8 - Exhibit D Special Conditions.pdf
PDF 256 KB Posted
- Attached to
- 438168-CC-24 RSL Room Upgrades
- Solicitation number
- 438168-CC-24
- Issued by
-
Department of Energy
About this file
This document is an Exhibit D - Special Conditions for a firm-fixed-price construction subcontract under Solicitation No. RFP 438168-CC-24. It outlines the requirements and terms for the subcontractor, including insurance coverage, drawings and data submittals, permits, invoicing, payments, work hours, wage rates, performance/payment bonds, use of roadways, and a workplace substance abuse program.
Key details include:
- The subcontractor must maintain specific insurance coverages, with the U.S. Government, Department of Energy, and the contractor named as additional insureds.
- The subcontractor must submit drawings, samples, certificates, and other data for review and approval prior to fabrication or installation.
- The subcontractor is responsible for obtaining all necessary permits, except those listed as furnished by the contractor.
- Invoicing and progress payment requirements are detailed, including a required certification.
- The subcontract is subject to the Davis-Bacon Act for construction wage rates.
- Performance and payment bonds are required for subcontracts between $35,000 and $150,000.
- The work is subject to a total small business set-aside.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit D Solicitation No. RFP 438168-CC-24
Subcontract No. TBD 8/29/2024 Page 1 of 12
MISSION SUPPORT AND TEST SERVICES, LLC
FIRM-FIXED-PRICE CONSTRUCTION
SUBCONTRACT
EXHIBIT D
SPECIAL CONDITIONS
TABLE OF CONTENTS
NO. TITLE PAGE
D-1 Expediting D-2 Insurance D-3 Contractor-Furnished Drawings, Specifications & Statements of Work D-4 Subcontractor-Furnished Drawings, Data and Samples D-5 Permits and Responsibilities D-6 Invoicing and Payment D-7 Payments Under Firm-Fixed-Price Construction or Design-Build Subcontracts D-8 Contractor Work Hours and Holidays D-9 Wage Rate Information D-10 Construction Labor Standards D-11 Performance and Payment Bonds D-12 Use of Roadways D-13 Non-Interference D-14 Workplace Substance Abuse Program D-15 Notice of Total Small Business Set-Aside D-16 Attachments
Subcontract No. TBD 8/29/2024 Page 2 of 12
D-1 EXPEDITING
Timely performance and delivery in accordance with the schedule herein are essential to this Subcontract.
The Products, including all warranty work, shall be subject to expediting by CONTRACTOR and Government.
CONTRACTOR's and Government's representatives shall be afforded free access during working hours to SUBCONTRACTOR’s plants. SUBCONTRACTOR shall notify CONTRACTOR in writing of any actual or anticipated delays immediately upon discovery. Such notice shall include an estimated period of delay, cause, and corrective actions being taken. Slippage in SUBCONTRACTOR's schedule may be deemed to be reasonable grounds for insecurity in which event CONTRACTOR may demand in writing that SUBCONTRACTOR provide adequate assurances that SUBCONTRACTOR will perform on time.
D-2 INSURANCE
(a) Unless otherwise specified in this Subcontract, SUBCONTRACTOR shall, at its sole expense, maintain in effect at all times during the performance of the Work insurance coverage with limits not less than those set forth below with insurers and under forms of policies satisfactory to CONTRACTOR.
SUBCONTRACTOR shall deliver to CONTRACTOR no later than 10 calendar days after Notice of Award, but in any event prior to commencing the Work or entering the jobsite, Certificates of Insurance as evidence that policies providing such coverage and limits of insurance are in full force and effect.
Certificates shall be issued in the form acceptable to CONTRACTOR. SUBCONTRACTOR agrees to provide not less than 30 calendar days advance written notice will be given to CONTRACTOR prior to cancellation, termination or material alteration of said policies of insurance. The Certificates shall identify on their face the project name and the applicable subcontract number. Unless expressly provided otherwise below, the United States Government, U.S. Department of Energy (DOE), the CONTRACTOR, Honeywell International, Jacobs Engineering, HII Nuclear, Inc., and their affiliates, agents, officers, directors, representatives, employees, heirs, successors, and assignees, etc. shall be named as Additional Insureds under all insurance policies required under this clause, but only with respect to liability arising out of the performance of the Work of the Subcontractor under this Subcontract. Such insurance shall be primary as regards any other coverage maintained for or by the Additional Insured and shall contain a cross-liability or severability of interest clause. All insurance shall provide for an insurer's waiver of subrogation rights in favor of CONTRACTOR and the Government.
