8-Attachment B Technical Special Specifications Inspection and Repair of Alley Sewers.pdf

PDF 4 MB Posted

Attached to
CDBG-DR Alley Sewer Repair Project: INSPECTION, REHABILITATION, AND REPLACEMENT OF ALLEY SEWERS IN DETROIT (AS-NEEDED)
Solicitation number
542974
Issued by
Wayne County, Detroit City, Michigan

About this file

This document comprises technical specifications for the City of Detroit Water and Sewerage Department (DWSD) for inspection, rehabilitation, and replacement of alley sewers on an as-needed basis under CDBG-DR funding. The project encompasses complex underground pipe, sewer, and catch basin work, with services including sewer video inspection, spot repairs, manhole rehabilitation, lateral replacement, and associated site restoration. The specification incorporates DWSD Standard Specifications (dated May 2023) and details requirements across 31 specification sections covering site clearing, excavation support systems, concrete work, asphalt and concrete paving, fence installation, seeding, and landscaping. Key administrative requirements include pre-construction meetings, e-Builder project management software for all documentation and communication, construction progress schedules in Primavera P6 format, GPS structure documentation, submittal procedures, safety programs with confined space entry protocols, quality control with independent testing, and electronic project record documentation. The contractor must obtain MISS DIG utility locates, maintain dewatering systems, implement erosion control measures, and comply with OSHA excavation standards and Michigan regulations.

Payment operates on a unit price basis with estimated quantities providing contract value calculations; actual payment depends on measured quantities accepted by the engineer. All costs for insurance, bonds, field office operations, traffic control, security clearances, and communications are included in unit prices and not paid separately. The contract requires mobilization and demobilization costs combined as single line items with no separate payment for sewer inspection, cleaning, lining, or trenchless repairs; additional repairs within one mile of issued work locations discovered during mobilization receive no additional mobilization payment. Material testing, quality assurance inspections, compaction verification, and field density testing are contractor-funded costs included in unit prices. The contractor must maintain a qualified workforce including a Construction Quality Manager, Safety Manager with minimum five years' experience, and supervisory personnel; employ independent testing laboratories certified by appropriate state departments; and provide all equipment, temporary facilities, and specialized tools at no additional cost. The work must comply with City of Detroit, MDOT, AASHTO, ASTM, ACI, OSHA, and Michigan Department of Labor standards, with particular emphasis on worker safety in confined spaces, proper material handling and compaction, and environmental protection through erosion control and contaminated material management procedures.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

December 2025

CITY OF DETROIT

Mike Duggan, Mayor

REQUEST FOR BIDS NO. XXXXXX

PROJECT NO. DWS-973

TECHNICAL SPECIFICATIONS

FOR

INSPECTION AND REPAIR OF ALLEY SEWERS IN THE CITY OF DETROIT

AS NEEDED

Book 2 of 2

BOARD OF WATER COMMISSIONERS

Michael Einheuser, Chairperson Mary E. Blackmon, Vice Chairperson

Lane Coleman John Henry Davis

Linda D. Forte Jane C. Garcia

Jonathan C. Kinloch

Gary Brown Director

Mohamad Farhat, P.E.

Chief Engineer

Samuel Smalley, P.E.

Deputy Director

Istakur Rahman Chief Financial Officer

December 2025

CITY OF DETROIT

Mike Duggan, Mayor

SPECIAL

SPECIFICATIONS

For DWS-973

BOARD OF WATER COMMISSIONERS

Michael Einheuser, Chairperson Mary E. Blackmon, Vice Chairperson

Lane Coleman John Henry Davis

Linda D. Forte Jane C. Garcia

Jonathan C. Kinloch

Gary Brown Director

Mohamad Farhat, P.E.

Chief Engineer

Samuel Smalley, P.E.

Deputy Director Istakur Rahman Chief Financial Officer

City of Detroit Water and Sewerage Department - Engineering Division

Special Specifications

The following Special Specification Sections shall replace the associated Standard Specifications Sections. The DWSD Standard Specifications (dated May 2023) are incorporated by reference. The Standard Specifications can be found on DWSD’s website.

01 11 00

01 14 00

01 20 00

01 30 00

01 31 27

01 32 16

01 32 25

01 33 00

01 35 29

01 40 00

01 52 00

01 55 26

01 57 13

01 57 15

01 57 33

01 70 00

01 78 39

02 01 20

02 22 30

02 61 13 03 10 00 03 20 00

03 25 00

03 30 00

03 31 00 03 39 00

31 10 00

31 23 16.26

31 23 19

31 23 23.33

31 23 33

31 50 00

Summary of Work

Work Restrictions

Price and Payment Procedures

Administrative Requirements

Project Management Communications

Construction Progress Schedule

GPS Structure Documentation

Submittal Procedures

Safety Program

Quality Requirements

Temporary Facilities

Traffic Control

Erosion Control Sedimentation and Containment of Construction Materials

Temporary Sewer Bypass Pumping

Temporary Security Measures

Execution and Closeout Requirements

Electronic Project Record Documentation

Protecting Existing Underground Utilities

Pre-Construction Video and Photographic Record

Excavation and Handling off Contaminated Materials

Concrete Forming

Concrete Reinforcing

Concrete Accessories

Cast-in-Place Concrete

Construction and Expansion Joints

Concrete Curing

Site Clearing

Rock Removal

Dewatering

Flowable Fill

Trenching and Backfill

Excavation Support Systems

City of Detroit Water and Sewerage Department- Engineering Division

Special Specifications

32 11 23 Aggregate Base Courses 32 12 16 Asphalt Paving 32 13 13 Concrete Paving 32 13 14 Permeable Concrete Chain Link Fences and Gates Wood Fences and Gates Seeding Plants

Security Clearances and Communications 33 01 30.30 Sewer Pipeline Inspection for Condition Assessment 33 01 30.60 Spot Repair of Existing Sewers 33 01 30.31 Manhole Inspection for Condition Assessment 33 01 30.32 Sewer Cleaning for Condition Assessment 33 01 30.81 Manhole Rehabilitation 33 31 11 Public Sanitary Sewerage Gravity Piping

01 11 00 - 1

SUMMARY OF WORK

DWSD Special Specification March 2025

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Contract description.

