8-BP 87N-0794-02 472-2023-085888 Redbud Multi-Use Path (Phase 2 - Rock Road).pdf
PDF 454 KB Posted
- Solicitation number
- 260288
- Issued by
- Sedgwick County, Kansas
About this file
Summary
This is a Request for Bid (RFB #260288) issued by the City of Wichita, Kansas for construction services to build the Redbud Multi-Use Path from Woodlawn to K-96, Phase 2 (Rock Road). The project is identified as 87N-0794-02/472-2023-085888 and includes construction of a pedestrian bridge, path improvements, and site restoration work. Sealed bids are due electronically through the City's Procurement Portal by 10:00 a.m. on Friday, November 13, 2026, with a pre-bid conference scheduled for Monday, November 30, 2026, at 11:00 a.m. at the Central Maintenance Facility. The contractor must start work no later than February 1, 2027, and complete all work except seeding, sodding, and tree plantings within 220 working days from the Notice to Proceed date, with an additional 30-day cleanup period allowed. Saturdays are excluded from working days unless the contractor elects to work, and work requiring engineer inspection is prohibited on Sundays. The contractor is required to work a minimum of five days per week, excluding official city holidays.
This state and federal aid contract requires a bid bond of 5 percent of the total bid amount, a performance bond of 100 percent of the contract value, and a labor and material payment bond in an amount not less than the total contract value. Award will be based on the lowest and best total net bid from a responsible and responsive vendor. The contractor must obtain a Kansas Sales Tax Exemption Certificate from the City Controller's Office prior to starting work and comply with Buy America regulations. Required insurance includes Commercial General Liability with minimum limits of $1,000,000 per occurrence and $2,000,000 annual aggregate, Comprehensive Automobile Liability of $1,000,000, Workers' Compensation at statutory requirements, and Umbrella Liability of $10,000,000. Liquidated damages are assessed at $1,000 per day for schedule overruns. The contractor must schedule a public information meeting at least seven days before construction begins and comply with special provisions regarding Evergy transmission pole relocation, Rock Road closure limitations for bridge setting, voluntary cleanup and soil management requirements, and restoration of disturbed properties.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
Provide conditions for living well.
City of Wichita 1 RFB #260288
N O T I C E T O C O N T R A C T O R S
Notice is hereby given that sealed proposals for constructing Redbud Multi-Use Path from Woodlawn to K-
96 (Phase 2 – Rock Road) will be received (electronically) in the office of the City Purchasing Manager, 12th Floor, City Hall, 455 North Main, Wichita, Kansas, prior to 10:00 O'CLOCK A.M., FRIDAY
December 11, 2026, at which time the bids will be opened publicly and read aloud and tabulated by the
Board of Bids and Contracts for consideration by the City Council. Bids received after said time will be returned unopened. Proposals are to be submitted through the City’s Procurement Portal
(wichita.gov/procurementportal).
NOTE: BIDDER SHALL AFFIX THE FOLLOWING PROJECT NUMBER TO THE BID ENVELOPE
OR FILE ATTACHMENT 87N-0794-02
ATTENTION ALL BIDDERS: A BID BOND IN THE AMOUNT OF FIVE PERCENT (5%) OF THE
TOTAL BID OR AN ANNUAL BID BOND IS REQUIRED PRIOR TO BID OPENING. SEE SECTION
102.3 OF THE CITY OF WICHITA STANDARD SPECIFICATIONS FOR FURTHER INFORMATION.
BIDDERS ARE ADVISED TO CONTACT THE OFFICE OF THE CITY ENGINEER (316-268-4501)
SHOULD THEY HAVE ANY QUESTIONS OR CONCERNS ABOUT THE PLANS, SPECIAL OR
SUPPLEMENTAL PROVISIONS, MINORITY STATUS, OR THE PROPER PREPARATION OF THE
BID DOCUMENT.
THE BID FORM SHALL BE PREPARED USING PRICES PER BID ITEMS, UNLESS OTHERWISE
NOTED
PERFORMANCE BOND FORMS, included in the bid package are to be used, in the amount of one hundred percent (100%) of the contract must be furnished by the successful vendor.
A LABOR & MATERIAL PAYMENT BOND FORMS, included in the bid package are to be used, running to the State of Kansas in a sum of not less than the total of the contract, must be furnished by the successful vendor.
If a Bonfire (“Procurement Portal”) registration for system access has not been completed, please visit wichita.gov/purchasing for assistance. On the Purchasing website, a video tutorial (Bonfire Registration Video) walkthrough and registration resources are available to help in the completion of the registration process. If further assistance is needed, please contact the Purchasing Office directly at purchasing@wichita.gov or by phone at 316-268-4636.