(b) Standard Coverage:
1. All Workers' Compensation insurance (or similar insurance) required by any applicable Federal, State, or local law or regulation.
Note: All SUBCONTRACTORS who are working on construction projects in Nevada are required to provide workers compensation insurance coverage to their employees either through obtaining a new policy for Nevada required coverage under Nevada Revised Statute (NRS), obtaining an endorsement to SUBCONTRACTOR’s current workers compensation policy issued in another state, or being self-insured pursuant to NRS 616B.612. Any out-of-state SUBCONTRACTOR meeting the definition of NRS 624.020 working temporarily in Nevada must obtain Nevada Workers’ Compensation Insurance prior to the start of any project.
If any of SUBCONTRACTOR’S employees are covered by the U.S. Longshoremen's and Harbor Workers' Compensation Act (46 U.S.C. §§ 901-950), the Jones Act (46 U.S.C. § 30104) or under other laws, regulations or statutes applicable to maritime employees, or under the Defense Base Act (covering employees performing work outside the United States under for national defense purposes (most, if not all, subcontracts issued by CONTRACTOR are for national defense purposes)), SUBCONTRACTOR shall obtain the appropriate coverage as required by law and submit to the CONTRACTOR Certificates of Insurance as evidence that policies providing such coverage and limits of insurance are in full force and effect within the time limits stated in paragraph
(a) above.
2. Employer's Liability of not less than $1,000,000 each accident.
3. General Liability Insurance
Subcontract No. TBD 8/29/2024 Page 3 of 12
i. Coverage
SUBCONTRACTOR shall carry Commercial General Liability Insurance covering all operations by or on behalf of SUBCONTRACTOR providing insurance for bodily injury liability and property damage liability for the limits of liability indicated below. The required limits may be satisfied by a combination of a primary policy and excess or umbrella policy:
$5,000,000 Combined single limit for Bodily Injury and Property Damage each occurrence;
$5,000,000 Personal Injury Limit each occurrence;
$5,000,000 Products-Completed Operations Annual Aggregate Limit; and
$5,000,000 General Annual Aggregate Limit (other than Products-Completed Operations).
The Commercial General Liability insurance shall be written on the Occurrence Coverage Form and shall include, but not be limited to, coverage for:
1. Premises and Operations
2. Products and Completed Operations
3. Contractual Liability
4. Broad from Property Damage
5. Explosion, Collapse, and Underground Hazards
6. Personal Injury Liability
4. Automobile Liability Insurance including coverage for the operation of any vehicle to include, but not limited to, owned, hired and non-owned vehicles.
The combined single limit for Bodily Injury and Property Damage Liability shall be not less than $2,000,000 for any one accident or loss. The required limits may be satisfied by a combination of a primary policy and an excess or umbrella policy.
SUBCONTRACTOR'S Automobile Liability Insurance shall include coverage for Automobile Contractual Liability. Higher limits shall apply if required by law, such as that required for the shipment of hazardous material (see for example, without limitation, 49 U.S.C. 31139(d)).
(c) Special Operations Coverage:
Should any of the work involve any of the following, the SUBCONTRACTOR shall maintain insurance coverage as specified below:
1. Involve Commercial Motor Vehicles, SUBCONTRACTOR shall carry Commercial Motor Vehicle Liability Insurance including coverage for the operation of any vehicle to include, but not limited to, owned, hired and non-owned vehicles. The combined single limit for Bodily Injury and Property Damage Liability shall be not less than $10,000,000 for any one accident or loss. The required limits may be satisfied by a combination of a primary policy and an excess or umbrella policy.
SUBCONTRACTOR'S Commercial Motor Vehicle Liability Insurance shall include coverage for Motor Vehicle Contractual Liability. Higher limits shall apply if required by law.