2. Contractor's use of Site.

3. Work sequence.

4. Permits.

5. Specification conventions.

1.2 CONTRACT DESCRIPTION

A. Perform Work of Contract under unit price Contract with Owner according to Conditions of Contract.

B. Description of Work included in the Project will be as presented in the Advertisement, Bid Schedule, and/or Drawings.

1.3 CONTRACTOR'S USE OF SITE

A. Limit use of Site to allow:

1. Owner occupancy.

2. Work by Others, if any, as listed in the Contract Documents.

3. Use of Site by the public right-of-way.

B. Construction Operations: Limited to areas indicated in the Contract Documents.

C. Time Restrictions for Performing Work: Comply with Section 01 14 00 – Work Restrictions.

D. Sound Level Restrictions: Sound pressure level measured at boundary of Site shall not exceed 90 dBA.

1.4 CLEANING OF SITE

A. On a daily basis, following completion of the Work (pipe installation, concreting and asphalting, spreading topsoil, or sodding and seeding) and prior to leaving the Site, the Contractor shall thoroughly clean the roadway and remove the excess material from the roadway so that it is not deposited in the roadway drainage system.

01 11 00 - 2

B. When directed by the Engineer, but not less than weekly, the Contractor shall sweep the streets with a street sweeper. The sweeper shall have a main broom, conveyor, sprinkler system, and a storage hopper. This requirement shall apply to any streets or roads in the vicinity of the Work that are affected by the Contractor's construction or hauling operations, and as well as to streets or roads in which the Work is located. Should the Contractor neglect his duties in maintaining the proper street or road cleanliness, the Owner has the authority to take necessary steps to perform such cleaning and will charge the Contractor for those costs.

C. The Contractor shall at all times keep the street pavement and right-of-way and any public or private premises temporarily occupied for purposes of Work under this Contract free from accumulations of waste material or rubbish caused by the Contractors employees or the Work.

This requirement should apply to any streets in vicinity of the Work which are affected by the Contractor's construction or hauling operations, as well as to streets in which the Work is located.

If the Contractor shall fail to keep any street cleaned of debris resulting from their operations, and therefore create a public nuisance, they shall be notified in writing by the Engineer to clean the street and remove the nuisance immediately. If, within 24 hours after the receipt of such notice, the Contractor shall have failed to clean such street satisfactorily, the Engineer shall order the street cleaned by the Department of Public Works or such other agency and all costs of such cleaning shall be paid by the Contractor.

D. Dirt, mud, construction materials or other debris deposited on public sidewalks or streets as the result of spilling, tracking by the wheels of trucks or construction equipment or by other actions of the Contractor, his employees or subcontractors shall be immediately removed by the Contractor.

1.5 MATERIAL STORAGE

A. Comply with Section 01 52 00 Temporary Facilities for all temporary staging area requirements for material, equipment, and supplies.

B. Materials delivered on the street shall be neatly and compactly stored in such a manner as to cause the least inconvenience to adjacent property owners and the general public.

C. Working and storage areas shall be promptly restored to their original conditions as soon as the required construction work has been completed at the particular location and shall not be used as a storage area for unneeded material or construction equipment.

D. All materials delivered and stored in close proximity to the working area shall be properly barricaded and protected, maintaining a safe Site for workers and the general public.

E. Only materials and construction equipment currently being used may be stored at the construction site and within the jurisdictional right-of-way.

01 11 00 - 3

1.6 WORK SEQUENCE

A. Construct Work in phases during construction period. Coordinate construction schedule and operations with the Engineer.

1.7 PERMITS

A. Acquire necessary permits for construction of Work as listed in the Contract Documents.

1.8 SPECIFICATION CONVENTIONS

A. These Specifications are written in imperative mood and streamlined form. This imperative language is directed to Contractor unless specifically noted otherwise. The words "shall be" are included by inference where a colon (:) is used within sentences or phrases.

1.9 STANDARD SPECIFICATIONS AND DETAILS

A. These Specifications include Sections that may or may not be directly relevant to the Work of this Contract as described in the Contract Documents. Some Specifications are included for reference and will only be relevant if the Specification topic is encountered or required over the course of the Work as a result of the Contractor’s performance and Site conditions.

B. DWSD Standard Specifications (dated May 2023) as listed on the DWSD website shall be referenced and used as relevant to the performance of the Contract Work.

C. DWSD Standard Details may be included for reference in the Drawings or Contract Documents.

All DWSD Standard Details as listed on the DWSD website shall be used and referenced as relevant to the performance of the Contract Work.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION - Not Used

END OF SECTION 01 11 00

01 14 00 - 1

WORK RESTRICTIONS

SECTION 01 14 00 - WORK RESTRICTIONS

1.1 SUMMARY

A. Section Includes:

1. Requirements.

2. Private Land.

3. Planned Construction Locations.

4. Open Excavations.

5. Test Pits.

6. Cooperation within this Contract.

7. Protection of Construction and Equipment.

8. Precautions during Adverse Weather.

9. Confined Space Entry.

1.2 REQUIREMENTS

A. Coordination:

1. Furnish personnel, equipment, and construction aids that will be efficient, appropriate, and sufficient to secure a satisfactory quality of work as defined by the Specification and a rate of progress that will ensure the completion of the Work within the time stipulated in the Contract Documents.