Vendors are encouraged to complete bidder registration by visiting the City of Wichita’s eProcurement Portal at wichita.gov/procurementportal, then follow the link to the Bonfire vendor registration page to register your company. Please check our website, wichita.gov/purchasing for upcoming registration opportunities, training dates & locations, and information as it is updated in the near future.
https://wichita.bonfirehub.com/ https://www.wichita.gov/purchasing mailto:purchasing@wichita.gov https://wichita.gov/procurementportal https://www.wichita.gov/purchasing
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
City of Wichita 2 RFB #260288
SPECIAL PROVISION TO CITY OF WICHITA, KANSAS
STANDARD SPECIFICATIONS
Redbud Multi-Use Path from Woodlawn to K-96 (Phase 2 – Rock Road)
87N-07694-02/472-2023-085888/47472122/E2109
The City of Wichita's Standard Specifications and Standard Special Provisions to the City of Wichita Standard Specifications are required provisions for the furnishing of all materials and doing all work to complete the above referenced project and are hereby made a part of these provisions as if fully set forth herein. Said Standard Specifications and Standard Special Provisions shall control except as modified by the following Project Specific Special Provisions. The Standard Specifications and Standard Special Provisions are on file in the City Engineer's Office, available for purchase from ARC for the construction of City projects, or can be found online at https://www.wichita.gov/630/Standard-Specifications **Electronic plan sheets for this project will only be available in the ARC Document Solutions plan room for the City of Wichita projects, which is located at https://customer.e-arc.com/arcEOC/ARCPlanRoom.aspx **The following Project Specific Special Provisions shall be applicable to this project:
The Contractor shall read and fully comprehend every aspect of the contract provisions included in this bid proposal, prior to submitting a bid for the project. Any questions prior to bid submittal should be directed to Val Falo, Buyer, at (316) 268-4414 or vfalo@wichita.gov.
THIS IS A STATE/FEDERAL AID CONTRACT.
PROJECT SPECIFIC
1. Pre-Bid Conference. Monday, November 30, 2026, at 11:00 a.m., Engineering Conference Room, Central
Maintenance Facility, 1801 S. McLean, Wichita Kansas.
2. Deadline for Questions. For comments that affect bid items and/or quantities: Noon Tuesday prior to bid opening. For questions and comments requiring clarification only: Noon Wednesday prior to bid opening.
This is necessary so appropriate changes and responses can be completed before bidding.
The tentative schedule will apply to this RFB and may change according to with the City’s needs or unforeseen circumstances. All dates and times will be in Central Standard Time (CST; CDT) and can be confirmed through the Purchasing Office located at 455 N. Main 12th Floor Wichita, KS 67202 by calling (316) 268- 4636, or by contacting the buyer listed on the solicitation document directly. Questions of a substantive nature will be reviewed and answered in written form as an addendum and posted to the City’s Procurement Portal at wichita.gov/procurementportal.
3. Public Information Meeting. Contractor will be required to schedule a ‘Public Information’ meeting at least 7 days in advance of construction. Contractor will provide a minimum three-day notice of said meeting’s time and location to adjacent residents, property owners and businesses. The Contractor will moderate the meeting and discuss issues such as construction schedules, phasing, traffic control, access to properties and any special considerations regarding the construction and phasing of the project. Key Contractor and City personnel should be in attendance.
4. Start Date. The work order on this project shall be issued at the Contractor’s request contingent upon the
City of Wichita having the Authority to Award from KDOT and an executed contract and at Engineer’s approval. The Contractor shall start no later than February 1, 2027.
5. Working Days/Completion Date. The work on this project, except for seed, sod, and tree plantings, shall be completed within 220 (two hundred twenty) working days from the Notice to Proceed date. Working days will be charged in accordance with the plans and Standard Specifications, once the work order is issued.
Liquidated Damages shall be assessed in the amount of $1,000 per day according to the City of Wichita Specifications.
For this project, the Contractor is required to work a minimum of five days per week excluding official https://www.wichita.gov/630/Standard-Specifications https://customer.e-arc.com/arcEOC/ARCPlanRoom.aspx mailto:vfalo@wichita.gov
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
City of Wichita 3 RFB #260288 city holidays. Saturdays shall not be considered a working day unless the Contractor elects to work. Work, which will require inspection by the Engineer, shall not be permitted on Sundays.
An additional Cleanup Time of 30 (thirty) working days based on the KDOT Specification 108.4.c and Table 108-A will be allowed after the contract time. Liquidated Damages shall be assessed at the rate of $1,000 per day for the cleanup time according to the City of Wichita Specifications.
6. Evergy Transmission Poles. The Evergy transmission poles are expected to complete construction at the end of the month of December. The Contractor will be required to work around the Evergy Transmission relocation in order to build the east ramp section of the pedestrian bridge.
7. Rock Road Closure for Setting of Bridge. The closure of Rock Road to allow setting of the pedestrian bridge will be allowed to happen no earlier than at 7 pm on a Friday and opening by 5 am the following Monday.
8. Buy America, Build America. The most up-to-date Buy America, Build America regulations apply to the project and information can be found at the following website:
https://www.fhwa.dot.gov/construction/cqit/buyam.cfm
9. Voluntary Cleanup Plan and Soil Management and Plan. The Contractor shall follow the provided
Voluntary Cleanup Plan and Soil Management Plan for disturbed soils. The Contractor may propose profile grade changes to be approved by the Engineer to reduce disturbance and/or excavation of ballast rock. It is the intent to eliminate off-site disposal of any generated excavations and use any materials as subgrade fill for paved areas per the Soil Management Guide. Should any waste be generated that requires removal from the project site a change order will be required for the associated costs to do so.