(d) Related Obligations:
1. The requirements contained herein as to insurance types and limits, as well as CONTRACTOR'S approval of insurance coverage to be maintained by SUBCONTRACTOR, are not intended to and shall not in any manner limit or qualify the liabilities and obligations assumed by SUBCONTRACTOR under this subcontract.
2. SUBCONTRACTOR shall require its subcontractors, if any, to maintain all the same insurance coverages as required by paragraph (b) and (c) of this clause to the extent applicable to the portion of the work which they shall perform, in accordance with the same terms and conditions as specified in this clause. SUBCONTRACTOR must furnish evidence of such insurance to CONTRACTOR prior to commencement of the work.
(e) CONTRACTOR or GOVERNMENT Furnished Insurance:
Neither CONTRACTOR nor Government is maintaining any insurance on behalf of SUBCONTRACTOR of any nature, including any insurance covering against loss or damage to the
Subcontract No. TBD 8/29/2024 Page 4 of 12
Work or to any other property of SUBCONTRACTOR unless otherwise specifically stated herein and as may be described by appendix hereto.
(f) Notifications:
In accordance with the submittal requirements outlined above, SUBCONTRACTOR shall deliver the original copy of the Certificate(s) of Insurance required by this clause and all subsequent notices of cancellation, termination and alteration of such policies to:
Mission Support and Test Services, LLC P.O. Box 98521, M/S NLV018 Las Vegas, NV 89193-8521 Attention: Corrine E. Carter Reference: Subcontract No. TBD
D-3 CONTRACTOR-FURNISHED DRAWINGS, SPECIFICATIONS & STATEMENTS OF
WORK
CONTRACTOR will furnish statements of work, specifications, and prints of engineering design drawings for each part of the Work under this Subcontract. Such drawings will give information required for the preparation of shop detail drawings by SUBCONTRACTOR, if required. SUBCONTRACTOR shall, upon receipt, check all statements of work, specifications and drawings furnished and shall promptly notify CONTRACTOR of any omissions or discrepancies in such statements of work, specifications or drawings.
D-4 SUBCONTRACTOR-FURNISHED DRAWINGS, DATA AND SAMPLES
CONTRACTOR review and permission to proceed does not constitute acceptance or approval of submittals including, but not limited to, design details, calculations, analyses, test methods, construction methods, rigging plans, certificates, or materials developed or selected by SUBCONTRACTOR and does not relieve SUBCONTRACTOR from full compliance with the subcontract requirements. The Subcontract shall utilize FRM-0226, Titled “Transmittal Sheet – Subcontract” to transmit Submittals and/or Request for clarifications to obtain authorization status by the Contractor.
Drawings:
If the SUBCONTRACTOR is required elsewhere in this Subcontract to submit to the CONTRACTOR for approval drawings, specifications, data, other design documents, or other similar submittals (collectively “Submittals”) for any reason:
Such Submittals shall be submitted by and at the expense of SUBCONTRACTOR as specified elsewhere in this Subcontract. If not otherwise specified, Submittals must be submitted at least 30 days prior to the relevant fabrication, installation or performance is commenced, in order to allow sufficient time for review by CONTRACTOR unless the Subcontract Administrator expressly authorizes the Subcontractor to deviate from this requirement. Drawings shall include, but not be limited to, match marks, erection diagrams and other details, such as field connections for proper installation, erection of equipment or materials, and performance of the Work.
Drawings of a specific piece of equipment shall identify components with the manufacturer's part number or reference drawing number clearly indicated. If reference drawing numbers are used, the review data of such drawings shall be included.
Drawings shall indicate design dimensions, maximum and minimum allowable operating tolerances on all major wear fits, (e.g., rotating, reciprocating, or intermittent sliding fits between shafts or systems and seals, guides, and pivot pins). The sequence of submission of all drawings shall be such that all information is available for reviewing each drawing when it is received.
All drawings submitted by SUBCONTRACTOR shall be certified by SUBCONTRACTOR to be correct, shall show the Subcontract number, and shall be furnished in accordance with the Subcontract Drawings and Data Requirements Form(s). CONTRACTOR will conduct a review of SUBCONTRACTOR'S drawings and a reproducible drawing marked with one of the following codes will be returned to SUBCONTRACTOR.
