80GSFC18R0045
Questions and Responses, Set #1
RFP Questions and Responses – Set #1
Question #1: Would responding with EEE parts according to ECSS standards be an acceptable approach for the PACE program?
Response #1: There are provisions in the SPEC and SOW that allow for INST-002 equivalent standards. Specifically, please review sections 2.0 of the SPEC and 7.0 of the SOW.
Question #2: Is it possible to extend the Star Tracker proposal due date to August 10, 2018?
Response #2: At this time, the Government cannot extend the proposal due date for the PACE
Star Tracker procurement.