This Soil Management Plan (SMP) is a technical document prepared by GSI Engineering, LLC for the City of Wichita, Kansas in coordination with the Kansas Department of Health and Environment (KDHE) under the Voluntary Cleanup and Property Redevelopment Program (VCPRP). The document establishes procedures for managing soil and ballast material disturbance during construction of the Redbud Multi-Use Path Phase 2, which extends approximately 2.6 miles from K-96 Highway to 159th Street East in east Wichita. The project involves construction of a nine to twelve-foot-wide, six-inch-thick concrete multi-use path with one to four-foot shoulders constructed of four-inch crushed limestone base. The plan addresses soil management activities necessary to construct the path while mitigating environmental concerns related to contamination from former railroad operations, including heavy metals, polycyclic aromatic hydrocarbons (PAH), and total petroleum hydrocarbons (TPH) detected in ballast material and soils at concentrations above KDHE Risk-Based Standards. Construction activities require excavation of contaminated ballast and soil materials to achieve proper subgrade elevations, with the concrete path functioning as a low-permeability cover system for remaining ballast.
The SMP establishes comprehensive procedures for pre-construction, construction, and post-construction activities, including utility clearance requirements, mandatory KDHE field notification a minimum of seven calendar days prior to soil disturbance, and submission of a Stormwater Construction Permit Notice of Intent. Soil characterization sampling protocols require a minimum of two soil samples per 100 linear feet of excavation for metals analysis (arsenic, cadmium, and lead) using X-ray Fluorescence (XRF) field screening per EPA Method 6200, with ten percent laboratory verification by KDHE-approved laboratories. One composite sample per 100 linear feet must be submitted for TPH-MRH and PAH analysis, with duplicate samples collected at a five percent ratio. Excavated soils are classified as clean fill material suitable for unrestricted reuse if contaminant concentrations meet Residential Scenario Soil Pathway and Soil to Groundwater Pathway Risk-Based Standards levels, or as contaminated media requiring special handling and onsite consolidation or off-site disposal if concentrations exceed cleanup goals. Any actions disturbing soil or ballast material require prior approval from both the City and KDHE.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
888.767.8854 www.gsinetwork.com
Geotechnical Engineering . Environmental Consulting . Materials Testing . Drilling . EHS Site Solutions
Engineering
Soil Management Plan
Redbud Bike Path K-96 to 159th St. East Wichita, Kansas
GSI Project No. 1774018 KDHE Voluntary Agreement 10VCP0031 September 4, 2019
Prepared by:
GSI Engineering, LLC 4503 E. 47th St. South Wichita, Kansas 67210
Prepared for:
City of Wichita 455 N. Main Wichita, Kansas 67203
Gregg Armstrong Senior Scientist
Rick L. Bean, P.G.
Principal Geologist taylor.stout Final taylor.stout Received taylor.stout Typewritten Text C2-087-72479 8.1 taylor.stout Typewritten Text
SEP 04 2019
Redbud Bike Path, Wichita, KS
10VCP0031
September 4, 2019
Page | i
GSI
TABLE OF CONTENTS
1.0 INTRODUCTION
2.0 PURPOSE AND OBJECTIVES
3.0 SITE DESCRIPTION AND BACKGROUND
3.1 Previous Investigations
4.0 RELEVANCE
5.0 SOIL MANAGEMENT PROCEDURES
5.1 Pre-Construction Activities
5.2 Construction Activities
5.3 Post-Construction Activities
6.0 HEALTH AND SAFETY
APPENDICES
Appendix A – Figures
Figure 1 – Site Location Map Figure 2 – Site Base Map Figure 3 – Site Base Map – Consolidation Cell and Access Poe and Associates Plan and Profile
Appendix B – KDHE Field Notification Form
10VCP0031
September 4, 2019
Page | ii
GSI
COMMONLY USED ACRONYMS AND ABBREVIATIONS
AS – air sparge
ASTM – American Society for Testing and Materials
BER – Bureau of Environmental Remediation bgs – below ground surface
COC – Contaminants of Concern
EPA – United States Environmental Protection Agency
GC – Gas Chromatograph
HSA – hollow stem auger
I.D. – inside diameter
IDW – Investigative Derived Waste
KDHE – Kansas Department of Health and Environment
MCL – Federal Maximum Contaminant Level mg/kg – milligrams per kilogram (this is a common soil analytical unit) mg/L - milligrams per Liter (this is a common water analytical unit) msl – mean seal level
MW – monitoring well
O.D. – outside diameter
OMM – Operations, Maintenance and Monitoring
P.E. – Professional Engineer
P.G. – Professional Geologist
PID – photoionization detector
POTW – publicly owned treatment works
QA – quality assurance