Subcontract No. TBD 8/29/2024 Page 5 of 12
Code Notation
1. Work may proceed
2. Revise and resubmit – work may proceed subject to resolution
3. Revise and resubmit – work may not proceed
4. Review not required – work may proceed
Although work may proceed on receipt of a drawing with a Code 2 notation, SUBCONTRACTOR must resolve the comments indicated, resubmit, and obtain a Code 1 notation before release for shipment or completion of the affected work.
Samples:
Where samples are required, they shall be submitted by and at the expense of SUBCONTRACTOR. Such submittals shall be made not less than 30 calendar days prior to the time that the materials represented by such samples are needed for incorporation into the Work. Samples shall be subject to review and materials represented by such samples shall not be manufactured, delivered to the job site, or incorporated into the Work without such review.
Each sample shall bare a label showing SUBCONTRACTOR'S name, Project name, subcontract number, name of the item, manufacturer's name, brand name, model number, supplier's name, and reference to the appropriate drawing number, technical specification section and paragraph number, all as applicable.
Samples, which have been reviewed, may, at CONTRACTOR'S option, be returned to SUBCONTRACTOR for incorporation into the Work.
Certificates and Data:
Where certificates are required, two copies of each such certificate shall be submitted by and at the expense of SUBCONTRACTOR. Such submittal shall be made not less than 30 calendar days prior to the time that the materials represented by such certificates are needed for Incorporation into the Work. Certificates shall be subject to review and material represented by such certificates shall not be fabricated, delivered to the Job site, or incorporated into the Work without such review.
Certificates shall clearly identify the material being certified and shall include but not be limited to providing the following information: SUBCONTRACTOR'S name, Project name, Subcontract number, name of the item, manufacturer's name, and reference to the appropriate drawing, technical specification section, and paragraph number, all as applicable.
All other data shall be submitted as required by the Subcontract Documents.
AS-BUILT DRAWINGS AND SPECIFICATIONS
Drawings:
a. Progress As-Built: During progress of the Work, SUBCONTRACTOR shall keep a marked-up-to-date set of as-built blue line drawings on the Job site as an accurate record of all deviations between work as shown and work as installed. These drawings shall be available to CONTRACTOR and OWNER for inspection at any time during regular business hours.
b. Final As-Built: SUBCONTRACTOR shall, at its expense and not later than 30 calendar days after Final Acceptance and before Final Payment, furnish to CONTRACTOR a complete set of marked-up as-built reproducible drawings with “AS-BUILT” clearly printed on each sheet. CONTRACTOR, without charge, will furnish SUBCONTRACTOR with reproducibles for mark-up by SUBCONTRACTOR. SUBCONTRACTOR shall accurately and neatly transfer all deviations from progress as-builts. As-built drawings shall be provided where specified and as required to reflect as-built conditions.
Specifications:
a. Progress As-Builts. During progress of the Work, SUBCONTRACTOR shall keep a marked-up-to-date set of as-built specifications on the Job site annotated to clearly indicate substitutions that are incorporated into the Work. Where selection of more than one product is specified, annotation shall show which product was installed. These specifications shall be available to CONTRACTOR and OWNER for inspection at
Subcontract No. TBD 8/29/2024 Page 6 of 12 any time during regular business hours.
b. Final As-Builts. SUBCONTRACTOR shall at its expense and not later than 30 calendar days after Final Acceptance and before Final Payment furnish to CONTRACTOR a complete set of marked-up as-built specifications with “AS-BUILT” clearly printed on the cover. CONTRACTOR, without charge, will furnish SUBCONTRACTOR a set of specifications for mark-up by SUBCONTRACTOR. SUBCONTRACTOR shall accurately and neatly transfer all annotations from progress as-builts to final as-builts.
Endorsement:
SUBCONTRACTOR shall sign each final as-built specification and shall note thereon that the recording of deviations and annotations is complete and accurate.
D-5 PERMITS AND RESPONSIBILITIES
(a) Except for permits furnished by the CONTRACTOR as specified in paragraph (b), the
SUBCONTRACTOR shall, without additional expense to the CONTRACTOR, be responsible for obtaining any and all necessary licenses and permits.
