This is a Mitigation Plan document for the City-Wide Alley-Sewer Repair Program (ASRP) in Detroit, prepared by the City of Detroit Housing and Revitalization Department (HRD) in partnership with the Detroit Water and Sewerage Department (DWSD). The plan establishes required activities and responsibilities for contractors engaged in alley sewer inspection, rehabilitation, and replacement work funded through CDBG-DR resources. Key requirements include submission of a Health and Safety Management Plan by the general contractor prior to construction for HRD approval, compliance with DWSD Excavation and Handling of Contaminated Materials specifications during construction, and mandatory archaeology training for field crews prior to work commencement. The plan identifies specific mitigation activities with defined parties responsible, including DWSD's responsibility to communicate work locations two weeks in advance to coordinate necessary field inspections and HRD's designation of an Archaeology Compliance Specialist to oversee Section 106 compliance activities throughout the project duration.
The mitigation plan incorporates cultural resource protection protocols requiring an archaeologist to conduct inspections at required intervals, document field visits through Survey123, and respond to any unanticipated discoveries of cultural material or human remains. A Post Review Discoveries Plan is mandated for the duration of construction, with specific procedures requiring work stoppage and immediate notification to Melissa Owsiany (melissa.owsiany@detroitmi.gov) upon discovery of unanticipated tanks, evidence of contamination, artifacts, or bones. The plan also requires formal consultation with the State Historic Preservation Office (SHPO) and Consulting Tribes if necessary, with documentation requirements determined through additional consultation processes.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City-Wide Alley-Sewer Repair Program Mitigation Plan
11-14-2025 Response Activity or Continuing Obligation
Required Activities Party Responsible for Completing Activity
Timing of Activity Cost Required Follow-up or Reporting
On-site Health & Safety Management Plan
Contractors must submit Health & Safety Plan to HRD for approval
General Contractor
Prior to Construction
N/A
HRD Approval
DWSD Safety Specifications
Comply with DWSD Excavation and Handling of Contaminated Materials DWSD Standard Specifications, Section 02 61 13.
General Contractor
During Construction
N/A
Documentation as needed
Section 106- Training
Field crews must attend archaeology training prior to work General Contractor
Prior to construction
N/A
Document attendance
Section 106-HRD Inspection and Monitoring Plan
Archaeologist Responsibilities
• Communicating with contractors and staying up to date on crew work locations and activities;
• Complying with the specific applicable requirements of Owner’s and Contractor’s safety programs of which they have been informed;
• Conducting inspections of work locations and activities at required intervals;
• Responding to any unanticipated discoveries of cultural material or human remains;
• Documenting field visits in Survey123; and
• Documenting any cultural material discovered during the project.
• Coordinating formal consultation with SHPO and
Tribes, if necessary
HRD
During Construction
N/A
Documentaiton as needed in survey
Section 106 – Avoidance and Inspection Zones
Zones are mapped by district. DWSD will communicate work locations 2 weeks in advance to allow archaeologist to coordinate necessary field visits.
DWSD
2 weeks prior to construction
N/A
HRD Archaeology Compliance Specialist
City-Wide Alley-Sewer Repair Program Mitigation Plan
11-14-2025
Section 106 – Post Review Discoveries Plan
Once construction has started, the Post Review Discoveries Plan shall be followed for the duration of the project.
HRD, Construction Crew, Foremen, Developer, SHPO, Consulting Tribes
During Construction
N/A
Documentation will be determined through additional consultation
If unanticipated tanks, evidence of contamination, tanks, artifacts or bones are discovered during ground disturbing activities, work will be halted, and the Melissa Owsiany will be contacted immediately for further guidance on how to proceed. You can reach her at melissa.owsiany@detroitmi.gov.