QC – quality control ppb – parts per billion ppm – parts per million
PVC – polyvinyl chloride (common well casing material)
RPD – relative percent difference
10VCP0031
September 4, 2019
Page | iii
GSI
RSK – Risk-Based Standards for Kansas
SOP – Standard Operating Procedures
SVE – soil vapor extraction
SWL – static water level µg/kg – micrograms per kilogram (this is a common soil analytical unit) µg/L – micrograms per liter (this is a common water analytical unit) µg/m3 – micrograms per meter cubed (this is a common air analytical unit)
VOCs – Volatile Organic Compounds
WWTP – wastewater treatment plant
XRF – x-ray fluorescence detector
CONTAMINANT SPECIFIC ACRONYMS AND ABBREVIATIONS
BTEX – Benzene, Toluene, Ethylbenzene and Xylenes
Cis 1,2 DCE – cis-1,2 dichloroethylene
CT or CCL4 – Carbon Tetrachloride
DCA - Dichloroethane
HRH – High-Range Hydrocarbons
LRH – Low-Range Hydrocarbons
MRH – Mid-Range Hydrocarbons
MTBE – Methyl tert-butyl ether
PAH – Polynuclear Aromatic Hydrocarbons
PCE – Tetrachloroethylene also known as Perchloroethylene
TCE – Trichloroethylene
TPH – Total Petroleum Hydrocarbons
Trans 1,2 DCE – trans-1,2 dichloroethylene
VC – Vinyl Chloride
10VCP0031
September 4, 2019
© 2019 GSI Engineering, LLC Page | 1
GSI
1.0 INTRODUCTION
This Soil Management Plan (SMP) has been prepared by GSI Engineering LLC (GSI) on behalf of Poe and Associates and the City of Wichita (the City), Kansas to describe soil management activities for the Redbud Path Project (Project). The Project entails the construction of approximately two and six tenths (2.6) miles of concrete multi-use path, corresponding shoulders and paved parking and access road along the former BNSF railroad right-of-way (ROW).
Environmental investigations have determined that ballast material (rock, soil, and fill) used during the construction and maintenance of the former railway may contain heavy metals, polycyclic aromatic hydrocarbons (PAH) and total petroleum hydrocarbons (TPH) at concentrations above
Risk-based Standards for Kansas (RSK) established by the Kansas Department of Health and
Environment (KDHE). Planned construction activities will disturb ballast material creating the potential for environmental concern.
To address this concern the City entered the Site into the KDHE’s Voluntary Cleanup and Property
Redevelopment Program (VCPRP). Construction activities associated with the Path will require excavation of ballast material and soils to achieve the proper subgrade elevations for the concrete path and corresponding path shoulders. The concrete path and shoulders will function as a low-permeability cover system for ballast left in place along the Path corridor.
The trail will be constructed as a nine to twelve feet wide, six-inch thick concrete slab on grade reinforced with wire fabric. The shoulders of the trail will extend one to four feet beyond pavement, depending upon trail segment location, to each side of the path. The shoulders will be constructed of a four-inch base of crushed limestone to be applied in accordance with the Plan Specifications.
This construction will result in a fourteen to sixteen-foot path engineered to mitigate residual metals and TPH-MRH impacts over the length of the project.
While the entire corridor segment will be capped with the concrete bike path, some areas will be excavated to correct grade/slope. Soil characterization analysis will be completed prior to construction for any path segment requiring excavation (cut) potentially impacting contaminated media.
2.0 PURPOSE AND OBJECTIVES
This document presents the procedures for management, handling and onsite placement of disturbed ballast material during, and after construction of the Path. Disturbance of ballast and bwaller Highlight This document presents the procedures for management, handling and onsite placement of disturbed ballast material during, and after construction of the Path.
bwaller Highlight Disturbance of ballast and
10VCP0031
September 4, 2019
© 2019 GSI Engineering, LLC Page | 2
GSI
soil will include grading, excavation, trenching, construction, utility, and all other excavation activities. The primary objective of this SMP is to protect human health and the environment by minimizing exposure and preventing fugitive transport of impacted material through the air, groundwater, and surface water systems.
This SMP is integral to, and a component of, remedial, stormwater, construction, and EUC plans and documents for the site. Changes to this SMP must be approved by the appropriate KDHE stakeholders prior to implementation of any changes. Similarly, KDHE must be notified and grant prior approval of any deviations to this SMP that may occur.