(b) The CONTRACTOR will without cost to the SUBCONTRACTOR, furnish the permits listed below. All such CONTRACTOR-furnished permits are available for examination at the project office of CONTRACTOR during regular business hours.
None
(c) The SUBCONTRACTOR shall also be responsible and liable for all materials delivered and Work performed until completion and acceptance of the entire Work, except for any completed unit of Work which may have been accepted under the Subcontract.
D-6 INVOICING AND PAYMENT
Electronic funds transfer is the preferred method of payment used by MSTS. To take advantage of this expedited payment process, SUBCONTRACTOR shall complete form FRM-0870.
https://www.nnss.gov/docs/docs_procurement/frm0870.pdf
Firm-Fixed-Price:
SUBCONTRACTOR invoices for Firm-Fixed-Price Work shall provide documentation that may include deliverables or other documentation signed by the Subcontract Administrator or the Subcontract Technical Representative (STR) demonstrating that performance of the Work has been completed and accepted by the CONTRACTOR in accordance with the Subcontract requirements. Unless progress payments or milestone payments are expressly authorized elsewhere in this Subcontract, SUBCONTRACTOR shall be entitled to invoice for payment only upon the successful completion and acceptance of all of the Work required by the SUBCONTRACT, Order, or Line Item (as applicable).
Failure to specify the full Subcontract number, corresponding Order Number (if applicable) and to submit full supporting documentation may be cause for invoice rejection or delay in payment. CONTRACTOR may withhold payment on any SUBCONTRACTOR invoice until all properly completed and signed documentation is received and, if applicable, badges/property returned by SUBCONTRACTOR.
To expedite payment, e-mail all invoices directly to the MSTS Accounts Payable Department at apinvprd@nv.doe.gov. Invoice images are accepted only in PDF and TIF format with each invoice to be submitted separately. This e-mail address is to be used for invoices only, not for Statements and Billing Slips.
If SUBCONTRACTOR cannot facilitate electronic submission, SUBCONTRACTOR shall submit all invoices, including the final invoice, detailed by Subcontract Line Item Number on the original invoice to:
Mission Support and Test Services, LLC P.O. Box 98521, M/S NSF025
Las Vegas, NV 89193-8521
Attention: Accounts Payable https://www.nnss.gov/docs/docs_procurement/frm0870.pdf mailto:apinvprd@nv.doe.gov
Subcontract No. TBD 8/29/2024 Page 7 of 12
Reference: Subcontract No. TBD
Note: If SUBCONTRACTOR has not received payment in accordance with the above, SUBCONTRACTOR shall contact the Accounts Payable at ACCTPAY@nv.doe.gov and the Subcontract Administrator. The email must include a listing the Subcontract Number, Line Item Numbers, and any additional details such as proof of delivery, dates etc. to help expedite payment. SUBCONTRACTOR shall include a copy of the invoice(s) with the email.
D-7 PAYMENTS UNDER FIRM-FIXED-PRICE CONSTRUCTION OR DESIGN-BUILD
SUBCONTRACTS
(a) Payment of price. The CONTRACTOR shall pay the SUBCONTRACTOR the Subcontract price as provided in this Subcontract.
(b) Progress payments. The CONTRACTOR shall make progress payments for a portion of the work as shown in Exhibit A (Quantities, Prices and Data) on a monthly basis as the Work proceeds, or at more frequent intervals as determined by the Subcontract Administrator, on estimates of Work accomplished which meets the standards of quality established under the Subcontract, as approved by the Subcontract Administrator.
(1) The SUBCONTRACTOR’S request for progress payments shall include the following substantiation:
(i) An itemization of the amounts requested, related to the various elements of the Work required by the Subcontract covered by the payment requested.
(ii) A listing of the amount included for Work performed by each lower-tier subcontractor under the Subcontract.
(iii) A listing of the total amount of each lower-tier subcontract under the Subcontract.
(iv) A listing of the amounts previously paid to each such lower-tier subcontractor under the Subcontract.
(v) Additional supporting data in a form and detail required by the Subcontract Administrator.
