This document is a detailed technical specification for the N254 HVAC Rehabilitation project at NASA Ames Research Center, outlining comprehensive requirements for replacing HVAC and uninterruptible power supply (UPS) systems in Building N254.
The project is divided into two primary phases: Phase #1 involves replacing existing evaporative coolers with two new packaged air conditioning units for Room 122, including installing temporary HVAC, removing existing equipment, and performing a 30-day operational burn-in test. Phase #2 focuses on replacing two existing UPS systems, which includes installing a temporary UPS system, removing and replacing UPS modules and batteries, and conducting extensive testing. The contractor must follow strict requirements including detailed work plans, extensive testing protocols, medical surveillance, training, and environmental controls. Specific requirements include using trained personnel with at least 10 years of experience in mission-critical facilities, conducting multiple acceptance tests, maintaining comprehensive documentation, and ensuring minimal disruption to the facility's ongoing operations. The project emphasizes safety, environmental protection, and maintaining the continuous operation of NASA's critical telecommunications infrastructure.
View the file
Other files for this federal contract opportunity
Show all 50
Western Regional Multiple Award Construction Contracts (WRMACC) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N254 HVAC Rehabilitation K21007
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
01 14 00 WORK RESTRICTIONS
01 20 00.00 20 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 16.00 20 CONSTRUCTION PROGRESS DOCUMENTATION
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR
CONTAMINATED SITES
01 35 40.00 20 ENVIRONMENTAL MANAGEMENT
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 40 QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19.00 20 TEMPORARY ENVIRONMENTAL CONTROLS
01 62 35 RECYCLED / RECOVERED MATERIALS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 75 00 STARTING AND ADJUSTING
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 86 12.07 40 RELIABILITY CENTERED ACCEPTANCE FOR MECHANICAL SYSTEMS
DIVISION 02 - EXISTING CONDITIONS
02 32 00 SUBSURFACE DRILLING, SAMPLING, AND TESTING
02 41 00 DEMOLITION
02 42 91 REMOVAL AND SALVAGE OF HISTORIC BUILDING MATERIALS
02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
02 61 23 REMOVAL AND DISPOSAL OF PCB CONTAMINATED SOILS
02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS
02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES
02 83 13.00 20 LEAD IN CONSTRUCTION
02 84 16 HANDLING OF LIGHTING BALLASTS CONTAINING PCBs AND LAMPS
CONTAINING MERCURY
02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS (PCBs)
02 85 00.00 20 MOLD REMEDIATION
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL
05 50 13 MISCELLANEOUS METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 51 13 BUILT-UP ASPHALT ROOFING
07 60 00 FLASHING AND SHEET METAL
07 84 00 FIRESTOPPING
PROJECT TABLE OF CONTENTS Page 1
07 92 00 JOINT SEALANTS
DIVISION 09 - FINISHES
09 23 00 GYPSUM PLASTERING
09 29 00 GYPSUM BOARD
09 90 00.00 PAINTS AND COATINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 00.00 10 SEISMIC PROTECTION FOR MECHANICAL EQUIPMENT
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND
EQUIPMENT
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 08 00.10 40 HEATING, VENTILATING & AIR CONDITIONING (HVAC) SYSTEM
COMMISSIONING
23 09 33.00 40 ELECTRIC AND ELECTRONIC CONTROL SYSTEM FOR HVAC
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 71.00 40 LOW VOLTAGE OVERCURRENT ELECTRICAL DEVICES
26 08 00.00 40 ELECTRICAL SYSTEM COMMISSIONING
26 20 00 INTERIOR DISTRIBUTION SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 LIFE SAFETY AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 DEFINITIONS
1.2 REQUIREMENTS
1.3 STANDARDS
1.4 SCOPE OF WORK
1.5 ADDITIONAL CONTRACTOR INSTRUCTIONS
PART 2 PRODUCTS
2.1 NEW MATERIALS
2.2 REUSED SALVAGE MATERIALS
2.3 GOVERNMENT-FURNISHED PROPERTY
2.4 EQUIPMENT FABRICATION & INSTALLATION
PART 3 EXECUTION
3.1 PROJECT MANAGEMENT
3.2 SHUTDOWNS AND OUTAGES
3.3 FACILITY SECURITY AND WORKER ACCESS
3.4 WORK IN N254 COMMUNICATIONS FACILITY
3.5 NASA MISSION FREEZE CONDITIONS
3.6 BURROWING OWL HABITAT
3.7 AIR EMISSIONS INFORMATION DURING CONSTRUCTION
3.8 CONSTRUCTION PHASING
3.9 TEST PLANS
3.10 PROJECT HOLD POINTS
3.11 FINAL WALK THROUGH
3.12 CONTRACTOR STAGING AREA
-- End of Section Table of Contents --
SECTION 01 00 00 Page 1
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 DEFINITIONS
The work to be performed under this contract consists of providing the labor, equipment, and materials to complete the above-titled project in accordance with the drawings, these specifications, and the contract clauses. This project has been designed in English units. The construction is to be in English units with dimensions as shown on the drawings. Materials and products are to be in English units and shop drawings must be submitted with English dimensions. When used in these specifications the following definitions apply:
a. Furnish: Contractor to supply and deliver equipment complete
b. Install: Contractor to place, secure, and connect equipment to make fully operational.
c. Provide: Contractor to furnish and install as defined above.
d. UPS System #1: Refers to UPS #1 components complete, Module #1, Tie-Panel and Module #2.
e. UPS System #2: Refers to UPS #2 components complete; Module #1, Tie-Panel and Module #2.
