7A - DAR - Replace AHUs 22 and 23 - 100 percent S and S Bid Documents for Construction.pdf
PDF 17 MB Posted
- Solicitation number
- 36C24824R0010
About this file
This file contains bid documents for a federal construction contract solicitation. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8 is soliciting bids to replace air handling units 22 and 23 at an unspecified facility. Bids are due by July 15, 2024 according to solicitation number 36C24824R0010. The construction project, numbered 673-21-152, will replace the aging HVAC equipment to maintain environmental conditions. The 17MB file includes specifications, drawings, and other requirements for the mechanical systems upgrade. Pricing is to be provided on a firm-fixed price basis. The award date was not specified but is presumed to be shortly after the bid due date pending evaluation of submissions.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace Air Handling Units 22 and 23 James A Haley VA Medical Center
Tampa, Florida
Contract 36C24822N0341, Project 673-21-152
DESIGN ANALYSIS REPORT
100% Bid Documents for Construction
Submission
Prepared for
Department of Veterans Affairs James A. Haley VA Medical Center
8875 Hidden River Pkwy, Suite 525
Tampa, FL 33637
Prepared by
3603 NW 98th Street, Suite B
Gainesville, Florida 32606
April 14, 2023
Design, Inc.
Replace Air Handling Units 22 and 23 Design Analysis Report – 100% Bid Documents for Construction Submittal James A Haley VA Medical Center, Tampa, FL
AKEA Design, Inc. Contents – Page 1 of 1
Contents
Submittal Letter
Schedule
VA Minor Checklists
Mechanical Narrative
Electrical Narrative
Architectural Narrative
Structural Narrative
Appendix
D.O. 36C248‐22‐N‐0341, PROJECT NO. 673‐21‐152 print date: 3/30/2023
PROJECT TITLE: A/E Design "Replace AHUs 22 and 23
PROJECT LOCATION: James A. Haley VA Medical Center, Tampa, Florida
Schedule Notes, see paragraph 4
Sub. Task
Incremental
Days Day
Notice to Proceed to DD 0 3/30/2022 added time for investigation
Investigation and Measured Drawings 14 14 4/13/2022 Wed
1 DD1 Schematics (10‐15%) 28 42 5/11/2022
VA Review 21 63 6/1/2022
2 30% submission ‐ DD2 42 105 7/13/2022
VA Review 32 137 8/14/2022
Notice to Proceed CD 1 138 8/15/2022 Mon
3 65% submission ‐ CD1 35 173 9/19/2022 Mon
VA Review 44 217 11/2/2022 Wed
4 95% submission ‐ CD2 20 237 11/22/2022 Tue
VA Review 83 321 2/14/2023 Tue
5 100% submission ‐ CD3 21 342 3/7/2023 Tue
VA Review 22 364 3/29/2023 Wed
6 Final S&S, per paragraph III.B thru III.E 16 380 Total Calendar Days 4/14/2023 Fri
VA schedule
203 53%
VA Review Days
NOTE: This schedule is proposed to match the contract statement of work. We reserve the right to modify the schedule upon successful completion of first investigative site visit.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Contract 36C24822N0341 Project 673-21-152
Architectural
VA MINOR CHECKLIST
Phase: Construction Documents Reviewer: Jennifer Fong/Rabi Al-Khazarji
Submittal Schematics
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Confirm
Location of:
Rooms ¹ ✓ N/A ✓ N/A ✓ Yes
Doors ² ✓ N/A ✓ N/A ✓ Yes
Corridor(s) ³ ✓ N/A ✓ N/A ✓ No
Basic column grid/sizes ✓ N/A ✓ N/A ✓ Yes
Expansion and seismic joints ✓ N/A ✓ N/A ✓ N/A
Electrical closets ✓ N/A ✓ N/A ✓ N/A
Equipment rooms ✓ N/A ✓ N/A ✓ Yes
Signal and telephone closets ✓ N/A ✓ N/A ✓ N/A
Mechanical shafts and space ✓ N/A ✓ N/A ✓ N/A
Stair(s) ✓ N/A ✓ N/A
Ramp(s) ✓ N/A ✓ N/A
Elevator(s) ✓ N/A ✓ N/A ✓ N/A
Automatic Conveyances ✓ N/A ✓ N/A ✓ N/A
Floor Plans/Drawings:
All floors (new and renovated) ✓ N/A ✓ N/A ✓ Yes
Penthouse ✓ N/A ✓ N/A ✓ N/A
Roof plan ✓ N/A ✓ N/A ✓ N/A
Pipe basement ✓ N/A ✓ N/A ✓ N/A
Pipe tunnel ✓ N/A ✓ N/A
Reflected ceiling⁴ ✓ N/A ✓ N/A
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Equipment floor plans 1:50 (1/4 inch) scale⁵
✓ N/A ✓ N/A
Demolition plans⁶ ✓ N/A ✓ Yes
Room names and numbers⁷ ✓ N/A ✓ Yes
Program net/designed net ✓ N/A ✓ N/A ✓ N/A
Exterior dimensions/total building gross area
✓ N/A ✓ N/A ✓ N/A
Size and shape of all departmental functions and services⁹
✓ N/A ✓ N/A ✓ N/A
Exterior building elevations¹⁰ ✓ N/A ✓ N/A ✓ Yes
Finish floor elevations¹¹ ✓ N/A ✓ N/A ✓ Yes
Door locations, sizes, and swings ✓ N/A ✓ Yes
Wall thickness and chase walls ✓ N/A ✓ Yes
Handrail location/dimensions ✓ N/A ✓ N/A
Fixed equipment ✓ N/A ✓ N/A
Equipment elevations and details ✓ N/A
Plumbing fixtures ✓ N/A ✓ N/A
Wheelchair accessible facilities ✓ N/A ✓ N/A
Wall sections¹² ✓ N/A ✓ Yes
Building sections¹³ ✓ N/A ✓ N/A
Finish grades at corners, entrances, exits, platforms, and ramps
✓ N/A ✓ N/A
Fire and smoke rated partitions¹⁴ ✓ N/A ✓ N/A ✓ Yes
Lead-lined and radio frequency-shielded partitions¹⁴
Fire extinguisher cabinets¹⁴ ✓ N/A ✓ N/A
Spray-on fire proofing (see fire protection)
Construction details¹⁵ ✓ N/A ✓ Yes
Drafting symbols, abbreviations, and general notes
✓ N/A ✓ Yes
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Door, window, and louver schedules ✓ N/A
Interior details, elevations, sections ✓ Yes
Finish schedule¹⁶ ✓ N/A ✓ N/A
Graphics and signage¹⁷ ✓ N/A
Color rendering ✓ N/A
Specifications ✓ N/A ✓ Yes
Lead abatement¹⁸ ✓ N/A ✓ N/A
Lead abatement specification¹⁸ ✓ N/A ✓ N/A
* Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). A scale of 1:200 (1/16 inch) is acceptable for architectural floor layout if an entire floor cannot be shown on one sheet. Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase.
