36C24824R0010 0002.docx
DOCX document 38 KB Posted
- Solicitation number
- 36C24824R0010
About this file
This document contains a request for information (RFI) and the agency responses to questions from potential offerors on an upcoming project to replace air handling units at a Department of Veterans Affairs medical facility.
The RFI provides specifications for the project such as external static pressures for the new supply and return fans. It also answers questions on the project scope, schedule, and requirements. The replacement of air handling units 22 and 23 has a proposal due date of January 12, 2024. The period of performance can be extended to 240 days to accommodate long lead times for temporary air handling equipment. The RFI response clarifies that different qualified personnel are required for the roles of superintendent, quality control manager, and safety officer. It also provides the location for staging areas and confirms Simplex as the current fire alarm system manufacturer.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information (RFI)
Replace AHUs 22 and 23
PROJECT # 673-21-152/ 36C24824R0010
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 673-21-152 36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) Tampa FL 33637 36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) Tampa FL 33637 To all Offerors/Bidders
36C24824R0010 11-20-2023
X
X
Project title: BB - REPLACE AIR HANDLING UNITS 22 AND 23 Project Number: 673-21-152
The purpose of this amendment is to provide answers to RFIs.
Proposal Due Date January 12, 2023, at 2:00 PM. EST. remains the same.
All other terms and conditions remain the same.
POC: David Hernandez. Email: david.hernandez1@va.gov
Contracting Specialist David Hernandez Project title: BB - REPLACE AIR HANDLING UNITS 22 AND 23.
Project Number: 673-21-152.
THE PURPOSE OF THIS AMENDMENT IS TO MAKE THE FOLLOWING CHANGES TO THIS SOLICITATION:
· The purpose of this amendment is to provide answers to RFIs.
| RFI NBR |
| Question/ |
Response
| Company Submitted By |
| Dated Received |
| 1. |
| M501 & M600: External static pressures are not listed for supply fan(s) or return fan(s). Engineer of Record please specify external static pressure of supply fans and return fans. ESP cannot be assumed based on the TSP’s listed. |
| American Veterans Const. Corp |
| 12/04/23 |
VA Response: 30-AHU-22/22T the ESP= 3.3 in.-wg. 30-AHU-23/23T the ESP= 3.8 in.-wg. The return fans are existing to remain.
| 2. |
| M800: AHU Control Diagram shows steam coil placed upstream of pre-heat water coil. Engineer of Record to confirm design intent is to have steam coil upstream of pre-heat coil |
| American Veterans Const. Corp |
| 12/04/23 |
VA Response The only steam coil is the pre-heat coil on all units.
| 3. |
| Is this project tax-exempt? |
| DAX Contracting Solutions, LLC |
| 12/05/23 |
VA Response:”VA to responsd” NO
| 4. |
| Can a Site Superintendent double hat as QC? |
| DAX Contracting Solutions, LLC |
| 12/05/23 |
VA Response: No. Per spec 01 45 00 section 3.2.B.10 “The Contractor must perform these inspections using independent qualified inspectors. Include the Special Inspection Plan requirements in the CQC Plan”
| 5 |
| Can a Site Superintendent triple hat as QC and SSHO? |
| DAX Contracting Solutions, LLC |
| 12/05/23 |
VA Response: No. per spec 01 35 26 section 1.7 C:
“However, the SSHO has be a separate qualified individual from the Prime Contractor’s Superintendent and/or Quality Control Manager with duties only as the SSHO. “
| 6 |
| Will the foundation work interfere with existing building structural? |
| DAX Contracting Solutions, LLC |
| 12/05/23 |
VA Response: It is not intended to interfere. The contractor is responsible for field verification of existing conditions per the drawings.
| 7 |
| Where is the staging area for material? |
| DAX Contracting Solutions, LLC |
| 12/05/23 |
VA Response: Will determined by VA’ COR.
| 8 |
| Where is the staging area for trailer? |
| DAX Contracting Solutions, LLC |
| 12/05/23 |
VA Response: Will determined by VA’ COR.
