This document is Amendment A00002 to solicitation 75H70126R00054 for the Crow Northern Cheyenne Phase II Renovation, a construction project issued by the Indian Health Service (IHS) Division of Engineering Services in Seattle. The amendment extends the proposal due date to September 9, 2026 at 5:00 PM PT, provides responses to 105 bidder questions submitted during the pre-bid phase, and includes a revised Section J with updated technical attachments and addendums.

The project is a 100% Indian Small Business Economic Enterprise (ISBEE) set-aside under NAICS code 236220 (Commercial and Institutional Building Construction) with an estimated magnitude between $5,000,000 and $10,000,000. Key project requirements include: renovation of an operating room department that will be shut down during construction with full contractor access; installation of a new rooftop HVAC unit (AHU-5/RTU-1) to replace existing equipment; coordination with hospital staff for utility shutdowns and system tie-ins; infection control and dust containment measures per an approved ICRA/PCRA; removal and salvage of existing equipment; separate roles for Superintendent, Site Safety and Health Officer, and Quality Control Manager; performance within 365 calendar days after receiving notice to proceed; and provision of performance and payment bonds within 10 days of award. Work is generally limited to 8:00 AM to 5:00 PM Monday through Friday with minimal after-hours work anticipated for specific disruptive activities. Government-provided utilities include power, water, and sewer, with temporary connections being the contractor's responsibility. The existing Building Automation System is Automated Logic WebCtrl, the fire alarm system is Siemens, and the facility uses Corbin Russwin 7-pin locks; contractors may use qualified service providers for these systems and are not required to use existing vendors. No TB screening or seasonal flu shots are required, and contractors must provide portable toilet facilities rather than utilizing hospital facilities.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

SF30 CONTINUATION OF BLOCK NARRATIVE

SUMMARY OF CHANGES

Solicitation Number 75H70126R00054 is hereby amended to address the following:

1. Extend the proposal due to 9/9/2026 at 5:00PM PT (2 pages)

2. Provide responses to questions submitted (22 pages)

3. Provide revised Section J

a. B01 Attachment J01c Addendum No. 1

b. BID RFI Response Attachments (Informational)

NOTICE TO OFFERORS: Offerors must acknowledge receipt of any and all amendments by number and date on their cover letter in their offer or by submitting a signed copy of the SF30. All other terms and conditions remain unchanged.

END OF SUMMARY OF CHANGES

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR

INFORMATION CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF PAGES

75H70126R00054

Indian Health Service Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104

Project: Crow Renovation Phase II

Project No: BI25CR400H11

See Section L for Proposal Submittal Instructions and Site Visit Information.

This project will be procured as a 100% Indian Small Business Economic Enterprise (ISBEE) set-aside under North American Industry Classification System (NAICS) code 236220, Commercial and Institutional Building Construction. The associated size standard for this procurement is $45 million.

CONSTRUCTION MAGNITUDE: The magnitude of this construction project is anticipated to be between $5,000,000 and $10,000,000.

Indian Health Service Division of Engineering Services (DES) - Seattle Attn: Taylor Kanthack 701 5th Ave Seattle, WA 98104

Taylor Kanthack taylor.kanthack@ihs.gov 240-478-1501 see box 10

1 4708/05/2026

9/9/2026

5:00PM PT

10 Days after award

Section F

AWARD (To be completed by Government)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES

CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

B.3

Indian Health Service, DES - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104

IHS Billings Area Office 2900 4th Ave North Billings, MT 59101

RFIs and Responses Crow Northern Cheyenne Phase II Renovation

75H70126R00054

Date 8/19/2026 Item RFI Response 1 Do you have any idea what brand the current fire alarm is? The panel is a Siemens

Date 8/31/2026

2 Infection Control: Will the Government provide the ICRA classification for each phase, or is the contractor expected to generate the full ICRA/PCRA for approval?

The Government will provide the ICRA/PCRA for each phase of the project. The Contractor will be expected to provide input and coordination as necessary to support the development and completion of the ICRA/PCRA

3 Staging/Laydown: Is there a designated area for the new RTU assembly and crane operations that will not block ambulance access?

Refer to attached site plan.

4 Can the Superintendent also be the SSHO and QC? No. Due to the complexity and high-risk nature of this project, the Government requires the Superintendent, Site Safety and Health Officer (SSHO), and Quality Control (QC) Manager to be separate individuals.

Each position has distinct responsibilities and applicable qualification and/or certification requirements. Maintaining these roles separately provides appropriate oversight of construction activities, safety, and quality control and helps ensure that each function can be performed independently and effectively throughout the project.

The Contractor shall provide qualified personnel for each position in accordance with the requirements of the Contract Documents.

5 Utility Interruption: What is the maximum allowable window for medical gas and HVAC shutdowns during the RTU transition?

