FCLP 8 Q and A-2-4.pdf

PDF 92 KB Posted

Attached to
Airfield Repair & Paving at Wallops Flight Facility - FCLP Phase 8
Solicitation number
80GSFC21B0004
Issued by

About this file

This document contains a question and answer file and federal contract opportunity notice related to airfield repair and paving work at Wallops Flight Facility. The National Aeronautics and Space Administration Goddard Space Center plans to issue an Invitation for Bids for repair projects at Wallops Airfield, including demolition, site work, concrete repairs and replacement. The contract value is estimated between $1 million and $5 million, with a performance period of 270 calendar days. Bids are due in early September 2021 in response to a solicitation to be released in early August. The questions and answers clarify that bidders should only provide pricing for the quantities in the project plans, and that temporary fencing will not be required around an interior laydown area. Red pavement paint type is specified in Section 32 17 23.

View the file

Other files

File Type Posted
80GSFC21B0004 Amendment 2.pdf PDF
80GSFC21B0004_Attachment H.pdf PDF
Amendment 1.pdf PDF
FCLP Airfield Phase 8 Site Visit Instructions.pdf PDF
Attachment F.pdf PDF
Attachment D.pdf PDF
COVID Health Screening and Badge Information for Site Visits.pdf PDF
Attachment G.pdf PDF
FCLP Phase 8 IFB 80GSFC21B0004.pdf PDF
Attachment B Specs.pdf PDF
Attachment E.pdf PDF
NoticeToBidders 80GSFC21B0004.pdf PDF
Attachment C Drawings.pdf PDF
Attachment A Final.pdf PDF
FCLP 8 Q and A-1.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A Airfield Repair and Paving at Wallops Flight Facility FCLP Phase 8 IFB 80GSFC21B0004

August 26, 2021

Solicitation Questions

2. Q. The Bid Items are Lump Sum, and the drawings contain quantities for each scope of work.

Please confirm if we are to bid only the quantities provided in the plans and that any growth in quantities at time of construction will be considered additional work and the Government will negotiate with the Contractor regarding time and cost impacts.

A. Bid only on the quantities provided in the plans.

3. Q. The laydown area shown on Sheet G-003 is located within the NASA Facility. Please confirm if temporary fencing with inserts is still required around laydown area per spec 01 50 00 – 3.5.3.

A. Temporary fencing with inserts is not required around laydown area that is located within the NASA Facility. Amendment 2 deletes Specification Section 01 50 00, Paragraph 3.5.3 Storage Area.

4. Q. There is no specification for red pavement marking material—please identify type of paint to be used for red markings.

A. Please refer to Specification Section 32 17 23.