3.0 SITE DESCRIPTION AND BACKGROUND
The Site includes specific segments of the proposed Redbud Path extending approximately 2.6 miles east from K-96 Highway to 159th Street East. This area is within the south half of Sections
10, 11 and 12, Township 27 South, Range 02 East in Sedgwick County, Kansas. The proposed trail extends through various residential and commercial developments in east Wichita north of the 13th Street corridor. Appendix A provides topographic and aerial diagrams illustrating the area.
The construction site tract is within the rail banked right-of-way and includes approximately 0.5 acres on adjacent City owned property southeast of Founders Circle at the location of a sanitary sewer lift station. Ballast rock cover remains at the surface within most areas of the former rail bed. Areas north and south of the bed are sloped with brush, trees, and drainage ways farther from the centerline. Several bridges and roadway crossings intersect the tract, most notably intersections with N. 127th St. East, N. 143rd St. East and N. 159th St. East. Non-roadway improvements are limited to bridges at stream crossings along the former railroad bed.
3.1 Previous Investigations
Two previous investigations were completed under the KDHE Brownfields Program between June
2017 and September 2017. Significant findings are summarized below.
Phase I Environmental Site Assessment (ESA)
GSI completed a Phase I BTA of the site in June 2017. The Phase I Report indicates on-site railroad operations for more than a century as a recognized environmental condition (RECs). GSI recommended a Phase II Limited Site Investigation in response to these findings.
Phase II Brownfields Targeted Assessment (BTA) bwaller Highlight soil will include grading, excavation, trenching, construction, utility, and all other excavation activities.
10VCP0031
September 4, 2019
© 2019 GSI Engineering, LLC Page | 3
GSI
GSI completed a Phase II BTA in September 2017 in response to the REC characterized above.
The Phase II Assessment included 8 soil sampling points along the length of the Trail corridor (6 linear miles total). Three of the eight sampling points, identified as SB-6, SB-7 and SB-8, are located within the 2.6 linear mile section of the railroad corridor addressed in this Voluntary
Cleanup.
Phase II results indicated medium range hydrocarbons (TPH-MRH), cadmium and lead in soil and fill materials encountered from 0 to 2 feet below ground surface (bgs) and arsenic in fill materials encountered from 2-4 feet bgs at sample point SB-7, located between 127th St. East and 143rd St. East. Reported concentrations of the specified metals exceeded their respective soil pathway KDHE Tier 2 Risk-Based Standards (i.e. default cleanup standards) for residential land use. TPH-MRH concentration exceeded the KDHE Tier 2 Risk-Based Standards for soil to groundwater pathway for residential and non-residential land use but was well below the KDHE
Tier 2 Risk-Based Standards for the soil pathway residential and non-residential land use.
4.0 RELEVANCE
The SMP is relevant to path and ancillary parking and access road construction, maintenance of the path and existing utilities, and future construction activities that may include, but are not limited to street crossings or installation of new utilities that result in soil disturbances to the Path or consolidation cell. Construction activities between survey station 143+80 and survey station
168+20, and any other contaminated segments will include excavation of ballast material and soils to achieve the proper subgrade elevation for the concrete path and corresponding path shoulders. Construction activities at the consolidation cell will include excavation of the consolidation cell and placement and compaction of excavated ballast material and soil from contaminated segments into the consolidation cell, and construction of the low-permeability subgrade and asphalt pavement system over the consolidation cell.
Any action which may disturb soil and/or ballast material remaining in place on the Path or placed in the consolidation cell must have prior approval from the City and KDHE. The City and KDHE may approve soil disturbance in these areas provided adequate measures are taken to mitigate impacts to the integrity of the cover systems. This document is further relevant to activities associated with the VCPRP and Environmental Use Controls.
bwaller Highlight Any action which may disturb soil and/or ballast material remaining in place on the Path or placed in the consolidation cell must have prior approval from the City and KDHE.
bwaller Highlight he City and KDHE may approve soil disturbance in these areas provided adequate measures are taken to mitigate impacts to the integrity of the cover systems.
10VCP0031
September 4, 2019
© 2019 GSI Engineering, LLC Page | 4
GSI
5.0 SOIL MANAGEMENT PROCEDURES
Soil Management procedures include the steps necessary to conduct soil disturbances at the
Site. Necessary pre-construction, during construction, and post-construction procedures are described below.