2. Coordinate with MISS DIG (811) and other Agencies having jurisdiction over property or structures in and around the construction area and locate all utilities potentially affected by the Work.

3. If at any time, Contractor’s resources appear to the Engineer to be inefficient, inappropriate, or insufficient to achieve the required quality or rate of progress of the Work, the Engineer may ask the Contractor to increase efficiency, change the character, or increase the number of personnel and equipment to meet the schedule of the Contract. Failure of the Engineer to give such direction shall in no way relieve the Contractor of its obligations to secure the required quality or rate of progress of Work.

B. Hours of Work:

1. Contractor may normally prosecute the Work during the daylight hours of any weekday excluding holidays, providing that the operations are conducted as to not create a public nuisance or disturb the peace. The Contractor may only perform the Work during the daylight hours and no earlier than 7 AM or later than 7 PM. However, should the Contractor be stopped, by order of a public authority, from working at times that are contrary to or in

01 14 00 - 2 violation of any law, ordinance, permit, or license, the Contractor shall not be entitled to an extension of time due to such stoppages.

2. At the beginning of Work, Contractor shall notify the Engineer in writing, of the days and hours that will constitute a normal work week. Whenever the Contractor intends to depart from the specified work week, the Contractor must request approval in writing so that the Engineer may review the request for approval and make the necessary arrangements to have required inspectors assigned to the Work. The request shall be made at least two (2) calendar days prior to the requested deviation from the specified work week. If an emergency arises that requires work to be performed outside of the normal working hours of the specified work week to save or protect life or property, the requirements of the request for approval would be waived. Notify the Engineer as soon as the Contractor determines that an emergency exists that necessitates a change in or extension of the normal hours of work. However, the Contractor’s determination of the existence of an emergency is subject to review and revision by the Engineer.

C. Shutdowns:

1. A Shutdown shall be defined as a portion of the normal operation of a unit or conduit that has to be suspended or taken out of service in order to perform the specified Work. For each shutdown, compile an inventory of labor and materials required to perform tasks, an estimate of the time required, including time for the Owner to take down and start up the unit or conduit, and a written description of steps required to complete all tasks. The inventory, the estimate, and written procedures shall be submitted to the Engineer for review 30 calendar days prior to the proposed start date of the shutdown. Request, in writing from the Engineer, approval for each shutdown a minimum of 14 calendar days prior to the proposed shutdown date. No shutdown shall be initiated until the inventory of materials and labor is verified by the Engineer on site prior to the proposed start date.

2. The Work required herein and any other Work required by the Engineer that may interrupt the normal operations shall be accomplished at such times that will be convenient to the Owner whether during the nighttime hours or during weekend hours. The Contractor shall include in its bid price all overtime and premium time required for performing any work associated with these shutdowns.

3. Have on hand and located in close proximity to the Work area, all temporary and permanent tools, equipment, spare parts, and materials necessary to complete each Work category without interruptions. Adequate numbers of personnel shall be scheduled for each shutdown, so that the Work shall be accomplished within the specified time frame. The Engineer shall be satisfied that Contractor has complied with these requirements, to the fullest extent possible, before shutdowns will be authorized.

4. If Contractor’s procedures cause an unscheduled shutdown of the facilities, perform all Work necessary to immediately re-establish satisfactory operation. Notify the Engineer, in writing, immediately of any unscheduled shutdown. Permit Owner’s personnel to work with Contractor’s personnel, as deemed necessary by the Owner, to maintain the facilities in continuous satisfactory operation. Fines levied by regulatory agencies resulting from unscheduled shutdowns or interruptions of continued safe and satisfactory operation of the facilities shall be the Contractor's responsibility, if it is demonstrated that Contractor was negligent in the Work or did not exercise proper precautions in conducting the Work.

01 14 00 - 3

5. Shutdowns of Electrical and Control Systems: Contractor and the Owner shall each lock out and tag circuit breakers and switches operated by the Owner and shall check cables and wires to be sure that they are de-energized to ground potential before Work begins. Upon completion of the Work, remove the locks and tags and notify the Engineer that the facilities are available for use. The Owner will then remove its locks and place facilities back into use. The Contractor shall supply own locks. Locks shall be checked at the beginning of each shift. Contractor shall comply with the Owner’s Lockout/Tagout procedure. Shutdowns for any electrical wiring or I&C cables shall be coordinated with the Owner.

D. General Requirements:

1. Develop a program in cooperation with the Engineer to provide for the construction and putting into service the new work in the most orderly manner possible and in coordination with continued operations of the facilities and all ongoing construction projects at the time of construction of this Project.

2. Adhere to such program except as deviations therefrom are expressly permitted in writing by the Engineer.

3. Plan all work of connecting with, cutting into, and reconstructing existing pipes or structures so as not to interfere with the operation and maintenance of the existing facilities.

Schedule work that will affect operation of existing facilities for the shortest possible time and when the demands on the facilities best permit such interference, even though it may be necessary to work outside of normal working hours to meet these requirements.

4. For water-main work, dewater process and utility pipelines back to the nearest closed valve at the beginning of each piping shutdown.

5. Provide all appropriate means and methods to ensure that water services in the areas and facilities associated with this Project are maintained uninterrupted during construction.