In the case of a conflict between this Specification Section 01 00 00 and any of the following Specification Sections or the Contract Drawings, this Section shall take precedence.
1.2 REQUIREMENTS
The project will be performed as design-bid-build. Refer to the following documents for project design requirements:
a. Drawings: RA254-2101-ALL.
b. Specifications: “NASA Ames Local Master Specifications (ALMS)” modified from the original Unified Facilities Guide Specifications (UFGS) to conform to Ames Research Center standard design practices. Most recent Revision 1, July 6, 2017.
c. Specifications added to the ALMS: i. UFGS Section 01 00 00, General Requirements.
1.3 STANDARDS
All work performed shall comply with the latest revision to the following standards as a minimum:
SECTION 01 00 00 Page 2
California Building Code (CBC)
Ref Id Ref Title
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE C2 (2023) National Electrical Safety Code
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70E (2021) Standard for Electrical Safety in the Workplace
INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)
NETA ATS (2021) Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems
AMES HEALTH AND SAFETY MANUAL
APR 8715.1 Ames Health and Safety Manual
1.4 SCOPE OF WORK
The Contractor shall provide all work, equipment and materials necessary to deliver a functional facility at the completion of the project as defined in the drawings and specifications in Section 1.2 and this document. In addition, the Contractor shall perform all electrical testing as defined below.
The Contractor and all Subcontractors shall meet the additional requirements defined in Paragraph 1.5 below.
The N254 Telecommunications Gateway facility is a NASA Mission Critical Facility that provides vital IT functions on a 24 x 7 x 365 basis.
Therefore, all work must be planned, coordinated, and approved by NASA. All activities shall be planned and executed to minimize risk and impact to IT operations.
a. Base Bid: Replace HVAC system serving Room 122. Furnish labor, equipment, and materials to complete the work as indicated in the drawings which includes, but not limited to, the following:
i. Replace existing roof-mounted evaporative cooing units serving Room 122.
1) The Contractor shall replace the two existing roof-mounted evaporative coolers with two new packaged HVAC units and associated ducting to cool Room 122.
2) The HVAC replacement shall be conducted in accordance with a Contractor prepared and NASA approved “HVAC Replacement Plan”. The plan shall identify all major work elements and their sequence, the installation and testing of the required temporary cooling for Room 122, demolition of existing evaporative coolers, roof structural modifications, sealing of roof penetrations, installation of the new packaged HVAC
SECTION 01 00 00 Page 3 units on the roof, and the planned commissioning tests of the completed HVAC system.
3) All new material and new HVAC equipment shall be available on-site at Ames Research Center (ARC) prior to the start of work.
4) Prior to the start of HVAC demolition, the Contractor shall provide, install, operate and maintain temporary HVAC for Room 122 cooling. A capacity of approximately 10 tons of cooling is required. The temporary HVAC shall be powered from Panel C1 in Room 123.
5) The operation of the temporary HVAC shall be demonstrated for a period of one week to prove to NASA representatives its satisfactory performance and reliability prior to NASA approval to start the demolition and installation of new HVAC equipment.
6) The Contractor shall demolish the two existing evaporative coolers, associated ducting, and utilities from the roof above Room 122.
7) The Contractor shall protect the operating UPS systems in Room 122 from falling dust and debris during the demolition of the existing HVAC equipment and the installation of the new HVAC equipment.
8) The Contractor shall install all structural supports required to support the new HVAC equipment and associated ducting and appurtenances.
9) The Contractor shall install the two new HVAC units, associated ducting, electrical and controls on the roof above Room 122.
10) The Contractor shall seal all roof penetrations to restore the roof to a water-tight condition. All sealed/patched areas shall be tested to demonstrate to NASA representatives that the roof is water-tight before proceeding further.
11) The Contractor shall interconnect the controls for the new HVAC with the existing facility management control system
(FMCS).
12) The Contractor shall perform air balance and commissioning tests to confirm the equipment is fully operational.
13) The Contractor shall conduct a 30-day burn-in test to demonstrate to NASA that the new HVAC equipment is reliably operating and able to maintain temperature in Room 122 with the existing operating UPS systems. The test shall also demonstrate the correct operation of the new equipment with the existing FMCS (e.g., rotation of lead/lag process;
redundancy fail over and fail back; etc.)
14) Successful completion of the 30-day test is required for NASA to approve proceeding with the UPS systems replacement.
SECTION 01 00 00 Page 4
b. Alernate Bid #1: Replace HVAC and UPS Systems in Room 122 Furnish labor, equipment, and materials to complete the work as indicated in the drawings which includes, but not limited to, the following:
ii. Provide temporary UPS system with batteries.
1) The Contractor shall provide, install, operate, and maintain a portable UPS system with batteries to maintain power to the facility IT equipment during replacement of the existing UPS systems.
2) The temporary UPS shall be rated for at least 200 kVA capacity with 480 volts, 60 Hz, three phase input and output.
The temporary UPS shall provide battery back-up capacity for at least 20 minutes at full load. The temporary UPS shall be connected to the N254 electrical plant as shown on the drawings.