5.1 Pre-Construction Activities
Pre-Construction activities include utility clearance, KDHE field notification, and submission of a
Notice of Intent (NOI) for Authorization to Discharge Stormwater Runoff from Construction activities. Adequate planning prior to soil disturbance activities must be conducted to allow for ample time to complete the pre-construction activities.
Utility Clearance
All excavators must request utility clearance at least two days prior to initiating soil disturbance activity. Utility Locate requests are made through Kansas One-Call by dialing 811 or 1-(800)-344-
7233. There is no fee for submitting at utility locate request.
KDHE Field Notification
KDHE shall be notified of field activities a minimum of 7 calendar days prior to initiation of soil disturbance activities at the Site. KDHE prefers being notified online via the KDHE Field Activities
Notification Form at http://www.kdheks.gov/remedial/fieldactivities_notification.html. A copy of this form is provided in Appendix B. Questions or problems using the form can be addressed by calling KDHE at (785) 296-1673. There is no fee for submitting a KDHE Field Notification.
Stormwater Construction Permit
Based on information provided by the City, a NOI for Authorization to Discharge Stormwater
Runoff from Construction Activities has been prepared and submitted to KDHE.
Excavation Permit
Prior to performance of any excavation, an Excavation Permit issued by the City coupled with formal notification to the KDHE may be required. When applying for an Excavation Permit from the City, drawings depicting the planned excavation area should be included. KDHE shall also be notified of field activities a minimum of 7 calendar days prior to initiation of soil disturbance activities.
Soil Characterization bwaller Highlight submission of a Notice of Intent (NOI) for Authorization to Discharge Stormwater Runoff from Construction activities.
bwaller Highlight KDHE shall be notified of field activities a minimum of 7 calendar days prior to initiation of soil disturbance activities at the Site.
bwaller Highlight KDHE prefers being notified online via the KDHE Field Activities Notification Form at http://www.kdheks.gov/remedial/fieldactivities_notification.html. A copy of this form is provided in Appendix B. Questions or problems using the form can be addressed by bwaller Highlight Prior to performance of any excavation, an Excavation Permit issued by the City coupled with formal notification to the KDHE may be required.
10VCP0031
September 4, 2019
© 2019 GSI Engineering, LLC Page | 5
GSI
Based on the results of previous investigations, representative samples of excavated ballast material shall be collected for laboratory chemical analyses of by a KDHE approved analytical laboratory.
The following soil characterization sampling and analysis protocol will apply:
Metals Analysis
Two soil samples per 100 linear feet of excavation will be collected and field screened for arsenic, cadmium and lead using an X-ray Fluorescence (XRF) analyzer. Field XRF procedures will be consistent with U.S. Environmental Protection Agency (USEPA) Method 6200. Samples will be homogenized prior to analysis to provide data representative of the entire sample interval. Rocks, gravel, and other heterogeneous materials will be removed from the samples prior to analysis to limit matrix interference. XRF sample collection and handling procedures are outlined in the following paragraph and summarized in Table 1 and Table 2. Appendix C, Quality Assurance
Project Plan (QAPP) discusses XRF quality control parameters.
XRF samples will be collected from depth intervals representative of the excavation as indicated by site plans. For example, if a 100 feet segment requires removal of an average 2 feet of existing material, the soil sample will be collected from the 0-2 feet depth interval. Sampling points will be randomly selected within each 100 feet segment and located to represent central and side grade soil conditions. Table 1 summarizes the proposed sampling strategy.
TPH-MRH and Polycyclic Aromatic Hydrocarbon (PAH) Analysis
One composite sample will be collected per 100 linear feet of cut and submitted to a fixed base laboratory for TPH-MRH and PAH analysis. Sample aliquots comprising the composite sample will be obtained at the same location as those collected for field metals analysis. The depth of the soil aliquot samples will be determined based on the planned depth of excavation and will provide a representative sample for that depth interval.
Duplicate soil samples will be collected at the ratio of 1:20 (5 %) for submittal to a fixed base laboratory for analysis of arsenic, cadmium, lead, and TPH-MRH. Duplicate sample results will be compared with the original sample analysis results using calculated relative percent difference
(rpd) to evaluate analytical accuracy.
10VCP0031
September 4, 2019
© 2019 GSI Engineering, LLC Page | 6
GSI
Table 1: Proposed Sampling Frequency
Sample Description XRF Sampling Frequency Laboratory Submission
Frequency Laboratory Analyses
Cleanup Verification and Soil Segregation Samples
Minimum of one soil sample per 100 linear feet.