(2) In the preparation of estimates, the Subcontract Administrator may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the SUBCONTRACTOR at locations other than the site also may be taken into consideration if-
(i) Consideration is specifically authorized by this Subcontract; and
(ii) The SUBCONTRACTOR furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this Subcontract.
(c) SUBCONTRACTOR certification. Along with each request for progress payments, the SUBCONTRACTOR shall furnish the following certification, or payment shall not be made: (However, if the SUBCONTRACTOR elects to delete paragraph (c)(4) from the certification, the certification is still acceptable).
I hereby acknowledge and certify, to the best of my knowledge and belief, that-
(1) Amounts paid to SUBCONTRACTOR pursuant to Subcontract No. [Subcontract No.] are mailto:ACCTPAY@nv.doe.gov
Subcontract No. TBD 8/29/2024 Page 8 of 12 reimbursed to the CONTRACTOR by the Federal Government through the U.S. Department of Energy
(2) The amounts requested herein are true and accurate and are only for performance in accordance with the specifications, terms, and conditions of the Subcontract;
(3) All payments due to employees and/or lower-tier subcontractors and suppliers from previous payments received under the Subcontract have been made as required by law, regulation, and/or lower-tier subcontract agreements, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with law, regulation, and/or lower-tier subcontract agreements;
(4) This request for progress payments does not include any amounts which the SUBCONTRACTOR intends to withhold or retain from a lower-tier subcontractor or supplier in accordance with the terms and conditions of the lower-tier subcontract; and
(5) I acknowledge and understand that false or fraudulent invoices, requests for payments, or certifications submitted to CONTRACTOR are considered false statements or false claims made directly to the United States Federal Government.
(6) This certification is not to be construed as final acceptance of a lower-tier subcontractor’s performance.
__________________________________________________ (Name)
__________________________________________________ (Title)
__________________________________________________ (Date)
(d) Refund of unearned amounts. If the SUBCONTRACTOR, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the SUBCONTRACTOR that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the “unearned amount”), the SUBCONTRACTOR shall-
(1) Notify the Subcontract Administrator of such performance deficiency; and
(2) Be obligated to pay the Government an amount (computed by the Subcontract Administrator in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until-
(i) The date the SUBCONTRACTOR notifies the Subcontract Administrator that the performance deficiency has been corrected; or
(ii) The date the SUBCONTRACTOR reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(e) Retainage. If the Subcontract Administrator finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Subcontract Administrator shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Subcontract Administrator may retain an appropriate percent of the amount of the payment until satisfactory progress is achieved. When the Work is substantially complete, the Subcontract Administrator may retain from previously withheld funds and future progress payments that amount the Subcontract Administrator considers adequate for protection of the CONTRACTOR and the Government and shall release to the
Subcontract No. TBD 8/29/2024 Page 9 of 12
SUBCONTRACTOR all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, Line Item, or other division of the Subcontract, for which the price is stated separately in the Subcontract, payment shall be made for the completed Work without retention of a percentage.
(f) Title, liability, and reservation of rights. All material and Work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-
(1) Relieving the SUBCONTRACTOR from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
(2) Waiving the right of the CONTRACTOR and/or the Government to require the fulfillment of all of the terms of the contract.
(g) Reimbursement for bond premiums. In making these progress payments, the CONTRACTOR shall, upon request, reimburse the SUBCONTRACTOR for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the SUBCONTRACTOR has furnished evidence of full payment to the surety. The retainage clauses in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.
(h) Final payment. The CONTRACTOR shall pay the final amount due the SUBCONTRACTOR under this Subcontract after-
(1) Completion and acceptance of all Work;
(2) Presentation of a properly executed invoice; and
(3) Presentation of release of all claims against the CONTRACTOR and the Government arising by virtue of this Subcontract (as prescribed elsewhere in this Subcontract), other than claims, in stated amounts, that the SUBCONTRACTOR has specifically accepted from the operation of the release. A release may also be required of the assignee if the SUBCONTRACTOR’s claim to amounts payable under this Subcontract has been assigned.
(i) Limitation because of undefinitized work. Notwithstanding any clause of this Subcontract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions such as change orders which have not yet been reduced to a formal, definitized, Subcontract modification.
