Date: June 14, 2019
Memo to: Solicitation No: 75N97019R00009
Subject: Amendment: 1 – Revised Package
From: Russell Reeves, Contract Specialist, National Library of Medicine
This memo is issued to:
Extend Response Date. The response date is amended as follows:
FROM: 12:00pm – June 24, 2019
TO: 12:00pm – July 1, 2019
Provide Revised Package to include
· Revised Statement of Work – 6/14/19
· Revised RFP – 6/14/19
· Revised Addendum to Terms and Conditions -6/14/19
· Employee Separation Checklist
· Commitment to Protect
· NIH Data Center Equipment List
· Wage Determination 2015-4269
Respectfully, Russell T. Reeves, Contract Specialist Office of Acquisition Management National Library of Medicine, NIH 6707 Democracy Boulevard, Bethesda, Maryland 20892 reevesru@mail.nih.gov image1.png