Minimum of ten percent of the total number of samples collected for XRF analysis
Total Arsenic, Cadmium and Lead by Method 6010
Duplicate Soil Samples
Duplicate XRF analysis at a frequency of five percent of the total number of samples collected, or one duplicate per day’s use, whichever results in the greater number.
Field duplicate samples will be collected at a frequency of five percent of the total number of samples submitted for laboratory analysis
Total Arsenic, Cadmium and Lead by Method 6010 and TPH-MRH by Method 8015M
Equipment Blank (rinsate) samples Not Applicable
Minimum of frequency of one equipment blank sample per sampling day.
Total Arsenic, Cadmium and Lead by Method 6010, TPH- MRH Modified 8015.
Laboratory verification analysis will occur at a minimum frequency of 10 percent of the total number of XRF samples collected. The samples selected for laboratory verification will include the full range of XRF samples. Laboratory samples will be analyzed for arsenic, cadmium and lead per USEPA Method 6010. Pace Analytical Services (Pace), Lenexa, KS or another KDHE-approved laboratory will perform all laboratory procedures. Table 2 summarizes the field and laboratory sample analytical methods, sample containers, preservatives and holding times.
Table 2: Analytical Methods and Sample Storage Sample Media Analysis Analytical
Method Container/Storage Preservative Holding Time
Soil
XRF Lead (field) 6200
1 x 1.0-liter plastic Zip- Lock® (or equivalent) bag
NA NA
Total Arsenic, Cadmium and Lead (laboratory)
6010 1 x 4 oz. glass; cool to 4 degrees C None 6 months
TPH-MRH Modified method 8015
1 x 4 oz. amber glass, cool to 4 degrees C
None 14 days
PAH Method
8270SIM
1 x 4 oz. amber glass, cool to 4 degrees C None 14 days
At areas that will be excavated, surplus soils will be segregated according to predetermined soil characteristics for unrestricted use, restricted use fill material at path segments requiring fill to meet subgrade elevations or consolidated onsite within a dedicated consolidation cell.
bwaller Highlight At areas that will be excavated, surplus soils will be segregated according to predetermined soil characteristics for unrestricted use, restricted use fill material at path segments requiring fill to meet subgrade elevations or consolidated onsite within a dedicated consolidation cell.
10VCP0031
September 4, 2019
© 2019 GSI Engineering, LLC Page | 7
GSI
Based on soil characterization analysis completed prior to excavation, soil exhibiting contaminant concentrations equal to or less than Residential Scenario Soil Pathway and Soil to Groundwater
Pathway RSK levels are considered clean fill material and are suitable for reuse with no restrictions. Soil exhibiting contaminant levels greater than Residential Scenario Soil Pathway and Soil to Groundwater Pathway RSK levels are considered contaminated media and will be subject to special handling and use restrictions.
RCRA regulations for characterization of hazardous waste will apply to any media removed from the site. Contaminated media exhibiting analytical detections exceeding 20 times the Toxicity
Characteristic Leaching Procedure (TCLP) limits listed in Table 1 will be further analyzed using
TCLP methods for waste characterization prior to determine disposal options. Contaminated media exhibiting hazardous waste characteristics will be contained and transported for disposal at an approved hazardous waste disposal facility in accordance with applicable local, State and
Federal regulations.
Table 3 provides the cleanup goals as established in the Risk-based Standards for Kansas, RSK
Manual – 5th Version, October 2010, Revised September 2015 and RCRA hazardous waste characteristic TCLP limits for contaminants of concern. KDHE Tier 2 RSK residential soil concentrations are considered site cleanup goals.
Table 3: Cleanup Goals and Criteria for Classification of Contaminated Media
Contaminant
Clean Fill Special Handling and Placement Required Hazardous Waste
Residential Soil Pathway
RSK
Residential Soil to Groundwater
RSK
Non- Residential Soil RSK
Non-Residential Soil to Groundwater RSK
TCLP Limit (Haz Waste Characteristic)
Arsenic <18.9 mg/kg Not established ≥18.9 mg/kg Not established ≥5.0 mg/l TCLP
Cadmium <39 mg/kg Not established ≥39 mg/kg Not established ≥1.0 mg/l TCLP
Lead <400 mg/kg Not established ≥400 mg/kg Not established ≥5.0 mg/l TCL_
TPH-MRH ≤250 mg/kg ≤50 mg/kg ≥250 mg/kg ≥50 mg/kg NA
Benzo(a)pyrene ≤1.09 mg/kg ≤23.5 mg/kg ≥1.09 mg/kg ≥23.5 mg/kg NA
Use Restrictions
No Restrictions on use or placement
Transport to on site consolidation cell or subgrade preparation for impermeable cap materials
Subject to RCRA Haz Waste Handling and Disposal Criteria.