| 9 |
| Is the VA hiring commissioning agent? |
| DAX Contracting Solutions, LLC |
| 12/05/23 |
VA Response: Per spec 23 08 00 section 1.1.B – “A Commissioning Agent (CxA) appointed by the VA will manage the commissioning process.”
| 10 |
| Is the VA hiring Special Inspector? |
| DAX Contracting Solutions, LLC |
| 12/05/23 |
VA Response: No. The contractor is responsible for hiring the special inspector. Refer to spec 01 45 35 section 1.4.A: “Special Inspector (SI) – A qualified person retained by the contractor and approved by the Contracting Officer as having the competence necessary to inspect a particular type of construction requiring Special Inspections. The SI must be an independent third party hired directly by the Prime Contractor.”
| 11 |
| What is the requirement for the superintendent, QC manager and safety officer. Can the superintendent be all three? |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: No. See response 4.
| 12 |
| Can the period of performance be changed to 240 days? As you know, one of the first critical path items is the temporary AHU’s which must be installed, tested, and put in operation prior to any replacement work starting. The lead time on the equipment is at least 8 – 12 weeks plus time (4 weeks) to install Johnson control components in Daikin equipment at the factory and/or in the field which is almost half the entire POP |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: VA to respond. - YES
| 13 |
| Once the temporary AHU’s and structural steel is removed, what is to be done with the foundations? Can they remain and cut off the anchor bolts? |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: Can remain if OK with VA
| 14 |
| Since the structural steel is temporary, is painting or coating of the steel required? If so, what is the specification? |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: coating requirements are on the drawings
| 15 |
| Can another site visit be arranged so more subcontractors can see the area? |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: VA to respond. – Yes Please contact COR at vinh.bui@va.gov
| 16 |
| Can a bid date extension be provided. We and many of our subcontractors were not aware of the project but very interested in bidding. |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: Proposal due date was extended to 01/12/2024 at 2:00PM
| 17 |
| Can the RFI due date be extended with a bid date extension? A bid date extension of 1 week beyond the 2nd site visit? |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: No
| 18 |
| Per drawing M100 – Pre-Demolition TAB notes, it states that no demolition can begin until we receive approval from the EOR and COR for the Pre-Demolition TAB report. How long are we to allow for approval once the TAB report is provided |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: Per spec 01 33 23 section 1.10.D: “VA review period is 15 working days for submittals.”
| 19 |
| Can any CHW and HHW temporary piping and ductwork (not to be used as permanent) be temporarily insulated with fiberglass wrap or what specification should be followed? |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: All insulation works shall be according spec 23 07 11.
| 20 |
| Can temporary hoses be used for the temporary chilled and HHW systems in lieu of rigid steel pipe? |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: All hydronics piping works shall be according spec 23 21 13.
| 21 |
| If the Daikin equipment specified in the DAR is provided and it is the basis of design for the temporary structural (already engineered), is a certified (stamped by contractor provided structural engineer) shop drawing required? If so, then is alternate HVAC equipment allowed since an engineered structure is required anyway? |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: No. All equipment shall be required according to spec 01 33 23.
| 22 |
| Can a copy of the site visit sign in sheet be provided. |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: yes
| 23 |
| Is Johnson Controls the basis of design for temperature controls and the current installed system? |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: Refer to spec 23 09 23.
| 24 |
| Is Simplex (JCI) the current Fire Alarm system? |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: VA to responsd. - Yes
| 25 |
| Detail #4 on S301 states the size of the bollard foundation to be 18”x18”. Can it be 18” round by using an auger? |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: Yes.
| 27 |
| Has a staging area been assigned, if so, where? |
| NAPC HSCC JV |
| 12/07/23 |
VA Response: Same as response 7.
| 28 |
| Can the POP be extended beyond 220 days? it is unlikely the unit will be constructed in that timeframe. |
| OST |
| 12/07/23 |
VA Response: VA to respond. - Yes
VA Response:
VA Response:
See attached document: SIGNING SHEET.
Attachment 2 RFI Tracking Log
File details come from the government source that posted it. Updated .