7S5 Independence PAPI - Pre-Bid Meeting Agenda.pdf
PDF 270 KB Posted
- Attached to
- Independence State Airport PAPI Replacement
- Solicitation number
- S-10900-00016084
- Issued by
- Oregon
About this file
This is a pre-bid meeting agenda for the Independence State Airport PAPI Replacement Project, organized by the Oregon Department of Aviation (ODAV) in coordination with Century West Engineering. The project involves the demolition of existing PAPI 4 box units at each end of the runway and construction of new PAPI 4 box units on the existing foundations with connections to the existing electrical system. A voluntary pre-bid conference was held on April 30, 2026, via MS Teams. Bids are due on May 14, 2026, at 2:00 p.m. with electronic opening via Teams. The contract timeline requires substantial completion within six calendar days after the Notice to Proceed and final completion within an additional six calendar days, meaning all work must be completed within a continuous six-day period with the runway closed during this time. Taxiway A will remain open for airport use. Construction staking will be performed by the contractor, and a proposed schedule must be submitted five days prior to the pre-construction conference. Contractors must comply with airport safety and security requirements, including the submission of a Safety Plan Compliance Document and adherence to specified work area restrictions shown on drawings G-3 and G-4.
The project is funded through Federal Aviation Administration Airport Improvement Program (AIP) funding. Award will be made to the lowest responsible and responsive bidder for the base bid items listed in Attachment A, Form A-2, with the sponsor reserving the right to withdraw any item from consideration. Liquidated damages are assessed at $1,000 per day for schedule delays. The contractor is responsible for obtaining all permits not obtained by the owner, and prevailing wage rates—the higher of Davis Bacon Wages or BOLI Prevailing Wages—apply to the project. As of the meeting date, DBE requirements previously applicable to federally funded projects have been suspended pending implementation of new Department of Transportation regulations, though ODAV maintains a nondiscrimination policy and encourages participation by all qualifying firms regardless of size or ownership.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5500 Meadows Road, Suite 250 | Lake Oswego, OR 9703
AGENDA – Independence State Airport – PAPI Replacement
Project
Pre-Bid Conference (Voluntary)
Project: Independence State Airport – PAPI Replacement Project (AIP 3-41-0027-012-2026)
Date & Time: April 30, 2026, 2:00 PM
Location: Electronic (MS Teams)
Attendees: See attached sign in sheet
Meeting Overview: This is the voluntary pre-bid meeting for all interested bidders.
I. Introductions
Engineer: Century West Engineering
• James Kirby, Century West Engineering – Sr Project Manager
• Ryan Halvorson, Century West Engineering – PM/Engineer of Record
Sponsor/Owner: Oregon Department of Aviation (ODAV)
• Anthony Beach, ODAV – State Airports Manager
• Alex Thomas, ODAV – Policy, Planning & Programs Manager
• Ermie Buncal – Program & Contracts Coordinator
II. Scope of Work
The work generally involves the following activities:
• Demolition of the existing PAPI 4 box units at each end of the runway. The existing foundations are to remain in place;
• Construction of new PAPI 4 box units on the existing foundation and connect to existing electrical system in existing foundations.
III. Bids Due
Date: May 14th, 2026
Time: As described in the Invitation to Bid/Oregon Buys (2:00 p.m., Local Time), Bids open at 2:00 p.m.
Location: Electronic opening per Invitation to Bid (Teams) at 2:00 p.m following bid closure
IV. Project Funding
Federal funding through the FAA Airport Improvement Program (A.I.P.)
V. Award
Basis of Award: Lowest responsible and responsive bidder for items selected for award, Attachment A, Form A-2, Base Bid. The Sponsor reserves the right to withdraw any item from award consideration
VI. Prevailing Wage Rates
Wage rates are included as part of the bid documents. The project shall pay the higher of Davis Bacon Wages or BOLI Prevailing Wages.
VII. Disadvantaged Business Enterprise (DBE) Goal
• DBE requirements that were applicable to federally funded projects prior to
10/03/2025 effective date of the Interim Final Rule by the US Department of
Transportation are no longer in effect, and DBE requirements have been suspended pending implementation of the DBE.
• ODAV has policy to practice nondiscrimination based on race, color, sex, or national origin in the award or performance of this Contract.
• Design team encourages participation by all firms qualifying under this solicitation regardless of size or ownership.
VIII. Contract Time
Refer to “Notice to Proceed” in the Proposal.
1. Substantial Completion to be achieved 6 calendar days after NTP
2. Final Completion to be achieved 6 calendar days after Substantial Completion
IX. Liquidated Damages
• $1,000 per day per the Invitation to Bid
X. Addenda
No anticipated addenda at this time. An addendum is anticipated after Question Due date of May 7th if necessary.
XI. Permits:
Contractor shall pay for and obtain all permits not obtained by the owner required to complete the work. Refer to Section 01160 of the technical specs.
XII. Airport Safety, Security, Work Areas
• Safety and security is a primary concern for airport projects.
• Access to east side of airport off Airport Road. Staging outside the airport within the existing gravel parking area as shown on G-3.
• No work can occur without the Engineer’s project representative or an Airport representative present. If subcontractors are working, a representative of the prime contractor shall be on site.
• The Airport Construction Safety and Phasing Plan is included in the Appendix.
Contractor shall comply with the provisions and submit Safety Plan Compliance
Document.
• Section 01300 of the specifications contains additional safety provisions and requirements. This includes the use and placement of low-level barricades, tubular markers, airport radios, checkered flags, rotating beacons on vehicles, etc.
• Section 01406 describes staking requirements for work areas.
• Drawings G-3 and G-4 show work area limits and describe their requirements.
• Airport security requirements are described in Section 01160.
• Staging areas, haul routes and project access points are shown on the plans.
• Refer to Drawing G-3 and G-4 for various work area sequencing, requirements, and restrictions.
Work Area Phasing:
• All work shall be completed within 6 continuous calendar days.
• 1 Phase is anticipated for the project.
Runway Closure Schedule:
• Runway closure anticipated to be closed for 6 continuous days.
• Taxiway A is to remain open for airport use as shown on G-3.
As required in Section 01160 of the General Requirements, the Contractor shall submit a proposed schedule for completion of the work 5-days prior to the pre-construction conference to allow the ODAV to coordinate notification with airport users.
XIII. Construction Staking
Construction staking shall be performed by the Contractor. Control monuments have been established. Refer to Section 01406. Contractor shall do all staking. Staking is anticipated to include, but is not limited to:
• PAPI elevations and runway centerline
XIV. Quantities
• Do not anticipate quantities to be different than bid items.
• If existing conditions differ from assumed design, quantities may need to be revised and will be reviewed in the field with RPR/Inspector.
XV. Erosion Control
Sediment fence is shown around the existing PAPIs per EC-1. No ground disturbance is anticipated with this project.
XVI. Questions?
File details come from the government source that posted it. Updated .