Summary of IFB - SGES Guided Horizontal Directional Drill (HDD) Under I-15 @ 400 East
This document set comprises technical specifications and general requirements for the City of St. George's Invitation for Bid (IFB) to perform a guided horizontal directional drill (HDD) installation beneath Interstate 15 at the 400 East crossing. The project involves installing seven (7) 3-inch HDPE Schedule 40 or IPS DR 13.5 continuous conduits to replace existing overhead power distribution facilities. Work must be completed within 30 calendar days of the Notice to Proceed, with liquidated damages assessed at $500.00 per calendar day for any delays. The scope includes bore and receiving pit excavation and backfill, traffic control acceptable to both UDOT and the City of St. George, potholing to verify existing utilities and bore alignment, flowable fill placement if authorized, and restoration of disturbed areas. Road closures are prohibited; shoulder closures and temporary use of center turn lanes are permitted. The contractor is responsible for obtaining all required UDOT and City encroachment permits, though anticipated permit fees are $0. A mandatory pre-bid meeting including site visit is required, and all submittals including a preliminary exhibit describing means and methods must accompany the bid proposal.
Conduit materials shall consist of 3.5-inch outer diameter HDPE continuous conduit with #12 coated copper tracer wire and a temporary secondary box (Carson #1419-12-4B). Flowable fill, if authorized, must conform to UDOT requirements with a minimum compressive strength of 50 psi. The contractor bears all costs for materials, labor, equipment, spoil disposal, drilling fluid management, potholing, traffic control design and maintenance, and environmental compliance including dust control and stormwater pollution prevention measures. All work must conform to current SGES Standards, UDOT specifications, City of St. George standards, and applicable federal safety regulations. A 5% bid bond is required with submission, and a 100% performance bond covering labor and materials will be required upon award. The contractor is responsible for re-testing and re-inspection costs when work fails to meet specifications, and any settlement or asphalt cracking resulting from borehole construction must be coordinated with UDOT personnel at the contractor's cost.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
weston.nelson Engineer 04.02.2026 weston.nelson Text Box SGES Guided Horizontal Directional Drill (HDD) Under I-15 @ 400 E.
Special Provisions-1
SPECIAL PROVISIONS
Standard Specifications
The City of St. George Standard Specifications for Design and Construction, July 1, 2000, Edition, latest revision, including all addenda shall govern the construction of this contract except as modified in these special provisions and the general conditions of the contract provided heretofore. The contractor shall always have a complete copy of the above-mentioned specifications on the project.
In case of conflict between the City of St. George Standard Specifications for Design and Construction and the general conditions, special provisions, modifications, and additions included in these agreements, the special provisions, modifications, and additions shall govern.
Guided HDD Utility Installation 02772S – Page 1 of 6
March 23, 2026
SPECIAL PROVISION
PROJECT # S-I15-1(146)6
PIN #18218
SECTION 02772S
GUIDED HORIZONTAL DIRECTIONAL DRILL (HDD)
UTILITY INSTALLATION
PART 1 GENERAL
1.1. SECTION INCLUDES
A. Materials and procedures for installing a buried utility by means of a guided horizontal directional drill (HDD).
1.2. RELATED SECTIONS
A. Section 01355: Environmental Protection
B. Section 01554: Traffic Control
C. Section 02056: Embankment, Borrow, and Backfill
D. Section 02316: Roadway Excavation
E. Section 02610: Drainage Pipe
F. Section 02922: Seed, Turf Seed, And Turf Sod
G. Section 03575: Flowable Fill
H. Section 13553: ATMS Conduit
1.3. REFERENCES
A. American Water Works Association (AWWA) Standards
B. Utah Administrative Code
C. American Railway Engineering and Maintenance-of-Way Association (AREMA) Standards
02772S – Page 2 of 6
1.4. DEFININTIONS
A. Carrier – A pipe or conduit directly enclosing a utility.
B. Casing – A steel pipe enclosing a carrier for the purpose of providing structural or other protection to the carrier or to allow for carrier replacement without excavation. (For this project, conduits are planned to be pulled through the borehole without a casing)
C. Roadway Prism – The roadway cross section that contains the embankment, pavement, shoulders and other features, together with the subsoils that underlie the same to the maximum depth of the subject utility.
1.5. SUBMITTALS
A. A stamped Guided HDD Plan (Borehole Plan) is included with the bid documents. The Contractor shall provide a pdf copy of their borehole plan that conforms to the stamped plan and demonstrates their means and method to complete the work.
1. The Contractor shall provide a preliminary exhibit and description of their means and methods to complete the bore shot with their bid proposal. Upon receipt of Notice of Award, Contractor shall provide other required submittals required by bid documents.
B. Include the following information: Please note: Applicable geotechnical information provided by UDOT design engineers working on the I-15 widening project is included with these bid documents.
1. Traffic Control Plan – Comply with Section 01554:
a. Location and dimensions of adjacent access roads
b. Location and dimensions of bore pit area “footprint”
c. Proposed traffic control
d. Amount of time the footprint will be exposed
2. Installation Plan:
a. Manufacturer’s current recommended installation for each type of pipe used and any incidental materials required for installation
b. Location and dimensions of bore pit
02772S – Page 3 of 6
c. Method of shoring, including details for all required ground support
d. Method of controlling line and grade
e. Method of spoil removal, including surface storage and disposal
f. Grouting techniques to be used for filling annular voids caused by over excavation if any, including equipment, pumping and injection procedures, flowable fill and mixture. Flowable fill mix shall conforms to UDOT Standard Specification 03575 “flowable fill,” with a minimum strength of 50 psi.
g. Method of dewatering and disposal
h. Emergency safety and repair plan for accidental damage caused to existing utilities, roadway surface, or other features resulting from construction operations
C. Do not begin work until the submittals have been reviewed and accepted by the Engineer.
1. The Engineer will have 10 working days for review and acceptance.
2. Provide new submittals upon receiving notification that the submittals are sufficient.
a. Allow an additional 7 working days for the Engineer’s review and acceptance.