(j) Interest computation on unearned amounts. In accordance with 31 U.S.C.3903(c)(1), the amount payable under paragraph (d)(2) of this clause shall be-
(1) Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the SUBCONTRACTOR receives the unearned amount; and
(2) Deducted from the next available payment to the SUBCONTRACTOR.
(k) As shown in Exhibit A (Quantities, Prices and Data), a portion of the Subcontract price for the Work to be completed under this Subcontract has been divided into smaller Firm- Fixed Milestone Payments as shown elsewhere in the Subcontract. SUBCONTRACTOR shall be entitled to invoice for each specified Milestone Payment only upon the successful completion, and CONTRACTOR’S acceptance of, each Milestone in accordance with the SUBCONTRACT requirements and specified acceptance criteria.
Invoices for Milestone Payments shall be accompanied by documentation signed by the Subcontract http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3
Subcontract No. TBD 8/29/2024 Page 10 of 12
Administrator or the STR demonstrating that the Milestone has been fully completed and accepted by the CONTRACTOR. Invoices shall be accompanied by the certification required by the Invoicing and Payment Clause of this Subcontract. Milestone Payments are considered “contract financing payments” as defined in FAR Section 32.001.
D-8 CONTRACTOR WORK HOURS AND HOLIDAYS
Remote Sensing Laboratory – Andrews (RSL-A) business hours are 8:00 a.m. to 5:00 p.m. (EST), Monday through Friday.
Deviation from the approved Site Work hours shall be requested in writing from the CONTRACTOR and such approval shall not be unreasonably withheld.
CONTRACTOR recognizes the following holidays:
New Year's Day Labor Day Martin Luther King Day *Veterans Day Presidents’ Day Thanksgiving Day Memorial Day *Day after Thanksgiving Juneteenth *Day before Christmas Day Independence Day Christmas Day **December 27, and December 28
*These holidays are not applicable on the 4/10 hour work schedule and are also subject to change.
SUBCONTRACTOR shall verify holidays with STR.
** Actual dates may change from year to year.
D-9 WAGE RATE INFORMATION
The Construction Wage Rate Requirements (formerly known as the Davis-Bacon Act) apply to this Subcontract. Wage Determination MD20240054 is attached.
D-10 CONSTRUCTION LABOR STANDARDS
The Subcontractor shall complete Standard Form (SF)1413, Part II Acknowledgment of Subcontractor and provide to the Subcontract Administrator within 10 days after award.
D-11 PERFORMANCE AND PAYMENT BONDS
Definitions. As used in this clause “Subcontract price” means the award price of the Subcontract or, for requirements Subcontracts, the price payable for the estimated quantity; or for indefinite-delivery type Subcontracts, the price payable for the specified minimum quantity.
The Subcontractor shall furnish, prior to the commencement of the Work or as otherwise provided in this Subcontract or as required by the Subcontract Administrator, performance and payment bonds or equivalent protection to the CONTRACTOR as follows:
(1) Subcontracts between $35,000 and $150,000 may use either a Payment Bond (original copy), or an Irrevocable Letter of Credit (ILC):
(i) The ILC format is provided as an attachment under the Special Condition for Attachments (see Table of Contents).
(ii) For the Payment Bond:
(a) The penal amount of payment bonds shall be 100 percent of the original subcontract price.
(b) The CONTRACTOR may require additional performance bond protection when the subcontract price is increased. The increase in protection shall generally equal 100 percent of the increase in subcontract price.
(c) The CONTRACTOR may secure additional protection by directing the SUBCONTRACTOR to
Subcontract No. TBD 8/29/2024 Page 11 of 12 increase the penal sum of the existing bond or to obtain an additional bond.
(d) Standard Form SF25A, Payment Bond, shall be modified to name the CONTRACTOR as well as the United States of America as obligees. The Form can be located at the following link:
https://www.gsa.gov/forms-library/payment-bond
The SUBCONTRACTOR shall furnish all executed bonds and/or Letters of Credit, including any necessary reinsurance agreements, to the CONTRACTOR no later than 10 calendar days after Notice of Award.
The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties.
The bonds shall be accompanied by a letter stating the name and contact information of the responsible individual of the Surety who will be servicing the bonds. SUBCONTRACTOR shall maintain this information current throughout the execution of the subcontract.