NOTES:
1. Use lines between spaces to indicate the centerline of the partition (for schematics only).
2. Indicate doors with a slash mark.
3. Along the corridor, the line shall represent the corridor side of the partition.
4. Indicate ceiling mounted equipment, lighting fixtures, air diffusers, registers, tracks, and other significant elements.
5. Identify all equipment for each room. Indicate and coordinate all equipment with the Equipment Guide List (Program Guide 7610) and Activated Equipment List. Use VA standard symbols and notation to distinguish between contractor-furnished and installed (CC), VA-furnished contractor-installed (VC), VA-furnished and installed (VV), VA-furnished with construction funds [VC(CF) and VV(CF)] and relocated (R) equipment. Equipment floor plans are not required for the offices, consultation rooms, classrooms, conference rooms, and waiting rooms within the above departments. Draw equipment details which are necessary for major decisions, though complete detailing is not required for this submittal.
6. Indicate existing finish schedule and notes on plan.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
7. Label as required for schematic drawings. Coordinate new room numbering with medical center.
8. Use the same names on drawings as those used in the space program. Provide area figures in fractional form, e.g., 400/390. Indicate space provided, but not called for in the space program, as: -/390.
9. Label each service or activity listed in the Project Scope Data of the Design Program and indicate boundaries with a distinctive line.
Include the activity code number (see Handbook 7610).
10. If the project requires exterior work, show all facades indicating massing, proposed fenestration and the building relationship to adjacent structures and the finish grade. Show all significant building materials, including their colors, any proposed roof top mechanical equipment, architectural screens, skylights, and stacks on the elevation drawings. If building is designed for future expansion (vertical and/or horizontal), delineate elevations with and without the future expansion. If project is an addition, show elevations of the existing building in sufficient detail to illustrate the relationship between the new and existing in terms of scale, material, and detail.
11. Define the relationship of the finish ground floor to finish grade at major entrances and docks.
12. Indicate construction including fire resistance rating, building materials and systems, and proposed sill and head heights of openings.
Indicate both new and renovated areas on form provided by VA.
13. Define building configuration. Draw sections at the same scale as floor plans, normally 1:100 (1/8 inch). If the building abuts an existing structure, indicate in the section how the new floor elevations align with existing.
14. Identify psychiatric areas where special considerations are required to ensure the safety of patients (e.g., hard ceilings, safety glazing, etc.).
15. Indicate new building components and systems, such as window design, roofing system, special entryways, building "skin", and any special architectural elements for the project. Complete detailing of miscellaneous items is not required for this submission.
16. Indicate all building systems, materials, and future expansion, if applicable.
17. Submit a drawing for all which is part of the construction contract.
18. Provide square meters (feet) of lead paint and x-ray shielding to be removed.
19. Format provided in SPECIFICATIONS. If there is no VA master specification, develop contract specification that is in compliance with regulations of the Environmental Protection Agency.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
ASBESTOS ABATEMENT
Reviewer: William Rodriguez
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Confirm
Narrative:
Asbestos abatement report including:
1. Summary results of building records
2. Summary results of station personnel interview
3. Determination of materials known to contain asbestos
4. Visual inspection of building to determine location and condition of asbestos
5. Sample strategy on the extent of asbestos present
✓ N/A
Name and location of qualified laboratory for sample analysis
Asbestos abatement drawing ✓ N/A
Major Decontamination Areas showing:
1. Limits of sealing off the location
2. Quantities of asbestos material
3. Arrangements for auxiliary rooms
4. Engineering of negative air systems
5. Path of asbestos to loading platform
6. Location and connection to required utilities
Minor Decontamination Areas showing:
1. Location, type, and length of pipe element to be abated by "Glove and Bag" approach
2. Other abatement features
Summary of:¹
Square meter (feet) of floor space for abatement
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Total linear and square meter (feet) of asbestos to be abated
Total cost of abatement² ✓ N/A ✓ Yes
Asbestos abatement drawings including:
1. Restoration of impacted building sub-systems
2. Integrated phasing on execution of abatement
✓ Yes
* Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch. Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from
1. Provide a copy of the summary to the construction cost estimator for inclusion as a separate bid item in the project estimate.
2. Include any cost for decontamination of equipment and fixtures.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Automatic Transport
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Automatic Transport Systems (ATS):
Narrative with recommended improvements for exiting system
Traffic study including existing and proposed ATS with alternate methods of distribution
Changes to existing systems (arch.
Dwgs.)