10. Surfacing Material (Special). The specifications and gradation for the Surfacing Material (Special) are attached.
11. Required Contract Provisions. The Contractor shall complete and submit with its proposal these provisions.
I. 08-10-66-R05 (LPA) Certifications-Noncollusion & History of Debarment II. 04-26-90-R05 (LPA) Declaration-Limitations on Use of Federal Funds for Lobbying III. 01-01-11 (LPA) Tax Clearance Certificate IV. 08-04-93-R3 (LPA) – Certification – Contractual Services with a Current Legislator or Current Legislator’s Firm V. 04-30-82-R07 – Certification – Financial Prequalification Amount VI. Proposed Subcontractors List VII. Buy America Certification
12. Basis of Payment. Payment for the bid items will be as a lump sum/measured quantity amount based on the bid quantities and unit prices in the bid proposal.
Bids submitted may not be withdrawn for a period of 60 days following the opening of this Request for Bid.
Prices MUST also be free of duties, federal, state, and local taxes unless otherwise imposed by a governmental body, and applicable to the material on the proposal.
13. Approved Materials List. A list of materials approved for use on City of Wichita construction projects can be found on the City website at https://www.wichita.gov/630/Standard-Specifications. All approved materials shall conform to the appropriate requirements set forth in the Standard Specifications, and shall have been previously approved by the Material Review Board (MRB). Information on obtaining approval for new materials through the MRB is available on the website.
14. Existing Conditions Documentation. Contractor shall document existing property conditions prior to construction. Documentation shall be video-recorded tape supplemented with 35 mm or digital photographs.
Neither videotape nor photographs shall be made from a moving vehicle. One (1) copy of the documentation package shall be provided to the Engineer prior to beginning construction on the project.
15. Additional Insurance Requirements On Bradley Fair Shopping Center Property. Contractor shall have https://www.fhwa.dot.gov/construction/cqit/buyam.cfm https://www.wichita.gov/630/Standard-Specifications
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
City of Wichita 4 RFB #260288 to acquire additional insurance requirements in accordance with Attachment 5 for entry onto the Bradley Fair Shopping Center property that exceed the required in the Liability Insurance in the Specifications.
16. Pedestrian Bridge Assembly Staging. A staging area for bridge assembly has been set aside as shown on
Sheet 99 of the Traffic Control Plans. The Contractor has until Jan 31, 2028 to vacate and restore the property.
The Contractor must follow the following provisions:
• Install “temporary construction/snow fence” along the perimeter of the property, a minimum of 5’ inside the property line. A Measured Quantity bid item shall be added for “Temporary Snow Fence”.
• Follow Special provision 10 and restore conditions post construction as part of Site Restoration.
• Provide a minimum of 5-days written notice to Grantor & Grantor Tenant of initial entry/use of TCE.
• Provide a minimum of 20-days written notice to Grantor & Grantor Tenant if there will be any partial closure of Rock Road adj. to the Haverty’s property & or any heavy haul movement within the Ingress/Egress roadway to Rock Road.
• Contractor needs to provide a copy of their certificate of insurance prior to accessing the TCE to Grantor & Grantor Tenant.
• If any property is damaged by City/Contractor, written notice shall be given to Grantor & Grantor Tenant within 24-hours of the damage occurrence.
Grantor:
GOKO, LLC
Attn: Tin Nelson 100 E English Wichita KS 67202 tnelson@fidelitybank.com and plambertz@fidelitybank.com
Grantor Tenant:
Haverty Furniture Companies, Inc.
Attn: General Counsel & Real Estate Manager 780 Johnson Ferry Road NW, Suite 800 Atlanta, GA 30342
17. 635.109 Standardized changed condition clauses shall be followed on this project
(a) The following changed conditions contract clauses shall be made part of, and incorporated in, each highway construction project, including construction services contracts of Construction Manager/General Contractor projects, approved under 23 U.S.C. 106:
(1)Differing site conditions.
(i) During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract, are encountered at the site, the party discovering such conditions shall promptly notify the other party in writing of the specific differing conditions before the site is disturbed and before the affected work is performed.
(ii) Upon written notification, the engineer will investigate the conditions, and if it is determined that the conditions materially differ and cause an increase or decrease in the cost or time required for the performance of any work under the contract, an adjustment, excluding anticipated profits, will be made and the contract modified in writing accordingly. The engineer will notify the contractor of the determination whether or not an adjustment of the contract is warranted.
(iii) No contract adjustment which results in a benefit to the contractor will be allowed unless the contractor has provided the required written notice.
(iv) No contract adjustment will be allowed under this clause for any effects caused on unchanged work.
mailto:tnelson@fidelitybank.com mailto:plambertz@fidelitybank.com https://www.law.cornell.edu/uscode/text/23/106
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
City of Wichita 5 RFB #260288
(2)Suspensions of work ordered by the engineer.
(i) If the performance of all or any portion of the work is suspended or delayed by the engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and the contractor believes that additional compensation and/or contract time is due as a result of such suspension or delay, the contractor shall submit to the engineer in writing a request for adjustment within 7 calendar days of receipt of the notice to resume work. The request shall set forth the reasons and support for such adjustment.
(ii) Upon receipt, the engineer will evaluate the contractor's request. If the engineer agrees that the cost and/or time required for the performance of the contract has increased as a result of such suspension and the suspension was caused by conditions beyond the control of and not the fault of the contractor, its suppliers, or subcontractors at any approved tier, and not caused by weather, the engineer will make an adjustment (excluding profit) and modify the contract in writing accordingly. The contractor will be notified of the engineer's determination whether or not an adjustment of the contract is warranted.
(iii) No contract adjustment will be allowed unless the contractor has submitted the request for adjustment within the time prescribed.