D. Alternative mix design: Refer to this Section, article 3.2.G for requirements.
1.6. QUALITY ASSURANCE
A. Third party utilities must meet the requirements of Utah Administrative Code Rule 930-7.
B. Adhere to manufacturer standards for products and installation methods.
1.7. ACCEPTANCE
A. Provide the Engineer horizontal and vertical alignment data, in latitude and longitude coordinates and elevation in feet, pertaining to the termini of installation, including but not limited to the beginning and end points and all intermediate boxes.
02772S – Page 4 of 6
B. Perform inspection and acceptance according to Section 02610 for carriers with a diameter greater than 12 inches.
PART 2 MATERIALS
2.1. (7) 3-inch HDPE Schedule 40 or IPS DR 13.5 Continuous Conduit
A. HDPE Conduit (Carrier for Future Power Conductors)
1. No casing is required if the carrier is structurally capable of resisting loading encountered during installation or during operation beneath highway facilities and is not required by this Section, article 2.1.A.
a. Carrier is to be locatable.
b. Refer to Section 13553 for requirements for detectable pull tape.
PART 3 EXECUTION
3.1. PREPARATION
A. Contractor shall attend the mandatory pre-bid meeting which will include visiting the site of the proposed borehole location. Prior to bidding, the Contractor shall review the stamped borehole plan, site conditions, and all geotechnical information provided with the bid documents.
1. Interpretation of soil investigation reports and data, investigating the site, and determination of the site soil conditions is the sole responsibility of the Contractor.
B. Verify the position of nearby utilities before installation. The horizontal and vertical location for the borehole, and clearances from existing and proposed utilities, is established per stamped plan.
C. The design of a bore pit and required bearing to complete the HDD is the responsibility of the Contractor.
D. Excavation:
1. Refer to Sections 02316 and 01355
2. Keep bore pit free of water.
a. Dewater according to the installation plan
b. Disposal of water must not cause damage or become a nuisance.
02772S – Page 5 of 6
E. Place bore pits outside the AASHTO clear zone.
1. Refer to TC Series Standard Drawings for mitigation if the bore pits cannot be located outside the AASHTO clear zone.
2. For City of St. George public streets outside of the UDOT ROW, all traffic control shall conform to current MUTCD standards for traffic control. If the bore pit is outside of the AASHTO clear zone next to a city street, refer to MUTCD traffic control requirements. If any traffic control is required within the I-15 ROW, refer to TC Series Standard Drawings for Traffic Control requirements.
3.2. INSTALLATION – GENERAL
A. Install the utility specified in the contract documents to the alignment and profile shown on the plans.
B. Continuously monitor the location and alignment of the pilot bore progress to insure compliance with the proposed installation alignment and to verify depth of the bore.
1. Provide the Engineer as-built drawings and an accurate log of the utility boring upon completion of the bore.
C. Monitor worksite for indications of displacement of the roadway prism and escaping boring fluids.
1. Suspend work immediately whenever fluids seep to the surface other than in the boring entrance or exit pit or when the paved surface is displaced.
a. Propose a method for acceptance by the Engineer to prevent further seepage or displacement before resuming the boring operation.
2. Provide GPS survey of the existing surface within the vicinity of the installation and at other locations as requested by the Engineer before and at the conclusion of the installation.
a. Changes to the existing surface will be evaluated and repaired at no additional cost to the Department.
b. Remediation plans must be approved by the Engineer before any work proceeds when required.
D. Repair any damage to the carrier conduits due to the HDD at no additional cost to the City.
02772S – Page 6 of 6
E. Contain excess boring fluids at the entry and exit points until recycled or removed from the site.
1. Verify that all boring fluids are disposed of in a manner acceptable to the appropriate local, state, and federal regulations.
F. Leave no exterior voids along the bore hole.
1. Fill the voids with an approved pressurized grout material at no additional cost to the Department if voids develop greater than the outside diameter of the conduit by 1 inch.
G. Fill the void immediately with flowable fill if an obstruction is hit during construction and the bore path is to be abandoned. Refer to Section 03575 for an approved mix design or submit an alternative mix design to be approved by the Region Materials Engineer.
1. Submit a new installation plan to the Engineer for approval before resuming work at another location.
H. Do not allow the use of water under pressure (jetting) or puddling to facilitate boring or jacking operations.
I. Seal the ends of the casing and carrier with structural grout to provide a barrier against debris and seepage between the two.