✓ N/A ✓ N/A
Hoistway (arch. dwg.) ✓ N/A ✓ N/A
Machine room vents (arch. dwg.) ✓ N/A ✓ N/A
Type of ventilation (mech. dwg.) ✓ N/A ✓ N/A
Electrical requirements (elect. dwg.) ✓ N/A ✓ N/A
Drawings¹²³:
Automatic Transport Systems ✓ N/A ✓ N/A
Elevators ✓ N/A ✓ N/A
Dumbwaiters ✓ N/A ✓ N/A
Other ATS systems ✓ N/A ✓ N/A
Sizes/dimensions/details:
Hoistway ✓ N/A ✓ N/A
Pits ✓ N/A ✓ N/A
Pit ladders ✓ N/A ✓ N/A
Machine area ladder and railings ✓ N/A ✓ N/A
Entrances ✓ N/A ✓ N/A
Machine rooms ✓ N/A ✓ N/A
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Locations/dimensions:
Elevator cars ✓ N/A ✓ N/A
Entrances ✓ N/A ✓ N/A
Counterweights ✓ N/A ✓ N/A
Trap doors ✓ N/A ✓ N/A
Location of hoistway vents ✓ N/A ✓ N/A
Location of steel hoisting beams ✓ N/A ✓ N/A
Size of machine beams ✓ N/A ✓ N/A
Size of end reactions ✓ N/A ✓ N/A
Location/detail of machine beam pockets ✓ N/A ✓ N/A
Rail loadings ✓ N/A ✓ N/A
Hydraulic elevator piston pit loads ✓ N/A ✓ N/A
Details:
Hoistway entrances for elevators ✓ N/A ✓ N/A
Car lifts ✓ N/A ✓ N/A
Dumbwaiters ✓ N/A ✓ N/A
Trash chutes ✓ N/A ✓ N/A
Linen chutes ✓ N/A ✓ N/A
ETVS ✓ N/A ✓ N/A
Elevator machine room equipment layout ✓ N/A ✓ N/A
Interface with automatic recall and shutdown (see fire protection)
Specifications ✓ N/A ✓ N/A
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
* Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from
1. Include tracking, piping, battery charging areas, blower rooms, queuing areas, cart holding areas, cart washer, central control area, and floor or wall recessed transport control units. Indicate architectural features in areas to be utilized for these systems. Indicate on architectural drawings all the major equipment located in machine rooms, secondary levels, pits, and the areas pertaining to ATS, AGVS and ETVS.
2. Indicate changes required on the architectural drawings where existing transport systems are retained and modified to serve new and existing areas.
3. Provide all electrical criteria (per basic electrical notes and Automatic Transport Design Manual) on electrical drawings.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Critical Path Method (CPM)
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Confirm
Phasing Narrative ✓ N/A ✓ N/A ✓ Yes
Phasing Plans (on reduced site plans) ✓ N/A
Phasing Diagram ✓ N/A
Phases (marked on full size drawing) ✓ N/A
Written list of systems¹ ✓ N/A ✓ N/A ✓ N/A
Phasing Diagram (drawn on Phasing Plan) ¹
CPM Phasing Plans (full size contract drawings) ²
1. Include temporary system by phase and separate by technical discipline.
2. One drawing may reflect several reduced site plans.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Electrical
Reviewer: Bob Haffeman
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Confirm
Narrative:
Design ✓ Yes
Life cycle analysis for electrical systems ✓ N/A
Location and size of:
Electrical equipment ✓ N/A
Electrical closets ✓ N/A
Telephone closets ✓ N/A
Signal closets ✓ N/A
Electrical distribution equipment ✓ N/A
Primary distribution switchgear/switchboard
✓ N/A ✓ N/A
Engine-generator sets ✓ N/A ✓ N/A
Substation/padmounted transformer ✓ N/A ✓ N/A
Manholes ✓ N/A ✓ N/A
Location of smoke dampers and duct smoke detectors
Interconnection of electrical control equipment with HVAC equipment (see fire protection)
✓ NA
Smoke partitions and fire alarm zones ✓ N/A ✓ N/A ✓ N/A
Fire alarm and signal riser diagrams (see fire protection)
✓ N/A ✓ N/A
Calculations for emergency generator(s) ✓ N/A ✓ N/A
Floor Plans/Drawings. Identify:
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Electrical plot plan of existing and proposed underground power (including manholes)
✓ N/A ✓ N/A ✓ N/A
Telephone systems ✓ N/A ✓ N/A ✓ N/A
Signal inter-building systems ✓ N/A ✓ N/A ✓ N/A
Proposed electrical system ✓ N/A ✓ Yes ✓ Yes
Electric symbols ✓ N/A ✓ Yes ✓ Yes
Lighting fixture schedule ✓ No ✓ N/A ✓ N/A
Symbols, note, abbreviations ✓ Yes ✓ Yes
List of specialty areas ✓ N/A
Method of short-circuit calculations ✓ N/A
Method of voltage drop and demand calculations
✓ N/A
Utility company correspondence ✓ N/A
Utility company requirements ✓ N/A ✓ N/A
Load calculations for normal & emergency use
✓ N/A ✓ No ✓ No
Lighting layouts ✓ N/A ✓ N/A
Power layouts ✓ Yes ✓ Yes
Signal layouts ✓ N/A ✓ N/A
Specialty area layouts ✓ N/A ✓ N/A
Demolition plans ✓ Yes ✓ Yes
Riser diagrams ✓ Yes ✓ Yes
Branch circuit wiring (typ.) ✓ N/A ✓ N/A
Other:
Phasing scheme ✓ N/A ✓ N/A
Electrical details ✓ Yes
Specifications ✓ Yes
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
* Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase.
ELECTRICAL NOTES:
1. Include basic assumptions, points of interconnection, impact of new construction to existing electrical distribution system, current demand loading (high voltage switchgear and primary feeder), and projected load of new construction. Propose various feasible electrical systems for project and provide advantages/disadvantages.