The OR wing can be isolated from the medical gas and HVAC systems serving other areas of the facility. If work requires the shutdown or interruption of medical gas, HVAC, or other building systems serving areas outside the OR wing, the Contractor shall coordinate with hospital staff in advance to establish an approved shutdown schedule and minimize impacts to hospital operations

6 Water Damage: Can the Government provide the remediation clearance reports for the water-damaged areas to establish the baseline condition?

All water-damaged areas are being resolved by separate contract and do not affect anything in the project scope of work.

7 Light Fixture Schedule Mismatches (Issue): Sheet E102.2-2 specifies fixture marks "S22", "C22", "C22A" which are omitted from the schedule on Sheet E600.2-1

These fixtures are not shown on floor plan E102.2 and are not a part of BP2.

8 Heavy HVAC Motor Loads on Critical Branch (Issue): Panel 2C1H on Sheet E600.2-1 feeds 480V 3-phase AHU supply/return fan motors from the Critical Branch, violating

NEC 517.31(A)

These will be moved from 2C1H to 2N3H.

9 Emergency Mechanical Loads on Normal Power (Issue):

Mechanical Schedule Notes on Sheet M600.2-1 mandate emergency backup for unit heater EUH-1, exhaust fan EF-2, and VAV controls, but Panelboard Schedule 2N5L on Sheet E600.2-1 feeds them from Normal Power.

These will be moved to 2C2L, there is not enough spare breaker space in this panel so it will be increased in breaker space to account for this, otherwise the panel will be completely filled.

10 Emergency Eyewash Mixing Valve Mismatch (Issue):

Section 22 40 00 specifies an ASSE 1070 mixing valve for EW-1, conflicting with the ASSE 1071 valve (Haws 9201EW) scheduled on Sheet P600.2-1.

ASSE 1071 is the correct standard.

11 Floor Sink Trap Primer Omission (Issue): Decontamination Room floor sink FS-3 on Sheet P202.2-1 lacks cold water trap primer piping connections.

Floor sink does not have a primer connection. Provide with trap seal.

12 Missing Medical Gas Riser Diagrams (Issue): Riser sheets P521.2-1 and P521.2-2 contain domestic water risers only, omitting medical gas distribution risers entirely.

Riser Sheet P523.2 to be issued in the upcoming Addendum.

13 High Pressure Steam Spec Omission (Issue): Sheet M201.2-1 shows an 80 PSI High Pressure Steam line

Only the low-pressure steam connections are to be modified.

entering PRV Station 1, but Section 23 22 13 specifies piping materials only up to 15 PSI Low Pressure Steam

14 AHU-5 Heating/Cooling Spec Mismatch (Issue): Section 23 74 13 specifies DX cooling and gas-fired heating, whereas Sheet M600.2-1 schedules AHU-5 with chilled water and glycol heating coils.

Specification section 237413 to be replaced by section 237313 in upcoming Addendum.

15 Sterilizer Utility Rough-In Gaps (Issue): Medical Equipment Schedule on Sheet A712.2 omits steam, condensate return, compressed air, and exhaust duct connections required for steam sterilizer STS and washer WD per Section 11 53 00.

The AMSCO 400 steam sterilizer has internal steam generator.

It will have a drain/condensate connection, cold water connection for the steam generator, RO connection for final rinse, and the sterilizer cavity is exhausted. There are no compressed air connection for that (the single chamber double door disinfector has it not these unit).

16 Electrified Door Hardware Rough-Ins (Issue): Hardware Sets 1.0, 2.0, 3.0, 6.0 in Section 08 71 00 mandate card readers and electric locks, but Sheet E202.2-1 and Sheet E302.2-1 lack 120V power connections or low-voltage box rough-ins.

Provide rough-in for power and low-voltage for scheduled door hardware. Refer to Addendum No. 1 for revised electrical plans.

17 Above-Ceiling Spatial Clashes (Issue): Main 32"x28" ducts, deep recessed luminaires, and VAV 5-02/5-05 units collide with structural steel W-beams in restricted 8'-0" corridor ceiling plenums.

Additional clarification required for exact interference concerns.

Recommend field verifying and routing ductwork as applicable to avoid interferences. Contractor shall schedule overhead coordination meeting to review any existing conflicts.

18 Work Hours / After-Hours Requirements The Scope of Work states that work within the existing building is generally limited to 8:00 AM to 5:00 PM, Monday through Friday, with after-hours work potentially required to minimize disruptions. However, the Infection Control/Life Safety drawings state that all work is to be performed after-hours/overnight or on weekends/holidays.

Please clarify the intended working hours for this project and identify which specific areas or activities are required to be performed after-hours, overnight, weekends, or holidays. For bidding purposes, please confirm whether the

Reference H.1 work Hours. The Contractor shall assume that work will generally be performed between the hours of 8:00 AM and 5:00 PM, Monday through Friday. Because the OR Renovation is located in a separate wing of the hospital and can generally be isolated from other occupied areas, after-hours, overnight, weekend, and holiday work is anticipated to be minimal.