3.3. RESTORE EXCAVATED AREA
A. Restore excavated or disturbed area to pre-installation conditions.
B. Backfill and compact excavation material to match the shape of the surrounding surface. Refer to Section 02056.
END OF SECTION
General Requirements & Project Description 101 - 1
SECTION 101
GENERAL REQUIREMENTS & PROJECT DESCRIPTION
1.1 SUMMARY OF THE WORK.
The BID SCHEDULE includes the construction and installation of a guided horizontal directional drill (HDD) under I-15 for seven (7) 3” conduits as per drawings stamped by
SGES dated March 2026. Work to include but is not limited to the following tasks:
a. Encroachment Permits: Work will be completed within UDOT right-of-way (ROW) and public streets. The Contractor shall obtain all required UDOT and City of St. George encroachment permits and comply with all permit conditions. The Contractor shall coordinate its work with UDOT and
City personnel. Permit fees are anticipated to be $0 for this work; however, the Contractor remains responsible for all actions, submittals, bonds/insurance documentation, and compliance required to obtain permits. The Contractor shall provide traffic control acceptable to UDOT and the City as required by the Contractor’s means and methods. Also, see Section 1.4 below.
b. Bore and Receiving Pits: The Contractor is responsible for all excavation and backfill work required for the bore and receiving pits. Surrounding areas are to be returned to before installation state. There are constraints for the bore and receiving pits. The plan identifies the approximate distance between the “Begin Borehole” and existing curb and gutter at 900 South. Please note that utilities south of the bore alignment are not shown on the profile view but the Contractor will need to consider how these utilities, including gas and fiber optic, may impact their operation. On the north side of I-15 the receiving pit may impact existing curb and gutter. For this project, road closures are not permitted but shoulder closure will be allowed. Traffic control may utilize the center turn lane where available to temporarily shift traffic. The Contractor must include with their bid proposal a preliminary exhibit and description of their means and methods to complete the borehole.
This shall include but not be limited to describing how their operation will be able to place the bore machine in the bore pit, to complete the borehole, stage and pull conduit, and work within these constraints. Incidental work under this section includes potholing/test holes as necessary to locate and verify existing utilities and determine bore and receiving pit extents, excavation, backfill, surface restoration, and coordination with utility owners. Traffic control for potholing shall be provided under Bid Item #4.
c. NOI & SWPPP: Excavation and stockpiled earth at the bore and receiving pits are anticipated to be less than one (1) acre at each location. As such, filing an NOI is not required. However, if total land disturbance at one or the other location meets or exceeds one (1) acre due to the Contractors means and methods, the Contractor shall be responsible for all plans, permits, filings, work, and costs to obtain coverage under the applicable construction stormwater permit (NOI) and prepare and implement a SWPPP acceptable to the City and UDOT. Regardless of whether the NOI is filed or not, the Contractor shall implement appropriate stormwater pollution prevention measures using best management practices (BMPs) throughout the project which shall include, but not be limited to dust control, proper containment/disposal of drill fluid and grout, inlet protection, and track-out control, etc.…. The City of St. George will provide a temporary water meter for construction.
d. Guided Horizontal Directional Drill: A guided horizontal directional drill (HDD) under I-15.
The horizontal and vertical location of the borehole must be verified beginning to end in accordance
General Requirements & Project Description 101 - 2 with UDOT specifications to provide adequate clearances under existing and proposed utilities shown per stamped plan and provide six feet minimum horizontal clearance between the borehole and the future MSE wall as shown on the stamped plan. Verification may include potholing/test holes as required based on the Contractor’s equipment capabilities, tracking limitations, and means and methods. Potholing shall be performed as necessary to verify clearances and avoid conflicts;
nonperformance does not relieve the Contractor of meeting plan clearances and the required borehole alignment tolerances. Potholing excavation/backfill/restoration to complete the borehole and verify the horizontal and vertical location of the borehole is incidental this item (Bid Item #2);
traffic control for potholing is included under Bid Item #4. See Section 02772, “Guided HDD,” included with the Special Provisions. Contractor is responsible for all materials, means, and methods required to stabilize the hole, pull conduit through the borehole, and fill the void space with flowable fill if necessary. If the borehole causes any settlement under the roadway, and/or asphalt cracking, the Contractor will need to coordinate a solution with UDOT personnel and be responsible for the work and cost to rectify. The Contractor will be required to mandrel all conduits after final placement and grout work is complete.
e. Materials: Contractor shall provide all materials, labor, and equipment to complete the Work.
Conduit installed within the borehole shall be seven (7) 3-inch conduits (3.5-inch O.D.), Schedule
40 or IPS 13.5 HDPE continuous conduit, or approved equal as approved by the Engineer who will coordinate with UDOT (gray color). Tracer wire shall be #12 coated copper wire. Temporary secondary box: Carson #1419-12-4B per SGES Standards. Flowable fill (if authorized) shall conform to UDOT requirements.
f. Traffic Control: The Contractor shall be responsible for all traffic control measures required by its operations, including design, setup, maintenance, and removal. Traffic control shall be acceptable to UDOT and the City of St. George. Road closures are not permitted; shoulder closures will be allowed. Traffic control may utilize the center turn lane, where available, to temporarily shift traffic. Traffic control costs shall be paid under Bid Item #4, including traffic control for any potholing.
g. Spoils: All spoils/drilling fluids removed from each site shall be hauled off-site and legally disposed of by the Contractor.
h. Standards: Contractor shall conform to current SGES Standards and applicable UDOT and City of St. George specifications and standards.
i. Testing and Inspections: Testing and inspection costs will be covered by the Owner. The
Contractor shall coordinate and schedule required testing and inspections (including during flowable fill placement, if authorized, and soil compaction testing). The Contractor shall be responsible for the cost of re-testing and/or re-inspection when required due to failed tests and/or deficient work.
j. Construction Staking: Survey work will be completed and covered by UDOT personnel or their project surveyor in accordance with UDOT Standard Specification 01721. UDOT will provide stakes for the borehole. If re-staking is required due to the Contractor’s operations disturbing or removing stakes, the Contractor shall be responsible for such costs. The City of St. George will retain a surveyor to check installed work; the cost for the City-retained surveyor will be covered by the City.
General Requirements & Project Description 101 - 3
Refer to Sections 106, “Mobilization,” and 107, “Method of Measurement and Basis of Payment” within the Technical Specifications for additional information regarding bid items and included work for the various payment items.