2. Include means and clearances for installation, maintenance, and removal/replacement of equipment.
3. Electrical, signal and telephone closets must stack vertically.
4. Include high voltage and low voltage switchgear, transformers and low voltage main and/or
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Equipment
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Confirm
Equipment (on architectural drawing) ✓ N/A ✓ N/A ✓ No
Activation Equipment List (Excel format) ✓ N/A ✓ N/A
* Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Estimating
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Cost estimate in compliance with Manual for Preparation of Estimates (Separate estimates for new construction and alteration work)
✓ N/A ✓ N/A ✓ Yes
Level "A" Summary Sheets for building ✓ N/A ✓ N/A
Level "A" Summary Sheets for sitework ✓ N/A ✓ N/A
Building gross area computation (new) ✓ N/A ✓ N/A
Building gross area computation (alteration work)
✓ N/A ✓ N/A
Project Data Sheet 1 ✓ N/A
Project Data Sheet 1 and 2 ✓ N/A ✓ N/A
Asbestos abatement ✓ N/A ✓ Yes
Detailed estimate take-off sheets ✓ Yes
Level "B" Summary Sheets for buildings ✓ Yes
Level "B" Summary Sheets for sitework ✓ N/A
Supplement A to SF 252 ✓ N/A
Detail Market Analysis ✓ N/A
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Fire Protection
Reviewer: William Rodriguez / Bob Haffeman /Jennifer Fong
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Confirm
Fire Protection Narrative¹:
Fire and smoke separation ✓ N/A
Fire sprinkler/standpipe system ✓ N/A
Size of fire pumps ✓ N/A
Water supply available/max. demand ✓ N/A
Water flow testing results ✓ N/A
Fire alarm systems² ✓ N/A
Existing to be modernized ✓ N/A
Base loop system for interface of new construction
✓ N/A
Kitchen extinguishing systems ✓ N/A
Size of air handling unit ✓ N/A
Exit paths from each zone ✓ N/A
Distances to stairs ✓ N/A
Occupancy of each area ✓ N/A
Exit calculations for each floor ✓ N/A
Smoke control features ✓ N/A
Floor Plans/Drawings³⁴:
Sprinkler zones ✓ N/A
Fire alarm zones ✓ N/A
Smoke zones ✓ N/A
Building water supply ✓ N/A
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Interior sprinkler supply lines ✓ N/A
Standpipes ✓ N/A
Fire extinguisher cabinets ✓ N/A ✓ N/A ✓ N/A
Fireproofing of structural members ✓ N/A
Sprinkler/standpipe riser supply piping ✓ N/A ✓ N/A
Termination of sprinkler main and inspector test drains
✓ N/A ✓ N/A
Sprinkler alarm valves ✓ N/A ✓ N/A
Waterflow and tamper switches ✓ N/A ✓ N/A
Sprinkler system fire department connections
✓ N/A ✓ N/A
Sprinkler design hazards per NFPA 13 ✓ N/A ✓ N/A
Exit signs and emergency lighting ✓ N/A ✓ Yes
Occupied areas not protected by automatic sprinklers
Calculations ✓ N/A ✓ N/A ✓ N/A
Estimated capacities for proposed air handling units in cubic meters (cubic feet) per minute
✓ N/A ✓ N/A
Location of:
Fire alarm system ✓ N/A ✓ Yes
Annunciator panels ✓ N/A ✓ Yes
Pull stations ✓ N/A ✓ Yes
Flow switches ✓ N/A ✓ Yes
Audio-visual devices ✓ N/A ✓ Yes
Smoke detectors ✓ N/A ✓ Yes
Duct smoke detectors ✓ N/A ✓ Yes
Smoke dampers ✓ N/A ✓ N/A
Fire dampers ✓ N/A ✓ Yes
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Fire alarm risers⁵ ✓ N/A ✓ N/A
Exit signs ✓ N/A ✓ Yes
Emergency lighting ✓ Yes
Fire sprinklers ✓ N/A
Standpipes ✓ N/A ✓ N/A
Fire hydrants ✓ N/A
Fire pumps ✓ N/A
Post indicator valves ✓ N/A ✓ N/A
Sectional valves ✓ N/A
Fire extinguisher cabinets ✓ N/A ✓ Select
Electromagnetic door-hold open devices ✓ Select
Wall sections indicating fire resistive ratings
✓ Yes
Staff sleeping rooms ✓ N/A
Excavation plan signage ✓ N/A
Door and window schedule with fire rating or fire-rated glazing
Zoning of each fire alarm initiating device
Details
Fire pump system (capacity and pressure)
Elevation and isometric view of fire pump
✓ N/A
Stairwell sign ✓ N/A
Annunciator panel ✓ N/A
Interconnection of fire alarm system with:
Smoke dampers ✓ N/A
Air handlers ✓ Yes
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Elevator controls ✓ N/A
Kitchen fire extinguishing and fire pump system
HVAC system with smoke duct detectors ✓ Yes
Single line riser diagram for fire alarm system
Height/configuration of storage racks and shelving
* Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from
1. Indicate NFPA 220 and UBC fire resistive rating of the building, NFPA 101 occupancy type, and fire protection code analysis to access compliance with NFPA 101.
2. Determine type, features, age, reliability, compliance with present day codes, capacity, zoning, supervision, control panel and power supplies, initiating devices and circuits, and auxiliary functions for existing fire alarm system. Indicate manufacturer, model number, voltage, and wiring style of existing alarm systems and devices. Provide recommendations for the proposed fire alarm work.
3. Provide information to meet JCAHO requirements, e.g., location of all fire rated barriers, smoke barriers, exit signs, fire extinguishers, manual pull stations, smoke detectors, and sprinkler flow switches. Show all interim life safety measures such as temporary systems Fire Alarm, Sprinkler, and Smoke.
4. At DD Submission, add room names, room numbers, door locations and swings, smoke and fire rated partitions, sprinkler/standpipe risers to floor plans. Identify psychiatric areas on drawings so areas for institutional type heads are identified. Add location of all valves (post indicator, sectional) and backflow preventer if provided.
5. Show new equipment and/or the necessary changes involved if modification to the existing system is required. Include any recommendations where certain requirements of VA criteria might be waived, in order to allow the existing equipment to be reused.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
HVAC
Reviewer: William Rodriguez, P.E.