Based on Phase II Brownfields Targeted Assessment (BTA) conclusions, contaminants of concern exceeding applicable KDHE Tier 2 Risk-based Standards for Kansas (RSK) goals are bwaller Highlight Based on soil characterization analysis completed prior to excavation, soil exhibiting contaminant concentrations equal to or less than Residential Scenario Soil Pathway and Soil to Groundwater Pathway RSK levels are considered clean fill material and are suitable for reuse with no restrictions. Soil exhibiting contaminant levels greater than Residential Scenario Soil Pathway and Soil to Groundwater Pathway RSK levels are considered contaminated media and will be subject to special handling and use restrictions.
bwaller Highlight RCRA regulations for characterization of hazardous waste will apply to any media removed from the site.
10VCP0031
September 4, 2019
© 2019 GSI Engineering, LLC Page | 8
GSI
limited to the trail segment extending west to east from 127th St. East to 143rd St. East. Surplus soil resulting from excavation between the following plan survey stations will be subject to soil characterization and management as specified in this plan as an added precaution. Segments listed below are shown on Figure 2 Appendix A.
• 100+80 to 105+80 (500 linear feet)
• 112+60 to 118+00 (460 linear feet)
• 120+80 to 125+60 (700 linear feet)
• 143+80 to 168+20 (2,200 linear feet)
• 201+00 to 203+20 (200 linear feet)
Red Bud Path plans specify construction of parking facilities and path access located at the southern end of Founders Circle. This component of the Path is located southeast of N. Founders
Circle, between Station 109+00 and 110+00 as indicated on Figure 3 Appendix A. Plan details for an access road, consolidation pit, and paved parking lot are included as sheets 29-30 of the construction plans. The location is owned by the City of Wichita and currently occupied by a City of Wichita sanitary sewer lift station that will be removed as an integral part of Red Bud Path construction.
Clean fill material for use on path segments requiring fill will be obtained from a borrow area at the same location. The borrow area will form a consolidation cell to receive excavated soil exhibiting contaminant levels exceeding Residential Scenario Soil Pathway and Soil to
Groundwater Pathway RSK levels. The consolidation cell will subsequently be capped with six
(6) inches of crushed rock subbase plus 6 inches of asphalt paving to complete the parking lot, effectively forming a low-permeability cap for the consolidation cell and isolating contaminated media preventing human exposure and minimizing contaminant migration potential.
Upon completion of all segments the Red Bud Path project, the consolidation cell will be enrolled in the KDHE Environmental Use Control (EUC) program. The EUC program will likely require annual inspection and reporting to KDHE documenting conditions of the site, and will prohibit future excavations within the site without appropriate notification and implementation of soil management plans.
bwaller Highlight Clean fill material for use on path segments requiring fill will be obtained from a borrow area at the same location. The borrow area will form a consolidation cell to receive excavated soil exhibiting contaminant levels exceeding Residential Scenario Soil Pathway and Soil to Groundwater Pathway RSK levels.
bwaller Highlight he consolidation cell will subsequently be capped with six
(6) inches of crushed rock subbase plus 6 inches of asphalt paving to complete the parking lot, effectively forming a low-permeability cap for the consolidation cell and isolating contaminated media preventing human exposure and minimizing contaminant migration potential.
bwaller Highlight Upon completion of all segments the Red Bud Path project, the consolidation cell will be enrolled in the KDHE Environmental Use Control (EUC) program.
bwaller Highlight The EUC program will likely require annual inspection and reporting to KDHE documenting conditions of the site, and will prohibit future excavations within the site without appropriate notification and implementation of soil management plans.
10VCP0031
September 4, 2019
© 2019 GSI Engineering, LLC Page | 9
GSI
5.2 Construction Activities
This section presents a general description of soil handling and management processes during the construction phase of the Project. Removal and consolidation of the top portions of the ballast material and soil will require appropriate care to avoid unintended offsite transport and/or creation of an additional exposure pathway. A description of the individual construction tasks and their soil handling processes follow.
Preparation of the Soil Consolidation Area
The initial construction activities will include preparation of the consolidation cell as shown on
Figure 3, Appendix A. Based on previous investigations conducted by others, native soil in the consolidation area is not impacted and special soil handling procedures are not required. Surplus impacted ballast and soil meeting restricted use criteria will be placed in the consolidation cell and compacted prior to placement of a low permeability asphalt paved cap which will provide parking and access the this segment of the Path.