3) The Contractor shall provide an installation and test plan 30 days in advance of the temporary UPS installation for NASA approval. The plan shall include at least the specifications of the proposed temporary UPS and its batteries, the proposed physical placement at N254, electrical connection methods, electrical safety measures, physical security measures, UPS cooling/ventilation measures, and weather protection for the UPS. The plan shall also define the testing for the temporary UPS and a procedure for transferring the IT loads to and from the temporary UPS source. Testing of the temporary UPS and its batteries shall include a least the following elements:
a) Load bank test of 4 hours operating at full load with load steps from 0% to 100% to 0% to 100% with waveforms, voltages and currents recorded.
b) Load bank test of 4 hours at full load with demonstration of failover to and from battery twice while recording waveforms and battery voltages and currents.
c) Battery discharge test under operation at full load to verify battery ride through time of 20 minutes.
Waveforms, output voltages and currents, and battery voltage and recharge current shall be recorded.
4) All above tests must be successfully completed and NASA concurrence provided prior to proceeding with replacement of existing UPS systems.
iii. Replace existing UPS Systems and Batteries.
1) The two existing UPS systems are each composed of two Eaton 9390 UPS modules rated at 160 kVA each operating through an Eaton Tie-Panel to permit paralleled operation for a combined rating of 320 kVA. The UPS modules are to be replaced with two 150 kVA UPS modules connected to the existing Eaton Tie-Panel. The existing battery cabinets, one for each module, shall be retrofitted for reuse and the existing
SECTION 01 00 00 Page 5 batteries replaced with new batteries having the same rated capacity, capable of at least 11 minutes of ride through at full load.
2) After the successful HVAC burn-in period and the successful installation and testing of the temporary UPS with it backup batteries, NASA will permit the Contractor to proceed with the replacement of the two existing UPS systems and their batteries.
3) The Contractor shall prepare for NASA approval, a UPS Replacement Plan, at least 60 days in advance of the proposed start date. The plan shall address the removal of the existing UPS modules and batteries, electrical safety measures, retrofitting of the battery cabinets, installation of the new UPS modules and batteries, start up and testing.
4) Factory in plant tests of the new UPS modules shall be witnessed by NASA representatives.
5) The Contractor shall have all necessary new equipment and materials on site prior to start of the UPS replacement.
6) The Contractor shall have the UPS manufacturer provide certified company technicians perform a least the following tasks:
a) Electrical and mechanical inspection of the installed UPS modules and their batteries.
b) Retrofitting the existing battery cabinets for re-installation and re-use with certification for warranty.
c) UPS module start-up, load bank testing, Tie-Panel operation for paralleled module operation, battery balancing and testing, battery failover testing and NASA acceptance testing.
7) The existing UPS systems are equipped with 3rd party Alber battery condition monitoring equipment which was installed by NASA. Prior to UPS replacement, NASA will remove the Alber equipment and connecting cabling so as not to interfere with the Contractor’s UPS replacement activity. Following successful completion of the burn-in period for the replaced UPS, NASA will be responsible for reinstallation of the battery monitoring equipment.
iv. Replace UPS System #1.
1) The electric power to Panel EE shall be transitioned, under NASA supervision, from UPS #1 to the temporary UPS source in accordance with the UPS Installation Plan. Power transitioning is expected to be performed on a weekend according to a NASA approved date and time. The temporary UPS shall power the critical IT loads on Panel EE for four weeks in advance to demonstrate reliable operation to NASA prior to approval to proceed further with the replacement of the existing UPS #1.
SECTION 01 00 00 Page 6
2) Having approval to proceed, the Contractor shall isolate and safe off all electrical power circuits to and from UPS System #1 and physically remove the two existing UPS modules and two battery cabinets, leaving the Tie-Panel in place to be re-used.
3) The Contractor shall ensure that the power to the operation of UPS #2 is not interrupted during all steps of the replacement of UPS #1.
4) The Contractor shall provide and install two new UPS modules connecting with the existing Tie-Panel.
5) The Contractor shall have the UPS manufacturer retrofit the two battery cabinets for re-installation with a certification of warranty.
6) The Contractor shall provide and install two new sets of batteries in the battery cabinets.
7) The Contractor shall have the UPS manufacturer perform the factory specified start-up inspections and tests, including load bank testing of each UPS module and load bank testing with both modules operating in parallel. All tests will be witnessed by NASA representatives. The minimum test requirements are defined below in Paragraph vi.
8) The new UPS Modules shall be programmed to operate in “double conversion mode” and set for load sharing between the two modules.
9) After successfully completing all testing of UPS #1, at a weekend date and time approved by NASA, the Panel EE IT loads shall be transitioned from the temporary UPS back to the new UPS #1 and its new batteries.
10) A 30-day burn-in period shall then begin to demonstrate to NASA that the new UPS #1 is stable and reliable under normal operating conditions. During the burn-in period, UPS #1 voltage and current will be monitored for any abnormalities.
The Contractor shall report any and all findings to NASA.
11) After successful completion of the burn-in test, UPS #1 shall be considered accepted for use by NASA.
12) The replacement of UPS #2 may then begin.
v. Replace UPS System #2
1) Following successful replacement of UPS #1, UPS #2 shall be replaced following the same steps and requirements as defined above in Section iv for UPS #1. The UPS #2 critical IT loads are connected through Panel EE1.
i. UPS System test requirements.