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
Description of HVAC systems ✓ Yes
Equipment for each functional space ✓ Yes
Life cycle cost analysis¹ ✓ N/A
Tentative location and size of:
Mechanical equipment room ✓ Yes
Principal vertical shafts ✓ N/A
Block layout of equipment ✓ Yes
Louvers²:
Outside air ✓ Yes ✓ Yes ✓ Yes
Exhaust air ✓ N/A ✓ Yes ✓ Yes
Relief air ✓ N/A ✓ N/A ✓ Yes
Engineering calculations³ ✓ N/A ✓ N/A ✓ Yes
Selection of HVAC equipment ✓ Yes ✓ Yes
Catalog cuts of equipment ✓ Yes ✓ Yes
Room by room heating and cooling loads
✓ N/A ✓ Yes
Zone by zone heating & cooling loads ✓ N/A ✓ Yes
Building block heating & cooling loads ✓ N/A ✓ Yes
Tabulation of steam consumption ✓ N/A ✓ Yes
Psychometric chart for air handling unit ✓ N/A ✓ Yes
Coil entering and leaving conditions ✓ Yes ✓ Yes
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Fan motor heat gains ✓ N/A ✓ Yes
Consumption of humidification loads ✓ N/A ✓ N/A
Sound/acoustic analysis ✓ N/A ✓ Yes
Room-by-room air balance charts⁴ ✓ N/A ✓ Yes
Chilled Water Plant⁵
Quantity and type of chillers ✓ N/A ✓ N/A
Capacity in tons of refrigeration ✓ N/A ✓ N/A
Electrical equipment ✓ N/A ✓ N/A
Heating System
Total heating load ✓ N/A ✓ Yes
Domestic hot water load ✓ N/A ✓ N/A
Humidification load ✓ N/A ✓ N/A
Equipment steam demand ✓ N/A ✓ Yes
Zoning of heating system ✓ N/A ✓ Yes
HVAC floor plan⁶
Main supply, return, and exhaust ductwork
✓ Yes ✓ Yes
Volume dampers ✓ Yes ✓ Yes
Fire and smoke partitions ✓ No ✓ No
Fire and smoke dampers ✓ N/A ✓ Yes
Smoke detectors ✓ Yes ✓ Yes
Automatic control dampers ✓ Yes ✓ Yes
Air quantities for each room ✓ N/A ✓ Yes
Air inlets/outlets ✓ N/A ✓ N/A
Rises and drops in ductwork ✓ N/A ✓ Yes
Expansion loops ✓ N/A ✓ Yes
Anchors ✓ N/A ✓ Yes
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Valves ✓ N/A ✓ Yes
Drip assemblies ✓ N/A ✓ Yes
Balancing fittings ✓ N/A ✓ Yes
Interconnection of HVAC equipment with fire protection equipment (see fire protection)
✓ N/A ✓ N/A
Plan/section of mechanical equipment rooms
✓ Yes ✓ Yes
Schematic flow and riser diagrams⁷ ✓ N/A ✓ Yes
Schematic control diagrams⁸ ✓ Yes ✓ Yes
HVAC demolition drawings ✓ Yes ✓ Yes
Phasing plan ✓ Yes ✓ Yes
Equipment schedule ✓ Yes ✓ Yes
Seismic bracing ✓ N/A ✓ N/A
VA symbols and abbreviation ✓ Yes ✓ Yes
Selection of:
Pumps ✓ Yes
Fans ✓ N/A
Sizing and selection of:
Expansion tanks ✓ Yes
Steam to hot water convertor ✓ N/A
Heat exchangers ✓ Yes
Other:
Sound analysis ✓ Yes
Complete selection data ✓ Yes
Outside chilled water and condenser water distribution⁹
N/A
Standard detail drawings ✓ Yes
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Automatic temperature control drawings¹⁰
HVAC specifications ✓ Yes
* Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase.
HVAC NOTES:
1. Provide specific design recommendations and full back-up data. Include the heating and cooling capacities of each functional area and the block cooling and heating loads for each new and/or existing building.
2. The locations of these louvers must not allow short circuiting of air from emergency generator exhaust or truck waiting and loading dock areas into air intake etc. Consider factors affecting louver location such as visibility, historical considerations, wind direction, nuisance and health hazard odors (from emergency generator or truck exhausts).3. Include room-by-room, peak zone-by-zone, and building block heating and cooling loads.
Provide a tabulation of steam consumption based on data from all sources. Show correlation between each HVAC zone boundary and architectural floor area correlation between the architectural room numbers and abbreviated/coded room numbers used with computer input data sheets.
3. Include room-by-room, peak zone-by-zone, and building block heating and cooling loads. Provide a tabulation of steam consumption based on data from all sources. Show correlation between each HVAC zone boundary and architectural floor area correlation between the architectural room numbers and abbreviated/coded room numbers used with computer input data sheets.
4. Show supply, return, exhaust, make-up, and transfer quantities with intended pressure relationships, i.e., positive, negative, or zero with respect to adjoining spaces.
5. Provide pertinent data on accessories such as pumps and cooling tower etc. Show the extent of the outside chilled water and condenser water piping. Clearly show how the piping will be laid in tunnels, trenches, or by direct burial.
6. Show ceiling clearances, at locations where ducts cross each other, by providing 1:50 (1/4 inch) scale local sections. Show all ductwork and piping 150 mm (6 inch) and larger in double line. Show separate floor plans for air distribution and piping unless waived by VA. Show clearances required for access and maintenance with coil and tube pull.
7. Show typical air handling systems and all hydronic systems with existing capacities and new estimated loads. Verify actual operating conditions and capacities of HVAC systems prior to design.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
8. Show control devices, such as, thermostats, humidistats, flow control valves, dampers, freezestats, operating and high limit sensors for all air systems and fluids, smoke dampers, duct detectors etc. Provide a written description of the sequence of operation on the floor plans. Detail the scope of work involved with the Central Engineering Center (ECC) and address if enough spare capacity is available or a new ECC is required.
Show a point schedule for analog/digital input/output to be included in ECC.