After-hours or weekend work may be required for specific activities that could disrupt hospital operations, including utility shutdowns, system tie-ins, or other work affecting occupied areas or critical hospital services. Such activities shall be coordinated in advance

Contractor should carry premium-time labor for all work or only specifically identified disruptive activities.

with hospital staff and performed during approved shutdown or off-hours periods, as required.

For bidding purposes, the Contractor should not carry premium-time labor for all project work. Premium-time labor should be anticipated only for activities that require after-hours, overnight, weekend, or holiday work due to operational impacts or approved shutdown requirements.

19 Phasing Specification Reference The Infection Control/Life Safety drawings direct the Contractor to Specification 010110 for information on work duration for each phase and area of work.

Specification Section 010110 does not appear to be included in the Project Manual provided for bidding.

Please provide the referenced specification and the required durations for each phase/area of work, or clarify that the Contractor is responsible for developing the construction phasing and durations within the overall contract performance period.

Reference H.12. The OR Department is located in a separate wing of the hospital and will be shut down for the duration of the renovation work. The Contractor will therefore have full access to the OR Department during the construction period, and Government-defined construction phasing or individual phase durations will not be provided.

The Contractor shall be responsible for developing and coordinating the sequencing and scheduling of the work necessary to complete the project within the overall contract performance period. Any work requiring shutdowns, tie-ins, or activities that may affect occupied portions of the hospital shall be coordinated in advance with hospital staff.

20 Required Construction Phasing Please provide clarification regarding the required sequence and phasing of the Central Sterile Department, Operating Room/Surgery, water-damaged areas, mechanical work, and associated support spaces.

Are there specific rooms or departments that must be returned to service before work can proceed into subsequent areas? If so, please provide the required sequence and any maximum allowable durations for each phase.

Reference H.12. The OR Department is located in a separate wing of the hospital and will be shut down for the duration of the renovation work. The Contractor will therefore have full access to the OR Department during the construction period, and Government-defined construction phasing or individual phase durations will not be provided.

The Contractor shall be responsible for developing and coordinating the sequencing and scheduling of the work necessary to complete the project within the overall contract performance period. Any work requiring shutdowns, tie-ins, or activities that may affect occupied portions of the hospital shall be coordinated in advance with hospital staff.

21 HVAC Changeover / Temporary HVAC The specifications require the existing HVAC system to remain operational until the new system is ready for changeover.

Please clarify whether temporary heating, cooling, ventilation, humidity control, or temporary air-handling equipment will be required during removal/changeover of the existing AHU and startup of the new rooftop unit. If temporary HVAC is required, please provide required capacities, environmental parameters, and anticipated duration.

The OR Department is located in a separate wing of the hospital and will be shut down for the duration of the renovation work.

Accordingly, temporary heating, cooling, ventilation, humidity control, or temporary air-handling equipment will not be required solely for the purpose of maintaining normal OR environmental conditions during removal of the existing AHU and changeover to the new rooftop unit.

During the HVAC transition period, the Contractor will not be required to maintain specific space temperature, humidity, or other normal operating environmental parameters within the OR Department.

However, the Contractor shall maintain all required infection control, dust containment, and construction-related air pressure/control measures throughout construction in accordance with the approved ICRA/PCRA and applicable project requirements. The Contractor shall provide any temporary ventilation, filtration, negative-air equipment, barriers, or other measures necessary to maintain the required infection-control conditions and prevent construction dust, debris, or contaminants from impacting occupied areas of the hospital.

Any HVAC shutdowns, system tie-ins, or work that may affect systems serving occupied portions of the hospital shall be coordinated in advance with hospital staff.

22 Existing BAS / Controls Provider The project requires integration of the new RTU and associated HVAC equipment into the existing Building Automation System.

Please identify the manufacturer of the existing BAS/DDC system and the Owner's current controls service provider/integrator. Please also clarify whether the Contractor is required to use the existing controls provider

The existing BAS/DDC system is Automated Logic WebCtrl. Use existing controls provider.

for programming, graphics, integration, commissioning, or warranty-related work.

23 Existing Access Control / Security Provider The Infection Control drawings require temporary construction access doors incorporating card readers, and the door hardware specifications include electrically operated/security hardware.

Please identify the manufacturer of the existing access-control/security system and the Owner's current security/access-control service provider. Please clarify whether the Contractor is required to use this provider for programming, installation, integration, testing, or final commissioning of access-control devices.

Temporary card readers not required. Disregard note.

24 Temporary Card Readers Please clarify whether temporary construction card readers are required at every temporary infection-control/construction entrance or only at the specific locations shown on the drawings.