6. Make minor modifications in such work relating to existing structures as may be necessary, without additional compensation.

7. Before starting any work that may interfere with the operation of the existing facilities, do all possible preparatory work and see that all tools, materials, and equipment to be installed are made ready and at hand.

8. Conduct construction operations in the most orderly manners such that these operations:

a. Interfere as little as possible with the operations of the existing facilities and other ongoing Construction Contracts.

b. Does not damage existing equipment, structures, etc., or cause disruption to the operations of the existing facilities.

9. Make no claim for additional compensation because of delay or inconvenience in adapting construction operations to the need for continuous operations of the existing facilities.

10. Not begin any portion of Work that will interfere with continued operations of the facilities until such schedule is accepted and approved in writing by the Engineer.

11. Contact the Systems Control Center fourteen (14) days prior to any required ‘Sewer Shutdown’ or ‘Manned Entry’ required within the sewer. Complete an Equipment Shutdown Request form and call 313-267-6000 to inform Systems Control of the planned

01 14 00 - 4 shutdown and entry. Equipment Shutdown Request form is found attached to this Specification.

1.3 PRIVATE LAND

A. Do not enter or occupy private land outside of the designated construction area or property limits, except as specified in the Contract Documents.

B. Provide the Engineer with copies of any agreements made by the Contractor with private landowners or other government agencies (i.e., Detroit Land Bank) to occupy or use their property.

C. Take photographs and/or video to document existing private land conditions and post construction conditions. The photographic documentation shall comply with Section 02 22 30 Pre-Construction Video and Photographic Record.

1.4 PLANNED CONSTRUCTION LOCATIONS

A. The Work shall be installed substantially as indicated on the Drawings and in the Contract Documents.

B. Where pipe fittings or other items are noted on the Drawings, such notation is for the Contractor's convenience and does not relieve the Contractor from installing different or additional items where required to complete the Work.

1.5 OPEN EXCAVATIONS

A. Comply with all requirements of MISS DIG Public Act 174 including contacting MISS DIG, hand excavation near utilities, and contacting 911 in case of emergency.

B. Contractor shall schedule in advance with the Engineer all open excavations and coordinate in such a way to minimize disruption and provide full restoration as soon as possible.

C. Excavations shall have sloping, sheeting, shoring, and bracing conforming with 29CFR1926 Subpart P-Excavations, and OSHA requirements. Contractors shall safeguard all open excavations by providing barricades, caution signs, lights, and other means to prevent accidents to persons or damage to property. Contractor shall provide suitable and safe bridges and other crossings for accommodating travel by pedestrians and workmen. Contractor shall remove bridges provided for access during construction when no longer required. The length of an open trench shall always be confined to the limits prescribed by the Engineer. If the excavation becomes a hazard, or if it excessively restricts traffic at any point, the Engineer may require special construction procedures such as limiting the length of the open trench, prohibiting stacking excavated material in the street, and requiring that the trench not remain open overnight.

01 14 00 - 5

D. Take precautions to prevent injury to personnel due to open trenches. All trenches, excavated materials, equipment, or other obstacles that could be dangerous to the public, shall be well lit at night.

1.6 TEST PITS

A. Excavate and Backfill test pits for the purpose of locating underground pipelines or structures in advance of the construction in accordance with Project Specifications and Drawings.

B. Immediately backfill test pits after their purpose has been satisfied and restore and maintain the surface in accordance with Project Specifications and Drawings.

1.7 COOPERATION WITHIN THIS CONTRACT

A. Contractor and its subcontractors shall assist in incorporating the work of other trades where necessary or required.

B. Cutting, patching, drilling, and fitting shall be carried out by the trade or subcontractors having jurisdiction, unless otherwise indicated herein or directed by the Engineer.

C. Phase the Work so that all chases or openings for the installation of its own or any other contractor's or subcontractor’s work are available to prevent delays. Contractor or its subcontractor shall properly set all sleeves or forms delivered to the work area in ample time to prevent delays. Contractor or its subcontractors shall accurately locate all chases, openings, and sleeves and shall be the proper size and shape. Contractor should consult with the Engineer and any other contractors and subcontractors related to this Work.

D. In case of failure to leave or cut all such openings or have all such sleeves provided and set in the proper time, cut them or set them afterwards at no additional expense to the Owner. In so doing, confine the cutting to the smallest extent possible consistent with the Work to be done. In no case shall piers or structural members be cut without the written consent of the Engineer.

E. Carefully fit around, close up, repair, patch, and point around the Work specified herein to the satisfaction of the Engineer.

F. Contractor shall carefully perform all of the Work using workers competent to do such work and with the proper tools. Power tools shall not be used except where the type of tool proposed can be used without damage to any Work or structures and without inconvenience or interference to the operation of any facilities. The Contractor is entirely responsible for such damage, inconvenience, or interference resulting from the use of such tools.

G. Do not alter or permit any worker or subcontractor to alter the Work of any other contractor or subcontractors working on said job, except with written consent of the other contractor or subcontractors whose Work is to be altered or with the written consent of the Engineer. All cutting, patching, or repairing made necessary by negligence, carelessness, or incompetence

01 14 00 - 6 of the Contractor or any of its subcontractors, shall be the responsibility of the Contractor and shall be done by or at the expense of the Contractor.

1.8 PROTECTION OF CONSTRUCTION AND EQUIPMENT

A. In accordance with the Contract Documents, carefully protect all newly constructed Work.

Contractor shall also minimize wheeling, walking, or placing heavy loads on the Site, and reconstruct, at its own expense, any portions of the Site that are damaged.