(iv) No contract adjustment will be allowed under this clause to the extent that performance would have been suspended or delayed by any other cause, or for which an adjustment is provided or excluded under any other term or condition of this contract.
https://www.law.cornell.edu/cfr/text/23/635.109 https://www.law.cornell.edu/cfr/text/23/635.109
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
City of Wichita 6 RFB #260288
BID TERMS
Bid Submission Sealed Request for Bid (RFB) will be received in the office of the City Purchasing Manager, 12th Floor, City Hall, 455 North Main, Wichita, Kansas 67202, prior to 10:00 O'CLOCK A.M., Friday, NOVEMBER 13, 2026.
Bids may be submitted on our website at (wichita.gov/procurementportal) using a secure login/password.
Electronic submissions are requested. Bids are to be submitted through the City’s Procurement Portal (wichita.gov/procurementportal). Respondents are responsible for checking the City’s Procurement Portal and acknowledging any addenda electronically as a part of the Procurement Portal submission’s electronic acknowledgment for all stipulated response forms and addendum acknowledgments.
If you haven't already completed a Bonfire registration for system access, please visit wichita.gov/purchasing for assistance. On the Purchasing website's page, you can find a video tutorial (Bonfire Registration Video) walkthrough and registration resources to help in the completion of the registration process. If you need further assistance, please contact the Purchasing Office directly at purchasing@wichita.gov or by phone at 316-268-4636.
All bids, including supporting documentation/manuals, shall become the property of the City.
Evaluation Criteria
Bid Award will be based on the Lowest and Best Total Net Bid from a Responsible and Responsive vendor.
The City, through its Board of Bids and Contracts, reserves the right to accept or reject any or all bids and any part of parts of any bid and to waive formalities therein to determine which is lowest and best bid. Any bid which is incomplete, conditional, obscure, or which contains additions not called for or irregularities of any kind, may be rejected. All bids are awarded subject to a check of the computations shown on the "Request For Formal Bid" form. In the event of a discrepancy in the extension(s) or total for the item(s), the unit cost shall prevail.
The City, through its Purchasing Manager, reserves the right to accept or reject any or all submittals and any part or parts of any submittal, and to waive formalities therein to determine which is the most beneficial bid.
Minimum Respondent Qualifications This section lists the criteria to be considered in evaluating the responsiveness of firms interested in providing the goods and/or service(s) specified in this Request for Bid. Firms should meet or exceed these qualifications to be considered for award. Any exceptions to the requirements listed should be clearly detailed in the proposer’s response. Bidders shall:
1. Have a minimum of 3 years’ experience in providing similar services specified in this RFB.
2. Understanding of industry standards and best practices.
3. Have experience in providing goods and/or services of comparable size and complexity to that being requested.
4. Have knowledge of and comply with all currently applicable, and as they become enacted during the contract term, federal, state and local laws, statutes, ordinances, rules and regulations. All laws of the State of Kansas, whether substantive or procedural, shall apply to the contract, and all statutory, charter, and ordinance provisions that are applicable to public contracts in the city shall be followed with respect to the contract.
5. Registration with the Kanas Secretary of State’s Office before contract execution.
6. Municipal government experience is desired, however, the City will make the final determination based on responses received and the evaluation process.
7. Have the capacity to acquire all bonds, escrows or insurances as outlined in the terms of this RFB.
8. Provide project supervision (as required) and quality control procedures.
9. Have appropriate material, equipment and labor to perform specified services.
10. Park only in designated areas and display parking permit (if provided).
11. Wear company uniform or ID badge for identification purposes.
https://wichita.bonfirehub.com/ https://wichita.bonfirehub.com/ mailto:purchasing@wichita.gov
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
City of Wichita 7 RFB #260288
12. Project must meet local, state, and federal guidelines as applicable.
13. Exceptions to any part of this document clearly delineated and detailed.
14. Responses that do not include all required forms/items may be deemed non-responsive.
Bid Requirements
1. Completed Procurement Portal (wichita.gov/procurementportal) submission.
2. Bids submitted may not be withdrawn for a period of 60 days following the opening of this Request for
Bid. Prices MUST also be free of duties and federal, state, and local taxes unless otherwise imposed by a governmental body, and applicable to the material on the proposal.
3. Pricing for all stipulated Item(s) and/or Group(s) requirements. Bidders who do not submit pricing for all items when stipulated may be deemed nonresponsive when not adhering to:
a. Lowest and Best Total Net Bid from a Responsible and Responsive vendor.
Debriefing
The City of Wichita encourages solicitation respondents to learn, grow, and improve their competitiveness for City procurement opportunities.
In the event of an unsuccessful solicitation response, solicitation respondents may request a debriefing regarding the selection process from the project manager and the buyer/purchasing representative identified in the solicitation document. The City of Wichita Purchasing Office may be directly contacted at (316) 268-4636 for assistance regarding the debriefing process.
Challenges and Protests
Challenges
A challenge is defined as a written objection by any party interested in responding to either a bid or proposal (collectively referred to as solicitations), when that party wishes to have the City consider an addition, substitution or modification to the specifications stated in the outstanding solicitation.
The written challenge of the solicitation specifications must be filed with the Purchasing Manager located on the 12th Floor, Finance Department at City Hall, 455 N Main, Wichita, KS 67202, telephone number (316)268-4636, at least five (5) business days before the solicitation opening due date and time as listed on the solicitation documents.