1.2 CONTRACT TIME.
The Contractor will be required to meet the following time schedule. All work must be completed within 30 calendar days of the issuance of the Notice to Proceed.
a. In the event the contractor(s) does not meet the above time schedule, liquidated damages of $500.00 per calendar day for each calendar day used beyond the contract time indicated will be assessed.
1.3 CONSTRUCTION STAKING.
The OWNER will provide construction staking via UDOT’s personnel or hired surveyor to establish the horizontal and vertical location at the beginning and ending of the borehole.
The Contractor shall pothole to field verify the location and elevation of existing utilities above the borehole. The Contractor shall be responsible for protecting the construction stakes. Any re-staking will be the Contractors responsibility. Also see part “i” Construction
Staking of 1.1 Summary of Work above.
1.4 ENCROACHMENT/TRAFFIC PERMITS.
The Contractor shall be responsible to obtain all encroachment and/or traffic permits for the project and follow all required excavation, backfill, curb and asphalt replacement procedures.
See parts “a” and “e” of 1.1 Summary of Work above.
1.5 SAFETY AND HEALTH
The contractor shall comply with, and is responsible for enforcement of safety and health regulations for construction, promulgated by the Secretary of Labor under Section 107 of the
Contract Hours and Safety Standards Act, as set forth in Title 29, C.F.R.
a. Copies of these regulations may be obtained from the Labor Building, 14th and
Constitution Avenue NW, Washington, DC 20013.
b. The contractor shall also comply with the provisions of the Federal Occupational
Safety and Health Act as amended.
1.7 REFERENCES.
Abbreviations used in this specification for various societies, organizations, or government bodies shall stand for the following:
AASHTO American Association of State Highway and Transportation Officials
ACI American Concrete Institute
ANSI American National Standards Institute
ASTM American Society for Testing and Materials
AISC American Institute of Steel Construction
General Requirements & Project Description 101 - 4
AITC American Institute of Timber Construction
AISI American Iron and Steel Institute
APA American Plywood Association
AWWA American Water Works Association
AWS American Welding Society
FHA Federal Housing Authority
ICBO International Conference of Building Officials
NEC National Electrical Code
NEMA National Electrical Manufacturers' Association
NESC National Electrical Safety Code
NWWDA National Wood Window & Door Association
UL Underwriter's Laboratory
UBC Uniform Building Code
1.8 QUANTITIES AND PAYMENT.
The amount of work to be done, and materials or services to be furnished under the Contract as noted in the proposal, are estimates and are not to be taken as an expressed or implied statement that the actual amount of work or materials will correspond to the estimate. In the event the total amount of the lowest acceptable bid exceeds the amount of funds available for the project, the scope of work will be modified as determined by the Owner and Engineer.
a. The right is reserved to increase or decrease or to entirely eliminate certain items from the work or materials if found desirable or expedient, and the Contractor is cautioned against unbalancing his bid by prorating his overhead into one or two items only when there are a number of items on the proposal. The overhead and indirect charges should be prorated on all items in the proposal.
b. The Contractor will be allowed no claims for anticipated profits, loss of profits, or for damages because of any difference between the estimated and the actual amount of work done, or materials furnished or used in the completed project.
c. Other items of work defined in the specifications, but not listed in the Bid Schedule, shall be considered incidental to one or more of the items listed in the Bid Schedule and shall be paid for under the bid item listed to which it is related, as determined by the Engineer.
1.9 STANDARD SPECIFICATIONS AND REFERENCES
The City of St. George Standard Specifications for Design and Construction (latest edition) and the City of St. George Energy Services Underground Power Construction Standards
(latest edition) shall govern the administration and construction of this Contract, except as modified in these special provisions, otherwise these Special Provisions shall govern the work.
General Requirements & Project Description 101 - 5
The City's standard specifications and standard drawings can be found at:
https://sgcityutah.gov/departments/public_works/engineering/standard_specifications_and_drawings.php
The City's Energy Services Underground standards can be found at:
http://www.sgcityutah.gov/departments/energy_services/distribution_standards
A copy of all applicable City Standards, as well as this document, shall be located at the job site at all times.
The governing rankings in case of a discrepancy is:
Dimensions Information
1. Plan 1. Special Provisions & Contract Documents
2. Calculated 2. Plans
3. Scaled 3. Measurement and Payment
4. Standard Specifications
5. Standard Drawings
1.9.1 SELECTED UDOT STANDARD SPECIFICATIONS
The following UDOT Standard Specifications are incorporated as technical specifications on this project and are included hereafter. Replace all references to “Department” or “Owner” with “City of
St. George”. Referenced related sections not contained in the list below should reference the appropriate section found in the City’s specification included by reference in Section 1.9.1 of this document.
• SECTION 01355 – ENVIRONMENTAL COMPLIANCE
• SECTION 01554 – TRAFFIC CONTROL
• SECTION 01572 – DUST CONTROL & WATERING
• SECTION 01721 - SURVEY
• SECTION 02056 – EMBANKMENT, BORROW, AND BACKFILL
• SECTION 02316 – ROADWAY EXCAVATION
• SECTION 03575 – FLOWABLE FILL
• SECTION 13553 – ITS CONDUITS
1.9.2 POTHOLING EXISTING UTILITIES
Perform Potholing for potential utility conflicts, or to accurately locate and survey other subsurface facilities/items as needed.
Potholing (open cut excavation) for miscellaneous utilities or other subsurface facilities/items
1.1 Notify and coordinate with Utility Owner prior to excavation.
http://www.sgcityutah.gov/departments/energy_services/
General Requirements & Project Description 101 - 6
1.2 Provide traffic control in compliance with the Manual on Uniform Traffic Control Devices and project traffic control plan if pothole is to be located within an active roadway.