B. Protect all structures in a manner approved by the Engineer. If, in the final inspection of the Work, any defects, faults, or omissions are found, Contractor shall repair or remove and replace the defects, faults, or omissions, utilizing specified materials and workmanship, without extra compensation for the materials and labor required. Maintain and repair the construction and other Work undertaken herein for the warranty period described in the Contract Document or until the end of the maintenance period, whichever is longer.

C. Take all necessary precautions to prevent damage to any part of the Work due to water pressure during and after construction until such Work is accepted by the Engineer.

1.9 WINTER SHUTDOWN PROVISIONS

A. The winter shutdown requirements as listed below will pertain to water main and sewer Capital Improvement Plan (CIP) Contracts. All other Contracts shall be excluded from winter shutdown provisions, unless otherwise notified by the Engineer.

B. Due to the extreme inconvenience to Detroit Water and Sewerage customers and the public in general, and also due to the impossibility of performing prompt, permanent restoration during the winter season, work on water main and sewer CIP Contracts shall be temporarily halted after the second week of November or as authorized by the Engineer. The Contract work shall promptly resume during the third week of April of the following year or as authorized by the Engineer.

C. All requests to continue Work during the winter season shall be submitted via request for information (RFI) for approval from the Engineer at least thirty (30) days prior to winter shutdown. The RFI shall include as a minimum:

1. Anticipated winter work schedule.

2. Scope of work.

3. Number of crews.

D. The following items shall be completed by the Contractor prior to winter shutdown:

1. All Contractor’s equipment shall be removed from the Site.

2. All pipe and materials not incorporated in the Work shall be removed from the Site.

01 14 00 - 7

3. Hard surfaces, where permanent restoration has not been made, shall have stone and cold patch installed subject to approval by the Engineer.

a. All hard surfaces must be restored within 30 days per the Contract unless otherwise stated in the Contract Documents.

4. All berm areas where mulched seeding has not been placed shall be rough graded and left free of depressions and piles of soil.

5. Repair of all known water main leaks.

6. Pumping out of all hydrants that were used.

7. Cleaning out of catch basins where required.

E. The above list is not inclusive. The Site(s) shall be made safe to the general public and abandoned in a manner to protect the Work. All winter shutdown provisions shall be performed to the satisfaction of the Engineer. All winter shutdown provisions are incidental to the cost of the Contract and no additional payment shall be allowed.

1.10 PRECAUTIONS DURING ADVERSE WEATHER

A. Take all necessary precautions in reasonable anticipation of and during adverse weather so that the Work may be done properly and satisfactory in all respects. Protection shall be provided by use of tarpaulins, wood and building-paper shelters, or other suitable means. All protection during adverse weather must be securely fastened.

B. During cold weather, materials shall be preheated, if required, and the materials and adjacent structure into which they are to be incorporated shall be made and kept sufficiently warm so that a proper bond will occur, and proper curing, aging, or drying will result. Protected spaces shall be artificially heated by suitable means resulting in a moist or a dry atmosphere according to the particular requirements of the Work being protected. Ingredients for concrete and mortar shall be sufficiently heated so that the mixture will be warm throughout when used. Provide suitable means of protection to prevent freezing below slabs and any other Concrete Work to frost heave.

This shall include all existing and new facilities. If the Contractor decides to continue working in cold weather, the Contractor shall be responsible for following all cold-weather provisions as specified in the Contract Documents.

1.11 CONFINED SPACE ENTRY

A. Follow applicable confined-space entry procedures.

B. At the preconstruction meeting, submit to the Engineer a copy of the Contractor’s Safety Plan for confined-space entry in accordance with current OSHA and MIOSHA requirements. Prior to entry into any confined space, submit to the Engineer a copy of the daily entry permit in accordance with current OSHA and MIOSHA requirements.

C. Perform all Work in accordance with the latest edition of Construction Safety Standards as adopted by the Michigan Department of Labor Construction Safety Standards for Occupational Health.

01 14 00 - 8

D. Perform all Work in accordance with the latest edition of Michigan Department of Environment, Great Lakes, and Energy Occupational Health Standard for Construction.

E. Comply with the latest edition of the requirements, specifications, and standards as provided for under the Michigan Occupational Safety and Health Act., as amended and in force at the date thereof, and all other applicable Owner requirements and Federal, State and Local requirements, ordinances, statutes, and laws.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Provide materials for construction aids.

B. Utilize new or used materials for construction aids only if they are suitable for the intended purpose and do not violate requirements of applicable laws, ordinances, codes, and standards.

C. Maintain facilities and equipment in first-class condition.

2.2 CONSTRUCTION AIDS

A. Provide construction aids and equipment necessary to facilitate the execution of the Work, such as scaffolds, staging, ladders, stairs, ramps, runways, platforms, railings, hoists, cranes, chutes, and other such facilities and equipment. Refer to respective sections for particular requirements for each trade.

B. When permanent stair framing is in place, provide temporary treads, platforms, and railings for use by construction personnel.

PART 3 - EXECUTION

3.1 PREPARATION

A. Consult with the Engineer, review site conditions and factors that will affect construction procedures and identify necessary construction aids.

B. Determine if adjacent properties and public facilities will be affected by execution of the Work and develop strategies to address impacts.

3.2 INSTALLATION

A. Installation: According to OSHA/MIOSHA standards and manufacturer's instructions.

01 14 00 - 9

3.3 REMOVAL

A. Completely remove temporary materials, equipment, and services when construction needs can be met by use of permanent construction and at the completion of the Work. Remove foundations and underground construction aids. Grade areas of the site affected by temporary installations to required elevations and slopes and clear fire area.