Any challenge to solicitation specifications received after the five (5) business days deadline will not be considered by the City. The Purchasing Manager will acknowledge receipt of the challenge. The written challenge is to include the name, address, email address and telephone number of the interested party, identification of the solicitation number and project title, a detailed statement of the reasons for the challenge, supporting evidence or documentation to substantiate any arguments, and the form of relief requested, e.g. the proposed addition, substitution or modification to the specifications. The Purchasing Manager will investigate the written challenge and any evidence or documentation submitted with the challenge.
In the event of a timely challenge of the solicitation specifications to the Purchasing Manager, the affected pending solicitation shall not proceed further until the challenge is resolved by Purchasing Manager decision. The Purchasing Manager will issue a written decision, which will be posted on the City’s Procurement Portal, wichita.gov/procurementportal, for viewing by all interested parties. The decision rendered by the Purchasing Manager will be final.
Protests
A protest is defined as a written objection to a proposed award, or the award of a contract, with the intention of receiving a remedial result. In order to be considered valid, a protest must 1) come from an actual bidder or proposer for the contract, 2) who claims to be the rightful award recipient, 3) whose economic interest may be affected substantially and directly by the award of a contract or by the failure to award a contract. Suppliers or subcontractors to a bidder or proposer cannot file a valid protest. A valid protest can only be filed by a bidder or proposer which can show that it would be awarded the contract if the protest were successful. Therefore, all conditions numbered 1 through 3 listed above in this paragraph must be met.
The written protest for bids must be filed with the Contract Compliance Officer located on the 12th Floor, https://wichita.bonfirehub.com/
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
City of Wichita 8 RFB #260288
Finance Department, City Hall, 455 N Main, Wichita, KS 67202, prior to 9:00 a.m. of the Tuesday immediately following the posting of the notice of intent to award on the City’s Purchasing Bid Results site wichita.gov/purchasing.
Failure of a protestor to file a written protest related to the award of a contract prior to the 9:00 a.m., Tuesday deadline will invalidate that protest and cause it not to be considered.
The written protest for proposals must be filed with the Contract Compliance Officer located on the 12th
Floor, Finance Department, City Hall, 455 N Main, Wichita, KS 67202, prior to 5:00 p.m. on the third business day following the day of issuing an email or written notification of award. Failure of a protestor to file a written protest related to the award of a contract prior to 5:00 p.m. on the third business day deadline will invalidate that protest and cause it not to be considered.
The Contract Compliance Officer will acknowledge receipt of the written protest. The written protest is to include the name, address, email address and telephone number of the protestor, identification of the solicitation number or contract number and project title, a detailed statement of the reasons for the protest which justify the relief sought, supporting evidence or documentation to substantiate any arguments, and a concise statement of the form of relief requested (e.g. reconsideration of the offer). All the above required information must be included in the protest at its submission. Untimely protests will be returned unopened. Incomplete protests will be rejected without consideration.
In the event of a valid, timely protest, the City shall not proceed with the execution of the contract until all
City administrative remedies have been exhausted or waived, or until a determination is made that a contract award is required to protect the interests of the City.
The decision of the Contract Compliance Officer, based on review of the written protest and information available from City sources, will be rendered within ten (10) business days after receipt of protest, will recite the reasons for the decision, and be provided to the protestor by email or written notification.
The protestor may seek reconsideration of the decision of the Contract Compliance Officer’s decision in writing to the Internal Auditor on the 13th Floor, City Manager Office, City Hall, 455 N Main, Wichita, KS 67202, prior to 5:00 p.m. on the third business day following the day of issuing an email or written notification of decision. Failure of a protestor to file a written reconsideration request related to the Contract Compliance decision prior to 5:00 p.m.
on the third business day deadline will invalidate that protest and cause it not to be considered. The Internal Auditor decision will be issued by email or written notification, within ten (10) business days after receiving the written reconsideration, unless this time for a response is extended in writing and agreeable by both parties.
The Internal Auditor’s decision will be final, unless the protestor seeks a hearing before the City Council, by written request filed with the City Clerk, located on the 13th Floor, City Hall, 455 N Main, Wichita, KS 67202, prior to 5:00 p.m. on the third business days after issuance of the Internal Auditor written decision. Failure of a protestor to file a written reconsideration request related to the internal Auditor’s decision prior to 5:00 p.m. on the third business day deadline will invalidate that protest and cause it not to be considered.
If there is a timely written reconsideration request, the protestor may seek reconsideration of the decision of the Internal Auditor by means of a hearing before the City Council. This hearing must be in aid of the City Council’s legislative authority to approve contracts for goods, services, and public improvements on behalf of the City, and does not imply any due process right of the protestor in an unawarded, unexecuted contract. The hearing must be scheduled as soon as practicable according to the City Council’s calendar. The hearing must be granted only upon such facts and issues as are presented in writing to the City Clerk for submission to City Council at or before noon on the Thursday preceding the scheduled hearing. No documents or other evidence must be accepted at the hearing.
The protesting party must have available no more than 20 minutes for presentation of argument, followed by no more than 20 minutes of argument presented by City staff. The City Council may deliberate in executive session to seek the assistance of the City Attorney, but must deliver its decision from the bench during the City Council meeting.