1.3 Provide equipment to locate and expose subsurface utility.
1.4 Provide labor to locate and expose subsurface utility.
1.5 Provide dewatering of excavation until utility is accurately located.
1.6 Repair any damage resulting from the potholing operation.
a. Provide the following temporary bituminous patching, only if pothole is within an active roadway with existing bituminous pavement.
b. Minimum of 6 inches of Untreated Base Course.
c. Minimum of 4 inches of Asphalt Concrete Mix.
Potholing is incidental to the borehole and bore and receiving pit Work specified by the Plans and applicable payment items. The contractor is responsible for potholing as necessary to avoid conflicts with existing infrastructure.
END OF SECTION 101
Project Meetings Section 102-1
SECTION 102
PROJECT MEETINGS
1.1 PRECONSTRUCTION CONFERENCE
A preconstruction conference between Engineer, Owner’s representative, and Contractor shall be held at the site prior to commencement of the Work.
a. This meeting shall be for the purpose of:
1. Resolving current problems
2. Further orienting Contractor to requirements of the Contract Documents
3. Informing Contractor of Engineer’s responsibility to Owner for inspection
4. Working out with Contractor a general schedule of inspection
1.2 PROGRESS MEETINGS
Periodic job site meetings will be held by the Engineer.
a. Contractor shall attend such meetings and shall require subcontractors to attend as necessary.
b. These meetings are for the purpose of:
1) Insuring that all activities are being coordinated properly on the project
2) To assist in staying on schedule
3) Checking Status of:
a) Submittals
b) Changes
c) Progress payments
d) Other matters will be reviewed
END OF SECTION 102
Submittals Section 103-1
SECTION 103
SUBMITTALS
1.1 SUBMITTALS
Deliver submittals for materials, schedule, and cost values to the Engineer unless indicated otherwise. Accompany each submittal with a letter of transmittal indicating:
a. Title of Project
b. Name of Contractor
c. Title of Submittal
1.2 PROGRESS SCHEDULE
Immediately after being awarded the Contract, prepare and submit for review an estimated progress schedule for the Work. Progress schedule shall be in sufficient detail to include but not be limited to:
a. Significant elements of the Work.
b. Time frame for each element of work with a beginning and ending point.
c. Percentage of progress of work placed or to be placed in a monthly period of time.
d. Value of the elements of work and relationship of elements of work one to the other for the total work under the Contract.
Progress schedule shall be updated monthly and submitted with each periodic estimate for partial pay, and shall show the original progress schedule or revised progress schedule one entry for each item of work as follows:
a. Progress of work placed prior to period of partial payment then being requested.
b. Progress during period of partial payment being requested.
c. Remaining work to be done by each item of work and for total work remaining under the Contract.
1.3 SUBMITTAL SCHEDULE
Contractor shall, within ten (10) calendar days after receipt of Notice to Proceed, furnish a
Submittals Section 103-2 submittal schedule listing all items that will be furnished for review to Owner and Engineer.
a. This schedule shall include, among other things, shop drawings, Manufacturer’s literature, certificates of compliance, materials samples, materials colors, guarantees, etc.
b. Schedule shall indicate type of item, contract requirement reference, Contractors scheduled dates for submitting the items, and projected need dates for review answers from Engineer: Schedule shall show a minimum of seven (7) calendar days after receipt for review by Engineer. If re-submittal is required, an additional five (5) days will be allowed after receipt. Contractor shall revise and/or up-date this schedule as appropriate and submit it with each payment estimate until all items have been submitted and reviewed.
c. Submittal schedule shall be coordinated with progress schedule for all the Work.
Contractor shall revise and/or up-date the schedule to ensure consistency with the progress schedule as it may be revised and/or updated. Such revised submittal schedules shall be promptly provided.
d. Furnishing of the submittal schedule or revision thereto shall not be interpreted as relieving Contractor of his obligation to comply with all the Specification requirements for items on the schedule.
Progress schedule shall be updated monthly and submitted with each periodic estimate for partial pay, and shall show the original progress schedule or revised progress schedule one entry for each item of work as follows:
a. Progress of work placed prior to period of partial payment then being requested.
b. Progress during period of partial payment being requested.
c. Remaining work to be done by each item of work and for total work remaining under the Contract.
1.4 PROGRESS REPORTS
Contractor shall prepare daily reports of his operations and forward them to Engineer on at least a weekly basis. The daily report will contain at least the following information:
a. Weather conditions,
b. Manpower on the job in each trade,
c. Major items of equipment on the job, Submittals Section 103-3
d. A brief summary of work accomplished that day,
e. Materials, equipment, or owner-furnished items arriving or leaving site,
f. Significant events,
g. Any tests made and their result if known,
h. Any oral instructions received,
i. Visitors to the job.
Contractor shall maintain a file of copies of all daily reports on the site and make it available to Engineer or Owner upon request.
1.5 SHOP DRAWINGS, PRODUCT DATA, & SAMPLES
Definitions:
1. Shop drawings are drawings, diagrams, illustrations, schedules, performance charts, brochures, and other data which are prepared by Contractor or any subcontractor, manufacturer, supplier, or distributor. Shop drawings illustrate some portion of the
Work and confirm dimensions and conformance to Contract Documents.
a. Shop drawings are not a part of the Contract Documents.
2. Samples are physical examples furnished by Contractor to illustrate materials, equipment, color, or workmanship and to assist in the establishment of standards by which the Work will be judged.