B. Clean and repair any damage caused by installation or use of temporary facilities. Restore permanent facilities used for temporary purposes to original condition unless otherwise specified.

END OF SECTION 01 14 00

01 20 00 - 1

PRICE AND PAYMENT PROCEDURES

SECTION 01 20 00 - PRICE AND PAYMENT PROCEDURES

1.1 SUMMARY

A. Section Includes

1. Permit allowances

2. Provisional allowances

3. Contaminated Material allowances

4. Schedule of Values

5. Application for Payment

6. Change procedures

7. Defect assessment

8. Unit prices

9. Measurement and Payment General Notes

10. Unit Price Schedule

1.2 PERMIT ALLOWANCES

A. If required, the Contract will include a stipulated sum/price for reimbursement of acquired permits as a permit allowance.

B. Cost of permit acquired by Contractor and applicable taxes are included in permit allowances.

Any cost the Contractor deems necessary for overhead, profit, and other expenses on account of a permit allowance must be included elsewhere as part of the bid in the total Contract price.

C. Contractor Responsibilities:

1. Arrange for and acquire all necessary permits as stated in the Contract documents.

2. Upon delivery, promptly inspect products for completeness, damage, and defects.

D. Payment under permit allowance will be on an actual-cost basis. The receipts for permits that have been secured by the Contractor shall be presented to the Owner for reimbursement.

E. At closeout of Contract, funds remaining in the permit allowance will be credited to Owner by Change Order.

1.3 PROVISIONAL ALLOWANCES

A. If required, the Contract will include a stipulated sum/price for use upon Owner's instruction as a provisional allowance.

01 20 00 - 2

B. Contractor's costs for products, delivery, installation, labor, payroll, taxes, equipment rental, overhead, and profit will be included in Construction Change Authorizations authorizing expenditure of funds from this provisional allowance. Insurance and Bond premiums shall be included elsewhere in the bid and are not redeemable in the provisional allowance.

C. Funds will be drawn from provisional allowance only by a Construction Change Authorization.

D. At closeout of Contract, funds remaining in the provisional allowance will be credited to Owner by Change Order.

1.4 CONTAMINATED-MATERIAL ALLOWANCES

A. If required, included in the Contract will be a stipulated sum/price for reimbursement of payment associated with the removal of contaminated material via a contaminated material allowance.

B. Requirements for the handling, hauling, disposal, and all associated costs and fees of hazardous waste materials, non-hazardous waste materials, and petroleum contaminated soils will be included in the reimbursement cost of the contaminated-material allowance. If chemicals of concern found in groundwater are of a nature or concentration that necessitates handling the groundwater as hazardous material, reimbursement of costs will be provided under the contaminated material allowance.

C. All costs for products, delivery, installation, labor, payroll, taxes, equipment, equipment rental, overhead, profit, field monitoring, on-site testing and laboratory testing for contaminated materials will be included elsewhere in the bid in the total Contract price and will not be included in the reimbursement via contaminated material allowance.

D. Payment under contaminated material allowances will be on an actual cost basis. The receipts for all reimbursement costs for the handling, hauling, disposal, and all associated costs and fees that have been incurred by the Contractor shall be presented to the Owner for reimbursement.

E. At closeout of Contract, funds remaining in contaminated material allowance will be credited to Owner by Change Order.

1.5 SCHEDULE OF VALUES

A. Within the deadline established in the Contract Documents, the Contractor shall submit a Schedule of Values for review and acceptance.

B. Use Unit Price Schedule of this specification. Identify each line item with number and title of major bid item followed by a schedule of values for payment including division of all Lump Sum items into a schedule of values for payment.

C. Revise Unit Price Schedule to list approved Change Orders and Construction Change Authorizations with each Application for Payment.

01 20 00 - 3

1.6 APPLICATION FOR PAYMENT

A. Content and Format: Transmit application for payment as specified in the Agreement. Use Schedule of Values for listing items in Application for Payment.

B. Payment Period: In accordance with the agreement between Owner and Contractor.

C. Substantiating Data: When Engineer requires substantiating information, submit data justifying dollar amounts in question.

D. Include the following as mandatory with each Application for Payment:

1. Partial release of liens from all Subcontractors and vendors.

2. An affidavit of Contractor stating that all previous progress payments received by

Contractor have been applied to discharge Contractor’s legitimate obligations associated with prior Applications for Payment.

3. Construction Progress Schedule revised and current as specified in Section 01 32 16 – Construction Progress Schedule.

4. Monthly Safety Reports as specified in Section 01 35 29 – Safety Program.

5. Updated Schedule of Submittals as specified in Section 01 33 00 – Submittal Procedures.

Include the following with each Application for Payment if requested by the Engineer:

1. Current construction photographs specified in Section 01 33 00 - Submittal Procedures.

2. Record Documents as specified in 01 70 00 – Execution and Closeout Requirements, for review by Owner, which will be returned to Contractor.

3. Affidavits attesting to off-Site stored products.

4. Test reports and documentation.

5. Updated Schedule of Submittals.

6. Application for Payment Bid Items supporting documentation, submittals, acceptance of work documents, etc.

1.7 CHANGE PROCEDURES

A. Submittals: Submit the name of an individual who is authorized to receive change documents and is responsible for informing others in Contractor's employ or Subcontractors of changes to the Work.

B. Carefully study and compare Contract Documents before proceeding with fabrication and installation of Work. Promptly advise Engineer of any error, inconsistency, omission, or apparent discrepancy.