Please also clarify whether the Owner will provide temporary access credentials and programming or whether all temporary card-reader equipment, cabling, programming, and integration are Contractor-provided.

Temporary card readers not required. Disregard note.

25 Existing Fire Alarm Provider Amendment A00001 identifies the existing fire alarm panel as Siemens.

Please identify the Owner's current Siemens fire-alarm service provider and clarify whether the Contractor is required to use this provider for modifications, programming, testing, certification, and final acceptance of the fire-alarm work.

The hospital’s current fire alarm service provider is Xenturis, located in Missoula, Montana. However, the Contractor is not required to use Xenturis for the fire alarm work associated with this project.

The Contractor may utilize any qualified fire alarm subcontractor that is capable of working on and programming the existing Siemens fire alarm system. It is anticipated that programming of the existing system will be required as part of the renovation.

Multiple fire alarm service providers in the surrounding area are capable of servicing and programming Siemens systems. The Contractor shall be responsible for coordinating all required modifications, programming, testing, certification, and system acceptance necessary to provide a complete and fully functional fire alarm system in accordance with the Contract Documents and applicable codes and standards.

26 Hazardous Materials The SOW states that all mold- and water-damaged drywall and flooring has already been remediated. The demolition specifications, however, provide procedures for discovery of asbestos-containing materials, lead, PCBs, mercury, and other hazardous materials.

Please confirm whether a hazardous-material survey has been completed for all areas included in this project and provide any available asbestos/lead/hazardous-material survey reports.

Please further confirm that abatement of previously unidentified hazardous materials encountered during construction is not included in the base bid and will be addressed by the Government through separate work or an equitable adjustment.

Hazardous materials are not known at this time. A hazardous material survey has not been completed.

27 Extent of Previous Mold/Water Remediation Please confirm that all required mold remediation and removal of water-damaged materials has been completed prior to this contract.

If additional concealed mold or water damage is discovered after demolition begins, please confirm that remediation and replacement beyond the specifically identified contract scope will be considered an unforeseen condition/change to the contract.

All previous mold and water damage has been or will be completed by separate contract. No work in area of this project.

28 Existing Conditions Behind Concealed Construction The solicitation states that dimensions shown are based upon available as-built information but may vary from actual field conditions.

Reference FAR 52.236-2, Differing Site Conditions. Concealed conditions meeting the requirements of this clause will be reviewed and, if applicable, addressed through the contract modification process.

Please confirm that concealed conditions that could not reasonably be identified during the pre-bid site visit— including unknown piping, ductwork, electrical systems, structural conditions, or utilities—will be addressed in accordance with the applicable Changes/Differing Site Conditions provisions where they materially affect the contract work.

29 Salvaged Items Please provide a definitive list of equipment, doors, hardware, fixtures, medical equipment, controls, and other materials that are to be:

• Removed and disposed of;

• Removed and salvaged to the Owner;

• Removed, stored, and reinstalled by the

Contractor; or

• Removed/relocated by the Owner.

This clarification is requested to eliminate ambiguity regarding demolition and equipment-handling responsibilities.

Removed and salvaged items to be re-used are noted in the documents. Contractor is responsible for removal, salvage and disposal of all items noted.

30 Medical Equipment Responsibility Matrix Specification Section 011000 states that the Contractor is required to remove, salvage, store, and later reinstall certain medical equipment; furnish and install other medical equipment; and install certain Owner-furnished equipment.

Please provide a consolidated equipment responsibility matrix identifying each piece of equipment as:

OFCI – Owner Furnished, Contractor Installed OFOI – Owner Furnished, Owner Installed CFCI – Contractor Furnished, Contractor Installed Existing – Remove/Reinstall

All existing equipment to be removed by Contractor. Salvaged items as noted. New equipment as noted in schedule and notes.

Coordinate with IHS COR.

31 Condition of Existing Equipment to Be Reinstalled For existing medical or facility equipment that the Contractor is required to remove, store, and reinstall, Contractor will not be responsible for pre-existing deficiencies, damage, operational issues, calibration problems, or code please confirm that the Contractor will not be responsible for pre-existing deficiencies, damage, operational issues, calibration problems, or code deficiencies associated with that equipment.

Please also clarify whether the Owner will document and verify operational condition prior to Contractor removal.

deficiencies associated with that equipment. Prior to removal, Owner and Contractor will inspect each equipment and notate the condition.

32 Owner-Furnished Equipment Delivery For Owner-furnished/Contractor-installed equipment, please provide anticipated delivery dates and confirm that delays in Owner-furnished equipment that affect the critical path will result in an appropriate contract-time adjustment.

Owner-furnished equipment is existing or already on-site.

33 Connections to Owner-Furnished Equipment Please clarify whether the Contractor is responsible for all final electrical, plumbing, medical-gas, data, controls, exhaust, and other connections to Owner-furnished equipment.