1) The Contractor shall prepare for NASA approval a UPS Test Plan for both UPS #1 and UPS #2.
SECTION 01 00 00 Page 7
2) Testing shall be witnessed by NASA representatives.
3) UPS manufacturer technical representatives/technicians shall perform the tests.
4) The tests must include at least the following:
a) Load bank test of individual UPS Modules at full load (assumed to be 80% of rated maximum capacity) for 2 hours with load steps for 0% to 100% to 0% to 100%.
Transfer to/from bypass, to/from battery while capturing waveforms and battery voltage and charging currents.
b) Load bank test of UPS Systems which consists of two modules operating in parallel at full load (assumed to be 80% of rated maximum capacity) for 4 hours with loads steps from 0% to 100% to 0% to 100%. Transfer to/from bypass, transfer to/from battery while capturing waveforms and battery voltage and charging currents.
c) Operate UPS System at 50% of full load and demonstrate failover on loss of one UPS Module. Demonstrate for each Module. Capture input and output waveforms in all cases.
d) Battery discharge test of UPS System with two Modules in parallel. With fully charged batteries, operate at full load (assumed to be 80% of rated maximum capacity).
Transfer to battery power and verify that the load can be maintained for at least 8 minutes (based on 75% of expected 11 minute run time to limit wear on batteries) then restore utility power while capturing waveforms in all cases and verifying proper battery voltage and current during recharge.
a. Alternate Bid #2: To fabricate and install exterior steel staircase ladder at the southside of Building N254. To submit shop drawings for approval prior to fabrication of steel staircase ladder.
b. Alternate Bid #3: Replace UPS batteries with new battery cabinets
i. Install new UPS battery cabinets instead of re-use of existing cabinets. The battery cabinets shall be newly manufactured by the UPS manufacturer and certified and warrantied for use with the UPS batteries and UPS modules.
1.5 ADDITIONAL CONTRACTOR INSTRUCTIONS
a. Qualifications:
i. The Construction Contractor is required to provide employees who are California licensed professionals, certified and experienced in performing the work required under the conditions existing for the project.
SECTION 01 00 00 Page 8
ii. The Contractor and all Subcontractors and the Manufacturer of the HVAC and UPS equipment shall have at least 10 years of demonstrated successful experience in performing work at Mission Critical Facilities (Data Centers in particular) comparable to the work necessary on this project.
iii. The Vendor selected to supply the portable HVAC equipment for temporary cooling of Room 122 and the portable UPS system for temporary power during construction shall have at least 10 years of successful experience in supporting High Availability Mission Critical requirements.
iv. The Contractor shall designate a qualified Supervisor or Superintendent who has the authority to act as a representative for the Contractor during the course of the project and shall be on site during the performance of any work.
a. All Contractor personnel working on this project must be U.S.
Citizens. A Green Card is not acceptable.
b. The Contractor shall provide Submittals to NASA for prior approval of all equipment and material used for the construction of this project.
c. After reviewing the documents associated with this project, the Contractor shall conduct all necessary field inspections and investigations to verify all dimensions, ratings, existing conditions, existing locations, quantities, and practical means and methods prior to start of work in order to successfully install the new HVAC and UPS equipment.
d. The Contractor shall provide a “Preliminary HVAC Installation Plan” and a “Preliminary UPS Installation Plan” for NASA review and comment.
These plans shall include all elements defined in this Section.
e. The Contractor shall provide a “Final HVAC Installation Plan” and a “Final UPS Installation Plan” for NASA approval, incorporating NASA’s review comments and the proposed installation date at least 60 days in advance to allow coordination with N254 operations and users. These plans must address all elements defined in this Section. These plans must be consistent with the Construction Phasing Plan defined in this Section 01 00 00 and the Project Schedule.
f. Lifting operations for removal of the existing evaporative coolers and placement of the new HVAC units shall require a Lift and Rigging Plan approved by NASA 30 days in advance of the installation date.
g. The Contractor shall provide written documentation of all test results for NASA review prior to cutting over the new HVAC and UPS equipment to permanent operation of the N254 cooling and electrical loads.
Tests of the new HVAC and UPS equipment shall include:
i. Standard Factory Acceptance Tests
ii. NETA Acceptance Tests prior to energization
iii. Functional Tests following energization
SECTION 01 00 00 Page 9
h. All required equipment and materials and temporary cooling and power sources shall be on-site at N254, successfully tested, and ready prior to NASA’s final approval to proceed with the HVAC and UPS replacement work.
i. Project close-out shall include the specified as-built drawings and reports of all factory and field tests. Hardcopy and electronic versions are required.
PART 2 PRODUCTS
2.1 NEW MATERIALS
All equipment and materials incorporated into the work by the Contractor shall be new, first-class, and delivered in the original unopened containers, except as otherwise specified and compliant to Buy America Act.
2.2 REUSED SALVAGE MATERIALS
Materials and equipment designated in the contract documents to be salvaged or reused shall be carefully removed, by the Contractor, so as to minimize damage thereto. The Contractor shall protect, store, clean, and recondition them prior to reinstallation or turning over to the Government.
2.3 GOVERNMENT-FURNISHED PROPERTY
NASA is not providing any Government Furnished Equipment as part of this project.
2.4 EQUIPMENT FABRICATION & INSTALLATION
Equipment fabrication and installation shall comply with UL, IEEE and NFPA standards and the specific standards listed in Section 1.3 above.