9. Show pipe sizes and insulation with plans, profile, sections, details, and all accessories, such as, anchors, expansion loops/joints, valves, manholes, capped and flanged connections, interface between the new and existing work (if any). Clearly indicate interferences (if any) with the existing utilities and/or landscape elements on outside piping layout drawings. Show rerouting any utilities, cuttings of roads, pavements, trees, etc., and the extent of new and demolition work. Outside utility drawings shall be based on the study of the latest site drawings, discussions with engineering personnel, and actual site inspection of the existing utility.
10. Show all duct detectors, control valves/dampers static pressure sensors, differential pressure control assemblies, etc., whose actual physical location is critical for the intended sequence of operation on floor plans.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Interior Design
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Confirm
Written interior design concept¹ ✓ N/A
Illustrate overall design solution² ✓ N/A
Material and finish samples ✓ N/A
Sketches ✓ N/A
Design solution for interior spaces:
Perspectives ✓ N/A ✓ Yes
Plans ✓ N/A ✓ Yes
Details ✓ N/A ✓ Yes
Elevations ✓ N/A ✓ Yes
Sections ✓ N/A ✓ N/A
Wayfinding ✓ N/A ✓ N/A
Floor patterns ✓ N/A ✓ N/A
Wall patterns ✓ N/A ✓ N/A
Lighting ✓ N/A ✓ N/A
Signage ✓ N/A ✓ N/A
Bumper guards ✓ N/A ✓ Yes
Specification section 09050 ✓ N/A ✓ N/A
Finish schedule ✓ N/A ✓ N/A
Exterior colors and materials ✓ N/A ✓ Yes
Sample boards for interior and exterior materials, products, and finishes
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Edited carpet and wallcovering specifications
✓ N/A ✓ N/A
Keyed Finnish plans ✓ N/A
Interior design details, elevations, and sections
* Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from
1. Provide a document of data collected in interior design programming. Include collection and analysis of data from the VAMC project coordinator and interior designer. Data includes, but is not limited to the following: existing interior and exterior design and materials, light, safety, patient profile, customer’s “vision” or desired image, public vs. private spaces, complete signage package, goals of customer, relationship to existing facilities, future expansion/renovation plans, regional influences, etc.
2. Discuss and illustrate the overall design solution for the primary areas of the project using marked-up floor plans, loose sketches, and material and finish samples. Use broad categories of materials, finishes, color palettes, patterns, textures, and scales. Separately group all major neutral background materials and finishes that will be used and discuss how they will be integrated with all other materials and finishes on the project. Include all primary and secondary corridors, typical patient and toilet rooms, lobbies, atriums, eating spaces, chapels, waiting rooms, and exam rooms. Show the relationship among departments and functions, and between public and private spaces.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
PLUMBING
Reviewer: William Rodriguez, P.E.
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Existing plumbing systems to be used and necessary modifications
✓ N/A ✓ N/A ✓ Yes
New plumbing systems ✓ N/A ✓ N/A ✓ N/A
New or modified water treatment ✓ N/A ✓ N/A ✓ N/A
Floor Plans/Drawings. Identify:
Room names ✓ N/A ✓ N/A ✓ N/A
Existing plumbing fixtures w/ VA numbering systems
New plumbing fixture w/ VA numbering systems
✓ N/A ✓ N/A ✓ N/A
Existing equipment ✓ N/A ✓ N/A ✓ N/A
New equipment ✓ N/A ✓ N/A ✓ N/A
New medical gas outlets ✓ N/A ✓ N/A
New laboratory gas outlets ✓ N/A ✓ N/A
Plumbing piping ✓ N/A ✓ N/A ✓ Yes
Size of pipe ✓ N/A ✓ Yes
Equipment schedule ✓ N/A ✓ N/A
Fire & smoke partitions ✓ N/A ✓ N/A ✓ N/A
Demolition plans ✓ N/A ✓ N/A
Riser diagrams ✓ N/A
Legends, notes, and details ✓ Yes
Other:
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Location and size of sprinkler riser, standpipes, and fire pumps (see fire protection)
Location of emergency eyewash and shower equipment
✓ N/A ✓ N/A
Calculations (equipment & piping) ✓ N/A ✓ N/A
List of required contract specifications ✓ N/A ✓ N/A
Contract Specifications ✓ Yes
* Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch).
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics phase.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase. Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch).
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Sanitary
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Existing sanitary systems: underground water, sanitary sewers, storm sewers, & fuel gas with sources, disposal methods, storage pressures, condition, etc.
New sanitary systems ✓ N/A ✓ N/A ✓ N/A
Provide water analysis & expected yield if well required
Circulation study to assess emergency vehicle access
✓ N/A ✓ N/A ✓ N/A
Install test well, if well is required ✓ N/A
Utility Plans/Drawings showing existing and new sanitary systems:
Size of pipes ✓ N/A ✓ N/A ✓ N/A
Invert elevations of sewers ✓ N/A ✓ N/A ✓ N/A
Locate/size:
Pumps ✓ N/A ✓ N/A ✓ N/A
Storage facilities ✓ N/A ✓ N/A ✓ N/A
Treatment equipment ✓ N/A ✓ N/A ✓ N/A
Fire hydrants ✓ N/A ✓ N/A
Sectional and post indicator valves ✓ N/A ✓ N/A
Backflow preventer ✓ N/A ✓ N/A
Areas of new irrigation system ✓ N/A
New irrigation system ✓ N/A
Profiles of sanitary and storm sewers ✓ N/A
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Demolition plans ✓ N/A ✓ N/A
Legends, notes, and details ✓ N/A
Other:
Point of connection to sprinkler system ✓ N/A ✓ N/A ✓ N/A
Calculations ✓ N/A ✓ N/A
List of specifications ✓ N/A
Contract specifications ✓ N/A
* Submit utility drawings at same scale as provided for Site Development drawings.
** Submit utility drawings at same scale as provided for Site Development drawings, incorporating all of the revisions required by comments from the schematics phase.
*** Submit utility drawings at same scale as provided for Site Development drawings, incorporating all of the revisions required by comments from the design development phase. Submit legend, notes, and details at a scale not less than 1:100 (1/8 inch).