Procedure
1. Contractor shall review and designate (stamp) his approval and submit to Engineer, with reasonable promptness and in orderly sequence, all shop drawings and samples required by the Contract Documents.
a. Divisions and Sections of the Project Manual requiring submission of shop drawings to Engineer are as follows. If a broad scope Section heading is given, all of the subsections in that Section are to submit shop drawings.
b. Shop drawings and samples not required by the Contract Documents but requested by Contractor or supplied by those under contract to him need not be submitted to Engineer for approval unless specifically requested. These shop drawings shall meet all specified shop drawing requirements except those relating to submission to Engineer.
Submittals Section 103-4
2. Shop drawings and samples shall be properly identified as specified or as Engineer may require.
3. Contractor shall reject shop drawings not in conformance with the Contract
Documents.
4. Shop drawings shall be complete and detailed. If reviewed by Engineer, each copy of the shop drawings will be identified as having received such approval by being so stamped and dated. If review “with exception” or “as noted” by Engineer is so identified, stamped, and dated, Contractor shall comply with notations shown. If such qualified review is shown or if the shop drawings are not reviewed by Engineer or if resubmission is so directed, Contractor shall make any corrections required or indicated by Engineer at Contractor’s expense.
a. Any shop drawing or correction indicated on a shop drawing which does not conform to the Contract Documents shall be submitted as a change order and approved, as required under Section 14, of the General Conditions, prior to performing the changed work.
b. Number of copies of shop drawings and other submittals required will be established at the Pre-construction Conference if more than three are required.
Contractor shall bear cost of reproducing copies of shop drawings required by all concerned. In lieu of prints, sepia may be required.
By approving shop drawings and samples, Contractor thereby represents that he has determined and verified all field measurements, field construction criteria, materials, catalog numbers, and similar data, or will do so, and that he has checked and coordinated each shop drawing and sample with requirements of the Work and of the Contract
Documents.
No work requiring a shop drawing or sample submission shall be commenced until submission has been approved by Engineer.
Samples
a. Where specified or required, Contractor shall submit samples to Engineer together with specification material, affidavits, and other documentation as may be required by Engineer.
b. It is Contractor’s specific responsibility to ascertain that samples submitted have been checked and approved by him.
c. Cost of samples, together with transportation, delivery, and any other costs, shall be borne by Contractor. Samples shall be submitted in duplicate and one of each sample shall be retained in the office of Engineer until completion of the Project.
Submittals Section 103-5
d. Where samples are specifically required to be submitted for approval, no work involving the sampled materials shall proceed until written approval has been obtained from Engineer.
Review by Engineer
a. Review of shop drawings by Engineer shall not be construed as a complete check but will indicate only that the general method of construction and detailing is satisfactory. Review of such drawings will not relieve Contractor of responsibility for any error which may exist in the submittals. –
1.6 SCHEDULE OF VALUES
A schedule of dollar values shall be submitted to Engineer and Owner not less than twenty
(20) days prior to first request for payment and shall be a condition precedent to processing first payment. Schedule of values shall be submitted on Owner’s standard payment request form. This breakdown shall follow the trade Divisions of the Specification and each item thereunder shall include its pro rata part of overhead and profit so the sum of the items will equal the contract price. Breakdown will correspond exactly to items of work in the progress schedule including work of subcontractors.
END OF SECTION 103
Material & Equipment Section 104-1
SECTION 104
MATERIAL & EQUIPMENT
1.1 MATERIAL & EQUIPMENT.
Conduit for the bore shot shall be 3” HDPE Conduits (3.5” O.D.) schedule 40 or IPS 13.5 continuous conduit or approved equal. Tracer Wire shall be coated #12 copper wire.
Flowable fill, minimum strength of 50 psi, per UDOT Standard Specification 03575
“Flowable Fill,” to fill in annular voids within the bore shot will be supplied by the
Contractor.
Contractor shall, if required, furnish evidence of the quality of any materials furnished by the Contractor.
Materials supplied by the Contractor not meeting requirements of the Contract Documents shall be removed from Project by Contractor without expense to Owner.
Contractor shall provide equipment capable of completing the guided bore shot, tracking the horizontal and vertical location of the bore head, and installing the conduit in accordance with the stamped plan.
1.2 DELIVERY, STORAGE, & HANDLING
Materials shall be delivered to the site in original packaging with labels and trademarks intact, and such labels and trademarks shall remain intact until used.
Contractor shall confine his apparatus, storage of materials, and operations of his workmen to limits indicated by law, ordinances, and permits and shall arrange and maintain parking of vehicles and storage of materials in an orderly manner leaving all walks, driveways, roads, and entrances, unencumbered.
All equipment on site shall be protected from physical damage and from the elements by measures satisfactory to Engineer.
It shall be the responsibility of the Contractor to coordinate with the supplier all delivery schedules and to unload all materials. Materials will be delivered to locations where the trucks can deliver under their own power.
It shall be the responsibility of the Contractor to inspect all materials, as they are unloaded at the project site. If there is any cause for rejection of the materials, the Contractor shall immediately notify the project inspector and shall obtain a written release of liability for the replacement of the damaged materials. Any material damaged by the Contractor unloading the material or of which a written release of liability for the replacement of
Material & Equipment Section 104-2 damaged materials is not obtained shall be replaced in kind by the Contractor.
1.3 PRODUCT OPTIONS & SUBSTITUTIONS.
When several materials are specified in the Contract Documents by name for one use, Contractor may select any one of those so specified. The mixing of several products specified by name for one use is prohibited.