PART 3 EXECUTION
The building N254 Telecom Gateway Facility is a mission critical facility supporting many NASA missions and critical communications functions.
Consequently, all construction work in this facility shall minimize the risk to the 24X7X365 operations and shall avoid to the greatest extent possible any and all electrical power or cooling outages. All work shall, therefore, be very carefully planned and executed with complete coordination with the responsible NASA personnel. The following special requirements and/or restrictions apply.
3.1 PROJECT MANAGEMENT
The Contractor shall provide an on-site Project Manager during normal working hours Monday through Friday and during non-prime time and weekend events such as power outages, electrical cutovers and testing.
a. The Project Manager shall actively participate in on-site weekly progress meeting in person where the accomplishments of the past week and planned work for the next three weeks is reviewed. The Project Manager shall provide a three-week look ahead schedule. These meetings shall be a forum for identification of problem areas and potential solutions, review of detailed work scripts, shutdown and test plans, SECTION 01 00 00 Page 10 and scheduled outages.
b. In the event of an exception where the Project Manager is unable to participate in the progress meeting, the Contractor shall designate in advance of the meeting, a representative who is familiar with the project’s status to participate in the meeting.
c. In the event of an absence of the on-site Project Manager, the Contractor shall designate in writing an on-site representative who is familiar with the project and who is authorized to make decisions for the Contractor.
d. The Contractor shall immediately notify the NASA PM of work not previously identified that may put the facility at risk during construction.
e. The Contractor shall provide detailed preliminary and final “Installation Plans” for NASA approval at least 60 days prior to the planned installation dates. The plans shall include detailed scripts for all work tasks for:
i. HVAC Replacement.
ii. The installation and testing of the temporary UPS System prior to use including the procedure for transition of the IT loads to/from the temporary UPS System.
iii. UPS replacement and testing of the new UPS and its batteries.
3.2 SHUTDOWNS AND OUTAGES
The following requirements are in addition to the requirements specified in Section 01 14 00 WORK RESTRICTIONS Paragraph 1.3 "Contractor Access and Use of Premises".
a. Facility-wide outages of electrical power and HVAC are prohibited.
b. Shutdowns: All planned shutdowns of electrical power circuits or HVAC equipment in the N254 facility shall be thoroughly coordinated in advance with NASA. At least 60 calendar days of advanced notice is required in order for NASA review and notification of the facility users. NASA approval of shutdowns and associated detailed work plans is required. All planned outages, whether mitigated with temporary sources or not, shall meet this requirement. Planned outages shall be identified in the project schedule and construction plans. Outage events shall be performed on weekends to minimize the risk to facility users.
c. Outages: Outages of electrical power circuits that supply IT equipment shall not exceed one hour in duration.
d. Detailed Scripts: The Contractor shall provide a detailed "script" outlining the specific steps to be performed for the individual outage, cutover, or test. The script shall be provided to NASA for review and approval at least 21 calendar days in advance of the event.
3.3 FACILITY SECURITY AND WORKER ACCESS
The following requirements are in addition to the requirements specified
SECTION 01 00 00 Page 11 in Section 01 14 00 Work Restrictions Paragraph 1.4 “Security Requirements”. Because of the secure nature of the Security Operation Center (SOC) at N254, the Contractor must comply with the following unique security requirements:
a. All information provided by NASA to the Contractor in the execution of this project has been determined to be “Controlled Unclassified Information” (CUI). This requirement shall flow down to all Subcontractors and Partners engaged in this project by the Contractor.
Information includes engineering drawings, specifications and photographs either in hardcopy or electronic format. The Contractor and their Subcontractors are responsible for safeguarding CUI information and returning all CUI hardcopy and electronic information to NASA at the completion of the project. The requirement for managing CUI information is defined in NASA Interim Directive (NID) 1600.55. Five percent (5%) of the contract value will be withheld until all CUI information is returned at the end of the project.
b. All Contractor personnel who perform work on this project shall be U.S. Citizens, Green Card workers are not acceptable. This requirement is applicable to design, construction and testing personnel.
c. Access to the N254 facility and the internal computer Rooms is controlled by an electronic access control system requiring use of a NASA-issued hard badge. NASA will provide a limited number of hard badges to designated Contractor employees for access to the facility.
d. Badging
i. All individuals applying for access to NASA Ames Research Center are subject to fingerprint background check.
ii. For contracts with a duration of 180 day or longer, the Contractor’s Project Manager, Superintendent and other permanent employees located on-site shall apply for the “hard” badge within 10 working days of the Contract Award date.
iii. The Contractor shall submit a Badge Request to the COR for each worker scheduled to come on-site, at least two working days prior to the work scheduled. Three types of badges are issued by NASA.
The amount of information required, and the level of background investigation increases with the length of time a person requires access to ta NAS Center. Badge types are:
Visitor Badge – Required for any person visiting or working at a NASA Center (or combination of NASA Centers) for a cumulative total of less than 30 days in a calendar year.
Temporary Badge – Required for any person working at a NASA Center (or combination of NASA Centers) for a cumulative total of more than 30 days, but less than 180 days in a calendar year.