C. Allot time in construction scheduling for liaison with Engineer and establish procedures for handling Requests for Interpretations (RFIs) and clarifications.

1. Use e-Builder for requesting interpretations.

2. Engineer will respond with a direct answer on e-Builder or via a Field Order.

01 20 00 - 4

D. Engineer will advise of minor changes in the Work not involving adjustment to Contract Sum/Price or Contract Time by issuing supplemental instructions on a Field Order form.

E. Contractor shall submit a Change Proposal to propose changes on the Work. The Contractor shall submit the request for change to the Engineer, describing the proposed change and its full effect on the Work. Contractor shall include a statement describing reason for the change and the effect on Contract Sum/Price and Contract Time with full documentation and a statement describing effect on the Work by separate or other Contractors.

F. Work Change Directive: Engineer may issue Work Change Directives, signed by Owner, instructing Contractor to proceed with change in the Work, for subsequent inclusion in a Change Order. The directive will describe changes in the Work and designate method of determining any change in Contract Sum/Price or Contract Time.

G. Stipulated Sum/Price Change Order: Based on Work Change Directive and Contractor's price quotation or Contractor's request for Change Order as approved by Engineer.

H. Unit Price Change Order: For Contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of that which are not predetermined, the Contractor shall execute Work under Work Change Directive. Changes in Contract Sum/Price or Contract Time will be computed as specified for Time and Material Change Order.

I. Time and Material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in Conditions of the Contract. Engineer will determine change allowable in Contract Sum/Price and Contract Time as provided in Contract Documents.

J. Contractor shall maintain detailed records of Work done on time and material basis and provide full information required for evaluation of proposed changes and to substantiate costs for changes in the Work.

K. Document each quotation for change in Project Cost or Time with sufficient data to allow evaluation of quotation.

L. Engineer will issue Change Orders for signatures of parties as provided in Conditions of the Contract.

M. Correlation of Contractor Submittals:

1. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as separate line item and adjust Contract Sum/Price.

2. Promptly revise Progress Schedules to reflect change in Contract Time, revise sub-schedules to adjust times for other items of Work affected by the change and resubmit.

3. Promptly enter changes in Record Documents.

01 20 00 - 5

1.8 DEFECT ASSESSMENT

A. Replace the Work, or portions of the Work, not conforming to specified requirements.

B. If, in the opinion of the Engineer, it is not practical to remove and replace the Work, the Engineer will direct appropriate remedy or adjust payment.

C. Individual Specification Sections may modify these options or may identify specific formula or percentage sum/price reduction.

D. The Engineer's authority to assess defects and identify payment adjustments is final.

E. Payment will not be made for unacceptable products for any of the following reasons:

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products not completely unloaded from transporting vehicle.

4. Products placed beyond lines and levels of the required Work.

5. Products remaining on hand after completion of the Work.

6. Loading, hauling, and disposing of rejected products.

1.9 UNIT PRICES

A. Authority: Measurement methods are delineated as indicated below in the unit price schedule.

B. Take measurements and compute quantities. Engineer may verify measurements and quantities.

C. Unit Quantities: Quantities and measurements indicated on Bid Schedule are for Contract purposes only. Actual quantities provided shall determine payment.

1. When actual Work requires more or fewer quantities than those quantities indicated, provide required quantities at contracted unit sum/prices.

2. When the extended price of a particular item of Unit Price Work amounts to 5 percent or more of the Contract Price (based on estimated quantities and Unit Prices in the Bid Schedule) and the variation in the quantity of that particular item of Unit Price Work actually furnished or performed by Contractor differs by more than 25 percent from the estimated quantity of such item indicated in the Bid Schedule, Owner or Contractor may claim a Contract Price adjustment.

D. Payment includes full compensation for (1) required labor, products, tools, equipment, plant and facilitates, transportation, services, and incidentals; (2) erection, application, or installation of item of the Work; and (3) overhead and profit.

E. Final payment for Work governed by unit prices will be made on basis of actual measurements and quantities accepted by Engineer multiplied by unit sum/price for Work incorporated in or made necessary by the Work.

01 20 00 - 6

F. Measurement of Quantities:

1. Weigh Scales: Inspected, tested, and certified by applicable State weights and measures department within past year.

2. Platform Scales: Of sufficient size and capacity to accommodate conveying vehicle.

3. Metering Devices: Inspected, tested, and certified by applicable State department within past year.

4. Measurement by Weight: Concrete reinforcing steel, rolled or formed steel, or other metal shapes will be measured by handbook weights. Welded assemblies will be measured by handbook or scale weight.

5. Measurement by Volume: Measured by cubic dimension using mean length, width, and height or thickness.

6. Measurement by Area: Measured by square dimension using mean length and width or radius.

7. Linear Measurement: Measured by linear dimension, at item centerline or mean chord.

8. Stipulated Sum/Price Measurement: Items measured by weight, volume, area, or linear means or combination, as appropriate, as completed item or unit of the Work.

1.10 MEASUREMENT AND PAYMENT GENERAL NOTES

All associated costs for these items shall be included in the total price of the Contract and among the bid items included in the bid schedule. Owner will not pay for the following items separately:

A. Insurance and Bonds

1. The costs of all required insurance and bonds as listed in the bid schedule and the Contract documents will not be paid for separately and shall be included in the unit prices of this Contract.

B. Field Office

1. If the Contractor wishes to operate out of a field office for any portion of the Work the costs will be included within the unit prices of this Contract.

C. Traffic Control

1. The costs of all materials, labor, and equipment for traffic control and closures will not be paid for separately and shall be included in the unit prices of this Contract.