Wherever an item or class of material is specified exclusively by trade name, name of maker, or by catalog reference, use such item only unless Engineer’s approval for a substitution is secured by Addendum a minimum of 10 days before bid opening time. Items and material not specified in the Contract Documents and installed in the Work shall be removed and replaced by specified items and material at no additional cost to Owner and for no additional time added to Contract.
Wherever words “Approved by”, “Satisfactory to”, “submitted to”, inspected by” or similar phrases are used in this Specification, they shall be understood to mean that the material or item referred to shall be approved by, be satisfactory to, submitted to, or inspected by
Engineer or Owners representative.
END OF SECTION 104
Contract Closeout Section 105-1
SECTION 105
CONTRACT CLOSEOUT
1.1 FINAL CLEANING
Contractor shall, at completion of work, remove all rubbish, from under and about the
Construction Site.
If Contractor fails to clean up, Owner may do so and the cost thereof will be charged to the
Contractor.
1.2 PRESUBSTANTIAL COMPLETION, SUBSTANTIAL COMPLETION, & FINAL
INSPECTIONS
Pre-substantial Completion Inspection
a. Upon Contractor’s request, Engineer (and his consultants as appropriate) will make an inspection and furnish to Contractor a list of items to be corrected by Contractor.
b. Upon correction of these items, Engineer will arrange a substantial completion inspection to include Owner.
Substantial Completion Inspection
a. At the substantial completion inspection, Owner, Engineer, and Contractor will execute a Certificate of Substantial Completion which states the dates for
1. Commencement of warranties
2. Final completion inspection
3. Modifications to the amount assessed for liquidated damages.
b. After inspection, Engineer will furnish final list of items to be corrected.
Final Inspection
a. Final Completion Inspection will ensure that all deficiencies noted at the substantial completion inspection have been corrected according to terms of the substantial completion certificate.
b. The contractor shall obtain signed release waivers from all suppliers and subcontractors before final payment will be authorized.
c. When all items have been corrected, Engineer will issue a certificate authorizing final
Contract Closeout Section 105-2 payment.
d. If all items have not been corrected as agreed, Owner may elect to complete the Work under provisions of Section 16 of the General Conditions.
1.3 PROJECT RECORD DOCUMENTS
Contractor shall deliver to Engineer prior to substantial completion inspection:
a. Accurate “as built’ drawings and letters of the work if the work is constructed in any way at variance to that shown on Contract Documents. “As built” drawings or descriptive letters for other work will be supplied if requested.
b. Certificates of inspection and of occupancy that may be required by authorities having jurisdiction over the Work.
1.4 OPERATING & MAINTENANCE DATA
Before execution of the Certificate of Substantial Completion, Contractor shall furnish the operating instructions and maintenance manuals as called for in Contract Documents.
1.5 WARRANTIES & BONDS
When written guarantees beyond one year after substantial completion are required of any section of the Work, Contractor shall secure such guarantees and/or warranties properly addressed and signed and in favor of Owner. These documents shall be delivered to
Engineer upon substantial completion of Contractor’s work and prior to execution of
Certificate of Substantial Completion.
Delivery of guarantees and warranties shall not relieve Contractor from any obligation assumed under any other provisions of his contract.
Nothing herein intends or implies that guarantees and/or warranties shall apply to work abused or neglected by Owner.
END OF SECTION 105
Mobilization Section 106-1
SECTION 106
MOBILIZATION
DESCRIPTION
1.1 GENERAL
This item of work is provided to cover the Contractor’s cost for general and miscellaneous responsibilities and operations not normally attributable to, or included in, any other single bid schedule item. This shall include, but not necessarily be limited to, work, described or enumerated in this section under the following subsections.
CONSTRUCTION
2.1 MOVING TO AND FROM JOB SITE
This shall include the Contractor’s preliminary arrangements for starting construction operations, work schedules, and transportation of equipment and personnel to and from the project.
2.2 TEMPORARY FACILITIES
Sanitary Facilities for Construction Workers
The Contractor shall provide, for all his workers on the project, adequate and reasonably convenient uncontaminated drinking water supply and temporary toilet facilities. All facilities shall comply with the Utah Safety and Health Act.
Utilities for Construction Operations
The Contractor shall make arrangements for, secure and pay for, any and all utility supplies such as electric power, water, natural gas or telephone that may be required for prosecution of the work.
Temporary Lighting
The Contractor shall provide all temporary lighting required for prosecution of his work and for employee and public safety. As a minimum, lighting levels during working hours shall meet the requirements of U.O.S.H.A. Subsection 1926.56 Illumination.
Heating and Ventilating
The Contractor shall provide any and all heating and ventilating equipment required to assure a safe environment for workers and to prevent damage to the project facilities from freezing or excessive temperature.
2.3 PUBLIC SAFETY AND TRAFFIC CONTROL
Traffic control measures provided for public safety will be paid for in a separate bid item for this project and is not included with the lump sum bid price for “Mobilization.”
Mobilization Section 106-2
2.4 RESTORATION OF CONSTRUCTION SITE
The cost of all clean-up work as specified in the following sections shall be included in the
Bid Schedule lump sum price for Mobilization.
2.5 TEMPORARY UTILITIES
The Contractor shall arrange for secure and pay directly any and all temporary utility supplies he may require for prosecution of his work. The cost of such utilities shall be included in the lump sum price of “Mobilization.”
2.6 BONDS AND PERMITS
The Contractor shall secure all bonds and permits required for the prosecution of the work, the cost of which shall be included in the lump sum price of “Mobilization.”