Hard Badge – Required for any person working at a NASA Center (or combination of NASA Centers) for a cumulative total of 180 days or longer in a calendar year.
iv. Temporary badges issued for regular working hours are not valid for work outside regular working hours. Work outside regular working hours requires a separate temporary badge request.
v. Employees shall wear and display the badge in the chest area at
SECTION 01 00 00 Page 12 all times while entering, remaining in, and exiting Ames. Each badge shall be used only by the specific individual named on the badge. Badged construction workers are authorized access only to the Project Site. They are not permitted to be outside the project boundaries except to perform contract work and to enter or leave Ames Research Center via the most direct route.
vi. Delivery truck drivers do not require badges if they have a valid U.S. State issued driver’s license and a printed bill of lading with the delivery location, building number and the name of the Contractor and recipient.
vii. The Contractor must maintain strict accountability over identification badges and passes issued by the Pass and ID Office.
Immediately report to the PASS and ID Office, any badges/passes missing or lost and the circumstances. Return badges/passes to the COR immediately upon termination of any employee, expiration, completion of contract, or when no longer required. The COR will ensure that all badges/passes are returned and forwarded to the PASS and ID Office.
3.4 WORK IN N254 COMMUNICATIONS FACILITY
The N254 facility must remain in full operation during the course of this construction. To mitigate the risk to communication services, NASA IT equipment, and NASA personnel the Contractor shall exercise particular caution and take steps to protect NASA personnel and equipment. The following requirements shall be met during construction within the facility:
a. Protection of personnel:
The Contractor shall provide warning signs, barriers and caution tape in areas where construction work is occurring to protect NASA personnel from construction-related injury. The Contractor shall be mindful of the other activities on-going in the facility and minimize the disruption to IT operations. When raised-floor panels are removed for under-floor access, caution tape and cones shall be placed to warn of the fall hazard.
b. Protection of IT equipment:
The Contractor shall protect the operating UPS and IT equipment in the area where construction is taking place from damage due to impact, dust and dirt, dislodging of cables, and overhead damage from falling debris. The Contractor shall protect under-floor and overhead cabling from damage in the work area.
c. Clean up:
At the end of each work day the Contractor shall remove all tools, materials and debris from the work area.
d. At the completion of the project, the Contractor shall thoroughly vacuum clean all Rooms where they performed work.
3.5 NASA MISSION FREEZE CONDITIONS
There may be occasions when on-site work must be suspended to accommodate launch, on-orbit maneuvers and other high risk events in which NASA will
SECTION 01 00 00 Page 13 issue a “freeze” directive to support facilities. During the “freeze”, all construction and/or modification work will cease in order to reduce the risk of an unplanned event that would impact the mission. The N254 facility is subject to these freeze events, which have a typical duration of 1 to 14 weeks. During these events all N254-related construction shall be suspended. NASA will provide the Contractor as much advanced notice as possible of freeze events and will make every effort to mitigate construction impacts.
3.6 BURROWING OWL HABITAT
Western burrowing owl habitat and an owl breeding preserve presently exist north and east of the N254/N254A fence lines. Development and construction activity at Ames is regulated according to the Burrowing Owl Habitat Management Plan (BOHMP). Where there is a discrepancy between the BOHMP and these notes, the BOHMP takes precedence.
Pursuant to the BOHMP, the project is governed by the following:
a. No permanent development or temporary construction activity is permitted within the preserve to avoid impacts to owls.
i. Impacts to owls include disturbance within 160 feet of an occupied burrow, destruction of an active burrow, or destruction/degradation of foraging habitat within 300 feet of an occupied burrow.
ii. To avoid "take" under the Migratory Bird Treaty Act and CDFG Codes, disturbance of active nesting territories should be avoided during the breeding season, from March 1 to August 31.
iii. To avoid impacts, disturbances must be 160 feet from occupied burrows during the non-breeding season and at least 250 feet away during the breeding season.
b. Equipment will not be staged within any preserve.
c. Surveys will be done within 1-2 weeks before starting any construction activity, including staging equipment. NASA will provide a qualified wildlife biologist to survey for occupied burrows upon request.
d. In the event that an occupied burrow or active nest is found within the relevant buffer, NASA will provide a qualified on-site biological monitor to ensure that disturbances do not cause burrow or nest abandonment. Biological monitor may use standard methods, including temporary stop-work and changing the work schedule to avoid times of day most likely to affect owls. The Contractor will coordinate monitoring schedule with Chris Alderete by phone at 650-604-3532 or by email at christopher.s.alderete@nasa.gov.
e. During the breeding season, if an occupied burrow is found within the 250' buffer, work may be delayed until the NASA wildlife biologist determines that nestlings have fledged.
3.7 AIR EMISSIONS INFORMATION DURING CONSTRUCTION
The Contractor shall submit, annually (within the performance period) and upon request by the Contracting Officer (CO), information on construction
SECTION 01 00 00 Page 14 and demolition activities, including operational air pollutant emissions.
Submittal shall comply with the latest NASA Ames Research Center (ARC) Construction Emissions Mitigation Plan (CEMP), in a format compatible with ARC's air pollutant emissions estimating model, subject to approval by the
CO.
