 L-03 Days
Flight Readiness Review (FRR) Flight Readiness Review (FRR) complete.
T-0 Launch Launch event occurred and documentation has been provided to NASA
7 TBP Delivery
Rendezvous and Docking Readiness Review (RDRR) complete.
Post-Delivery Review complete.
NASA verifies that cargo is delivered without any violation of the requirements and without any degradation of the cargo or ability of the logistic vehicle or payloads to perform all required functions.
Applicable sections in DRD GLS-102
8 TBP Docked Operations On-orbit operational support complete.
Number Program Event (Launch +/- months) 1, 2 Accomplishment Criteria1
9 TBP End of Mission Review (EMR) Undocking Readiness Review (URR) complete.
End of Mission Review complete.
Final Report submitted and the NASA Contracting Officer has determined mission success.
1 The “Program Event” and “Accomplishment Criteria” descriptions may be tailored to align with the contractor’s standard launch service process as long as the “Program Event” and “Accomplishment Criteria” descriptions remain substantially the same as is stated above.
2 When a mission includes common GLS configuration changes, the work plan may be updated to Common Configuration Integration Reviews at NASA’s discretion. When a common GLS configuration change is contractor driven, these events will be performed at no additional cost to the Standard GLS Mission price.
File details come from the government source that posted it. Updated .