Where applicable, please provide manufacturer rough-in requirements for equipment that has already been selected.

Contractor is responsible for all final equipment connections.

34 Existing AHU Removal Path Please clarify the required means and route for removal of the existing second-floor AHU. If the equipment cannot be removed intact through existing building openings, please confirm whether dismantling the unit in place is acceptable.

Please identify any architectural demolition/reconstruction required specifically to facilitate removal.

Dismantling the unit in place is acceptable and the intent was to utilize the existing outside air louvers as a path of egress for the equipment.

35 RTU Crane Operations Please clarify whether there are any hospital-specific restrictions regarding crane setup, crane operating hours, road/parking closures, helicopter flight paths, emergency access, or required critical-lift procedures beyond those contained in the contract documents.

Refer to attached site plan.

Please also identify the approved crane staging/setup location, if predetermined by the Owner.

36 Existing Roof Manufacturer and Warranty The roofing specifications require the Contractor to maintain the existing PVC roofing-system warranty and to coordinate with the existing roof warrantor before beginning work.

Please provide:

1. Existing roofing manufacturer;

2. Roofing system/product;

3. Current roofing installer, if known;

4. Existing warranty documentation;

5. Remaining warranty term; and

6. Manufacturer/warrantor contact information.

Please also confirm whether the Contractor must utilize an installer specifically certified by the existing roofing manufacturer.

Refer to Amendment A00002, Attachment: B01 Attachment J01c Addendum No. 1

37 Existing Roof Assembly Please provide the existing roof assembly, including membrane manufacturer/type, membrane thickness, cover board, insulation type/thickness, vapor retarder, roof deck, and fastening method, to allow bidders to accurately price the required RTU opening and roofing restoration

Refer to Amendment A00002, Attachment: B01 Attachment J01c Addendum No. 1

38 Extent of Roofing Replacement Please confirm that roofing work is limited to areas disturbed by installation of the new RTU, curbs, structural modifications, piping/duct penetrations, and associated work, rather than replacement of the entire existing roof area.

Refer to sheet A232.2 added in Addendum No. 1.

39 Rooftop Utility Conflicts The roofing specifications require coordination of rooftop utilities remaining active during the work.

Please identify any rooftop utilities, communications systems, antennas, mechanical equipment, or other

Contractor to field verify existing conditions prior to any work.

systems that must remain continuously operational and that may interfere with crane operations, RTU installation, or roofing work.

40 Utility Shutdown Durations Please provide the maximum allowable shutdown duration for:

• Normal electrical power;

• Emergency power;

• Domestic water;

• Sanitary systems;

• Medical gases;

• Steam/condensate;

• HVAC;

• Fire sprinkler;

• Fire alarm;

• BAS/controls; and

• Data/security systems.

Please identify which shutdowns must occur after-hours and whether IHS personnel are required to perform any portions of the shutdowns.

Refer to response 5 above.

41 Medical Gas Shutdowns Please clarify the required process for medical-gas shutdowns, including required notice, hospital personnel involvement, temporary medical-gas requirements, certification/testing requirements, and whether an independent medical-gas verifier is Contractor-provided.

Refer to response 5 above.

42 Temporary Egress / Corridor Width The drawings permit corridor reduction for construction containment while maintaining a minimum five-foot hospital circulation path subject to Hospital Safety/Infection Prevention review.

Please confirm that the five-foot clear dimension is the minimum required construction-phase corridor width at the locations shown and identify any areas requiring

Disregard note. All project scope contained in project work area.

greater clear widths for patient-bed transport or emergency operations.

43 Existing Sprinkler System Configuration Please clarify whether the affected areas are served by wet-pipe, dry-pipe, preaction, or a combination of sprinkler systems. The specifications contain requirements for multiple system types, making the required project-specific scope unclear.

Please identify which existing systems are being modified under this contract.

The existing areas are served by wet-pipe sprinkler systems and only wet-pipe will be modified.

44 Fire Watch Please clarify whether fire watch will be required during approved sprinkler/fire-alarm shutdowns and, if required, whether fire-watch personnel are to be provided by the

Provide fire watch as required and coordinated with IHS COR.

45 Contractor Staging and Storage Please identify the specific exterior staging, laydown, dumpster, crane, and Contractor parking areas available for the project.

The specifications also indicate that existing building spaces may be used for storage. Please identify which interior areas will be made available to the Contractor and any restrictions associated with their use.

Refer to attached site plan.

46 Temporary Construction Fencing Specification Section 015000 requires a six-foot-high fence around the construction site.

Please clarify the intended limits and approximate extent of required temporary fencing, particularly since the majority of the work occurs within an occupied hospital. Please identify the exterior areas that must be fenced.

Refer to attached site plan.