3.8 CONSTRUCTION PHASING
Project construction shall be performed in two major phases as follow:
a. Phase #1: HVAC Replacement
i. Install and test temporary HVAC for Room 122.
ii. Replace existing evaporative coolers with two packaged A/C units on the roof.
iii. Install controls for the A/C units and interconnect with the Facility Management Control System (FMCS).
iv. Start-up, balance, test and commission the new HVAC equipment.
v. Perform 30-day burn-in operational test to verify performance and reliability.
vi. Successful completion of the burn-in period and with NASA approval Phase #2 can begin.
b. Phase #2: UPS Replacement.
i. Install and test temporary UPS System and batteries.
ii. Phase #2.1: Replace UPS System #1.
1) Remove existing UPS Modules and batteries and install new UPS Modules.
2) Install new batteries in retrofitted existing battery cabinets.
3) UPS manufacturer to perform start-up and testing of new
UPS.
4) Restore UPS #1 to operational service with a 30-day burn-in period.
5) After successful performance of the 30-day burn-in, UPS #2 can be replaced.
i. Phase #2.2: Replace UPS System #2.
1) Remove existing UPS Modules and batteries and install new UPS Modules.
2) Install new batteries in retrofitted existing battery cabinets.
3) UPS manufacturer to perform start-up and testing of new
SECTION 01 00 00 Page 15
UPS.
4) Restore UPS #2 to operational service with a 30-day burn-in period.
5) After successful performance of the 30-day burn-in, UPS replacement is complete.
3.9 TEST PLANS
The Contractor shall prepare the test plan/script for each test specified.
The test plan will define the sequence of events required to meet the objectives of the test and be designed to ensure the safety of personnel conducting the test, ensure safety of the N254 facility and its IT operations, mitigate risk to IT operations, and use resources efficiently.
The test plan/script shall be submitted to the CO at least 30 calendar days prior to the planned test event for NASA approval.
3.10 PROJECT HOLD POINTS
Specific hold points for inspections are defined on the "Permit and Inspection Record" to be posted at the job site and may include, but not be limited to some or all of the following areas.
a. Underground Utilities -- after piping/conduit is in place and bedded, but before it is covered.
b. Foundation/Concrete Pre-pour -- after formwork/rebar is in place, but before concrete is mixed.
c. Frame -- After framing, rough electrical, plumbing, vents, and duct work are in place, but before sheathing.
d. Electrical -- raceways, pull boxes.
e. Bolt/Welding -- after bolts are torque wrench tightened and welds made, but before painting or covering.
f. Hazardous Analysis -- Checking for lead and asbestos.
g. Compaction Testing -- under pads and over duct banks.
3.11 FINAL WALK THROUGH
A final walk through will be done at the completion of the project to verify that all punch list items have been addressed. The Contractor's Project Manager shall be present at the walk through.
3.12 CONTRACTOR STAGING AREA
The material and equipment staging area will be in the immediate vicinity of Bldg. N254/N254A. A specific location has not been determined yet, but the Contractor can assume it will be immediately south of Bldg. N254A.
-- End of Section --
SECTION 01 00 00 Page 16
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 SUMMARY
1.2 WORKING DAYS DEFINITION
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
1.3.2 Entry to Radiologically Controlled Areas
1.3.2.1 Radioactive Materials and Equipment
1.3.3 Working Hours
1.3.4 Work Outside Regular Hours
1.3.5 Occupied and Existing Buildings
1.3.6 Utility Cutovers and Interruptions
1.3.7 Hot Work (Welding, and Burning) Permits
1.3.8 Location of Underground Facilities
1.3.9 Notification Prior to Excavation
1.3.10 Site Work
1.4 SECURITY REQUIREMENTS
1.4.1 Employment Restrictions
1.4.2 Badging Requirements
1.4.3 On-Site Security
1.4.4 WORK BY NASA CONTRACTORS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
Revised: 05/2024
PART 1 GENERAL
1.1 SUMMARY
This section covers the requirements for work and site restrictions.
1.2 WORKING DAYS DEFINITION
In all sections of these specifications the term "working days" shall refer to the Government's working days: 5 days per week excluding Government holidays.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Permission to interrupt any Base roads, and/or utility service shall be requested in writing a minimum of 10 working days prior to the desired of interruption.
Ensure that Contractor personnel employed on the Base become familiar with and obey Base regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification
1.3.2 Entry to Radiologically Controlled Areas
Contractor personnel shall not, under any circumstances, enter a radiologically controlled area or cross any posted radiological boundary.
This paragraph applies to all phases of contract work. Radiation areas are posted with signs consistent with OSHA requirements. Ensure that employees are familiar with the radiation signs and symbols.
Should contract workers encounter radiological postings and/or boundaries which appear to limit their ability to access or carry out their intended work, they shall notify their contract administrator for resolution of the problem.
1.3.2.1 Radioactive Materials and Equipment
All testing equipment, containing a radioactive source, shall be operated in accordance with an approved radioactive equipment plan. This plan shall be submitted to the COR and approved by the Radiation Officer, prior to bringing the equipment on-site. This plan shall include:
a. The name and type of equipment.
SECTION 01 14 00 Page 2
b. The type and size of radiation source.
c. The dates and locations of the equipment's usage.
d. The radiological controls that the Contractor will use while operating the equipment.
A different radioactive equipment plan will be required for each different type of equipment, type of radioactive source, or size of radioactive source. A data sheet of for each piece of new radioactive equipment shall be submitted to the COR to forward to the Government's Radiation Safety Officer. The data sheet shall contain the following information:
a. Name of equipment.
b. Name and address of equipment manufacturer.
c. Type and size of radiation source.
d. The location of the installed radioactive equipment (i.e. building no., floor, code/shop area).
