8-Addendum 2.pdf

PDF 169 KB Posted

Attached to
Wabank Road Municipal Campus project
Solicitation number
US.257506
Issued by
Lancaster County, Pennsylvania

About this file

This is Addendum 2 to the Wabank Road Municipal Campus project solicitation issued by Lancaster Township in Pennsylvania. The addendum addresses clarifications and modifications to the original bidding documents for this municipal campus construction project. A mandatory pre-bid meeting was held on Monday, October 26 at 10:00 AM, and questions submitted online through the PennBid platform were accepted until 11:00 AM on Thursday, October 29. Electronic bids were due by 11:00 AM on Wednesday, November 4, with all bids to be publicly opened and made available through the PennBid portal. All bidders were required to review the proposed project with the Municipality's Representative prior to submitting their bids. Lancaster Township Board of Supervisors reserved the right to accept or reject any or all bids received.

The addendum modifies specific terms, requirements, or specifications from the original bid documents to provide clarification or address bidder inquiries. Bidders were required to register on the PennBid platform (https://pennbid.bonfirehub.com/) to access all project documents at no cost and to submit their bids electronically. Questions could only be submitted through the online "Ask A Question" feature in PennBid; inquiries submitted after the October 29 deadline were not acknowledged. No specific pricing information, set-asides, incumbent contractors, or funding sources are detailed in this addendum excerpt.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum 2 – Lancaster Township Wabank Road Municipal Campus Project

October 27, 2026

The purpose of this addendum is to provide direction for the proposed depth of millings that are to be placed by the Contractor.

The placement of millings is to achieve a minimum depth of 12”.