About this file
This document is an attachment containing required photos for a procurement solicitation issued by the Utah Communications Authority (UCA) for the Parker Mountain Radio Tower and Shelter Installation project located in Piute County, Utah. The solicitation requires bidders to submit photographs documenting specific aspects of the proposed installation work. Questions regarding the solicitation must be submitted by May 29, 2026, no later than 10:00 AM Mountain Time through the U3P portal, with proposals due by June 4, 2026, no later than Noon Mountain Time, also via U3P. The project site is located at Parker Range on State Trust Lands at coordinates 38.324602, -111.892773. The document serves as a specifications attachment outlining the photographic documentation requirements that bidders must include with their proposals to demonstrate compliance with project specifications and installation standards.
The required photographs function as a critical component of the bid submission process, enabling the UCA to verify that bidders understand the scope of work and can document compliance with technical and quality standards. This attachment does not address pricing terms, set-asides, or funding sources, as it focuses exclusively on the documentation and photographic evidence requirements. Bidders should note the 1GB file upload limitation for individual submissions and ensure all required photographs are included within their complete proposal package submitted through the designated U3P system.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment L — Required Closeout Photographs Parker Mountain Communications Tower Site All photographs listed below are part of the project closeout package. The project cannot be signed off and completed without delivery of every required photograph identified in this attachment. Photographs are grouped by system for ease of organization and review. The checklist table at the end of this document may be used to track completion.
Important: Photographs that show items prior to backfill, prior to concrete, or prior to sealing must be taken before the covering work proceeds. Photographs taken after covering will not satisfy the closeout requirement.
Tower Foundation Photographs
1. Tower foundation excavation with rebar in place prior to concrete pour.
1. Tower foundation concrete pour prior to backfill.
1. Tower lightning rod and extension installation.
Shelter Foundation Photographs
1. Shelter foundation with rebar in place prior to concrete pour.
1. Shelter foundation concrete pour prior to backfill.
Propane Line and Sensor Photographs
1. Propane fuel line at 18-inch depth prior to backfill.
1. Propane line bedded with sand prior to backfill.
1. Propane sensor conduit at 18-inch depth prior to backfill.
1. Propane sensor line bedded with sand prior to backfill.
Ice Bridge Photographs
1. Ice bridge vertical support to shelter foundation prior to backfill.
1. Ice bridge vertical support to tower foundation prior to backfill.
Solar Conduit Photographs
1. All solar conductor conduits at 18-inch depth prior to backfill, showing sand bedding.
Microwave Antenna Photographs
1. Tape-drop photograph of microwave antenna centerline.
1. Microwave antenna installation.
1. Microwave ice shield installation.
1. Ground kits installed on microwave LMR-400 cable at the dish.
Radio Frequency (RF) System Photographs
1. Ground kits on seven-eighths inch (7/8 inch) cable and on both one-half inch (1/2 inch) RF lines.
1. RF antenna mounts, both transmit (TX) and receive (RX).
1. All RF antenna connections, both prior to sealing and after sealing with PVC and butyl tape.
Grounding System Photographs
1. All grounding copper lines and ground rods, showing cadwelds.
Closeout Photograph Tracking Checklist The following table may be used by the contractor and the UCA project manager to track photograph submission status. Mark each row as complete when the corresponding photograph has been delivered.
| Number |
| Required Photograph |
| Status |
| 1 |
| Tower foundation excavation with rebar in place prior to concrete pour. |
| 2 |
| Tower foundation concrete pour prior to backfill. |
| 3 |
| Tower lightning rod and extension installation. |
| 4 |
| Shelter foundation with rebar in place prior to concrete pour. |
| 5 |
| Shelter foundation concrete pour prior to backfill. |
| 6 |
| Propane fuel line at 18-inch depth prior to backfill. |
| 7 |
| Propane line bedded with sand prior to backfill. |
| 8 |
| Propane sensor conduit at 18-inch depth prior to backfill. |
| 9 |
| Propane sensor line bedded with sand prior to backfill. |
| 10 |
| Ice bridge vertical support to shelter foundation prior to backfill. |
| 11 |
| Ice bridge vertical support to tower foundation prior to backfill. |
| 12 |
| All solar conductor conduits at 18-inch depth prior to backfill, showing sand bedding. |
| 13 |
| Tape-drop photograph of microwave antenna centerline. |
| 14 |
| Microwave antenna installation. |
| 15 |
| Microwave ice shield installation. |
| 16 |
| Ground kits installed on microwave LMR-400 cable at the dish. |
| 17 |
| Ground kits on seven-eighths inch (7/8 inch) cable and on both one-half inch (1/2 inch) RF lines. |
| 18 |
| RF antenna mounts, both transmit (TX) and receive (RX). |
| 19 |
| All RF antenna connections, both prior to sealing and after sealing with PVC and butyl tape. |
| 20 |
| All grounding copper lines and ground rods, showing cadwelds. |
Accessibility Statement This document has been formatted for compatibility with screen readers and other assistive technologies. The structure follows Web Content Accessibility Guidelines (WCAG) 2.1 Level AA. Headings use proper outline levels, lists use semantic list formatting, the tracking table includes a designated header row, and all measurements and abbreviations are expressed in plain language to support assistive-technology pronunciation.
Attachment L — Parker Mountain Required Closeout Photographs — Page of
File details come from the government source that posted it. Updated .