If a written protest is made against any proposed award or the award of a contract that relies in part on federal funding, then the Contract Compliance Officer must notify the Granting Authority in writing with all information
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
City of Wichita 9 RFB #260288 regarding the protest. A protestor must exhaust all administrative remedies with the City of Wichita before pursuing a protest with the Granting Authority. Protestors are put on notice that according to federal regulations, certain determinations made at the local level are not subject to appeal to the Granting Authority. If a review is granted by the Granting Authority, it will be limited to:
1. the City of Wichita’s failure to have or follow its protest procedures, or its failure to review a complaint or protest; or
2. violations of Federal law or regulations.
The Contract Compliance Officer will provide notice to the Granting Authority Regional Office or Headquarters Office of any request for reconsideration before the City Council, and also provide notice of the decision rendered by the City Council, or any alternative resolution reached.
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
City of Wichita 10 RFB #260288
LIABILITY INSURANCE SPECIFICATIONS
The Successful Bidder will be required to furnish a Certificate of Insurance (prior to the Purchase Order, Agreement, or Contract being issued) with the following minimum coverage:
1. Commercial General Liability
Covering premises---operations, xcu hazards, Product/Completed Operations, Broad Form Property Damage and Contractual Liability with minimum limits as follows:
Bodily Injury Liability $1,000,000 Each Occurrence $2,000,000 Annual Aggregate
Property Damage Liability $1,000,000 Each Occurrence $2,000,000 Annual Aggregate
Or
Bodily Injury and Property Damage $1,000,000 Each Occurrence Liability (Combined Single Limit) $2,000,000 Annual Aggregate
2. Comprehensive Automobile Liability All Owned, Non-Owned, and Hired vehicles with minimum limits as follows:
Bodily Injury Liability $1,000,000 Each Occurrence Property Damage Liability $1,000,000 Each Occurrence
Or
Bodily Injury and Property Damage Liability (Combined Single Limit) $1,000,000 Each Occurrence
3. Workers' Compensation to meet Statutory requirements.
4. Employers Liability $1,000,000 Each Accident $1,000,000 Occupational Disease $1,000,000 Annual Aggregate The following additional coverages will apply when selected:
Required: YES___ NO _X__
5. Professional Liability (Claims made basis) $1,000,000 Each Claim $1,000,000 Annual Aggregate Required: YES___ NO _X__
6. Pollution Liability $1,000,000 Each Claim $1,000,000 Annual Aggregate Required: YES_X__ NO ___
7. Umbrella Liability $10,000,000 Each Claim $10,000,000 Annual Aggregate
The City of Wichita shall be added as primary and non-contributory additional insured to the general commercial and automobile liability coverages. The policy shall also provide coverage for contractor’s/vendor’s contractual obligations created in the Agreement. Coverage shall be the greater of the requirements stated here or the contractor’s existing policy and contractor shall provide a Certificate of Insurance evidencing such coverages prior to beginning of services under this Agreement.
The Certificate of Insurance must be submitted within ten (10) days after notification of award to the City of
Wichita Purchasing Manager, City Hall, 12th Floor, 455 North Main, Wichita, Kansas, 67202-1694.
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
City of Wichita 11 RFB #260288
GENERAL SPECIFICATIONS
BID FORMS
All bids MUST be electronically submitted and acknowledged (Yes/No) by an officer or employee authorized to submit and bind the bidder to the terms of the solicitation and bidder. Any exceptions, to the specifications, terms and/or other conditions concerning the bid, must be noted in the “bid" submitted to be considered. The "bid" is to be submitted electronically through the City’s Procurement Portal (wichita.gov/procurementportal) using a secure login/password. Vendors are requested to submit current literature or brochures relating to their bid.
LICENSE
Vendors bidding on commodities or services for the City of Wichita must be currently licensed by the City of Wichita or the State of Kansas, where applicable, before a purchase order or contract will be issued.
BILLING TERMS
Discounts for prompt payment will be considered in the evaluation of your bid. The discount time will not begin until the City receives all of the commodities or services. If testing is required, the discount time will begin upon completion of the testing.
Billing terms must be noted on the bid form to consider the deduction in the award.
CONTRACT
The successful bidder agrees to enter into a contract with the City, and when required, as per specifications, to furnish bond by a surety company authorized to do business in the State of Kansas.
SMALL & EMERGING BUSINESS ENTERPRISE (S/EBE) PARTICIPATION ENCOURAGEMENT
The City of Wichita encourages all bidders to include small and emerging business participation in their bid.
ARBITRATION PROVISIONS
"Notwithstanding anything to the contrary contained in these bid documents or the contract to be awarded herein, the City shall not be subject to arbitration and any clause relating to arbitration contained in these bid documents or in the contract to be awarded herein shall be null and void."
ANTITRUST LITIGATION CLAUSE
"For good cause, and as consideration for executing a purchase order/contract, the contractor, acting therein by and through its authorized agent, hereby conveys, sells, assigns, and transfers to the City of Wichita, all rights title and interest in and to all causes of action it may now or hereafter acquire under the antitrust laws of the United States and the State of Kansas, relating to the particular product, products, or services purchased or acquired by the City of Wichita, Kansas, pursuant to a purchase order/contract.
CONSTRUCTION - PAVING PROJECTS
On construction or paving projects, contractors MUST contact the City Controller's Office, City Hall, 12th Floor, 455 North Main Street for a Kansas Sales Tax Exemption Certificate prior to starting work. Contractors will be responsible for paying Kansas Sales Tax on any purchase for these projects made before the certificate is issued.
