6 - Exhibit B SOW.pdf
PDF 241 KB Posted
- Attached to
- 438168-CC-24 RSL Room Upgrades
- Solicitation number
- 438168-CC-24
- Issued by
-
Department of Energy
About this file
This document is an Exhibit B Statement of Work (SOW) for a firm-fixed-price construction subcontract under Solicitation Number 438168-CC-24. The SOW requires the subcontractor to perform modifications to an existing meeting room at the Remote Sensing Laboratory - Andrews facility to meet nationally mandated security requirements.
The key requirements include demolition of an existing demountable wall partition and door, installation of a new wall and access door meeting specific technical specifications, removal and reattachment of surface-mounted items, and finishing work such as ceiling repair, painting, and installation of vinyl baseboards and door seals. The subcontractor must provide detailed project sketches for review and approval, and demonstrate functional compliance with the technical specifications upon completion. The work location is the Remote Sensing Laboratory - Andrews at Andrews AFB, Maryland. No specialized experience, training, or certifications are specified. The subcontractor must use environmentally preferable products when available. Several submittals are required, including an environmental, safety, and health plan; insurance certificates; schedule of values; and project completion report.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit B (Ver May 2023) Solicitation Number: 438168-CC-24 Date: Rev 1 – 07/08/24 Subcontract Number: TBD
MISSION SUPPORT AND TEST SERVICES, LLC
FIRM-FIXED-PRICE CONSTRUCTION SUBCONTRACT
EXHIBIT B
STATEMENT OF WORK, SPECIFICATIONS AND DRAWINGS
TABLE OF CONTENTS
NO. TITLE PAGE
B-1 Scope/Background 2 B-2 Requirements 2 B-3 Technical Specifications 3 B-4 Drawings 3 B-5 Delivery & Work Location 3 B-6 Clearance Requirements 4 B-7 Specialized Experience/Specific Training/Specific Certifications 4 B-8 Environmentally Preferable Products 5 B-9 Attachments 5 B-10 Submittals 6
B-1 SCOPE/BACKGROUND
1. Scope: CONTRACTOR requires SUBCONTRACTOR to perform modifications to an existing meeting room to meeting nationally mandated security requirements.
2. Project Background: Per national policy the CONTRACTOR is required to meet certain security standards.
The national policy has been updated and it has been identified that a portion of the facility no longer meets the standard. Modifications are required to get the facility up-to-standard and re-certified.
3. General Site Information:
3.1. The Nevada National Security Sites (NNSS) is a U.S. Department of Energy, National Nuclear Security Administration (NNSA) installation, operated by Mission Support and Test Services, LLC (CONTRACTOR), comprising approximately 3,561 square kilometers (1,375 square miles) of federally owned land located in southeastern Nye County, Nevada. Located approximately 105 kilometers (65 miles) northwest of Las Vegas, Nevada, the NNSS is accessed from U.S. Highway 95, which roughly forms the southern boundary of the site.
3.2. The CONTRACTOR also operates the North Las Vegas Facility (NLV); the Remote Sensing Lab at Nellis AFB, North Las Vegas, NV (RSLN); the Remote Sensing Lab at Andrews AFB, Maryland (RSLA); Special Technologies Lab at Santa Barbara, CA (STL); Livermore Operations at Livermore, CA (LO); and Los Alamos Operations at Los Alamos, NM (LAO).
B-2 REQUIREMENTS
1. General: The SUBCONTRACTOR shall provide all tools, labor, and materials necessary to perform contact hands-on work to modify the CONTRACTOR’s existing interior wall to meet these requirements.
2. Detailed Requirements:
2.1. The SUBCONTRACTOR shall provide
2.2. SUBCONTRACTOR shall perform demolition of existing demountable wall partition and door.
2.3. SUBCONTRACTOR shall build and install Wall A as identified in the Technical Specifications for Construction and Management of Sensitive Compartmented information Facilities version 1.5.
