This is Amendment A00003 to Solicitation 75H70126R00018 for Rosebud Lift Station Construction, issued by the Indian Health Service (IHS) Division of Engineering Services in Seattle, Washington. The amendment is effective January 30, 2026, and makes the following modifications to the original RFP: posts a conformed version of the RFP with highlighted changes; amends block 11 of the SF-1442 and Section C to extend the Period of Performance (POP) to 240 calendar days; adds notes regarding the Vaughan Model V3V/V3VR brand name or equal requirement in Section C, paragraph I; amends paragraph F.2(a) to reflect the 240-calendar-day completion requirement; adds attachment J02a containing a Geotech Report from 300 feet away; and replaces attachment J01 Plans with an updated version dated February 13, 2026, correcting the coversheet.
Additionally, the amendment adds attachment J02b, a Consolidated Questions and Answers document addressing inquiries received to date. A critical clarification provided in the Q&A addresses Base Course Thickness, confirming that 12 inches of base course underneath the concrete pad is sufficient. Offerors must acknowledge receipt of this amendment prior to the deadline specified in the solicitation by completing items 8 and 15 on the SF-30 form, acknowledging receipt on each copy of their offer, or by separate letter or electronic communication referencing the solicitation and amendment numbers. All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A00003
Daniel Cotto
Read the continuation sheet.
Indian Health Service (IHS) Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1650 Seattle, WA 98104
75H70126R00018
GP25RB500Z10, PA#141
1 2
Same as 16C
01/24/2026
1/30/2026
Rosebud Lift Station Construction Solicitation: 75H70126R00018
1. The purpose of this solicitation amendment A03 is to:
a. Post the conformed version of the RFP changing the following:
- Replace the original “B01 RFP RLSC 75H70126R00018” with “B01-A03 Conformed RFP
RLSC 75H70126R00018”. Changes are highlighted.
- Amend block 11 of the SF-1442 changing the POP to 240 days.
- Amend Section C, paragraph C to read 240 days.
- Amend Section C to add paragraph I Notes on the Vaughan Model V3V/V3VR brand name or equal requirement.
- Amend paragraph F.2(a) to read 240 calendar days.
b. Add attachment J02a RB Geotech Report from 300 feet away.
c. Replace attachment “J01 Plans RLSC 30Jan2026” with “J01 Plans RLSC 13Feb2026” fixing the coversheet.
d. Add attachment “J02b Consolidated Q&A RLSC” posting the questions and answers (Q&As) received as of this date.
- Refer to question # 13 for an update on the Base Course Thickness: 12-inches of base course underneath the concrete pad is sufficient.
2. Remember to acknowledge all amendments with your offer.
3. All other terms and conditions remain unchanged.
End of Continuation Sheet.