MUTUAL WAIVER OF CONSEQUENTIAL DAMAGES
The contractor and owner waive claims against each other for consequential damages arising out of or relating to this contract.
This mutual waiver includes, but is not limited to:
1) Damages incurred by the owner for rental expenses, for loss of use, income, profit, financing, business and reputation and for loss of management or employee productivity or for the services of such persons; and
2) Damages incurred by the contractor for principal office expenses, including, but not limited to, the compensation of personnel stationed in such principal office, for losses of financing, business and reputation and for the loss of profit, except anticipated profit arising directly from the construction.
RESTORATION
"Contractor shall, as a condition of final payment, restore all right-of-way and adjacent private property which has been disturbed, damaged or otherwise affected by construction to a condition equal to or better than existed prior to the commencement of construction. Such restoration shall include but not be limited to regrading and seeding of areas where grass was planted and growing prior to construction; provided, however, such regrading and seeding of lawn areas, when completed, shall be considered to be restoration of an area to a condition equal to or better than previously existing grass growth and Contractor shall have no responsibility to ensure growth of such seeded area(s). This restoration shall be considered part of the contract work and Contractor shall be responsible for the performance of such restoration work in the same manner as it is responsible for the performance of the contract work."
https://wichita.bonfirehub.com/
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
City of Wichita 12 RFB #260288
FEDERAL EXCISE TAX
The articles specified in this bid are for the exclusive use of the City of Wichita, Kansas. Therefore, Federal Excise Tax shall not be imposed. The City of Wichita, Kansas Federal Excise Tax Exemption Certificate Number is 48 77 0021K.
ESTIMATED QUANTITIES
If estimated quantities are shown, on the "Request For Formal Bid" form, they are used to evaluate the bid only. The figure(s) listed is the estimated usage only and is not intended to limit or guarantee in any way, the amount the City may purchase under the purchase order/contract.
CITY OF WICHITA CREDIT CARD
Presently, many City Agencies use a City of Wichita Procurement Card (Visa) in lieu of a City warrant to pay for some of its purchases. No additional charges will be allowed for using the card.
DELIVERY
Delays in delivery caused by bona fide strikes, government priority or requisitions, riots, fires, sabotage, acts of God or any other delays deemed by the Board of Bids and Contracts to be clearly and unequivocally beyond the contractor's control, will be recognized by the City, and the contractor will be relieved of the responsibility of meeting the delivery time, as stipulated in the contract, upon contractor's filing with the Board of Bids and Contracts a notarized just and true statement signed by a responsible official of the contractor's company, giving in detail all the essential circumstances which, upon verification by the City, justifies such action by the Board of Bids and Contracts.
AWARD
The City, through its Board of Bids and Contracts reserves the right to accept or reject any or all bids and any part of parts of any bid and to waive formalities therein to determine which is lowest and best bid. Any bid which is incomplete, conditional, obscure, or which contains additions not called for or irregularities of any kind, may be cause for rejection of the bid. All bids are awarded subject to a check of the computations shown on the "Request For Formal Bid" form. In the event of a discrepancy in the extension(s) or total for the item(s), the unit cost shall prevail.
If there are tie bids, the Board of Bids and Contracts will recommend the successful bidder, and final determination will be made by the City Council. THE AWARD WILL BE BASED ON THE LOWEST AND BEST TOTAL NET BID FROM A
RESPONSIBLE AND RESPONSIVE VENDOR.
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
City of Wichita 13 RFB #260288
EXHIBIT A
CITY OF WICHITA MANDATORY CONTRACTUAL PROVISIONS ATTACHMENT
1. Terms Herein Controlling Provisions. The terms of this attachment shall prevail and control over the terms of any other conflicting provision in any other document relating to and a part of the Agreement.
2. Choice of Law. This Agreement shall be interpreted under and governed by the laws of the State of Kansas. Any dispute or cause of action that arises in connection with this Agreement will be brought before a court of competent jurisdiction in Sedgwick County, Kansas.
3. Termination Due to Lack of Funding Appropriation. If, in the judgment of the City’s Director of Finance, sufficient funds are not appropriated to continue the function performed in this Agreement and for the payment of the charges hereunder, City may terminate this Agreement at the end of its current fiscal year. City agrees to give written notice of termination to Contractor at least thirty (30) days prior to the end of its current fiscal year and shall give such notice for a greater period prior to the end of such fiscal year as may be provided for in the Agreement, except that such notice shall not be required prior to ninety (90) days before the end of such fiscal year. Contractor shall have the right, at the end of such fiscal year, to take possession of any equipment provided to City under the Agreement. City will pay to Contractor all regular contractual payments incurred through the end of such fiscal year, plus contractual charges incidental to the return of any related equipment. Upon the effective termination of the Agreement by City, title to any such equipment shall revert to Contractor. The termination of the Agreement pursuant to this paragraph shall not cause any penalty to be charged to the City or the Contractor.
4. Disclaimer of Liability. As a Kansas municipality, City shall not be obligated to protect, defend, hold harmless, or indemnify any Contractor beyond that liability incurred under the Kansas Tort Claims Act (K.S.A. 75-6101 et seq.). City specifically reserves and does not intend to waive any defenses, limitations of liability or damages, and/or immunities available to it under the Kansas Tort Claims Act or other state or federal law. It is understood that the duty to indemnify or hold harmless includes the duty to defend. This indemnification and hold harmless clause shall apply whether or not insurance policies shall have been determined to be applicable to any of such damages or claims for damages. In no event shall either party be obligated to indemnify the other on account of the negligence or willful misconduct of the party seeking indemnity or any agent or employee thereof.