D. Security Clearances and Communications

1. All Contractor requirements for security clearances and communications as identified in the condition assessment portions of Section 33 01 30.18 will not be paid for separately and shall be included in the unit prices of this Contract.

2. The Engineer will provide the Contractor with print-ready door hanger files it has identified as necessary to properly inform the community of Work planned. All door hangers will be printed and delivered by the Contractor.

01 20 00 - 7

E. Miscellaneous Field Activities

1. Any flow control to temporarily retain flow or to remove standing water is incidental to the contract.

2. The use of the cleaning equipment in conjunction with the CCTV camera inspection shall not be considered an additional cleaning pass but is incidental to the contract.

3. Time spent searching for and locating a manhole is incidental to the contract.

4. Time spent exposing buried manholes in unpaved areas to a depth of two (2) feet is incidental to the contract.

5. Time spent backfilling buried manholes at the confirmation of the Engineer that have been exposed in unpaved areas to a depth of two (2) feet and restoration for full reinstatement of all items including but not limited to seeding and sod for backfilled manhole locations is incidental to the contract.

6. Trees smaller than six (6) inches in diameter measured at a point 4.5 feet above grade (diameter at breast height) shall be removed as part of the work and is incidental to the contract.

7. Time spent clearing restricted alleyways or easements to enable the mobilization of inspection and cleaning equipment is incidental to the contract.

8. All costs associated with protection of hydrants for water supply are incidental to the contract.

1.11 UNIT PRICE SCHEDULE

The measurement and payment descriptions of this section provide a summary of the pay items. Please refer to the individual technical specifications for additional details on general requirements, materials, and execution.

Mobilizations/Demobilization

a. The Contractor shall furnish all necessary personnel, equipment, labor, and materials for movement of equipment and personnel to the project site.

b. Payment for mobilization costs will be made in conjunction with the demobilization of the

Site including punch list completion, removal of equipment and final site clean-up, subject to the Contractor’s compliance with the requirements specified in the Contract Documents.

c. No payment for mobilization or demobilization will be made for the purpose of sewer video inspection, sewer cleaning, sewer lining or trenchless point repairs. All costs should be included within the items for sewer inspection, cleaning, lining and trenchless point repairs.

d. No payment for mobilization will be made for additional open cut sewer repair and replacements within a one-mile radius if the locations of work are issued at the same time or if additional repairs are discovered upon mobilization and inspection within the same vicinity of the issued work.

e. The accepted quantities for this work will be paid for at the contract unit price “Mobilization, Sewer Repair and Replacement, Open Cut…EA” complete in place.

01 20 00 - 8

Traffic Control

a. The costs of materials, labor, equipment, and all other incidental materials necessary for traffic control including furnishing, installing, maintaining, relocating, replacing defective items and removal of the following: traffic control devices, temporary hot-mix asphalt, temporary stone, plating, and temporary pavement marking for the purposes of traffic control and restoring public access shall be included in the cost of the pay item.

b. Payment under this item will not be made for traffic control on local City of Detroit residential streets which do not classify as a major thoroughfare. All costs of materials, labor, and equipment as listed above for traffic control and closures on local City of Detroit residential roadways and alley ways will not be paid for separately and shall be included in the unit price cost of separate items.

c. Payment for Traffic Control items shall be made only once per Site setup for all continuous work performed at the same location.

d. The accepted quantities for this work will be paid for at the contract unit price “Traffic Control.… EA” complete in place.

Safety Program

a. The costs of materials, labor, equipment, and all other incidental materials necessary for the submittal of the Contractor Safety Program as described in the technical specifications including but not limited to the Project Specific Safety Plan, Emergency Response Plan, and personnel training shall be included in the cost of the pay item.

b. This item shall include the Project Specific Safety Plan preparation, submittal, and all coordination and resubmittals associated with the reviews until final approval.

c. The accepted quantities for this work will be paid for at the contract unit price “Safety Pro-gram…LS” complete in place.

d. Contractor to submit schedule of values for all Lump Sum items subject to approval by the Owner.

Pre-Construction Site Documentation

a. The costs of materials, labor, equipment, and all other incidental materials necessary for pre-construction site documentation as described in the technical specifications including resident notifications, photographic documentation, and site video shall be included in the cost of the pay item.

01 20 00 - 9

b. The accepted quantities for this work will be paid for at the contract unit price “Pre- Construction Site Documentation…EA” complete in place.

Sidewalk, Rem completion of sidewalk removal including saw cutting, removing, hauling, and disposal of existing subgrade, sidewalk base material and sidewalk shall be included in the cost of the

b. Payment under this item will only be made for additional removals located outside any water main and sewer approved trench limits. Surface, base, and trench removals will be included in applicable water main and sewer structure and pipe items as listed in the measurement and payment descriptions.

c. Payment under this item will include sidewalk removal to full depth of existing sidewalk and

ADA ramps regardless of depth of existing sidewalk.

d. The accepted quantities for this work will be paid for at the contract unit price “Sidewalk, Rem…SYD” complete in place.

Sidewalk, Conc, 4 inch Sidewalk, Conc, 6 inch completion of sidewalk installation including preparation of subgrade; furnishing and compacting sidewalk base; furnishing reinforcement bars, dowels, tie bars, joint filler, sealant and accessories; furnishing, forming, finishing, curing, and sealing concrete sidewalk shall be included in the cost of the pay item. Removal of existing sidewalk shall be paid for separately.

b. The concrete mixes and procedures included in the cost of this pay item shall be performed to the standards and requirements of the local jurisdiction or permitting agency with authority in the right of way where the work is performed.