This file contains general instructions for bidders on a natural channel stream restoration project sponsored by the Donegal Chapter of Trout Unlimited (DTU), funded through a Section 319 Nonpoint Source Pollution Grant administered by the Pennsylvania Department of Environmental Protection. The project encompasses stream restoration work at two properties: the Samuel E. Lapp site (2384 Robert Fulton Hwy, Peach Bottom 17563) involving 1,300 feet of stream restoration on Conowingo Creek, and the Amos Beiler site (824 Conowingo Rd, Quarryville 17566) involving 628 feet of stream restoration. Bidders must submit two separate lump sum bids: one for both sites combined and one for the Lapp property only. Award will be made to a single contractor for both sites if the combined bid is less than available grant funds; if the combined bid exceeds available funds, the contract will be awarded for the Lapp property only. The contractor must provide all equipment, labor, materials, and supplies to complete work according to supplied drawings and approved permits. The project completion date is March 1, 2028, and bidders may withdraw proposals at any time prior to the submission deadline through the PennBid portal.
All work is bid as lump sum items, and bids exceeding $250,000 require a 5% bid guarantee, performance bond, and payment bond each equal to 100% of the contract amount. The project is subject to federal prevailing wage requirements under the Bacon-Davis Act, and contractors must determine applicable wage categories for all labor. Prior to starting construction, the selected contractor must provide certificates of insurance including Worker's Compensation, Public Liability and Property Damage, and Automobile Bodily Injury and Property Damage coverage, each in the amount of $1,000,000. Contractors shall submit monthly itemized invoices with anticipated payment within 90 days of receipt, contingent on timely reimbursement from DEP. DTU will verify work quality against specification and BMP drawing requirements, with the funding organization making final determination of acceptability. The contractor is responsible for locating and protecting all utilities and must obtain material approval from the oversight inspector prior to use. Regulatory permits are already in place for both properties. Bid questions should be submitted through the PennBid portal, with other inquiries directed to DTU at coodinator@donegaltu.org. All bidders must comply with Commonwealth Standard Terms and Conditions (Grant Version, Revised 10/1/2023).
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DONEGAL CHAPTER OF TROUT UNLIMITED
NATURAL CHANNEL STREAM RESTORATION
INFORMATION AND INSTRUCTION FOR PROJECT BIDDERS
Project Information:
The project will be funded by a Section 319 Nonpoint Source Pollution Grant. The 319 funding is part of the Environmental Protection Agency-approved Watershed Implementation Plans (WIP) and managed in Pennsylvania by the Department of Environmental Protection (DEP).
The project locations:
1. Samuel E Lapp: 2384 Robert Fulton Hwy Peach Bottom 17563 Drawings: Conowingo Creek Samuel E Lapp Stream Plans 2025-04-17
2. Amos Beiler: 824 Conowingo Rd Quarryville 17566 Drawings: Conowingo Creek Amos Beiler Site 1 Stream Plans 2025-06-24
All work is bid as LUMP SUM items.
· The contractor will supply a combined bid for Lapp and Beiler together (so as to take advantage of mobilization costs), and a separate bid for Lapp only. The final award will be awarded to one contractor based on:
1. If the combined bid is less than amount of funds available
2. If the combined bid is greater than funds available, award will be for S. Lapp property only.
· The contractor shall provide all equipment, labor, materials, and supplies necessary to complete the work per the supplied drawings. The Project Design and Technical Specifications are intended to cover one contract. The contractor shall, at all times and in all respects, be the party primarily responsible for the performance of work under the contract or any work thereunder.
· The regulatory approved permits are in place for the S. Lapp and A. Beiler. See attached permits and approved drawings.
· Materials shall be approved by the oversight inspector prior to use.
· The contractor shall be responsible for locating and protecting all utilities.
· DTU is acting as the Project Sponsor. Bid questions should be sent through PennBid portal. All others inquires contact DTU at coodinator@donegaltu.org
· Oversight and Reporting includes:
1. Adequate construction oversight to assist and document the construction of the approved and permitted plans
2. Take photographs to document field conditions and installations of the various BMPs, structures, grading, E&S controls, seeding, and mulching
3. Provide appropriate information as to the status of construction and assist Donegal TU with the preparation of quarterly status reports as required by the 319 grant.
4. Provide appropriate information for final reporting upon completion of construction and assist Donegal TU with the preparation of the final report as required by the 319 grant.
· Project Completion Date: March 1, 2028
· Any bidder may withdraw a proposal at any time prior to the scheduled closing time for receipt of proposals. A Bid may be withdrawn or modified at any time within PennBid prior to the due date and time identified in the Invitation for Bids.
Award of a contract shall be made on the earliest possible date from the bid opening date. In the event no satisfactory bids are received, all bidders shall be so notified within a 24-hour period.
The contractor to whom award is made shall provide the following information to the contracting representative (Donegal TU) prior to starting construction.
A. Standard Accord Certificate(s) of Insurance (Contractual Liability Type) ($1,000,000)
1. Worker’s Compensation Insurance
2. Public Liability and Property Damage Insurance
3. Automobile Bodily Injury and Property Damage Insurance
The following apply to bids in excess of $250,000.
A. A bid guarantee in the amount of 5% of the bid price is required with the submittal bid B. A Performance Bond (100% of the contract amount provided prior to award) C. A Payment Bond (100% of the contract amount provided prior to award)
Prevailing Wages Project is a Federal contract, and therefore, prevailing wage per the Bacon-Davis Act apply to this project. All labor performed on this project must be paid prevailing wages. Bidders should determine the specific wage categories appropriate for the project (i.e. Operators, Truck drivers, Labors etc.).
Reimbursement The Contractor shall submit an itemized invoice on a monthly basis as the project progresses up and to final completion. Upon verification of work, it is anticipated that payments shall be made to the contractor within 90 days of receipt of invoice, depending on timely reimbursement from the DEP. DTU will verify the quality and work meets the specification and BMP drawing requirements. Funding and/or buyer organization will make the final determination that the work is acceptable.
Indemnification The Contractor shall indemnify and hold harmless the landowner, Donegal Chapter of Trout Unlimited, the Pennsylvania Department of Environmental Protection, and all other of their representatives against any and all claims for damages to persons or property asserted by any person, partnership, corporation, or other organization, arising out of services performed or undertaken by said Contractor, its agents, employees, or subcontractors, except for claims for damages directly caused by the sole fault or negligence of the parties hereto, their officers, or employees.
Commonwealth Standard Terms and Conditions All bidders need to follow the following standard terms and conditions outlined in the: Commonwealth Standard Terms and Conditions Grant Version (Revised-10/1/2023), Attachments B through E. (supplied).
File details come from the government source that posted it. Updated .