2.7 STORMWATER POLLUTION PREVINTION (NOI / SWPPP)
Excavation and stockpiled earth at the bore and receiving pits are anticipated to be less than one (1) acre at each location. As such, filing an NOI is not required. However, if total land disturbance at one or the other location meets or exceeds one (1) acre due to the
Contractors means and methods, the Contractor shall be responsible for all plans, permits, filings, work, and costs to obtain coverage under the applicable construction stormwater permit (NOI) and prepare and implement a SWPPP acceptable to the City and UDOT.
Regardless of whether the NOI is filed or not, the Contractor shall implement appropriate stormwater pollution prevention measures using best management practices (BMPs) throughout the project which shall include, but not be limited to dust control, proper containment/disposal of drill fluid and grout, inlet protection, and track-out control, etc...
The City of St. George will provide a temporary water meter for construction.
All stormwater pollution prevention Work and costs, as defined above, required by the
Contractors means and methods to satisfy State, City, and UDOT requirements using acceptable BMPs shall be included in the lump sum price of “Mobilization.”
2.8 CONSTRUCTION STAKING
Survey work will be completed and covered by UDOT personnel or their project surveyor in accordance with UDOT Standard Specification 01721. UDOT will provide stakes for the borehole. If re-staking is required due to the Contractor’s operations disturbing or removing stakes, the Contractor shall be responsible for such costs. The City of St. George will retain a surveyor to check installed work; the cost for the City-retained surveyor will be covered by the City.
The cost of any re-staking shall be included in the lump sum price of “Mobilization.”
END OF SECTION 106
Method of Measurement and Basis of Payment Section 107-1
SECTION 107
METHOD OF MEASUREMENT AND BASIS OF PAYMENT
Bid Item #1 – Mobilization (Lump Sum):
Payment for this work will be made at the contract unit price for “Mobilization” under Bid Item
#1 of the Bid Schedule. This item shall consist of all material, labor and equipment necessary to provide and obtain bonds, permits, and complete other Work described by Section 106 –
“Mobilization.” Payments will be made in accordance with the following schedule.
(1) When 5% of the original contract amount is earned, excluding the deposit amount required to order the prefabricated steel structures (if used), 25% of the amount bid for mobilization or 2 ½% of the original contract amount, whichever is lesser will be paid.
(2) When 25% of the original contract amount is earned, an additional 35% (cumulative total:
60%) of the amount bid for mobilization, or 6% of the original contract amount, whichever is lesser, will be paid.
(3) When 65% of the original contract amount is earned, an additional 30% (cumulative total:
90%) of the amount bid for mobilization, or 9% of the original contract amount, whichever is lesser, will be paid.
(4) When 80% of the original contract amount is earned, an additional 10% (cumulative total:
100%) of the amount bid for mobilization, or 10% of the original contract amount, whichever is lesser, will be paid.
(5) Upon completion of all work on the contract any unpaid amount of the original contract amount for mobilization will be paid.
Nothing herein shall be construed to limit or preclude partial payments. Payment for this item will be made at the contract lump sum price specified under Bid Item #1 of the Bid Schedule.
Bid Item #2 – Borehole & Tracking (Lineal Foot):
This item shall consist of furnishing all labor, materials, equipment, and incidentals necessary to complete a guided horizontal directional drill (HDD) installation under I-15 as shown on the stamped plans. The horizontal and vertical alignment of the installed conduits shall conform to the plan line and grade within a maximum deviation of 6 inches horizontally and 6 inches vertically, unless otherwise approved by the Engineer.
Equipment used shall be capable of accurately locating and tracking the drill head and maintaining the bore path within the required tolerances. The Contractor shall provide drill tracking logs and an as-built record of the bore path (horizontal and vertical) demonstrating conformance to the plans. Incidental work may include potholing within the I-15 corridor to verify the horizontal and vertical location of the borehole, as required based on the Contractor’s equipment, tracking limitations, and the Contractor’s means and methods of completing the work. Traffic control associated with any potholing within the I-15 corridor shall be included and paid for under Bid Item #4.
Method of Measurement and Basis of Payment Section 107-2
A separate bid item is provided to fill annular voids around the conduits within the borehole with flowable fill after the conduits have been installed. Flowable fill for annular voids is not included in this bid item and will be paid under Bid Item #6.
Incidental work includes but is not limited to equipment setup; drilling the borehole; tracking the bore head; borehole stabilization as required; staging conduits; pulling conduits through the borehole; removing spoils, drilling fluids/water, and other materials from the borehole and receiving pits; managing drilling fluid and spoils, including hauling and legal off-site disposal;
installing one (1) #12 coated copper tracer wire in a designated conduit; capping conduit ends;
providing and installing a temporary secondary box; and pulling a mandrel through each conduit upon completion.
The Contractor shall coordinate with City of St. George and UDOT personnel, including inspectors and testing personnel. Work shall conform to applicable City and UDOT specifications.
Work shall be completed by a qualified Contractor who is properly licensed through the State of
Utah (DOPL), as applicable, shall have a minimum of five (5) years experience performing guided HDD installations of similar scope, and shall provide related project experience with their proposal.
Measurement and Payment: Measurement for payment of this item shall be per lineal foot as specified in the Bid Schedule under Bid Item #2. Payment will be made at the contract unit price per lineal foot and shall constitute full compensation for all labor, materials (excluding HDPE conduit which is paid separately under bid item #5), equipment, drilling fluid management and off-site disposal, and incidentals necessary to complete the work described herein, placed in accordance with the plans, complete and accepted by the Engineer.
Bid Item #3 – Excavation for Bore Pits, Potholing, Dewatering, and Work/Staging Areas
(Lump Sum)
This item shall consist of all labor, materials, equipment, and incidentals necessary to perform excavation and earthwork required to construct, maintain, and backfill the bore entry/exit pit(s), receiving pit(s),…