47 Construction Access Route Please identify the approved Contractor material-delivery and debris-removal route through the hospital, including elevators, stairways, corridors, loading docks, or temporary openings that may be used.

Refer to attached site plan and sheet G112.2.

Please clarify whether any elevators will be designated for Contractor use and whether there are restrictions on hours of use.

48 Dumpster / Waste Handling Please identify the approved dumpster location and confirm whether construction debris may be transported through the building using the designated construction route.

Please also identify any special hospital requirements for covered carts, sealed containers, cleaning, or disinfection during debris removal.

Refer to attached site plan.

49 Fourth-Floor Work Reference The Infection Control/Life Safety drawings include a note referencing "work in the fourth floor area," while the primary renovation scope appears concentrated on the first/second floor and rooftop/mechanical areas.

Please clarify whether any fourth-floor construction is included in this solicitation. If so, please identify the applicable drawings, scope, and required work.

Disregard ALL references to Fourth Floor. No fourth floor.

50 The Life Safety Plan shows opening B247A in blue linework designated as a 2-hour fire-rated partition. The Door & Frame Schedule assigns B247A a 45-minute minimum fire rating; the sheet’s U.L. label table identifies that as a ¾-hour rating. A 2-hour fire barrier requires a 90-minute opening protective, so the scheduled rating for B247A is insufficient.

Linework is shown as existing smoke barrier. Door B247A is scheduled correctly.

51 The second-floor medical-gas plans show new medical-gas piping and a connection to a zone valve box, but do not depict or call out area alarm panels, master alarm panels, alarm sensors, or associated alarm wiring for OR B248, OR/OB B250/B251, Pre-Op B243, Post-Op B255, or RECPT.

OR CONTROL B244. P302.2-1 and P302.2-2 were visually checked; neither identifies medical-gas alarm equipment.

The cited riser sheets contain domestic-water riser

The intent is to reuse the existing zone valve box and associated area alarm panels and connections as applicable.

diagrams rather than medical-gas alarms or distribution information: P521.2-1 and P521.2-2. The electrical special-systems plans likewise identify only the listed special-systems work and no medical-gas alarm system: E302.2-1 and E302.2-2. Section 22 60 00, 1.06.A and 3.01.A require the medical-gas work to comply with NFPA 99. The documents therefore do not establish the required Category 1 area/master alarm coverage, locations, sensors, or electrical interface for the renovated medical-gas zones.

52 Mechanical Schedule on sheet M600.2-1 and Electrical Roof Power Plan sheet E203.2-1 designate the rooftop air handler as "AHU-5". However, Electrical Panelboard Schedule 2C1H on sheet E600.2-1 (Ckts 1,3,5 and 2,4,6), Panel 2N5L Ckt 10 on sheet E600.2-1, and Special Systems Plan sheet E302.2-1 designate the same equipment as "RTU-1" / "ROOFTOP UNIT RTU-1". This naming contradiction creates ambiguity during bidding, submittal review, and panelboard directory labeling.

Refer to Amendment A00002, Attachment: B01 Attachment J01c Addendum No. 1 and Bid Response Attachments

53 The COMP-1 air-compressor schedule identifies a 480 V, three-phase compressor with MCA 6 A and MOCP 15 A.

Panel 2N3H on the electrical schedules depicts COMP-1 on circuits 16, 18, and 20 with a 20 A three-pole breaker.

The documents therefore provide inconsistent overcurrent-device ratings for the same equipment. The second-floor power-plan keynotes also require the compressor power connection requirements to be field verified with the equipment supplier.

The breaker has been adjusted accordingly

54 The mechanical schedules require EUH-1 to be “ON EMERGENCY POWER” (Electric Heater Schedule Note 3), EF-2 to be on emergency power (Exhaust Fan Schedule Note 2), and the hot-water VAV terminal units to be on emergency power (VAV Schedule General Note B). In contrast, Panel 2N5L assigns EUH-1 to circuit 12, EF-2 to

These circuits have been moved to the emergency panel circuit 19, and the second-floor VAV boxes to circuits 14, 16, and 18. The partial electrical riser feeds 2N5L directly from existing panel 2N1DP and contains no emergency/essential-power source, transfer equipment, or branch designation. The issued documents therefore do not reconcile the mechanical emergency-power requirements with the indicated normal-power feeder path.

55 The two small toilet rooms between Decontamination B227 and Clean Workroom B230 don't carry finish tags on A602.2. Are they in the Phase 2 paint scope?

No small toilet rooms between those rooms.

56 Door B233B is the only wood door on the schedule marked FF. Is that field finish by the painter, and is it paint or stain?

Door B233B shall be VF not FF.

57 Spec 099123 includes a waterborne dryfall system for exposed structure in utilitarian spaces. Which rooms does that apply to?