Clean soil excavated from the consolidation cell will be stockpiled for use as fill material as necessary. Standard stormwater best management practices (BMPs) such as straw bales or silt fencing will be required to eliminate offsite transport of soils that may impact waters of the State.
Refer to Appendix C Storm Water Pollution Prevention Plan for BMP specifications for stockpiled soil.
Preparation of the Contaminated Material Staging Area (if needed)
If construction workflow requires temporary stockpiling of contaminated media, a contaminated soil staging area will be required. This will only be required if direct placement of contaminated media the consolidation cell or at low areas along the Path is not possible. Impacted soil stockpiled temporarily must be placed on polyethylene sheeting to avoid direct contact with the ground. If the impacted soil is left overnight it shall be covered with plastic sheeting and then weighted to minimize water infiltration and wind transport. Refer to Appendix C Storm Water
Pollution Prevention Plan for BMP specifications.
Preparation of Select Soil Staging Area
Construction workflow may require stockpiling of clean soil as needed for construction of the Path.
Special soil handling procedures are not required for clean soil staging. Standard stormwater
BMPs such as constructing berms, silt fencing, or straw bales shall be employed to minimize the bwaller Highlight The initial construction activities will include preparation of the consolidation cell bwaller Highlight Surplus impacted ballast and soil meeting restricted use criteria will be placed in the consolidation cell and compacted prior to placement of a low permeability asphalt paved cap which will provide parking and access the this segment of the Path.
bwaller Highlight Clean soil excavated from the consolidation cell will be stockpiled for use as fill material as necessary. Standard stormwater best management practices (BMPs) such as straw bales or silt fencing will be required to eliminate offsite transport of soils that may impact waters of the State.
10VCP0031
September 4, 2019
© 2019 GSI Engineering, LLC Page | 10
GSI
potential for offsite transport of select soil. Refer to Appendix C Storm Water Pollution Prevention
Plan for BMP specifications.
Removal and Consolidation of Impacted Material
Characterization of media to be excavated must be completed prior to excavation to establish appropriate soil management protocol in accordance with previously stated classifications.
Restricted use ballast materials and soils removed from the railroad bed may be used as subgrade fill for paved areas of the Path or placed in the consolidation cell. Special soil handling procedures must be employed during excavation, transport, placement, and compaction activities. In lieu of providing a vehicle wash facility for trucks transporting impacted media, all trucks used to transport media to offsite locations will travel on clean gravel paths and be loaded on clean gravel.
Visual inspection of these vehicles will be performed prior to leaving the site to ensure no contaminated soils are inadvertently transported off-site on truck bodies or wheels. Trucks transporting contaminated media on public roadways will be covered with tarps to prevent fugitive emissions
As the ballast materials and soils are excavated by grading and placed in a dump truck, walled trailer or other suitable methods for transport, care should be taken to minimize dust and airborne transport during excavation and transport by moistening with a sprayer as needed. Extra vigilance is required to prevent fugitive emissions when excavating during windy days. Impacted material placed in the consolidation cell may require temporary cover with plastic sheeting to minimize the potential for airborne transport or direct contact by workers or the public until the pavement system is completed.
Construction of Low-Permeability Soil Cover (Consolidation Cell)
The low-permeability soil cover system will consist of 6 inches of crushed rock base overlain by
6 inches of asphalt paving. The low-permeability paving will encapsulate the contaminated media, isolating it from direct contact, groundwater and surface water systems.
Compaction and Construction Concrete Pavement Cover
The Path will consist of a concrete pavement cover and compacted soil shoulders constructed over the impacted material left in place. Impacted material left in place will be compacted and then engineered subgrade base and concrete pavement cover will be constructed. Care should be taken to minimize dust and airborne transport during compaction and controlling airborne bwaller Highlight Restricted use ballast materials and soils removed from the railroad bed may be used as subgrade fill for paved areas of the Path or placed in the consolidation cell.
bwaller Highlight pecial soil handling procedures must be employed during excavation, transport, placement, and compaction activities.
bwaller Highlight In lieu of providing a vehicle wash facility for trucks transporting impacted media, all trucks used to transport media to offsite locations will travel on clean gravel paths and be loaded on clean gravel bwaller Highlight Visual inspection of these vehicles will be performed prior to leaving the site to ensure no contaminated soils are inadvertently transported off-site on truck bodies or wheels. Trucks transporting contaminated media on public roadways will be covered with tarps to prevent fugitive emissions bwaller Highlight The low-permeability soil cover system will consist of 6 inches of crushed rock base overlain by 6 inches of asphalt paving.