1.3.3 Working Hours
Regular working hours shall consist of a period established by the COR, between 7 a.m. and 5:00 p.m., Monday through Friday, excluding Government holidays.
1.3.4 Work Outside Regular Hours
Work outside regular working hours requires COR approval. Make application 5 working days prior to such work giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the COR may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the COR.
1.3.5 Occupied and Existing Buildings
Provide temporary closures as required to maintain security as directed by the COR.
Provide dust covers or protective enclosures to protect existing work that remains and Government material during the construction period.
Provide dust covers or protective enclosures to protect existing work that remains and Government material during the construction period.
1.3.6 Utility Cutovers and Interruptions
a. The Contractor shall verify the elevations of existing piping and utilities.
b. Work shall be scheduled to hold outages to a minimum.
c. COR may permit utility outages at his discretion.
d. Contractor shall not be entitled to additional payment for utility outages and connections required to be performed outside the regular
SECTION 01 14 00 Page 3 work hours.
e. Requests for utility outages and connections shall be made in writing to the COR at least 15 calendar days in advance of the time required.
Each request shall state the system involved, area involved, approximate duration of outage, and the nature of work involved.
Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays unless otherwise approved by the COR. Conform to procedures required in the paragraph "Work Outside Regular Hours."
f. Interruption to water, sanitary sewer, storm sewer, telephone or data service, electric service, air conditioning, heating, fire alarm, natural gas, and compressed air, shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
g. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
h. Interruption to water, sanitary sewer, storm sewer, telephone or data service, electric service, air conditioning, heating, fire alarm, natural gas, and compressed air, shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
i. Building-wide shutdowns shall require 15 working days advanced written notice to the COR. Government will make required Center notifications.
j. Utility shutdown: Do not operate any utilities without prior permission from the COR. This includes, but is not limited to, opening or closing valves or switches. Government will shutdown system.
1.3.7 Hot Work (Welding, and Burning) Permits
ACTIVITY SUBMISSION DATE
Hot Work Permits 15 calendar days prior to work
Permits shall be posted at a conspicuous location in the construction area.
Burning of trash or rubbish is not permitted on project site.
Any off-site burning of trash or rubbish shall be done in strict compliance with requirements established by the authority having jurisdiction.
1.3.8 Location of Underground Facilities
Obtain excavation permit prior to start of excavation by contacting the COR 15 calendar days in advance. The Contractor shall hire a professional utility locating company to locate and mark the surface of the ground where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
SECTION 01 14 00 Page 4
1.3.9 Notification Prior to Excavation
Notify the COR at least 5 calendar days prior to starting excavation work.
Contractor is responsible for marking all utilities.
1.3.10 Site Work
Limit surface loading to 5,000 pounds per square foot in paved areas, and 2,000 pounds per square foot in unpaved areas unless an analysis by a licensed professional engineer demonstrates higher values can be used.
1.4 SECURITY REQUIREMENTS
1.4.1 Employment Restrictions
All personnel who perform on-site work on this contract must be either a U.S. citizen or a Legal Permanent Resident with a permanent resident card (green card) in their possession. All personnel must also be in possession of a current federal government approved photo ID.
1.4.2 Badging Requirements
a. All individuals applying for access to NASA Ames Research Center are subject to a fingerprint background check.
b. For contracts with a duration of 180 days or longer, the Contractor's Project Manager, Superintendent and other permanent employees located on-site shall apply for a "Hard" Badge within 10 working days of the Contract Award date.
c. The Contractor shall submit a Badge Request to the COR for each worker scheduled to come on-site, at least two working days prior to the work scheduled. Three types of badges are issued by NASA. The amount of information required and the level of background investigation increases with the length of time a person requires access to a NASA Center. Badge types are:
Visitor Badge -- Required for any person visiting or working at a NASA Center (or combination of NASA Centers) for a cumulative total of 29 days or less in a calendar year.
Temporary Badge -- Required for any person working at a NASA Center (or combination of NASA Centers) for a cumulative total of more than 29 days, but less than 180 days in a calendar year.
Hard Badge -- Required for any person working at a NASA Center (or combination of NASA Centers) for a cumulative total of 180 days or longer in a calendar year.
d. Temporary badges issued for regular working hours are not valid for work outside regular working hours. Work outside regular working hours requires a separate temporary badge request.
e. Employees shall wear and display the badge in the chest area at all times while entering, remaining in, and exiting Ames. Each badge shall be used only by the specific individual named on the badge.
Badged construction workers are authorized access only to the Project Site. They are not permitted to be outside the project boundaries
SECTION 01 14 00 Page 5 except to perform contract work and to enter or leave Ames Research Center via the most direct route.
f. Delivery truck drivers do not require badges if they have a valid U.S.
State issued driver's license and a printed bill of lading with the delivery location building number and the name of the Contractor and recipient.
g. Maintain strict accountability over identification badges and passes issued by the Pass and ID office. Immediately report to the Pass and ID Office, any badges/passes missing or lost and the circumstances.
Return badges/passes to the COR immediately upon termination of any employee, expiration, completion of contract, or when no longer required. The COR will ensure that all badges/passes are returned and forwarded to the Pass and ID Office.
1.4.3 On-Site Security
a. Restore all…
This is the start of the file's text. The full file is on GovTribe.