No exposed structure. Disregard note regarding dryfall paint system.

58 Per Dwg. E500.2, Detail 3----New panelboard 2N3H should be fed from existing panelboard 2N2H. 2N3H is called out to be a 250amp panel. 2N2H is only rated for 225amps and per the manufacturer has no provisions for a 250amp sub feed circuit breaker. (See page 2)

225A is acceptable

59 Substitution Request see attached lighting IHS will not provide prior approval of the proposed equipment.

The contractor will need to bid in accordance with the project plans and specifications. If they believe the equipment they are proposing meets the specifications and is equivalent to the specified equipment, they should bid accordingly.

Any proposed equipment will be reviewed for compliance with the contract requirements through the normal submittal process after award.

60 With the proposal bid question due this week and the proposal is due the following week would you consider postponing the bid due date to later date?

See amendment 2 - the proposal due date has been extended to 9/9/26.

No further questions shall be accepted.

61 Can you clarify the facility specific background clearance procedures and badging if required?

Refer to Section H of the Contract for facility-specific background clearance and security requirements.

All Contractor and subcontractor personnel working on-site will be required to obtain and display a visitor badge while at the facility.

Visitor badges can be obtained through the Facilities/Security Department. The Contractor shall be responsible for coordinating with Facilities/Security to obtain the required badges for all personnel prior to performing work within the facility.

62 Will any of the work areas on this project require escorts for access?

No. Contractor and subcontractor personnel with the required visitor badges will not require escorts for access to the designated project work areas. Access shall be limited to authorized construction areas and other areas necessary to perform the work. Refer to H.9 and H.43

63 H.6 Key Personnel - Can you clarify if the Superintendent may provide a Dual role and perform the QC manager role also?

See response 4.

64 H.6 Key Personnel, Section 13526 1.1 - Can you clarify if the Superintendent may provide a Dual role and perform the site Safety Officer role also?

See response 4.

65 H.6 Key Personnel Section 13526 1.1 - Can you clarify if the Superintendent may provide a Triple role and perform the Supervision, quality control and site Safety Officer roles concurrently?

See response 4.

66 Can you clarify if the site safety officer requires to be a direct employee by the prime contractor?

The Site Safety and Health Officer (SSHO) may be either a direct employee of the General Contractor or a subcontractor. As long as the SSHO is provided by the General Contractor, the position shall remain under the General Contractor’s responsibility and liability. The SSHO shall meet all applicable qualification, training, and certification requirements identified in the Contract Documents.

67 Can you clarify the CQC Manger requires to be a direct employee by the prime contractor?

The Contractor Quality Control (CQC) Manager may be either a direct employee of the General Contractor or a subcontractor.

As long as the CQC Manager is provided by the General Contractor, the position shall remain under the General Contractor’s responsibility and liability. The CQC Manager shall meet all applicable qualification, training, and certification requirements identified in the Contract Documents.

68 Can you clarify any government tests/ inspections that will be performed by IHS for this project?

The general contractor is responsible for all tests and inspections identified in the contract documents. Any additional testing (if required) will be coordinated through the

IHS COR.

69 Can you clarify if we are required to work off-hours? If so can you provide the off-hours working times?

See response 18

70 Can you clarify if this project requires TB Screening? No. TB screening is not required for Contractor or subcontractor personnel working on this project.

71 Can you clarify if this project requires seasonal flu shots? No. Seasonal influenza vaccinations are not required for Contractor or subcontractor personnel working on this project.

72 Are we able to utilize existing toilet facilities in hospital during construction?

No. The Contractor will not be permitted to utilize existing hospital toilet facilities during construction. The Contractor shall provide and maintain temporary toilet facilities (portable toilets) and appropriate hand-washing facilities for all construction personnel for the duration of the project.

73 Can you provide the construction staging area assigned to this project?

Refer to attached site plan.

74 Is there any concurrent work being performed that will disrupt and/or require coordination with this project?

There is currently another project underway at the hospital. However, the OR Renovation is located in a separate wing of the facility, and the work associated with the concurrent project is not anticipated to interfere with or disrupt the OR Renovation.

No significant coordination between the two projects is anticipated.

The Contractor shall coordinate with hospital staff and COR as necessary should any unforeseen conflicts or impacts arise during construction

75 Can you clarify the cost of power, water, sewer etc will be provided by the Government?

Utilities for construction will be provided by the Government. Any temporary connections will be the responsibility of the contractor.

76 Can the pre-bid site visit for attendees be provided? Provided via amendment A00001.

77 Is IHS providing a commissioning agent if required? Contractor is to provide commissioning services per the contract documents.

78 Would we be able to receive a design notice to proceed and then a construction notice to proceed to procure materials as the HVAC unit is expected to be a long lead item?

Lead time per the manufacturer is estimated to be 7 to 13 weeks for the HVAC unit.