5. Acceptance of Agreement. This Agreement shall not be considered accepted, approved or otherwise effective until the statutorily required approvals and certifications have been given.
6. Arbitration, Damages, Jury Trial and Warranties. The City does not ever accept binding arbitration or the payment of damages or penalties upon the occurrence of a contingency and expressly denies such acceptance for this Agreement. The City never consents to a jury trial to resolve any disputes that may arise hereunder and expressly denies such consent for this Agreement. Contractor waives its right to a jury trial to resolve any disputes that may arise hereunder. No provision of any document within the Agreement between the Parties will be given effect which attempts to exclude, modify, disclaim or otherwise attempt to limit implied warranties of merchantability and fitness for a particular purpose.
7. Representative's Authority to Contract. By signing this Agreement, the representative of the Contractor thereby represents that such person is duly authorized by the Contractor to execute this Agreement on behalf of the Contractor and that the Contractor agrees to be bound by the provisions thereof.
8. Federal, State and Local Taxes. Unless otherwise specified, the proposal price shall include all applicable federal, state, and local taxes. Contractor shall pay all taxes lawfully imposed on it with respect to any product or service delivered in accordance with this Agreement. City is exempt from state sales or use taxes and federal excise taxes for direct purchases. These taxes shall not be included in the Agreement. Upon request, City shall provide the Contractor a certificate of tax exemption. City makes no representation as to the exemption from liability of any tax imposed by any governmental entity on the Contractor.
9. Insurance. As a Kansas municipality, the City is self-insured for the purpose of general liability insurance. City shall not be required to purchase any insurance against any liability loss or damage to which this Agreement relates, nor shall this Agreement require the City to establish a "self-insurance" fund to protect against any such loss or damage. Subject to the provisions of the Kansas Tort Claims Act (K.S.A. 75-6101 et seq.), Contractor shall bear the risk of any loss or damage to any personal property to which Contractor holds title.
10. Conflict of Interest. Contractor shall not knowingly employ, during the period of this Agreement or any extensions to it, any professional personnel who are also in the employ of the City and providing services involving this Agreement or services similar in nature to the scope of this Agreement to the City. Furthermore, Contractor shall not knowingly employ, during the period of this Agreement or any extensions to it, any City employee who has participated in the making of this Agreement until at least two years after his/her termination of employment with the City.
11. Confidentiality. Contractor may have access to private or confidential data maintained by City to the extent necessary to carry out its responsibilities under this Agreement. Contractor must comply with all the requirements of the Kansas Open Records Act (K.S.A. 42-215 et seq.) in providing services and/or goods under this Agreement. Contractor shall accept full responsibility for providing adequate supervision and training to its agents and employees to ensure compliance with the Act. No private or confidential data collected, maintained or used in the course of performance of this Agreement shall be disseminated by either party except as authorized by statute, either during the period of the Agreement or thereafter. Contractor must agree to return any or all data furnished by the City promptly at the request of City in whatever form it is maintained by Contractor. Upon the termination or expiration of this Agreement, Contractor shall not use any of such data or any material derived from the data for any purpose and, where so instructed by City, shall destroy or render such data or material unreadable. The parties accept that City must comply with the Kansas Open Records Act and will produce upon written request all documents pertaining to this Agreement other than those covered by express exceptions to disclosure listed in the Act.
12. Cash Basis and Budget Laws. The right of the City to enter into this Agreement is subject to the provisions of the Cash Basis Law (K.S.A. 10-1112 and 10-
1113), the Budget Law (K.S.A. 79-2935), and all other laws of the State of Kansas. This Agreement shall be construed and interpreted to ensure that the City shall always stay in conformity with such laws, and as a condition of this Agreement the City reserves the right to unilaterally sever, modify, or terminate this Agreement at any time if, in the opinion of its legal counsel, the Agreement may be deemed to violate the terms of such laws.
Our Mission as an exceptionally well-run city, we will: Keep Wichita safe; Grow our economy; build dependable infrastructure;
City of Wichita 14 RFB #260288
13. Anti-Discrimination Clause. Contractor agrees: (a) to comply with the Kansas Act Against Discrimination (K.S.A. 44-1001 et seq.), the Kansas Age Discrimination in Employment Act (K.S.A. 44-1111 et seq.), the Discrimination Against Military Personnel Act, K.S.A. (44-1125, et seq.), and the applicable provisions of the Americans with Disabilities Act (ADA) (42 U.S.C. 12101 et seq.); (b) to not engage in illegal discrimination in employment against its contractors, subcontractors, or employees on the basis of their age, color, disability, familial status, genetic information, national origin or ancestry, race, religion, sex, veteran status or any other factor protected by law (“protected class”), subject to the qualifications found at 2.06.060 of the Municipal Code of the City of Wichita and to follow other applicable provisions of the City of Wichita Non-Discrimination Ordinance found at Chapter
2.06.010 et seq. of the Municipal Code of the City of Wichita; (c) to include in all solicitations or advertisements for employees the phrase “equal opportunity employer;” (d) to comply with the reporting requirements set out at K.S.A. 44-1031 and K.S.A.