10VCP0031
September 4, 2019
© 2019 GSI Engineering, LLC Page | 11
GSI
emissions by moistening with a sprayer is required. Extra vigilance is required to prevent fugitive emissions when excavating during windy days. Refer to Appendix C Storm Water Pollution
Prevention Plan for BMP specifications.
5.3 Post-Construction Activities
Post-construction activities include actions taken as required by the EUCs as well as operation and maintenance of the path. Post construction activities may also include, but are not limited to, excavation associated with maintenance of existing utilities, future street crossings and/or installation of new utilities.
If chemical analyses indicate that reported concentrations of contaminants in ballast material exceed residential RSKs, a waste determination will be required in order to determine appropriate disposal. Assuming that the excavated ballast material is not a characteristic hazardous waste, a waste disposal authorization from the KDHE’s Bureau of Waste Management (BWM) and a
KDHE permitted Municipal Solid Waste Landfill (MSWLF) will be required. Upon receipt of waste disposal authorization from BWM, excavated material may be transported to the approved
MSWLF for disposal and the excavation backfilled with clean soil.
In the event that chemical analyses indicate that excavated ballast material is a characteristic hazardous waste, excavated material must be managed in accordance with the applicable provisions of the Kansas Statutes Annotated (KSA) Chapter 65-Public Health, Article 34-
Hazardous Waste and Kansas Administrative Regulations (KAR) 28-31-1 through 28-31-279a.
Environmental Use Controls
Since this project results in on-site encapsulation of contaminated media, EUC specifying appropriate limitations of property use and development is required. An O&M Plan will be prepared which describes routine inspection and maintenance activities required to maintain the integrity and longevity of the encapsulation systems.
6.0 HEALTH AND SAFETY
All soil disturbance activities shall be conducted in accordance with 29 CFR 1910.120 and all other applicable federal, state, and local regulations. Although previous investigations have adequately characterized known environmental concerns, if additional contamination is unexpectedly encountered during construction activities, work will be stopped and KDHE will be notified to determine the appropriate course of action.
© 2019 GSI Engineering, LLC
APPENDIX A
Figure 1 – Site Location Map
Figure 2 – Site Map
Figure 3 – Site Base Map – Consolidation Cell and Access
Poe and Associates Plan and Profile
Redbud Path K-96 to 159th St. East
Untitled Path
8 RE£T D
ALL LOC AT IONS AND BOUNDARIES ARE APPROXIMATE
FIGURE
SIT
E
BA
SE
M
AP
RE
D
BU
D
TR
AI
L K-
TO
9th
S t.
AN
DO
VE
R, K
AN
SA
S
G.
AR
MS
TR
ON
G
-0 7-1
C.
D
RE
YE
R
I
DR
AW
N
BY
DW
G#
DA
TE
PR
OJ
.M
AN
GR
1 inch = 1,000 feet
0 1,500750 Feet
= Rails to Trails Corridor
LEGEND
0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000 11,000 12,000 13,000 14,000500 Feet garmstrong Rectangle garmstrong Line garmstrong Text Box Cut 1 100+80-105+80, 500' garmstrong Rectangle garmstrong Text Box Cut 2 112+60 - 118+00 460' garmstrong Line garmstrong Rectangle garmstrong Text Box Cut 3 120+80 - 125+60 700 ' garmstrong Line garmstrong Rectangle garmstrong Text Box Cut 4 Sheet 143+80 - 168+20 2,200' garmstrong Line garmstrong Rectangle garmstrong Text Box Cut 5 201+00 - 203+20 200' garmstrong Line
ALL LOCATIONS AND BOUNDARIES ARE APPROXIMATE
3.0
FIGURE
SIT
E B
AS
E M
AP
RE
D
BU
D
TR
AI
L
K-
TO
9th St
AN
DO
VE
R, KA
NS
AS
G.
AR
MS
TR
ON
G
-08 -29
CN
I
DR
AW
N
BY
DW
G#
DA
TE
PR
OJ
.M
AN
GR
1 inch = 1,000 feet
0 1,500750 Feet
= Parking Lot to Red Bud Trail
LEGEND
0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000 11,000 12,000 13,000 14,000500 Feet
© 2019 GSI Engineering, LLC
APPENDIX B
KDHE Field Notification Form