2.3.1. Only the applicable Technical Specification criteria to this project will be required
2.4. SUBCONTRACTOR shall install an access door in the same location as the previous door.
2.4.1. The STC 50 access door shall be compliant to the Technical Specifications for Construction and Management of Sensitive Compartmented information Facilities version 1.5, Chapter 9.
2.5. The SUBCONTRACTOR shall provide detailed project sketches or drawings for CONTRACTOR review and approval prior to scheduled work.
2.5.1. The SUBCONTRACTOR sketches shall be submitted no later than one week after subcontract award.
2.6. The SUBCONTRACTOR shall remove and reattached all surface mounted items from the existing wall to the equivalent location and method for new wall.
2.7. The SUBCONTRACTOR shall perform the following finishing work:
2.7.1. Repair ceiling as needed at location of new wall.
2.7.2. Paint rooms where the new wall is located to match the existing paint color for each side of the wall.
2.7.3. Provide and install vinyl baseboard on new drywall partition.
2.7.4. Provide and install new door seal two existing doors.
2.8. SUBCONTRACTOR shall demonstrate functional compliance with the technical specification requirements upon completion of work. CONTRACTOR’s subcontract technical representative (STR) will witness the functional demonstration and provide approval of the completed work.
2.8.1. The CONTRACTOR’s Accrediting Official (AO) will perform required performance testing and accreditation approval of operational performance in compliance with the technical specification requirements for completed work.
2.9. The SUBCONTRACTOR shall provide a report of the work performed, findings, and suggestions for the CONTRACTOR’s review.
B-3 TECHNICAL SPECIFICATIONS
SPEC NUMBER TITLE REV PAGES
N/A
B-4 DRAWINGS
DRAWING NUMBER TITLE REV PAGES
N/A
B-5 DELIVERY & WORK LOCATION
Delivery Location:
Remote Sensing Laboratory - Andrews 1783 Arnold Ave. Andrews AFB, MD 20762
Work Location:
Remote Sensing Laboratory - Andrews - 1783 Arnold Ave., Rm 236, Andrews AFB, MD 20762
Additional Delivery/Work Locations: N/A
B-6 CLEARANCE REQUIREMENTS
1. Check all that apply:
☒ No security clearance; unclassified work
☐ DOE L
☐ DOE Q
☐ HSPD-12 PIV Credential
2. If applicable, add any or all parts of the following statement security qualifications:
☐ The SUBCONTRACTOR shall have the ability to obtain a U.S. Department of Energy (DOE) facility security clearance and have personnel capable of obtaining a Q-type or L-type security clearance.
☐ Q- or L-type security clearance is required for all SUBCONTRACTOR personnel having access to classified information or special nuclear material when performing such work.
☐ A corresponding level of security clearance from another federal agency may be applicable if approved by the CONTRACTOR and DOE.
☒ N/A
3. Security Misc.:
3.1. N/A
B-7 SPECIALIZED EXPERIENCE/SPECIFIC TRAINING/SPECIFIC CERTIFICATIONS
1. Licenses – SUBCONTRACTOR shall have the following job-specific licenses.
1.1 All licenses required in compliance with local, state, and federal building codes.
2. Training – SUBCONTRACTOR shall have the following job-specific training:
2.1. N/A.
3. Certifications – SUBCONTRACTOR shall have the following job-specific certifications:
3.1 N/A.
B-8 ENVIRONMENTALLY PREFERABLE PRODUCTS
NOTE TO SUBCONTRACTORS: Federal Contractors such as MSTS are required by the U.S. Department of Energy to purchase Environmentally Preferable Products (EPP) (also known as green or sustainable purchasing) and are also required to flow those procurement requirements to their Subcontractors. When designing materials and/or supplying materials to be used onsite as part of a subcontract scope-of-work, those materials must meet these same requirements.