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Site Development
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Confirm
Narrative ✓ N/A
Analysis of site ✓ N/A
Circulation study ✓ N/A
Phasing analysis ✓ N/A
Parking analysis ✓ N/A
Development concept showing proposed buildings and structures
Landscape drawings with plant groupings
Topographic, utility, and landscape survey
✓ N/A ✓ N/A
Demolition plan ✓ N/A ✓ N/A ✓ N/A
Layout plan showing location of:
Building and structures ✓ N/A ✓ N/A ✓ N/A
Roads ✓ N/A ✓ N/A ✓ N/A
Fire access N/A ✓ N/A ✓ N/A
Parking ✓ N/A ✓ N/A ✓ N/A
Accessible spaces ✓ N/A ✓ N/A
Van spaces ✓ N/A ✓ N/A
Mechanical and electrical equipment on grade
✓ N/A ✓ N/A ✓ N/A
Future expansion ✓ N/A ✓ N/A ✓ N/A
Off-site roads ✓ N/A ✓ N/A ✓ N/A
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Off-site utilities ✓ N/A ✓ N/A ✓ N/A
Service area(s) ✓ N/A ✓ N/A
Entrances and exits ✓ N/A ✓ N/A
Walks ✓ N/A ✓ N/A
Inlets ✓ N/A ✓ N/A
Contractor’s staging area ✓ N/A ✓ N/A
Vertical and horizontal road alignment ✓ N/A ✓ N/A
Paving joint patterns ✓ N/A ✓ N/A
Grading plan showing:
Existing contours ✓ N/A ✓ N/A
Proposed contours ✓ N/A ✓ N/A
Spot elevations at structure corners, entrances, equipment pads, etc.
First floor elevations ✓ N/A ✓ N/A
Rim and invert elevations on storm drainage fixtures
✓ N/A ✓ N/A
Erosion and sediment control ✓ N/A ✓ N/A
Rock excavation (quantity) ✓ N/A ✓ N/A
Planting plan showing: ✓ N/A ✓ N/A
List of plant material ✓ N/A ✓ N/A ✓ N/A
Limits of irrigation ✓ N/A ✓ N/A ✓ N/A
Other ✓ N/A ✓ N/A
Site details ✓ N/A ✓ N/A
Landscape details ✓ N/A ✓ N/A
Signage plan and schedule ✓ N/A ✓ N/A
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
* Submit site and landscape plans at an appropriate scale to show all work involved.
** Submit site and landscape plans at same scale as topographic/utility survey incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated site and landscape plans incorporating all revisions required by comments from the design development phase.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Space Planning
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Confirm
Space-Accounting Summary Table ✓ 1 N/A ✓
2 N/A ✓ 3 N/A
1. Provide a tabular table with columns entitled Departmental Function, H-7610 Requirements, Approved Space Program [Net Square Meters (Net Square Feet)], Variance Between H-7610 and Approved Space Program, Departmental Conversion Factor, Planned Departmental Gross Square Meters (Feet); column totals; and a Total Project Net to Gross Factor. Also, list separately the area required for additions to the program, unassigned space, major circulation (inter-departmental corridors, stairs, elevators), major mechanical and electrical spaces, exterior walls, connecting corridors to other buildings, space for future mechanical system expansion, and similar special requirements.
2. Update table. Justify in writing substantial deviations from the approved space program.
3. Update table.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Specifications
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Confirm
Specifications (All Disciplines) ✓ 1,2,3 N/A ✓⁴,⁵ Yes
1. Submit for all technical disciplines the original VA Master Specification section drafts marked-up with pencil showing the editing for the project. Clearly identify modifications, deletions and insertions. Assure the specification drafts have been edited and tailored in their application to represent accurate coordination between drawings and specifications.
2. When no VA Master Construction Specification exists for a "unit of work", prepare the specification section consistent with VA Master Construction Specifications format.
a. Use generic or non-proprietary specifications describing the minimal acceptable product criteria level where no "Standard" exists to define quality and workmanship levels.
b. Use applicable "Standards" to define quality and workmanship when these publications exist. List complete designation and title of each publication used in Part 1; follow format in VA Master Construction Specifications for Applicable Publications.
c. Do not use proprietary specifications or systems that restrict competition unless authorization in writing has been received from the VA Project Manager for such proprietary specification. See the Federal Acquisition Regulation (FAR) Part 10, Part 14, and Part 36.
d. Do not use trade names or manufacturers brand names, except as previously noted.
e. When a deviation is requested, define and specify the minimum acceptable levels of essential criteria in descriptive, physical, functional, or performance requirements.
3. Type specifications in final format and content including any desk copy changes made by the VAMC staff at the previous review. Submit a complete set of the typed specifications for review. Include one set of full size final drawings of all disciplines, fully coordinated.
4. Return all draft specifications reviewed at DD review to aid the final bid document review. These draft specifications will later be returned to the A/E.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Steam Distribution (Outside)
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Estimate steam and condensate loads ✓ N/A ✓ N/A ✓ N/A
Life-cycle cost analysis of steam distribution system
✓ N/A ✓ N/A ✓ N/A
Calculations of pipe sizing ✓ N/A ✓ N/A ✓ N/A
Steam distribution plot plan ✓ N/A ✓ N/A ✓ N/A
Existing underground utilities ✓ N/A ✓ N/A ✓ N/A
Soil conditions report ✓ N/A ✓ N/A ✓ N/A
Performance requirements for steam traps
✓ N/A ✓ N/A
Calculate pipe stress ✓ N/A ✓ N/A
Select expansion for piping ✓ N/A ✓ N/A
Location of:
Manholes ✓ N/A ✓ N/A
Pipe expansion devices ✓ N/A ✓ N/A
Profile drawings including existing utilities
✓ N/A ✓ N/A
Plan views/sections/dimensions for major piping, pipe layout and pipe support of:
Manholes ✓ N/A ✓ N/A
Trenches ✓ N/A ✓ N/A
Tunnels ✓ N/A ✓ N/A
Other:
Demolition Plans ✓ N/A ✓ N/A
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
* Submit outside steam generation plans at an appropriate scale to show all work involved.
