This document provides details for a solicitation seeking construction services. The National Institutes of Health is issuing an 8(a) Multiple Award Construction Contract for projects at Research Triangle Park, North Carolina. Offerors must have 8(a) program certification from the Small Business Administration. The pre-proposal conference will be held on December 14th and questions are due by December 28th. Proposals are due on January 11th, 2023. The period of performance is from March 2023 to March 2028. Allowable overhead and profit percentages for change orders are provided, with a maximum of 10% overhead for prime contractor work and 5% for subcontractor work. The profit percentage will be negotiated up to 10%.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

75N99023R00003 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Bethesda, MD 20892-5711

ORF

9000 Rockville Pike Building 13, Room 2E-47 OD - Office of Research Facilities National Institutes of Health

12/22/20220002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

12/01/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this Amendment is to provide:

1) Questions and Answers to RFIs into the solicitation. Please see attachment labeled "8(a)

MACC - RFI Log Amendment 02" spreadsheet.

///// Additional changes are listed below on the Continuation Page /////

RFI Cutoff and Proposal Due Dates are NOT extended.

Period of Performance: 03/20/2023 to 03/19/2028

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

ADDISON T. MILLER

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

2. Change Section M, Factor 1 - Technical, Subfactor 3 Construction Experience to Read:

FROM:

"Submit four (4) relevant construction projects or Design/Build projects for the Offeror that best demonstrates your experience on relevant projects that are similar in size, scope, and complexity to the projects contemplated by this RFP.

For purposes of this evaluation, a relevant project is further defined as:

Size Defined: A final construction cost of $250,000.00 or greater. At least one (1) project must have a final construction cost of $2,000,000.00 and greater.

Scope/Complexity: New building construction and/or interior/exterior alteration or renovation of laboratories.

Recency: Projects submitted for the Offeror shall be completed within three (3) years of the date of issuances of this RFP (recency).

Additionally, submitted relevant projects shall, cumulatively, demonstrate the following characteristics:

Offerors shall have acted as the prime contractor on submitted projects. Offeror's experience performing as subcontractor will not be considered, nor will experience of companies proposed to work as subcontractors on the awarded contract. Offeror shall provide at least one Construction Experience Project Data Sheet (Attachment 1) for each of the following types of projects (projects must be relevant and recent as defined in size and scope/complexity as described above):

a) Demonstrated experience from one (1) of the following project types must be included: Biomedical Research Laboratories, Animal Care Facilities, or predominantly utility project.

b) Demonstrated experience from one (1) of the following remaining project types, which must be different from the facility type experience demonstrated in (a) above: Biomedical Research Laboratories, Animal Care Facilities, or predominantly utility project.

c) Demonstrated experience must include at least one renovation/repair project

d) Demonstrated experience must include at least one design-build project

NOTE: Failure to demonstrate experience in ALL four (4) types of relevant construction projects shall be considered a deficiency; thus unacceptable."

TO:

"Submit four (4) relevant construction projects or Design/Build projects for the Offeror that best demonstrates your experience on relevant projects that are similar in size, scope, and complexity to the projects contemplated by this RFP.

For purposes of this evaluation, a relevant project is further defined as:

Size Defined: A final construction cost of $250,000.00 or greater. At least one (1) project must have a final construction cost of $2,000,000.00 and greater.

Scope/Complexity: New building construction and/or interior/exterior alteration or renovation of facilities that include repairs to multiple building systems and infrastructures.

Recency: Projects submitted for the Offeror shall be completed within three (3) years of the date of issuances of this RFP (recency).

Additionally, submitted relevant projects shall, cumulatively, demonstrate the following characteristics:

Offerors shall have acted as the prime contractor on submitted projects. Offeror's experience performing as subcontractor will not be considered, nor will experience of companies proposed to work as subcontractors on the awarded contract. Offeror shall provide at least one Construction Experience Project Data Sheet (Attachment 1) for each of the following types of projects (projects must be relevant and recent as defined in size and scope/complexity as described above):

a) Demonstrated experience from one (1) of the following project types must be included:

Biomedical Research Laboratories, Animal Care Research Facilities, Hospitals, or predominantly utility project.

b) Demonstrated experience from one (1) of the following remaining project types, which must be different from the facility type experience demonstrated in (a) above: Biomedical Research Laboratories, Animal Care Research Facilities, Hospitals, or predominantly utility project.

c) Demonstrated experience must include at least one renovation/repair project

d) Demonstrated experience must include at least one design-build project

NOTE: Failure to demonstrate experience in ALL four (4) types of relevant construction projects shall be considered a deficiency; thus unacceptable.

3. Add the below information to G.5 Proposal Contents and Preparation Costs, Paragraph (c) Price

G.5.(c).1 Allowable overhead, profit, and percentages for change orders.

Allowable overhead, profit, and percentages are given at the end of this paragraph. These percentages shall be limited to three tiers only and shall be considered to include, but not limited to, all insurance other than FICA, FUTA, SUTA and Workmen's Compensation, field and office supervisors and assistants, use of small tools, incidental job burdens, and general office expense. Incidental job burdens include, but are not limited to, review and coordination, and estimating and expediting relative to contract changes that are associated with field and office supervision.

No percentages for overhead and profit shall be allowed on FICA, FUTA or SUTA. The percentages for overhead and profit to be allowed by NIH may vary according to the nature, extent, and complexity of work involved, but in no case shall exceed the following:

The percentages of overhead to be allowed by the Contracting Officer will be 10% for all contract changes performed by prime contractor personnel and 5% for all contract change work performed by subcontract personnel.

The percentage for profit to be allowed by NIH will vary according to the nature, risk, extent, and complexity of work involved, but in no case shall exceed 10%. Percentages for overhead and profit will be as follows:

Overhead / Profit

To subcontractors and/or to the Contractor for work performed with his own forces - Max of 10% (1% - 10%) To Contractor on work performed by other than his own forces - Max of 5% (1% - 5%)

The percentage of profit is to be negotiated. The burden is on the contractor to propose and justify to the Government the percentage of profit to be paid on each modification to the contract.

On proposals involving both increases and decreases in the amount of the contract, overhead and profit will be allowed on the net increases only. On net decreases, corresponding overhead and profit will be deducted.

When change proposals are not submitted with a Time Impact Analysis, it is mutually agreed that the particular change order, modification, delay or Contractor request does not require an extension of the contract time (or milestone).