Will any of the commissioning for this project require commissioning services for existing systems in the building?

Commissioning services shall comply with the contract document requirements.

80 Can you clarify and define which items the hospital be responsible for moving existing equipment out of the construction area?

All existing equipment to be removed by Contractor. Salvaged items as noted. Coordinate with COR.

Please advise if there are any environmental or HAZMAT concerns in any of the areas where work will take place including asbestos, lead, mold in the areas we are working in and has the abatement been completed?

Information is not available.

Can you define and provide a list of items that the IHS will be relocating by their own team members?

All existing equipment to be removed by Contractor. Salvaged items as noted. Coordinate with Owner.

83 Can you provide full set of existing conditions / as-builts for the project in particular the roof system on 1st floor and the height of floors?

Not available.

84 Can you clarify if there are any components that are required for blast rated?

None required.

Is there any seismic design requirements required for this project?

Can you provide shop drawings or product data for new equipment where we provide installation or Connections?

None required.

Can you provide shop drawings or product data for existing equipment where we provide the relocation, installation or connections?

Not available.

Will IHS Facility be able to provide attic stock for ceiling tile, wall coverings, flooring where we may be tying into?

No. IHS Facilities will not be able to provide attic stock for ceiling tile, wall coverings, or flooring.

Can you clarify if any sprayed fireproofing is required to be repaired for any existing areas?

Patch/repair/replace all areas damaged by demolition as required.

Who is the vendor or contractor currently servicing and maintaining the Building Automation System or Temperature Controls System?

Automated Logic Northwest (Standard Plumbing & Heating) Jason Michael jason.michael@carrier.com 406-465-9087

Who is the vendor or contractor currently servicing and maintaining the Fire Alarm System?

See response to 25.

Demolition sheets AD102.2 and AD221.2 Demolition Keynotes Number D3 Remove Wallpaper is not indicated on the plans can you provide the wall locations were this wallpaper is removed?

Disregard keynote D3. Not used.

Demolition sheets AD102.2 and AD221.2 Demolition Keynotes Number D2a Remove Gypsum Board is not indicated on the plans can you provide the wall locations where this Gypsum Board is removed?

Disregard keynote D2a. Not used.

Demolition sheets AD102.2 and AD221.2 Demolition Keynotes Number D13 Remove bathroom partitions is not indicated on the plans can you provide the room locations where these partitions are removed?

Disregard keynote D13. Not used.

Demolition sheets AD102.2 and AD221.2 Demolition Keynotes Number D17 Remove X-Ray Equipment is not indicated on the plans can you provide the room locations where this equipment is removed?

Refer to Corridor B247 and interior elevation 27 on sheet A820.2. X-ray viewing box shall be removed, salvaged and reinstalled at new height TBD to not conflict with new counter.

Can you provide the manufacture that holds the current roofing warranty?

See response to 36

Section 070150.19 Preparation for Re-Roofing – 2.01 can you clarify that the existing roof meets or exceeds the Factory Mutual’s 1-90 Wind Uplift Requirements?

See response to 37

Can you provide the Cross Section / Roof Detail for the new HVAC roof curb required. Detail Sheet A232.2 Sheet is missing from the plans?

Refer to attached Sheet A232.2.

Can you provide penetration details for the existing exterior wall for the new Ductwork defined in note 3 on sheet M103.2 required for AHU on the roof?

Refer to wall section Sheet A102.2.

On Sheet A712.2 Medical Equipment Schedule can you identify the ORT1 and IV shown on the plans as there is not an equipment Description in the schedule.

ORT1 should be OPT. IV is portable IV and will be provided by the Owner.

100 On Sheet A712.2 Medical Equipment Schedule can you identify the ORT1 and IV shown on the plans as there is not an equipment Description in the schedule.

See response to 99

101 On Sheet A712.2 Medical Equipment Schedule can you identify the ORT1 and IV shown on the plans as there is not an equipment Description in the schedule.

See response to 99

Door B282 is listed in hardware group 16, but doesn’t show on the door schedule. Was this door eliminated from the project?

B282 is B278 in schedule provide hardware group 25.

Door B237B is in hardware group 17 in the spec, but shows group 10 on the door schedule. Which is correct?

Provide door hardware group 10.

Door B261 is in hardware group 24 in the spec, but shows group 16 on the door schedule. Which is correct?

Door should have privacy lock. Provide door hardware group 16.

Do you happen to know what the existing key system is at the hospital?

Corbin Russwin 7-pin locks

ADPAA4.tmp
END OF SUMMARY OF CHANGES
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
1. Project Description
3. Submittals
4. Schedule/Meetings
5. Miscellaneous
a.
b.
c.
d.
e.
f.
6. Payments to the Contractor
7. IHS Personnel
8. Invoice Format
9. Closeout Documents