** Submit outside steam generation plans at same scale as topographic/utility survey incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated outside steam generation plans incorporating all revisions required by comments from the design development phase.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Steam Generation
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
A/E
Report on new and existing steam loads¹ ✓ N/A
Life-cycle cost analysis of steam supply alternatives
Analysis of alternate plant locations ✓ N/A
Life-cycle cost analysis for alternative types of equipment
Life-cycle cost analysis for heat recovery alternatives
✓ N/A
Data on emissions regulations ✓ N/A
Data on methods of compliance ✓ N/A
Selection of major equipment ✓ N/A
Plot plan with new and existing plant locations
Fuel related storage and handling facilities
Alternate plan view layouts of new and existing plant
Plot plan of steam generating facility² ✓ N/A ✓ N/A
Catalog cuts on equipment from two manufacturers
✓ N/A ✓ N/A
Plans/sections/locations of:
Equipment ✓ N/A ✓ N/A
Major piping ✓ N/A ✓ N/A
Pipe supports ✓ N/A ✓ N/A
Demolition plans ✓ N/A ✓ N/A
Schematic flow diagrams of all piping systems
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Calculations
Equipment sizing ✓ N/A ✓ N/A ✓ N/A
Major piping systems ✓ N/A ✓ N/A
Steam load ✓ N/A ✓ N/A
Control and regulating valve ✓ N/A ✓ N/A
Flowmeter systems ✓ N/A ✓ N/A
Steam trap ✓ N/A ✓ N/A
Heating and ventilating system ✓ N/A ✓ N/A
Steam piping ✓ N/A ✓ N/A
Schedules ✓ N/A ✓ N/A
Equipment lists ✓ N/A ✓ N/A
Verification of emission regulations ✓ N/A ✓ N/A
List of standards and details ✓ N/A
* Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from
1. Include maximum and minimum summer and winter demands and total annual production. Provide break-down of new steam loads into categories of end use such as building heating, humidification, reheat, domestic hot water, sterilization, line losses, kitchen, and laundry.
2. Show boilers, pumps, heat recovery devices, tanks, and emission control devices.
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Structural
Reviewer: S. Morgan
(15-30%) A/E
Confirm
DD
A/E Confirm
CD
Three alternative structural systems for typical bays¹
✓ Select
Supporting calculations² ✓ Select ✓ Yes ✓ Yes
Cost estimates for each system³ ✓ Select
Recommend preferred system ✓ Select
Column locations ✓ Select
Sheer load resisting elements⁴ ✓ Select
Boring location plan⁵ ✓ Select
Structural plans⁶ ✓ Yes ✓ Yes
Sections ✓ Yes ✓ Yes
Details ✓ Yes ✓ Yes
Size/location of:
Columns ✓ Yes ✓ Yes
Beams ✓ Yes ✓ Yes
Lateral load resisting elements ✓ Yes ✓ Yes
Slabs ✓ N/A ✓ N/A
Foundations ✓ Yes ✓ Yes
Elevations ✓ Yes
Schedules ✓ Yes
General notes ✓ Yes
Boring logs ✓ N/A
Subsurface investigation report ✓ N/A
Replace Air Handling Units 22 and 23 VA Minor Checklist – 100% Bid Documents for Construction Submittal
Estimated quantity of rock ✓ N/A
* Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from
1. When only one structural system is possible due to other project requirements, include an explanatory statement and submit only that structural system.
2. Include vertical and lateral load design for CD submission.
3. Include foundation and fireproofing.
4. Indicate existing utilities and structures within, adjacent, or contiguous to the new construction.
5. Upon approval of the subsurface investigation criteria, submit qualifications of at least three consultants being considered for the work together with the proposal of the consultant recommended as most qualified.
6. If there is only a CD submission, provide a Structural Engineering Analysis Submission within six weeks from the notice to proceed including sketches, calculations, and cost estimates of three alternative structural systems for typical bays, boring location plan for subsurface investigation, and consultant qualifications. For vertical expansion projects, analyze existing structure for structural feasibility.
Replace Air Handling Units 22 and 23 Design Analysis Report – 100% Bid Documents for Construction Submittal
AKEA Design, Inc.
Design Narratives
Replace Air Handling Units 22 and 23 Design Analysis Report – 100% Bid Documents for Construction Submittal
AKEA Design, Inc. Mechanical Narrative – Page 1 of 6
Prepared by:
William Rodriguez, P.E.
Tim Murray, Sr. Mechanical Designer
OVERVIEW
This project involves the replacement of two air handling units (AHUs) at the James A. Haley
VA Medical Center in Tampa, FL. This narrative describes the mechanical design intent and basis of design, including assumptions made. This design project is based on a direct replacement of two AHUs, 30-AHU-22 and 30-AHU-23, with like-kind, matching the 1972 replacement design provided by the VA.
HVAC EXISTING SYSTEM
The existing AHUs, 30-AHU-22 and 30-AHU-23 were designed and installed in 1972 in the
Building 30 Mechanical Room 011. The existing AHUs are deteriorated and rusted with degraded performance due to age and environmental conditions within Mechanical Room 011.
The 30-AHU-22 and 30-AHU-23 serve ground floor areas, consisting of 7,220 square feet and
6,190 square feet, respectively. The North Wing, Nurses Stations, West Wing, and East Wing are the areas affected by this design. Please refer to Table 1 and Table 2 ‘Areas Served” for details.
The existing units are located in Electrical Room 30-011, on the ground floor. The unit replacements will be installed in the existing units’ locations within this room. An existing outside air intake louver, serving both units, is located on the north wall of the adjacent room, Electrical 30-011a, and will be reused for the new units.
The existing 30-AHU-22 is a 100 percent outdoor air unit with a heating hot water (HHW) pre-heating coil, chilled water (CHW) coils, (MERV 8)…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .