This Scope of Work document outlines the electrical subpanel replacement requirements for the Housing Authority for the City of Alameda (AHA) at Parrot Gardens, a multifamily community located at 1854 St. Charles St, Alameda, California. The project involves upgrading eleven electrical subpanels across eight units, with work including circuit re-feeding, subpanel upgrades, decommissioning of outdated panels, installation of new waterproof-rated main panels, installation of code-compliant feeders, transfer of existing branch circuits, installation of new breakers with standard GFCI and/or AFCI protection, and patching and painting as necessary. A mandatory bid walk is scheduled for Wednesday, September 23, 2026, at 1:00 P.M. at the project site. The deadline for submitting questions through the Bonfire Portal is Thursday, October 1, 2026, at 4:00 P.M., with proposals and bids due through the Bonfire Portal on Thursday, October 22, 2026, at 4:00 P.M.
The project addresses existing conditions across eight units with varying panel configurations and amperages ranging from 145 to 405 amps. Specific concerns identified include the replacement of outdated Stab-Lok panels, removal of knob-and-tube wiring where present, resolution of non-functioning outlets, and installation of GFCI and AFCI protection in kitchens, bathrooms, and laundry areas. Two units at 1862 and 1864 St. Charles Street are connected and share panel systems. The project will require State Prevailing Wages and will be monitored by a third-party consultant. Licensed electrical contractors must provide qualifications and bids for both supply and installation services.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Parrot Garden Electrical Subpanel Replacement Scope of Work
Circuit Re-feed and subpanel upgrade
Trace the hot buss circuits currently being powered from the main panel. Safely disconnect the subpanel feed from the interior buss circuits, then permanently decommission the box panel. Cover box panel with metal plate.
Remove existing exterior panel and all outdated hardware. Supply and install new waterproof rated main panel. Install new code compliant feeder to interior box panel.
Transfer all existing branch circuit feeds to the new exterior panel. Supply and install new breakers, standard GFCI and/or AFCI as required by code.
The Stab-Lok 1858 St. Charles St. will need to be replaced asap.
Patch and paint in areas where necessary.
This project will require State Prevailing Wages and will be monitored by a third party consultant.
Existing Conditions
Unit # AMPS Comments
#1843 Bay St. (1) panel with (2) 40 amps circuits switches for the dryer
(1) panel with: 240 amps
(1) panel � 315 amps
Eaton and SWD circuit breakers. Two separate sub panels and meters.
#1843 � 315 amps one subpanel and another subpanel is the dryer - 80 amps (2 separate 40 amp switches) House panel: 240 amps � lights & irrigation
#1845 Bay St. (1) Panel 405 amps Knob and tube box unit in bedroom the closet
The circuit switch named �House Panel� shuts o power to the knob and tube box in the unit.
Siemens and SWD circuit breakers 405 amps
#1849 Bay St (1) Panel 355 amps Knob and tube box unit in the closet
The blue switch turns o power to the box in the unit. The circuits in the inside box have wire nuts.
Bryant (compatible with now Eaton) and SWD circuit breakers 355 amps
#1862 St.
Charles St.
Connected to #1864 St.
Charles St.
(1) Left side panel: 295 amps Metal panel with buss circuits in unit.
Did not test which switch turns of the buss circuits.
Connecticut circuit breakers Interior panel is General Switch Co which is now Siemens 295 amps
#1864 St.
Charles St.
Connected to #1862 St.
Charles St.
(1) Panel right side panel - 145 amps
Metal panel on the bedroom wall with buss circuits. Bathroom outlet not working. Can move panel in the living room or the niche back of the living room.
The 20 amp switch on the right in the electrical panel shuts o the box inside.
145 amps
#1858 St.
Charles St.
(1) Panel - 380 amps Could not locate box or panel in the unit. Kitchen and bathroom outlets connected to GFIs.
Stab-Lok need to be replaced asap; 380 amps
#1854 St.
Charles St.
(1) Panel - 405 amps The bottom red 20 amp switch controls the box inside. Kitchen GFI, no GFI in laundry and bathroom. Bathroom controlled by �Main� switches in the electrical panel.
SWD circuit breakers 405 amps
#1850 St.
Charles St.
O ice
(1) Panel Interior: 170 amps
(1) Panel Exterior: 320 amps
GE inside subpanel. No knob and tube or old buss fuses.
170 amps in the interior panel 320 exterior panel
11 total panels
1854 Bay St.
1845 Bay St.