The following is a list of EPP types that must be used if they are available:
• Products with Recycled Content. U.S. Environmental Protection Agency (EPA) list
• Water Efficient Plumbing Products. EPA WaterSense® list
• Non-Toxic or Less Toxic Alternatives
• Green Certified Products. (e.g., Design for Environment, Green Seal)
• Bio-Based Products. U.S. Department of Agriculture list
• Energy Efficient Products. EPA Energy Star® or Federal Energy Management Program designated products
• Energy Efficient Electronics. EPEAT®-silver-rated or higher rated desktop computers, laptops and monitors, televisions, multifunction devices and printers
• Non-Ozone Depleting Alternative Products
B-9 ATTACHMENTS
Attachment Number TITLE REV PAGES
No Document Number Technical Specifications for Construction and Management of Sensitive Compartmented information Facilities
1.5 209
B-10 SUBMITTALS
(ADM = Subcontract Administrator; STR = Subcontract Technical Representative; NLT = No Later Than;
NTP = Notice to Proceed; TLO = Transmittal Letter Only)
Description Reference Copies Received By Due Date Comments
PROCUREMENT RELATED SUBMITTALS
Environmental, Safety, and Health Plan
Exhibit E 1 STR
ADM
(TLO)
NLT 10 calendar days from award/Prior to start of work
Site-Specific Plan
Safety Data Sheet(s) Exhibit E 1 STR
ADM
(TLO)
NLT 10 calendar days from award/Prior to start of work
Safety and Personnel Report
Exhibit E 1 STR
(TLO)
Monthly, NLT 28th day of the new month
Provided using CONTRACTOR Form FRM-1253, “SUBCONTRACTOR Hours”
Insurance Certificates Exhibit D 1 ADM NLT 10 calendar days from award/Prior to start of work
Payment/Performance Bonds
Exhibit D 1 ADM No later than 10 calendar days from date of award
Prior to the start of Work
Subcontract Schedule Exhibit D 1 ADM No later than 10 calendar days from date of award
Prior to the start of Work
Hazard Communication Program
Exhibit E 1 STR
ADM
TLO
No later than 10 calendar days from Notice to Proceed prior to start of Work
Prior to start of Work
Certified Payrolls Exhibit D 1 ADM Weekly by the Subcontractor and all on-site Lower-Tier Subcontractors
Both paper and electronic copies are required
Schedule of Values Exhibit A 2 ADM
STR
No later than 10 calendar days from date of award
Prior to the start of Work
Workplace Substance Abuse Program to include Evidence of Compliance with SUBCONTRACTOR’s Workplace Substance Abuse Program
Exhibit D 1 ADM With Proposal and annually, based on date of
CONTRACTOR
acceptance
Provide any changes to the Program and evidence for that year’s compliance in accordance with Title 10 Code of Federal Regulations Part 707
Subcontract Release Statement – FRM-
Exhibit C Exhibit D
1 ADM Following completion of work prior to final payment for each Task Order
SUBCONTRACTOR shall submit a Subcontract Release Statement FRM-2206. The Subcontract Release Statement shall include a certification that states the following: "All GOVERNMENT and CONTRACTOR-furnished property has been returned, consumed, delivered or
Description Reference Copies Received By Due Date Comments otherwise disposed of as instructed by CONTRACTOR."
SUBCONTRACTOR’s Authorized Representative
Exhibit C 1 ADM Prior to the start of work
Also, when changes occur
PROJECT SPECIFIC AND TECHNICAL SUBMITTALS/DELIVERABLES (documentation only)
Description Reference Copies Received By
Due Date Comments
Final Project Sketches Exhibit B 1 ADM/STR NLT one week following award.
CONTRACTOR approval required
Project Completion Report
Exhibit B 1 ADM/STR NLT work completion. CONTRACTOR approval required
| B-1 Scope/Background |
| B-2 Requirements |
| B-3 Technical Specifications |
| B-4 Drawings |
| B-5 Delivery & Work Location |
| B-6 Clearance Requirements |
| B-7 Specialized Experience/Specific Training/Specific Certifications |
| B-8 Environmentally Preferable Products |
| B-9 Attachments |
| B-10 Submittals |
File details come from the government source that posted it. Updated .