Other assets may be pledged in lieu of bonds. However, they must conform to FAR 28.204.
D-12 USE OF ROADWAYS
SUBCONTRACTOR shall comply with CONTRACTOR’S and Government’s traffic regulations when utilizing CONTRACTOR or Government roadways. It shall be the responsibility of the SUBCONTRACTOR to familiarize itself and its employees with the traffic and safety requirements applicable to the Site.
D-13 NON-INTERFERENCE
SUBCONTRACTOR is responsible to ensure the non-interference of its own personnel, lower-tier subcontractors or suppliers with ongoing operations and personnel at the NNSS.
SUBCONTRACTOR shall not, in any manner, interfere with, or permit any of its subcontractors or suppliers to interfere with ongoing operations. Any interference shall be immediately addressed, and the cause identified, and measures taken to prevent reoccurrence.
D-14 WORKPLACE SUBSTANCE ABUSE PROGRAM
SUBCONTRACTOR shall develop and implement a written Workplace Substance Abuse Program in accordance with 10 CFR Part 707 Workplace Substance Abuse Programs at Department of Energy Sites, as a condition for award of the subcontract. CONTRACTOR shall review and approve the SUBCONTRACTOR’s program, and shall periodically monitor the implementation of the program for effectiveness and compliance with 10 CFR Part 707. In addition, SUBCONTRACTOR shall include a statement that “medical marijuana (although prescribed by a physician) is not recognized as a legal drug in the federal environment”.
CONTRACTOR has included an attachment, Checklist for Subcontractors Workplace Substance Abuse Program, to be completed and submitted with your companies Workplace Substance Abuse Program. See Section D-16 below.
D-15 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE
(a) Definition: (See FAR 52.219-6)
“Small business concerns,” as used in this solicitation and throughout the Subcontract and related documents means “a small business as defined pursuant to Section 3 of the Small Business Act and relevant regulations promulgated pursuant thereto.”
(b) General:
https://www.gsa.gov/forms-library/payment-bond
Subcontract No. TBD 8/29/2024 Page 12 of 12
Offers are solicited only from small business concerns as defined above. Offers received from concerns that are not small business concerns shall be considered non-responsive and will be rejected. Any award resulting from this solicitation will be made to a small business concern.
(c) Limitations on Lower-Tier Subcontracting
By submission of a proposal/bid and execution of a Subcontract, the OFFEROR/ SUBCONTRACTOR agrees that in performance of the Subcontract in the case of a contract for—
(1) Services (except construction). At least 50 percent of the cost of Subcontract performance incurred for personnel shall be expended for employees of the concern.
(2) Supplies (other than procurement from a nonmanufacturer of such supplies). The concern shall perform work for at least 50 percent of the cost of manufacturing the supplies, not including the cost of materials.
(3) General construction. The concern will perform at least 15 percent of the cost of the Subcontract, not including the cost of materials, with its own employees.
(4) Construction by special trade contractors. The concern will perform at least 25 percent of the cost of the Subcontract, not including the cost of materials, with its own employees.
D-16 ATTACHMENTS
1. Form 0870 “Supplier Payment Information Changes”
2. Form 2206, “Subcontractor Release Statement”
3. Davis-Bacon General Decision MD20240054.
4. Standard Form (SF)1413, Statement and Acknowledgement
5. WSAP Checklist
| D-1 Expediting |
| D-2 Insurance |
| D-3 Contractor-Furnished Drawings, Specifications & Statements of Work |
| D-4 Subcontractor-Furnished Drawings, Data and Samples |
| D-5 Permits and Responsibilities |
| D-6 Invoicing and Payment |
| D-7 Payments Under Firm-Fixed-Price Construction or Design-Build Subcontracts |
| D-8 Contractor Work Hours and Holidays |
| D-9 Wage Rate Information |
| D-10 Construction Labor Standards |
| D-11 Performance and Payment Bonds |
| D-12 Use of Roadways |
| D-13 Non-Interference |
| D-14 Workplace Substance Abuse Program |
| D-15 Notice of Total Small Business Set-Aside |
| D-16 Attachments |